3 Submission Civil structural drawings & design for foundation and plant building. Completed
Civil Markings on site & Completion of Civil Work on Site post the drawings finalization Completed
5
7.11 Supply of MS Flanges and round pipes for puddles fabrication - Internal Factory 30.05.2023
2 Making base ring and tank base fabrication 1 and 2 03.05.2023 05.05.2023
7
ring fabrication on second layer tank 1 & 2 11.05.2023 12.05.2023
2 Making base ring and tank base fabrication 1 and 2 03.05.2023 05.05.2023
6
second layer of circular tank fabrication tank 1 & 2 11.05.2023 11.05.2023
2 Making base ring and tank base fabrication 1 and 2 18.05.2023 20.05.2023
4
first layer of circular tank fabrication tank 1 & 2 23.05.2023 23.05.2023
11
full welding on second layer tank 1 & 2 01.06.2023 02.06.2023
2
Fit-up and welding of structural members inside Outer Base Frame of container. 05.06.2023 06.06.2023
Installation:
1 Piping with Valves for transferring sludge to Sludge Sump 21.06.2023 25.06.2023
2 Installation of RAS Piping with complete piping work 21.06.2023 25.06.2023
Installation of Main Lifting Pumps with NRV's, expansion bellows, Motorised Vales,
3 25.06.2023 30.06.2023
Ultrasonic Flow Meter and piping works.
4 Installation of Agitator in Flash Mixer 21.06.2023 25.06.2023
5 Installation of Diffusers in SBR Tanks 21.06.2023 25.06.2023
6 Installation of Tube Media in settling Tank 21.06.2023 25.06.2023
Installation of Air Blower and piping work with supports and required fittings and acoustic
7 01.07.2023 07.07.2023
chamber.
8 Installation of Thimble Gate Valves 01.07.2023 07.07.2023
9 Installation of Coarse Screens with lifting arrangements. 25.06.2023 30.06.2023
10 Installation of Auto Fine Screens with interconnecting piping 25.06.2023 30.06.2023
11 Installation of Screw Pumps and Screw Press with piping fittings and poly dosing system. 01.07.2023 07.07.2023