Professional Documents
Culture Documents
Method Statement For Gas System: Kingsville at Kallang Way
Method Statement For Gas System: Kingsville at Kallang Way
METHOD STATEMENT
FOR GAS SYSTEM
Page 1
KINGSVILLE @ KALLANG WAY
1. INTRODUCTION
2. SCOPE OF WORKS
3. MATERIAL
4. PIPE INSTALLTION & TESTING
Page 2
KINGSVILLE @ KALLANG WAY
1. Introduction
This method statement explains about the installation and testing of Gas pipe
works.
2. Scope of work
The scope of works for gas pipe installation above ground &underground are as
follows;
Obtain relevant permits from Main Contractor’s Safety Department
Mobilization of Machineries/Equipment
Demobilization of Machineries/Equipment’s
3. Material
(b) Ball valves –All brass ball valves complying with BS EN 331.
(a) Pipes and fittings – (i) API pipes and fittings - Welded joints.
(ii) GI pipes and fittings – Threaded joints.
(iii) PE pipes and fittings –Electro Fusion joints.
Page 3
KINGSVILLE @ KALLANG WAY
(b) The pipe shall be laid with a fall gradient of 10mm in 2 m to the main, if
the Relative levels will allow. Where this is not practicable, a syphon
should Be provided for the removal of condensate from the lowest point
of the Pipe, the pipe having a fall to this point from both directions.
Page 4
KINGSVILLE @ KALLANG WAY
(e) A surface box and ductile cover to BS 5834 shall be placed over the
siphon Standpipe and service valve.
(f) After the pipe had been laid, electronic markers have to be attached to all
tees, bends and at 30 meters apart along the pipeline; these markers are
for future locating of the pipeline.
(g) A layer of quarry dust has to be backfill up to 300mm above the pipe,
follow by a strip of approved PVC protection strip.
(h) The PE pipe shall end with a stud flange to connect to the API pipe.
(a) All pipes laid will have to be pigged to remove debris in the pipes.
(b) One end of the pipe will be inserted with a pig and blanked off;
compressed air will be introduced to push the pig through the pipes.
(c)The other end of the pipes will have to be left opened to allow debris
and the pig to exit from it.
(c) The air pressure in the pipes shall be raised to the test pressure of 140kpa
Page 5
KINGSVILLE @ KALLANG WAY
(d) The pressure shall not be any fall in the test, After period of not less than
10 minutes
(g) Witness by Consultant /RE/RTO for the tested piping before releasing air
pressure.
Main activities
Materials inspection by RTO and representative from Main Contractor to be
cleared before it is allowed to be used for installation.
Marking out of Pipe Routing on Wall and Soffit in accordance to the
Approved Shop Drawings.
Installation of Pipe: Galvanised Iron (GI) Pipe and American Petroleum
Institute (API) Pipe.
Hot Work – Cutting of API Pipe and Welding of API Joint.
100% radiography examination (X-ray) for API pipe routing in accordance
to API 1104 Standard.
Air Pressure Testing for Gas Pipe Routings.
Painting and Labelling works.
Jacketing of API Gas Pipe Routings within false ceiling spaces.
API Pipes within false ceiling spaces (e.g. lift lobbies, false ceiling) shall
be boxed-up with sheet metal sleeve, as known as Jacketing in the industry.
Ball valve shall be installed at each dropper point at kitchen.
Check the position of pipe routing layout from approved drawing.
Use the pipes and fittings that are approved by the Authority and
Consultants as per submitted approved samples.
Preparation of all needful tools and materials.
Using a marker, mark the route of the pipe on the slab soffit as per
approved drawing.
Using a drill and drill bit of 10mm, drill the ceiling to a depth of 40mm of
Page 6
KINGSVILLE @ KALLANG WAY
the marked position. Always hang up the electrical cables to prevent others
from tripping on the wire.
Mount the wall plug into the ceiling.
Tightened a galvanized iron threaded/stud rod to the wall plug and to one
end of the rod.
Tightened the other end of the rod to the bracket.
For every two to three meters of API pipe routing, install a bracket.
After all the brackets are installed, ensure the pipelines are straight for
smooth installation of API pipe.
Measure the API pipe and cut according to the required dimensions.
Install the API pipe to fit onto the brackets
Page 7
KINGSVILLE @ KALLANG WAY
There will be three types of welding method to be used for this project,
namely: 1) Fillet Welds, 2) Groove Joint Design and 3) Welding
Sequence as shown below as Figure 1:
Page 8
KINGSVILLE @ KALLANG WAY
Page 9
KINGSVILLE @ KALLANG WAY
Page 10
KINGSVILLE @ KALLANG WAY
Page 11
KINGSVILLE @ KALLANG WAY
Page 12
KINGSVILLE @ KALLANG WAY
Page 13
KINGSVILLE @ KALLANG WAY
numbers 0-1, 1-2, etc., or letters A-B, B-C, ... etc., shall be placed on the
marked area to indicate the segment in the film.
8 Project No., Line No., Drawing No. etc. as per the requirement of client
prepared in a lead strip shall be placed 3mm away from along the sides of the
weld. To determine the sensitivity of radiograph a wire type penetro-meter (IQI)
shall be placed across on the source side of the weld. When IQI placed on the
film side a lead letter F shall be paste on the IQI. IQI shall be selected
according to the specification requirement.
9 Type I or Type II film sandwiched with lead screens and loaded in a cassette
(film holder) shall be placed (should cover the area of interest, lead markers
and penetrometer) on the weld segment prepared for radiography testing.
10 To minimize the Geometric Un-sharpness Source-to-film distance shall be as
far as possible as recommended in the specification.
12 Exposure time Calculation shall be based on the part thickness, Source-to-film
distance and curie strength used.
13 Source shall be kept "ON" for particular exposure time by driving the source
from a remote control type source container. After completion of the exposure
source shall be drive back to the source container.
14 Now the exposed film is ready for processing (film shall be handled with great
care
When loading the film and processing the film).
The exposed films shall be processed in accordance with the conditions
recommended by the film and chemical manufacturer to obtain the selected
film quality. Particular attention shall be paid to temperature development time
and washing time to obtain a radiograph, which shall be free from defects due
to processing or other causes that would interfere with interpretation.
TRANSPORTATION OF RADIATION SOURCE:
Transportation of Radioactive material (Projector) to the Site:
o The inspector shall carry the projector and related instruments by hand trolley to
the location required.
o Projector should be carried in this way due to relative high radiation level, which
high radiation exists at the surface of projector. At no time should the projector
be carried or held against the body or carried at shoulder level.
o Caution shall be exercised such that projector is not dropped in any way while
moving it, particularly when carrying it up ladder, working at height.
o The route to be taken from the storage pit to the exposure site will be checked by
the radiographer carrying the projector.
Page 14
KINGSVILLE @ KALLANG WAY
o This placard shall be displayed on the left and right side of the vehicle.
o L6 license holder is required to monitor the transporting of radioactive material.
o The projector shall be secured during transport in a lead lined box located in the
rear of the vehicle positioned at all times in such a way that a maximum distance
between the driver and his assistant and the source is maintained.
o At no time shall non-radiation worker be carried in the same vehicle when
transporting radioactive materials.
o The vehicle will be surveyed on its outside surfaces to ensure that radiation
levels in excess 0f 2.0 mRem/hour are not present.
o Should radiation levels exceed the stipulated maximum value, the vehicle shall
be posted on each side with additional radiation sign which shall state:
“CAUTION: RADIATION AREA – DO NOT REMAIN UNNECESSARY
NEAR THIS VEHICLE”.
Page 15
KINGSVILLE @ KALLANG WAY
EMERGENCY PROCEDURES:
In the event of an emergency for leaking source or radiation mishap, the
Radiation safety officer or "L6 License holder" shall inform be informed.
Emergency Not Affecting Radiographic Exposure Device:
NOTE: Emergencies in this category are those such as fire, flood, personal
accidents or similar incidents in areas adjacent to the radiographic operations,
but which do not immediately cause danger to the exposure device.
Return the source to its shielded position within the exposure device.
Disconnect the source extension tube and control cables, insert the
safety plugs, lock the projector and remove it from the danger area.
If necessary, return the source to the isotope storage pit.
Once the exposure device has been made secure, the restricted
radiation areas should be made free by removing the rope barriers
and the radiation warning signboard
If radiographic personnel are the only one present at the time of the emergency,
they should immediately notify the radiation safety officer.
(b) Pipes from underground to riser and riser pipes shall be tested to 70kPa.
Pressure gauge. If there is no fall in pressure as registered on the pressure
gauge at the end of 30 minutes, the system is considered satisfactory. It
should be followed by a second test of pressure 300mm water gauge for
duration of 10 minutes.
(c) Pipes from riser to equipment shall be tested to 300mm water gauge using
a manometer. The air pressure shall be raised to 300mm wg and allowed to
stabilize for 1 minute before recording down the pressure. If there is no fall
in pressure at the end of 10 minutes, the system is considered satisfactory.
(d) For API pipes the testing medium shall be air, pressure at 70KPa for
duration of 30 minutes.
2. Prepare inspection form and drawing plan indicating the testing location.
3. All joints to be exposed for inspection during testing.
4. Open pipe ends shall be temporarily capped.
5. One of the pipe ends shall be installed with the testing kit, pressure gauge and
compressor pump.
6. Piping under testing shall be pumped with air to the require test pressure
stated.
7. Check for pressure drop by monitoring the calibrated pressure gauge / u-
gauge as required duration stated.
8. Upon testing satisfactory, witness by RTO for the tested piping before
releasing air pressure.
a) Installation of Jacketing/Box-up
Check the position of pipe routing layout from approved
drawing.
Use the materials that are approved by the Authority and
Consultants as per submitted approval sample.
After finished pipe work arranges metal jacketing require size.
Page 17
KINGSVILLE @ KALLANG WAY
Page 18