ACTIVITY PBM, BIKANER

Description Start Date End Date

1 Submission of Drawing & Design Completed


2 Approval of Drawings & Design Completed

3 Submission Civil structural drawings & design for foundation and plant building. Completed

4 Approval of Civil structural Drawings & Design Completed

Civil Markings on site & Completion of Civil Work on Site post the drawings finalization Completed
5

6 Completion of Civil Foundation Works to start fabrication works at site. 30.04.2023

7 Supply of 1st Lot of material - Internal Factory:


7.1 Supply of MS C-Channels for Base Frame and internal Structure 01.05.2023
7.2 Supply of MS Sheet for Base Frame 01.05.2023
7.3 Supply of MS Sheet sent for corrugation 01.05.2023
7.4 Supply of MS Corners 01.05.2023
7.5 Supply material to vendor for rolling tank 1 and 2 01.05.2023
7.6 Base rolling material for layer 1 dispatch 01.05.2023
7.7 Supply of round tank second layer rolling sheet and channel 01.05.2023
7.8 Supply of round tank third layer rolling sheet and channel 01.05.2023
7.9 Supply of MS Corrugated Sheets (Side & Partition Sheets) 01.05.2023

Supply of MS Chequered Sheets, MS Pipes for Railings, MS C-Channels, MS Angles for


7.10 30.05.2023
steps

7.11 Supply of MS Flanges and round pipes for puddles fabrication - Internal Factory 30.05.2023

7.12 Supply of MS Plate for Ribs - Internal Factory 30.05.2023

MS Tank Fabrication work of EQT 1 & 2

1 Outer Frame Work of Container Base Frame 1 and 2 03.05.2023 03.05.2023

2 Making base ring and tank base fabrication 1 and 2 03.05.2023 05.05.2023

3 complete welding of both tanks base 1 and 2 06.05.2023 08.05.2023

4 first layer of circular tank fabrication tank 1 & 2 09.05.2023 09.05.2023

5 ring fabrication on first layer tank 1 & 2 10.05.2023 10.05.2023

6 second layer of circular tank fabrication tank 1 & 2 11.05.2023 11.05.2023

7
ring fabrication on second layer tank 1 & 2 11.05.2023 12.05.2023

8 third layer of circular tank fabrication tank 1 & 2 12.05.2023 13.05.2023

9 ring fabrication on third layer tank 1 & 2 13.05.2023 14.05.2023

10 full welding on first layer tank 1 & 2 14.05.2023 15.05.2023

11 full welding on second layer tank 1 & 2 15.05.2023 16.05.2023

12 full welding on third layer tank 1 & 2 16.05.2023 17.05.2023

MS Tank Fabrication work of Tube Settler Tank 1 & 2


ACTIVITY PBM, BIKANER
Description Start Date End Date

1 Outer Frame Work of Container Base Frame 1 and 2 03.05.2023 03.05.2023

2 Making base ring and tank base fabrication 1 and 2 03.05.2023 05.05.2023

3 complete welding of both tanks base 1 and 2 06.05.2023 08.05.2023

4 first layer of circular tank fabrication tank 1 & 2 09.05.2023 09.05.2023

5 ring fabrication on first layer tank 1 & 2 10.05.2023 10.05.2023

6
second layer of circular tank fabrication tank 1 & 2 11.05.2023 11.05.2023

7 ring fabrication on second layer tank 1 & 2 11.05.2023 12.05.2023

8 third layer of circular tank fabrication tank 1 & 2 12.05.2023 13.05.2023

9 ring fabrication on third layer tank 1 & 2 13.05.2023 14.05.2023

10 full welding on first layer tank 1 & 2 14.05.2023 15.05.2023

11 full welding on second layer tank 1 & 2 15.05.2023 16.05.2023

12 full welding on third layer tank 1 & 2 16.05.2023 17.05.2023

MS Tank Fabrication work of SBR Tank 1 & 2

1 Outer Frame Work of Container Base Frame 1 and 2 18.05.2023 18.05.2023

2 Making base ring and tank base fabrication 1 and 2 18.05.2023 20.05.2023

3 complete welding of both tanks base 1 and 2 21.05.2023 22.05.2023

4
first layer of circular tank fabrication tank 1 & 2 23.05.2023 23.05.2023

5 ring fabrication on first layer tank 1 & 2 23.05.2023 24.05.2023

6 second layer of circular tank fabrication tank 1 & 2 24.05.2023 25.05.2023

7 ring fabrication on second layer tank 1 & 2 25.05.2023 26.05.2023

8 third layer of circular tank fabrication tank 1 & 2 26.05.2023 27.05.2023

9 ring fabrication on third layer tank 1 & 2 28.05.2023 29.05.2023

10 full welding on first layer tank 1 & 2 30.05.2023 31.05.2023

11
full welding on second layer tank 1 & 2 01.06.2023 02.06.2023

12 full welding on third layer tank 1 & 2 03.06.2023 05.06.2023

MS Tank Fabrication work TESR & Sludge Sump

1 Outer Frame Work of Container Base Frame 05.06.2023 05.06.2023

2
Fit-up and welding of structural members inside Outer Base Frame of container. 05.06.2023 06.06.2023

3 Fit-up and welding of MS Sheets above MS C-channels frame. 06.06.2023 07.06.2023

4 Welding from bottom of Base frame. 07.06.2023 07.06.2023

5 Coal tar Epoxy Paint at bottom of Base Frame. 08.06.2023 08.06.2023

6 Fitup MS Corners and pipe 09.06.2023 09.06.2023

7 Fabrication of ms sheets 10.06.2023 13.06.2023

8 Complete welding of ms sheets 13.06.2023 15.06.2023


ACTIVITY PBM, BIKANER
Description Start Date End Date

9 Water testing of all tanks 15.06.2023 18.06.2023

10 leakage rectification of all tanks 18.06.2023 20.06.2023

11 FRP lining inside Containers 20.06.2023 28.06.2023


12 Epoxy Paint of all conatiners 28.06.2023 30.06.2023

Supply of 2nd Lot of Material:

1 Supply of Fine Screen 20.06.2023


2 Supply of all Pumps 20.06.2023
3 Supply of Screw Press 20.06.2023
4 Supply of Electrical Panel & SCADA 20.06.2023
5 Supply of Decanters with Hydraulic lifting arrangements 20.06.2023
6 Supply of Air Blowers with acoustic chambers and diffusion systems. 20.06.2023
7 Supply of Motorised Valves, check valves, NRV, etc. 20.06.2023
8 Supply of Cable, Cable Tray's, piping, fittings, etc. 20.06.2023
9 Supply of Thimble Gate Valves with EO System 20.06.2023
10 Supply of Flow meters 20.06.2023
11 Supply of UV's 20.06.2023

Installation:
1 Piping with Valves for transferring sludge to Sludge Sump 21.06.2023 25.06.2023
2 Installation of RAS Piping with complete piping work 21.06.2023 25.06.2023
Installation of Main Lifting Pumps with NRV's, expansion bellows, Motorised Vales,
3 25.06.2023 30.06.2023
Ultrasonic Flow Meter and piping works.
4 Installation of Agitator in Flash Mixer 21.06.2023 25.06.2023
5 Installation of Diffusers in SBR Tanks 21.06.2023 25.06.2023
6 Installation of Tube Media in settling Tank 21.06.2023 25.06.2023
Installation of Air Blower and piping work with supports and required fittings and acoustic
7 01.07.2023 07.07.2023
chamber.
8 Installation of Thimble Gate Valves 01.07.2023 07.07.2023
9 Installation of Coarse Screens with lifting arrangements. 25.06.2023 30.06.2023
10 Installation of Auto Fine Screens with interconnecting piping 25.06.2023 30.06.2023

11 Installation of Screw Pumps and Screw Press with piping fittings and poly dosing system. 01.07.2023 07.07.2023

12 Installation of UV's 21.06.2023 25.06.2023


13 Installation of Decanting System. 21.06.2023 25.06.2023
14 Installation and laying of Cable Tray's 08.07.2023 10.07.2023
15 Laying of Cables 10.07.2023 12.07.2023
16 Installation of Panel and Scada 12.07.2023 13.07.2023
17 Dressing and Termination of Cables 13.07.2023 15.07.2023
ACTIVITY PBM, BIKANER
Description Start Date End Date
Testing & Commissioning 14.07.2023 15.07.2023