BOBOT
NO DESKRIPSI QTY UNIT
PROGRESS LAST PROGRESS UP TO THIS PROGRESS THIS PROGRESS
04 DIRECT COST
4.01 WORKSHOP 1,00 lot 4,348% 46% 2,000% 46% 2,000% 0% 0,000%
4.02 WEIGHBRIDGE STATION 1,00 lot 0,510% 9% 0,046% 9% 0,046% 0% 0,000%
4.03 STERILIZER STATION 1,00 lot 6,155% 43% 2,646% 43% 2,646% 0% 0,000%
4.04 THRESHING STATION 1,00 lot 0,157% 71% 0,111% 71% 0,111% 0% 0,000%
4.05 PRESSING STATION 1,00 lot 34,219% 40% 13,756% 41% 14,197% 1% 0,442%
4.06 CLARIFICATION STATION 1,00 lot 12,938% 55% 7,175% 55% 7,175% 0% 0,000%
4.07 NUT & KERNEL 1,00 lot 3,644% 45% 1,636% 46% 1,659% 1% 0,024%
4.08 BOILER STATION 1,00 lot 6,110% 38% 2,349% 41% 2,477% 2% 0,128%
4.09 POWER HOUSE 1,00 lot 9,493% 59% 5,568% 59% 5,568% 0% 0,000%
4.10 WATER TREATMENT PLANT 1,00 lot 12,823% 47% 6,056% 47% 6,056% 0% 0,000%
INDIRECT COST
Contractor Services 1,00 lot 7,044% 46% 3,222% 46% 3,268% 1% 0,046%
Construction Services 1,00 lot 2,558% 46% 1,170% 46% 1,187% 1% 0,017%
Sundries 0,000%