FIRST 250MMSCFD

TRAIN OF KM500
GAS TREATMENT
PLANT

059-T-001 Fire Water Tank CPSC- CATHODIC PROTECTION SUPPORT CLEAT

HAV-EXT-DC-FRM-XXXX

EXTERRAN - REVIEW STAMP

Proj. No.: 4996 P.O. No.: 89004388

DOCUMENT REVIEW CODES:


1 2
Approved & Accepted as Final. Approved & Accepted as
WORK may proceed. Marked. Revise & Re-Submit.
WORK may proceed.
3 4
Rejected & Returned. Revise Review NOT required. For
and Re-Submit. WORK shall information only. WORK may
NOT proceed. proceed.

Acceptance of this document by Exterran does not relieve the CONTRACTOR


or Supplier/Vendor of any responsibility for compliance with the terms and
conditions of the Contract/PO.
Name: Signature:
Date:

A 04.05.2023 ISSUED FOR APPROVAL MA ZU BO


REV. DATE REVISION STATUS PREPARED BY CHECKED BY APPROVED BY
TECHNICAL QUERY FORM

Document Code:HAV-EXT-DC-FRM-0012 Issue Date:06.03.2023 Rev.No:A Rev.Date: - Page No: 1/ 3


TECHNICAL QUERY FORM

Document Code:HAV-EXT-DC-FRM-0012 Issue Date:06.03.2023 Rev.No:A Rev.Date: - Page No: 2/ 3

Section 1(To be completed by Originator)


TQ No: Discipline: Mechanical
Description of Query (Define all attachments):

In the 059-T-001 Fire Water Tank


Mechanical project does not indicate any details of the
Cathodic Protection Support Cleat.
No fabrication has been made for the angle bracket and pad plate.

Documents Sketch
141-059-ME-DET-0050-001-0A
141-059-ME-DET-0050-002-0A
141-074-A-EL-DWG-0002_B installation of sacp
141-074-A-EL-GAD-0002-C layout for sacp tank
Mail

Deviation: Query: Effect: Urgent:


Proposed Action (Define all attachments):
If you approve, we would like to fabricate attach sketch.
Effect on Cost: NO Effect on Delivery: YES
Effect on Quality:       Effect on Weight: 219.8 Kg
Requested By: (Name & Position) Signature: Date:
Mehmet ATABAY 04.05.2023
Section 2 (To be completed by Company)
Comments / Recommendations by Responsible:
     

Section 3 (Decision)
Accept: Accept: (with comments) Reject: Clarify
Sign Off Name: Signature: Date:
Responsible Engineer            
Construction Manager            
Site Manager            
Project Director            
NOTE: Only the applicable signatures are required