COMMENT RESOLUTION SHEET (CRS)

CLIENT M/s Oil & Natural Gas Corporation Ltd. CLIENT JOB NO 9655
CLIENT PMC M/s Triune Energy Services Pvt. Ltd. SOPAN JOB NO 21007
LSTK CONTRACTOR M/s Sopan O&M Company Pvt. Ltd. DATE 30-06-2023
PROJECT Construction Of Early Production System At Kasomarigaon, Jorhat Asset
DOC NAME Purchase Specification for Closed Drain Pump
DOC NO KSMG-EPS-ME-PS-CDR-A-017

Reference
Sr.
Clause COMMENT/ OBSERVATION RESOLUTION/ ACTION
No.
No.
Rev 1
Cover
1. Pump Supplier Name & PO No. Noted & Incorporated
Page
i) Vendor to summarize all the instruments being
Index supplied along with this pump. Kindly confirm
2.
Sheet whether the level transmitter mentioned at page
14 of 31 is being supplied by the pump vendor.
Index ii) Process P&ID no. along with revision no. is also
3. Noted & Incorporated
Sheet to be mentioned somewhere in this document.
iii) M/s SOPAN is to confirm that requirement of
Index
4. instruments is as per project tender as well as Confirmed
Sheet
API code requirements.
Contractor has not submitted rev-3 datasheet of
Page No. pump for review. Process department has latest Rev.3 datasheet has been submitted &
5.
8 of 31 reviewed rev-02 Data sheet, and in this PS latest approved in Code-2
rev is attached rev-3 without CRS of rev-2.
Page No.
6. Kindly furnish Noted & furnished.
10 of 31
Page No. Relative density or specific gravity should be
7. Petrokem
10 of 31 0.909, recheck and update.
As per TBP, pumping temp. is considered 10-50
Page No. degC & in process calculation report hydraulics
8. Petrokem
10 of 31 has been done by taking 30 degC, contractor to
remove the inconsistency as required.
Page No.
9. Mention normal flow rate. Petrokem
10 of 31
Page No.
10. Pump efficiency curve to be submitted by vendor
10 of 31
Page No.
11. Min. is 8 degC and max is 40degC Petrokem
10 of 31
Page No.
12. Space Heater Requirement? 240V, 1P, 50Hz
10 of 31
Page No.
13. Kindly check
10 of 31
Page No.
14. Kindly check with API
11 of 31
15. Page No. Kindly furnish ASTM designation
COMMENT RESOLUTION SHEET (CRS)
CLIENT M/s Oil & Natural Gas Corporation Ltd. CLIENT JOB NO 9655
CLIENT PMC M/s Triune Energy Services Pvt. Ltd. SOPAN JOB NO 21007
LSTK CONTRACTOR M/s Sopan O&M Company Pvt. Ltd. DATE 30-06-2023
PROJECT Construction Of Early Production System At Kasomarigaon, Jorhat Asset
DOC NAME Purchase Specification for Closed Drain Pump
DOC NO KSMG-EPS-ME-PS-CDR-A-017

Reference
Sr.
Clause COMMENT/ OBSERVATION RESOLUTION/ ACTION
No.
No.
11 of 31
As per 02-TS-674, Supplier shall state in the offer
Page No. its recommendations for long term storage (up to
16.
13 of 31 12 months) for both indoor and open air storage
in a marine/humid environment.
Page No. Is this level transmitter in pump vendor's scope?
17.
14 of 31 Kindly confirm
LSTK to include below documents in PS:
Page No.
18. 1) Pump Performance curves duly marked with
15 of 31
duty points
Page No. 2) Kindly include 02-TS-610 Spec. of Centrifugal
19.
15 of 31 Pumps Process Service.
Page No.
20. 3) Guarantee Points
15 of 31
Page No.
21. 4) Deviation list (if any)
15 of 31
Page No. 5) P&ID with scope demarcation between Pump
22.
15 of 31 vendor and LSTK
Page No.
23. 6) DCI List
15 of 31
Page No.
24. 7) Painting Specification
15 of 31
Page No. 8) Electrical & Instrumentation Design Basis /
25.
15 of 31 Standard Spec
Page No.
26. Note to be updated as per vendor data
16 of 31
Page No.
27. Kindly indicate
16 of 31
The shut off pressure is given 3.7 kg/cm2g in TBP,
Page No. but as per process calculation report, Shut off
28.
16 of 31 pressure is not calculated out to be 3.5 kg/cm2g.
Check and update
Space Heater Required for all Motors as per
Page No.
29. Design Basis. Deviation if any shall be raised for
21 of 31
consideration.
30. Page No. Since it is a Flameproof Motor,
21 of 31 1. Contractor to ensure Cable Size shall be in
COMMENT RESOLUTION SHEET (CRS)
CLIENT M/s Oil & Natural Gas Corporation Ltd. CLIENT JOB NO 9655
CLIENT PMC M/s Triune Energy Services Pvt. Ltd. SOPAN JOB NO 21007
LSTK CONTRACTOR M/s Sopan O&M Company Pvt. Ltd. DATE 30-06-2023
PROJECT Construction Of Early Production System At Kasomarigaon, Jorhat Asset
DOC NAME Purchase Specification for Closed Drain Pump
DOC NO KSMG-EPS-ME-PS-CDR-A-017

Reference
Sr.
Clause COMMENT/ OBSERVATION RESOLUTION/ ACTION
No.
No.
accordance with project requirements &
approved cable sizing document.
2. Contractor to ensure suitably sized Exd Cable
Glands shall be included.
Page No.
31. Unused cable entry shall be supplied with
21 of 31
Flameproof blanking Plugs.

Page No. Refer Comments on Motor Data Sheet, Space


32.
23 of 31 Heater Required
Kindly add
Page No. Prepared by
33.
30 of 31 Checked by
Approved by