Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 2

HOT WORK PRE-INSPECTION CHECKLIST

TRAIN 3 OF WARA PRESSURE MAINTENANCE PROJECT. EF- 1945,


CONTRACT NO : 17052048

Location: -------------------------------- Date: -----------------------------------

S.No Concerns Inspections YES NO N/A

Is the welder Qualified to Welder Qualification Checked


1.
the job

Awareness to KOC.SA.021 Checked training Records


2.
for welding and cutting
Fire Protection Enough fire Protection measures like
measures, PPE, work 1. Removal of flammable substances from site?
3.
location, Suitability to 2. Ventilation is provided?
work, workforce
3. PPE appropriate?
confession on safety of
the area to work, HSE & 4. SIMOPS which may lead to fire avoided?
Construction site 5. Is the welding booth safe enough for the task to be
Representative’s carried out?
inspection and 6. Enough safe measures for acetylene usage?
Confession on Suitability 7. Leak tests on torches done?
of the work location prior 8. Hoses were properly colour coded?
to start of the work 9. Flash back system Functional?
10. Correct torches and nozzles were selected as per
grade of work and manufacturer guidelines?
11. Oxygen is closed while torch was lit?
12. Welding / cutting torches handles as per 5.2.7 of KOC
SA.021?
PPE (as per KOC.SA.021 5.2.8)
1. Cotton cover all with approved aprons, sleeves,
leggings are available and worn?
2. Is PPE made up of non-ignitable material?
Work Site Supervisor
1. Is he competent to the job?
2. Has taken HOT PERMIT to carry job and available
onsite associated with JSA, TBT?
3. Fire extinguisher and gas monitors were available on
the area?
4. Is he remaining onsite throughout the job and stops it
when he needed to leave as per PTW
Procedure?
5. Trained Fire watcher is available and competent?
HOT WORK PRE-INSPECTION CHECKLIST
TRAIN 3 OF WARA PRESSURE MAINTENANCE PROJECT . EF 1945,
CONTRACT NO : 17052048

Location: -------------------------------- Date: -----------------------------------

Metal Arc Welding as Per 5.4 of KOC.SA.021


1. Convenient and quick electrical disconnection was
provided?
2. The insulation of cables, electrode holders, plugs and
sockets were in good condition ensuring adequate current
carrying capacity to conductor?
3. The welding Equipment is having KOC Clearance
certificate from controlling team and daily and
periodical?
4. The stationary transformer or generator is equipped
with a power switch for Power isolation in case of
emergency?
5. Polarity equilibrium maintained whenever multiple
welders using same welding machine?
6. Adequate Ventilation and suitable breathing apparatus
is providing while working in a confined space?
7. Presence of material that evolve toxic fumes or
flammable gases such as paints, thinners,
coatings,oils,grease,chemical,galvanized metals, zinc,
bronze and manganese steel etc.?

During our onsite JOB Safety Analysis we found that the area is safe to work. Yes / No
Needed following improvements before starts o the work.
Remarks:

NAME
Area HSE
Designation Work Site Supervisor Permit Applicant Representative
Company

The work environment to carry out the mentioned HOT Work is safe. Yes / No

No Needs Further Improvement:

Welder name & Signature

You might also like