Professional Documents
Culture Documents
Part 1
Part 1
Part 1
Features and
Introduction
Introduction to Fidic
1
02/08/2022
2
02/08/2022
Consult.
Subcontracts Others
Copy rights for Asel El Housan 7
2008
2005
2006
2010
3
02/08/2022
10
11
Shared risks
LAW
Copy rights for Asel El Housan 12
12
4
02/08/2022
Employer
Service
Agreement
Construction
DAB
Contract
Conflict Engineer
Contractor
13
Risk Allocation
14
15
5
02/08/2022
16
17
18
6
02/08/2022
19
20
85% of the
More than 80% of
definitions and
the content was
expressions were
consistent
the same
21
7
02/08/2022
22
23
24
8
02/08/2022
25
General Conditions
26
General Conditions
27
9
02/08/2022
28
29
Particular Conditions
30
10
02/08/2022
Contract Agreement
31
32
• Forms of Security
• Form of Letter of Tender
• Contract Agreement,
• Dispute Adjudication Agreement.
Copy rights for Asel El Housan 33
33
11
02/08/2022
34
User Friendliness
35
36
12
02/08/2022
37
38
Preparation of
Conditions of Contract
39
13
02/08/2022
40
41
42
14
02/08/2022
43
44
45
15
02/08/2022
Particular Conditions
46
47
48
16
02/08/2022
49
50
Responsibilities of the
Main Parties
51
17
02/08/2022
Clause 1 - General
Provisions and
General Issues
52
Definitions
53
Letter of Acceptance
Letter of Tender
Appendix to Tender
54
18
02/08/2022
55
56
Commencement Date
57
19
02/08/2022
Contract Price
Cost
58
Works
Site
59
60
20
02/08/2022
61
62
63
21
02/08/2022
64
65
66
22
02/08/2022
67
68
69
23
02/08/2022
Clause 2 –
The Employer
70
71
72
24
02/08/2022
73
74
Clause 3
The Engineer
75
25
02/08/2022
Instruct
Approve Determine
Variations
EOT Payments
Variations
Entitlements Certificates
Copy rights for Asel El Housan 76
76
Duties
Inspection monitoring
Test Check
RFI meetings
Examine Correspondences
Copy rights for Asel El Housan 77
77
Authorities
Approve Determine
Certify Instruct
Consent Correspondences
Request Notify
Copy rights for Asel El Housan 78
78
26
02/08/2022
Authorities
The Engineer shall be deemed to act on behalf
of the Employer
79
80
81
27
02/08/2022
The Contractor
The Engineer does not
confirms an Oral
contradict within 2 days
instruction within 2
of receipt
days
82
83
Clause 4
The Contractor
84
28
02/08/2022
85
86
87
29
02/08/2022
88
89
90
30
02/08/2022
91
Contractor shall:
Satisfy himself as to the suitability and
availability of access to the Site;
bears all the costs and risks associated with
access.
92
DAB
93
31
02/08/2022
94
95
Clause 5
Nominated
Subcontractor
96
32
02/08/2022
97
98
99
33
02/08/2022
The Design-Build
Responsibility
100
Clause 5
Design
101
Yellow Book
102
34
02/08/2022
Contractor’s Obligations
103
104
Contractor’s Documents
105
35
02/08/2022
106
Silver Book
107
Contractor’s Obligations
108
36
02/08/2022
Contractor’s Obligations
109
Contractor’s Obligations
110
111
37
02/08/2022
Contractor’s Documents
112
113
Management of
Projects
114
38
02/08/2022
Clause 6
Staff and Labour
115
General
116
General
117
39
02/08/2022
General
118
General
119
120
40
02/08/2022
Clause 7
Plant, Materials and
Workmanship
121
Summery
122
7.3: Inspection
123
41
02/08/2022
124
125
126
42
02/08/2022
7.4: Testing
127
7.5: Rejection
Termination
Pass
Re-do the work Retest
Deduction
Failed
Copy rights for Asel El Housan 128
128
Termination
Deduction
129
43
02/08/2022
Clause 8
Commencement,
Delays and
Suspension
130
28d 7d
Project Execution
42d Max. Time for Completion – 8.2
Issuance of
LOA 1.1.1.3 Commencement
Date – 8.1
Copy rights for Asel El Housan 131
131
28d 21d
Notice to
Commence Programme Comments
132
44
02/08/2022
133
134
EOT
Procedure
135
45
02/08/2022
Preparation
of Claim
136
Claim
Substantiation
137
138
46
02/08/2022
Work Suspension
EOT
Prolongation Costs
Copy rights for Asel El Housan 139
139
140
Advance Warning
Sub-Clause 8.4 of
2017 Edition
141
47
02/08/2022
142
143
144
48
02/08/2022
Clause 12 –
Measurement and
Evaluation
145
Measurement
146
147
49
02/08/2022
148
149
150
50
02/08/2022
151
Clause 13 –
Variations and
Adjustments
152
153
51
02/08/2022
Request for a
Instruction
proposal
154
155
156
52
02/08/2022
Definition
157
changes to the
quantities of any item of
work Any changes of the
form, quality or quantity
of the Works that may
Definition be necessary or it shall
be appropriate to
omission of any work complete the works
unless it is to be carried
out by others
Copy rights for Asel El Housan 158
158
159
53
02/08/2022
160
Contractor’s to
Further test
search
Copy rights for Asel El Housan 161
161
Value Engineering
162
54
02/08/2022
Value Engineering
163
Value Engineering
164
General Principle
Based on
BOQ Rate New Rate
BOQ Rate
165
55
02/08/2022
166
Provisional Sum
167
Provisional Sum
168
56
02/08/2022
Daywork
It should be for
Minor Incidental
OR
works nature
169
Daywork
Material
170
Other Resources
171
57
02/08/2022
Daywork
172
173
174
58
02/08/2022
Clause 14 – Contract
Price and Payment
175
176
Advance Payment
177
59
02/08/2022
178
179
Whichever is later
Copy rights for Asel El Housan 180
180
60
02/08/2022
Construction Contract
Progress payment
On stages payment
quantities of work
The Contractor will
executed,
submit a payment
applying the unit rates
whenever the stage is
and prices from the
completed
BOQ
181
182
183
61
02/08/2022
184
185
186
62
02/08/2022
187
188
Delayed Payment
189
63
02/08/2022
Outstanding balance
First 50% of retention
for retention money
money shall be
shall be certified
certified after the issue
promptly after the
of the Taking Over
expiry of the Defects
Certificate
Notification Period
190
191
192
64
02/08/2022
193
194
195
65
02/08/2022
196
197
198
66
02/08/2022
199
200
201
67
02/08/2022
Project Closure
202
Tests
203
Tests on Completion
204
68
02/08/2022
205
206
Permanent
Deduction Test to be Test
repeated Failed
11.4 Failure to
Remedy Defects
Test
Employer to carry pass
Deduction Termination
out the works
Copy rights for Asel El Housan 207
207
69
02/08/2022
Contractor’s Obligations
It is the responsibility of the Contractor to
carry out the Tests on Completion. Before the
Tests are carried out, the Contractor must
provide the as-built drawings and operations
and maintenance manuals.
In accordance with the Specification and in
sufficient detail for the Employer to operate,
maintain, dismantle, reassemble, adjust and
repair this part of the Works
Copy rights for Asel El Housan 208
208
Contractor’s Obligations
209
Contractor’s Obligations
210
70
02/08/2022
Delayed Tests
If the Employer unduly delays the Tests on
Completion then the provisions of Sub-Clause
9.2 or Sub-Clause 7.4 or 10.3 apply and the
Contractor may be entitled to additional time
and costs.
The Contractor will give notice to the
Engineer under Sub-Clause 7.4 and follow the
Sub- Clause 20.1 procedure to claim for an
extension of time and an additional payment
Copy rights for Asel El Housan 211
211
Delayed Tests
212
Delayed Tests
213
71
02/08/2022
Retesting
If the Works do not pass the Tests on
Completion, the Engineer can reject the
Works and require the Tests to be repeated
214
Retesting
There is no limit set on how many times the
Works can be carried out
215
Tests After
Completion
216
72
02/08/2022
Procedure
217
Yellow Book
218
Yellow Book
219
73
02/08/2022
Yellow Book
220
Silver Book
221
Silver Book
222
74
02/08/2022
Silver Book
223
Silver Book
224
Procedure
225
75
02/08/2022
Notice
226
Notice
227
Yellow Book
228
76
02/08/2022
Delay
229
Delayed Tests
230
Delayed Tests
231
77
02/08/2022
232
If
• If the Works do not pass any or all the
1
Tests after Completion,
• There is a sum for such failure stated in
the Contract, and
• The Contractor paid the amounts during
the Defect Notification Period.
233
234
78
02/08/2022
The Contractor
The Contractor will
proposed
be instructed by the
modification or
2
The Contractor Employer
will
adjustment
remain liable to carry
such modification
The Contractor will The Employer will
do the modification grant access to the
or adjustment facility
235
236
237
79
02/08/2022
Clause 10
Employer’s Taking
Over
238
239
240
80
02/08/2022
241
242
243
81
02/08/2022
Clause 11
Defect Notification
Period
244
TOC
10.1 Notifying of
defects –
11.1(b)
Copy rights for Asel El Housan 245
245
246
82
02/08/2022
247
248
249
83
02/08/2022
250
251
Recover from
The Employer the Contractor
Do the work;
can; the Employer’s
full costs
252
84
02/08/2022
Maximum 2 years
253
Termination
254
255
85
02/08/2022
Performance Certificate
To be issued
256
Suspension and
Termination
257
Clause 15 &16 –
Suspension and
Termination
258
86
02/08/2022
259
260
261
87
02/08/2022
262
263
264
88
02/08/2022
substantially fails to
fails to provide his financial
perform his
arrangements
obligations
265
266
For each of the above events, the Contractor may give 14 days’
notice to the Employer of termination; except that he may give
notice of immediate termination for (2) and (3).
267
89
02/08/2022
268
269
270
90
02/08/2022
271
272
273
91
02/08/2022
274
275
276
92
02/08/2022
277
278
279
93
02/08/2022
280
281
282
94
02/08/2022
283
284
remedying, at its
Works and own risk and cost,
Goods any damage for
which it is
responsible
Copy rights for Asel El Housan 285
285
95
02/08/2022
286
287
Notice to the
Loss or damage
Engineer
288
96
02/08/2022
289
290
291
97
02/08/2022
292
Clause 18–
Insurance
293
294
98
02/08/2022
295
Contractor’s Equipment
296
297
99
02/08/2022
298
299
Clause 19 –
Force Majeure
300
100
02/08/2022
301
302
Notice to the
Force Majeure
Engineer
303
101
02/08/2022
304
305
306
102
02/08/2022
Clause 20
Claims, Disputes
and Arbitration
307
Contractor’s Claim
308
309
103
02/08/2022
310
Background of Dispute
Resolution
311
312
104
02/08/2022
• Language.
• Experienced in the field.
• Nationality.
• Will be free.
313
Construction Plant
Harmonised EPC/Turnkey
DBO
314
Upon Agreement of
If the Parties or one of
the Parties
them failed to comply
If the Board didn’t
with the DAB
comply with the DAB
Agreement
Agreement Conditions
315
105
02/08/2022
DAB Payment
316
• Retainer fee
• Being available on 28 days’ notice
• Becoming and remaining conversant with
the Project requirements.
• The office and overhead expenses.
• Daily fee for preparing reports and ….
• Reimbursement of reasonable costs
• Reimbursement of taxes
Copy rights for Asel El Housan 317
317
318
106
02/08/2022
DAB Mechanism
319
• The Referral
• Site Visit
• The Response
• The Hearing
• The Decision
320
Amicable Settlement
321
107
02/08/2022
Arbitration
322
323
The Rules of
Language Place
Arbitration
ICC
Appendix to
Tender
Copy rights for Asel El Housan 324
324
108
02/08/2022
325
Differences between
1987 Red Book and
1999 Construction
Contract
326
327
109
02/08/2022
328
329
330
110
02/08/2022
331
332
333
111
02/08/2022
334
335
336
112
02/08/2022
337
338
Differences between
First Edition 1999 and
Second Edition 2017
339
113
02/08/2022
340
341
342
114
02/08/2022
343
344
• Contractor’s Risks
• CV System
• Engineer’s Representative
• Exceptional Events
• Joint Venture Undertaking
• Key Personnel
• Non-Performance Damages
• QM System
• Schedule of Performance Guarantee
345
115
02/08/2022
346
347
348
116
02/08/2022
349
Other Provisions
350
351
117
02/08/2022
352
Thank You
Asel El Housan
B.Sc., MBA, Dipl PM, ACIarb,
Arbitrator, CMC Certified
Mediator, Expert Witness
FIDIC Certified Trainer
FIDIC Affiliate member
FIDIC TG9 Member
Asel.Housan@aehconsultancy.com
AEH Consultancy
+44 7427 668859
+971 50 446 8548
Copy rights for Asel El Housan 353
353
118