FORMULAES USED

 To find the number of days required to complete the work

Quantity
No. of days = labour output X no . of teams

Here, quantity = quantity of work

Labour output = quantity of work that a team can do per day

No. of teams = number of teams required to complete the work

No. of days = number of days required to complete the work

 To calculate the formwork quantity = 2 ( l + b )

Where , l = length

b = breadth

 RCC quantity in slabs , beams & columns with the ratio of 1 : 1.5 : 3

1 1440
No. of cement bags required = Quantity x 5.5 x 50

1.5 1740
Quantity of fine Aggregate in tones = Quantity x 5.5 x 1000

3 1550
Quantity of coarse Aggregate in tones = Quantity x 5.5 x 1000

quantiy X 78.5
Quantity of steel = 1000

 To calculate the PCC quantity in foundation, flooring with the ratio of

1:4:8

1 1440
No. of cement bags required = Quantity x 13 x 50
4 1740
Quantity of fine Aggregate in tones = Quantity x 13 x 1000

8 1550
Quantity of coarse Aggregate in tones = Quantity x 13 x 1000

Quantity
 To calculate the number of bricks required = 0.002

NO. OF WORKERS ASSESSED IN EACH TEAM FOR VARIOUS

TYPES OF WORKS

SL.NO TYPE OF WORK SKILLED LABOUR SEMI - SKILLED UNSKILLED TOTAL WORKERS / TEAM
1 RCC 1 2 2 5
2 Formwork 4 3 3 10
Painting ,primer
3
& putty works 1 1 1 2

SHORTCUTS USED

Level 1 – ground floor

Level 2 – first floor

Level 3 – second floor

Level 4 – third floor

Level 5 – fourth floor

Level 6 – fifth floor

PART 1 – 1 to 4 flats
PART 2 – 4 to 8 flats