Professional Documents
Culture Documents
PSS Scopes For LSS
PSS Scopes For LSS
4. PSS
(i) Stage 1: Stage 1 PSS using “generic” modeling of the Facility (including but not
limited to the solar PV components), the SPP IF and the SPP Interconnector.
Description: Stage 1 PSS mainly verifies the impact on the existing Grid System
as well as proposes any mitigation measures, which can be analyzed based on
relevant information of the Facility already known at the point of time.
Submission: Final report of Stage 1 PSS (revised for compliance with the Grid
Owner’s recommendations) shall be submitted along with the RFP submission.
(ii) Stage 2: Stage 2 PSS using the actual modeling of the Facility (including but not
limited to the solar PV components), the SPP IF and the SPP Interconnector taking
into consideration the topology and converter type.
43
Technical Specifications for Transmission-Connected LSS I Appendix B
Submission: Final report of Stage 2 PSS (revised for compliance to the Grid
Owner’s recommendations) shall be submitted no later than sixty (60) days prior
to the Commencement Date for approval by the Grid Owner.
Both stages of the PSS shall include, but not limited to, the following scopes:
(i) Table 1: Scope of Stage 1 PSS
44
Technical Specifications for Transmission-Connected LSS I Appendix B
45
Technical Specifications for Transmission-Connected LSS I Appendix B
46
Technical Specifications for Transmission-Connected LSS I Appendix B
47
Technical Specifications for Transmission-Connected LSS I Appendix B
48
Technical Specifications for Transmission-Connected LSS I Appendix B
49
Technical Specifications for Transmission-Connected LSS I Appendix B
50
Technical Specifications for Transmission-Connected LSS I Appendix B
A copy of the Grid Code and TSRS can be obtained from the official portal of the
Commission. LSS Developer shall obtain the other specified standards for the PSS at
its own expense.
LSS Developers should take note that fifteen (15) business days are required for the
finalization of the terms and conditions of the non-disclosure agreement. The stamping
cost for the non-disclosure agreement shall be fully borne by the LSS Developer.
51
Technical Specifications for Transmission-Connected LSS I Appendix B
Prior to making a decision on the connection scheme and reinforcement, TNB may
request LSS Developer to clarify on its findings of the Stage 1 PSS and Stage 2 PSS.
TNB shall provide its decision on the connection scheme and reinforcement.
Submission of the final reports and simulation models in PSS®E for Stage 1 PSS and
Stage 2 PSS are compulsory for LSS Developer to receive final and unconditional
approval from TNB.
Submission of the final Stage 1 PSS and Stage 2 PSS reports and RFP to the
Commission is subject to the following conditions:
(a) the LSS Developer has received final and unconditional approval from the Grid
Owner; and
(b) the submission of the final Stage 1 PSS and Stage 2 PSS reports and RFP
must be accompanied by a letter evidencing that final and unconditional
approval from the Grid Owner as referred to in Section 4.5 (a) above has been
obtained.
For such case, the Stage 1 PSS report, as approved by the Grid Owner shall be valid
for three (3) years from the date of submission subjected to the following conditions:
(i) Same Connection Point / connection scheme / capacity;
(ii) Load levels at the vicinity of the studied site does not show major changes;
52
Technical Specifications for Transmission-Connected LSS I Appendix B
(iii) Generation plant-up within the vicinity of the studied site that may affect the
system stability; and
(iv) The adequacy of transmission facilities.
LSS Developer shall submit models of the LSS Plant to be connected to the Grid
System. At the minimum, the models shall represent the following behaviour and/or
control system for Stage 1 PSS and Stage 2 PSS:
53
Technical Specifications for Transmission-Connected LSS I Appendix B
54
Technical Specifications for Transmission-Connected LSS I Appendix B
55
Technical Specifications for Transmission-Connected LSS I Appendix B
application form shall be submitted together with the relevant information of the Facility,
SPP IF and SPP Interconnector to the following address:
56