LAPORAN MINGGUAN

Pekerjaan : Pekerjaan Penambahan Monitoring Panel ESKALATOR Terminal 3


Bandara Soekarno - Hatta
No SPP/ SPK : PJJ.14.01/01/02/2023/0164
Tanggal SPP/ SPK : 02/02/2023
Dep/ Instansi : Mechanical Facility Terminal 3 Tanggal : 2 Februari s/d 8 Februari
Pelaksana : PT. ARTA VICTORI ATMAJA Minggu ke :1
Last
NO URAIAN PEKERJAAN Volume Bobot This Progres
Progres
1 2 3 4 5 6
A Pekerjaan Persiapan 1 lot 2.19% 0.00% 0.24%
B Hardware
1 PLC (Logic Controller) 8 unit 10.79% 0.00% 0.0%
2 Modbus Analog Input Module 8 ch (4/20mA) 12 unit 12.54% 0.00% 0.0%
3 Modbus Analog Input Module 8 ch (PT 100) 12 unit 12.54% 0.00% 0.0%
4 Converter Serial to Ethernet 8 unit 5.01% 0.00% 0.0%
5 Switch Manageable 24 port 3 unit 5.18% 0.00% 0.0%
6 Rack Wallmount 4U 3 unit 1.62% 0.00% 0.0%
7 MCB 1P 16a 3 pcs 0.07% 0.00% 0.0%
8 Stop Kontak 3 Lubang 3 pcs 0.03% 0.00% 0.0%
9 Pipa Conduit 325 pcs 1.73% 0.00% 0.0%
10 Panel With Accesoris 8 unit 9.76% 0.00% 0.0%
11 Power Supply 24VDC 8 unit 3.23% 0.00% 0.0%
12 Kabel NYAF 1x1,5 mm 12 roll 1.39% 0.00% 0.0%
13 Kabel NYY 3x2,5 mm (100m) 6 roll 3.42% 0.00% 0.0%
14 Kabel UTP Cat 6 (300m) 3 roll 2.12% 0.00% 0.0%
15 Accesoris (Dynabolt skun kabel) 8 set 2.29% 0.00% 0.0%
C Pekerjaan dan Jasa
1 Assembling dan Download Program 1 lot 6.79% 0.00% 0.0%
2 WEB Base Development 1 lot 5.38% 0.00% 0.0%
3 Instalasi dan Konfigurasi Switch Manageable 1 lot 0.61% 0.00% 0.0%
4 Penarikan Kabel NYY 3x2,5 1 lot 2.91% 0.00% 0.0%
5 Penarikan Kabel UTP 1 lot 3.66% 0.00% 0.0%
D TESTING & COMMISIONING
1 Testing & Site Accaptence Test (Commisioning) 1 lot 5.88% 0.00% 0.0%
2 Training 1 lot 0.85% 0.00% 0.0%

Jumlah Seluruh Pekerjaan 100%


LAPORAN MINGGUAN
Pekerjaan : Pekerjaan Penambahan Monitoring Panel ESKALATOR Terminal 3
Bandara Soekarno - Hatta
No SPP/ SPK : PJJ.14.01/01/02/2023/0164
Tanggal SPP/ SPK : 02/02/2023
Februari Dep/ Instansi : Mechanical Facility Terminal 3 Tanggal : 9 Februari s/d 15 Februari
Pelaksana : PT. ARTA VICTORI ATMAJA Minggu ke : 1
Bobot
NO URAIAN PEKERJAAN Volume Bobot Last Progres
Progres
7 1 2 3 4 5
0.24% A Pekerjaan Persiapan 1 lot 2.19% 0.24%
B Hardware
0.00% 1 PLC (Logic Controller) 8 unit 10.79% 0.00%
0.00% 2 Modbus Analog Input Module 8 ch (4/20mA) 12 unit 12.54% 0.00%
0.00% 3 Modbus Analog Input Module 8 ch (PT 100) 12 unit 12.54% 0.00%
0.00% 4 Converter Serial to Ethernet 8 unit 5.01% 0.00%
0.00% 5 Switch Manageable 24 port 3 unit 5.18% 0.00%
0.00% 6 Rack Wallmount 4U 3 unit 1.62% 0.00%
0.00% 7 MCB 1P 16a 3 pcs 0.07% 0.00%
0.00% 8 Stop Kontak 3 Lubang 3 pcs 0.03% 0.00%
0.00% 9 Pipa Conduit 325 pcs 1.73% 0.00%
0.00% 10 Panel With Accesoris 8 unit 9.76% 0.00%
0.00% 11 Power Supply 24VDC 8 unit 3.23% 0.00%
0.00% 12 Kabel NYAF 1x1,5 mm 12 roll 1.39% 0.00%
0.00% 13 Kabel NYY 3x2,5 mm (100m) 6 roll 3.42% 0.00%
0.00% 14 Kabel UTP Cat 6 (300m) 3 roll 2.12% 0.00%
0.00% 15 Accesoris (Dynabolt skun kabel) 8 set 2.29% 0.00%
C Pekerjaan dan Jasa
0.00% 1 Assembling dan Download Program 1 lot 6.79% 0.00%
0.00% 2 WEB Base Development 1 lot 5.38% 0.00%
0.00% 3 Instalasi dan Konfigurasi Switch Manageable 1 lot 0.61% 0.00%
0.00% 4 Penarikan Kabel NYY 3x2,5 1 lot 2.91% 0.00%
0.00% 5 Penarikan Kabel UTP 1 lot 3.66% 0.00%
D TESTING & COMMISIONING
0.00% 1 Testing & Site Accaptence Test (Commisioning) 1 lot 5.88% 0.00%
0.00% 2 Training 1 lot 0.85% 0.00%

0.24% Jumlah Seluruh Pekerjaan 100%

Jakarta, 25 November 2022


ASSISTANT MANAGER OF PT. Jakarta Process Automation
MECHANICAL FACILITY TERMINAL 3

MOKHAMMAD RIFAI DIMAS ABHIARDANA


erminal 3

9 Februari s/d 15 Februari


1
This Bobot
Progres Progres
6 7 0.7 4.9
0.24% 0.48%

0.0% 0.00%
0.0% 0.00%
0.0% 0.00%
0.0% 0.00%
0.0% 0.00%
0.0% 0.00%
0.0% 0.00%
0.0% 0.00%
0.0% 0.00%
0.0% 0.00%
0.0% 0.00%
0.0% 0.00%
0.0% 0.00%
0.0% 0.00%
0.0% 0.00%

0.0% 0.00%
0.0% 0.00%
0.0% 0.00%
0.0% 0.00%
0.0% 0.00%

0.0% 0.00%
0.0% 0.00%

0.48%
LAPORAN MINGGUAN

PEKERJAAN PENAMBAHAN
MONITORING PADA PERALATAN AHU TERMINAL 3
BANDARA SOEKARNO-HATTA

PT. JAKARTA PROCESS AUTOMATION


NOMOR KONTRAK
PJJ.14.01/01/02/2023/0164
2 February 2023
LAPORAN MINGGUAN
Pekerjaan : PEKERJAAN PENAMBAHAN MONITORING PADA PERALATAN AHU TERMINAL 3
BANDARA SOEKARNO-HATTA
No SPP/ SPK : PJJ.14.01/01/02/2023/0164
Tanggal SPP/ SPK : 02/02/2023
Dep/ Instansi : Mechanical Facility Terminal 3 Tanggal : 2 Februari s/d 8 Februari
Pelaksana : PT. ARTA VICTORI ATMAJA Minggu ke :1

NO URAIAN PEKERJAAN Volume Bobot Last Progres This Progres Bobot Progres
1 2 3 4 5 6 7
A Pekerjaan Persiapan 1 lot 2.19% 0.00% 0.24% 0.24%

B Hardware
1 PLC (Logic Controller) 8 unit 10.79% 0.00% 0.0% 0.00%
2 Modbus Analog Input Module 8 ch 12.54%
(4/20mA) 12 unit 0.00% 0.0% 0.00%
Modbus Analog Input Module 8 ch
3 12 unit 12.54% 0.00% 0.0% 0.00%
(PT 100)
4 Converter Serial to Ethernet 8 unit 5.01% 0.00% 0.0% 0.00%
5 Switch Manageable 24 port 3 unit 5.18% 0.00% 0.0% 0.00%
6 Rack Wallmount 4U 3 unit 1.62% 0.00% 0.0% 0.00%
7 MCB 1P 16a 3 pcs 0.07% 0.00% 0.0% 0.00%
8 Stop Kontak 3 Lubang 3 pcs 0.03% 0.00% 0.0% 0.00%
9 Pipa Conduit 325 pcs 1.73% 0.00% 0.0% 0.00%
10 Panel With Accesoris 8 unit 9.76% 0.00% 0.0% 0.00%
11 Power Supply 24VDC 8 unit 3.23% 0.00% 0.0% 0.00%
12 Kabel NYAF 1x1,5 mm 12 roll 1.39% 0.00% 0.0% 0.00%
13 Kabel NYY 3x2,5 mm (100m) 6 roll 3.42% 0.00% 0.0% 0.00%
14 Kabel UTP Cat 6 (300m) 3 roll 2.12% 0.00% 0.0% 0.00%
15 Accesoris (Dynabolt skun kabel) 8 set 2.29% 0.00% 0.0% 0.00%

C Pekerjaan dan Jasa


Assembling dan Download
1 1 lot 6.79% 0.00% 0.0% 0.00%
Program
2 WEB Base Development 1 lot 5.38% 0.00% 0.0% 0.00%
Instalasi dan Konfigurasi Switch
3 1 lot 0.61% 0.00% 0.0% 0.00%
Manageable
4 Penarikan Kabel NYY 3x2,5 1 lot 2.91% 0.00% 0.0% 0.00%
5 Penarikan Kabel UTP 1 lot 3.66% 0.00% 0.0% 0.00%

D Testing dan Comissioning


Testing & Site Accaptence Test
1 1 lot 5.88% 0.00% 0.0% 0.00%
(Commisioning)
2 Training 1 lot 0.85% 0.00% 0.0% 0.00%

Jumlah Seluruh Pekerjaan 100% 0.24%

PT. ANGKASA PURA II PT. JAKARTA PROCESS AUTOMATION


PENGAWAS PELAKSANA PEKERJAAN

(SUPARYONO) (ROSARILA DWI JAYANT) (DIMAS ABHIARDHANA)


LAPORAN MINGGUAN
Pekerjaan : PEKERJAAN PENAMBAHAN MONITORING PADA PERALATAN AHU TERMINAL 3
BANDARA SOEKARNO-HATTA
No SPP/ SPK : PJJ.14.01/01/02/2023/0164
Tanggal SPP/ SPK : 02/02/2023
Dep/ Instansi : Mechanical Facility Terminal 3 Tanggal : 9 Februari s/d 15 Februari
Pelaksana : PT. ARTA VICTORI ATMAJA Minggu ke :2

NO URAIAN PEKERJAAN Volume Bobot Last Progres This Progres Bobot Progres
1 2 3 4 5 6 7
A Pekerjaan Persiapan 1 lot 2.19% 0.24% 0.24% 0.48%

B Hardware 0.00%
1 PLC (Logic Controller) 8 unit 10.79% 0.00% 0.0% 0.00%
2 Modbus Analog Input Module 8 ch 12.54%
(4/20mA) 12 unit 0.00% 0.0% 0.00%
Modbus Analog Input Module 8 ch
3 12 unit 12.54% 0.00% 0.0% 0.00%
(PT 100)
4 Converter Serial to Ethernet 8 unit 5.01% 0.00% 0.0% 0.00%
5 Switch Manageable 24 port 3 unit 5.18% 0.00% 0.0% 0.00%
6 Rack Wallmount 4U 3 unit 1.62% 0.00% 0.0% 0.00%
7 MCB 1P 16a 3 pcs 0.07% 0.00% 0.0% 0.00%
8 Stop Kontak 3 Lubang 3 pcs 0.03% 0.00% 0.0% 0.00%
9 Pipa Conduit 325 pcs 1.73% 0.00% 0.0% 0.00%
10 Panel With Accesoris 8 unit 9.76% 0.00% 0.0% 0.00%
11 Power Supply 24VDC 8 unit 3.23% 0.00% 0.0% 0.00%
12 Kabel NYAF 1x1,5 mm 12 roll 1.39% 0.00% 0.0% 0.00%
13 Kabel NYY 3x2,5 mm (100m) 6 roll 3.42% 0.00% 0.0% 0.00%
14 Kabel UTP Cat 6 (300m) 3 roll 2.12% 0.00% 0.0% 0.00%
15 Accesoris (Dynabolt skun kabel) 8 set 2.29% 0.00% 0.0% 0.00%

C Pekerjaan dan Jasa 0.00%


Assembling dan Download
1 1 lot 6.79% 0.00% 0.0% 0.00%
Program
2 WEB Base Development 1 lot 5.38% 0.00% 0.0% 0.00%
Instalasi dan Konfigurasi Switch
3 1 lot 0.61% 0.00% 0.0% 0.00%
Manageable
4 Penarikan Kabel NYY 3x2,5 1 lot 2.91% 0.00% 0.0% 0.00%
5 Penarikan Kabel UTP 1 lot 3.66% 0.00% 0.0% 0.00%

D TESTING & COMMISIONING 0.00%


Testing & Site Accaptence Test
1 1 lot 5.88% 0.00% 0.0% 0.00%
(Commisioning)
2 Training 1 lot 0.85% 0.00% 0.0% 0.00%

Jumlah Seluruh Pekerjaan 100% 0.48%

PT. ANGKASA PURA II PT. JAKARTA PROCESS AUTOMATION


PENGAWAS PELAKSANA PEKERJAAN

(SUPARYONO) (ROSARILA DWI JAYANT) (DIMAS ABHIARDHANA)


LAPORAN MINGGUAN
Pekerjaan : PEKERJAAN PENAMBAHAN MONITORING PADA PERALATAN AHU TERMINAL 3
BANDARA SOEKARNO-HATTA
No SPP/ SPK : PJJ.14.01/01/02/2023/0164
Tanggal SPP/ SPK : 02/02/2023
Dep/ Instansi : Mechanical Facility Terminal 3 Tanggal : 16 Februari s/d 22 Februari
Pelaksana : PT. ARTA VICTORI ATMAJA Minggu ke :3

NO URAIAN PEKERJAAN Volume Bobot Last Progres This Progres Bobot Progres
1 2 3 4 5 6 7
A Pekerjaan Persiapan 1 lot 2.19% 0.48% 0.19% 0.67%

B Hardware
1 PLC (Logic Controller) 8 unit 10.79% 0.00% 5.39% 5.39%
Modbus Analog Input Module 8 ch
2 12 unit 12.54% 0.00% 0.0% 0.00%
(4/20mA)
Modbus Analog Input Module 8 ch
3 12 unit 12.54% 0.00% 0.0% 0.00%
(PT 100)
4 Converter Serial to Ethernet 8 unit 5.01% 0.00% 0.0% 0.00%
5 Switch Manageable 24 port 3 unit 5.18% 0.00% 0.0% 0.00%
6 Rack Wallmount 4U 3 unit 1.62% 0.00% 0.0% 0.00%
7 MCB 1P 16a 3 pcs 0.07% 0.00% 0.0% 0.00%
8 Stop Kontak 3 Lubang 3 pcs 0.03% 0.00% 0.0% 0.00%
9 Pipa Conduit 325 pcs 1.73% 0.00% 0.0% 0.00%
10 Panel With Accesoris 8 unit 9.76% 0.00% 4.9% 4.88%
11 Power Supply 24VDC 8 unit 3.23% 0.00% 1.6% 1.61%
12 Kabel NYAF 1x1,5 mm 12 roll 1.39% 0.00% 0.7% 0.70%
13 Kabel NYY 3x2,5 mm (100m) 6 roll 3.42% 0.00% 1.7% 1.71%
14 Kabel UTP Cat 6 (300m) 3 roll 2.12% 0.00% 1.1% 1.06%
15 Accesoris (Dynabolt skun kabel) 8 set 2.29% 0.00% 1.1% 1.14%

C Pekerjaan dan Jasa 0.00%


1 Assembling dan Download 6.79%
Program 1 lot 0.00% 0.0% 0.00%
2 WEB Base Development 1 lot 5.38% 0.00% 0.0% 0.00%
Instalasi dan Konfigurasi Switch
3 Manageable 1 lot 0.61% 0.00% 0.0% 0.00%
4 Penarikan Kabel NYY 3x2,5 1 lot 2.91% 0.00% 0.0% 0.00%
5 Penarikan Kabel UTP 1 lot 3.66% 0.00% 0.0% 0.00%

D TESTING & COMMISIONING 0.00%


Testing & Site Accaptence Test
1 (Commisioning) 1 lot 5.88% 0.00% 0.0% 0.00%
2 Training 1 lot 0.85% 0.00% 0.0% 0.00%

Jumlah Seluruh Pekerjaan 100% 17.16%

PT. ANGKASA PURA II PT. JAKARTA PROCESS AUTOMATION


PENGAWAS PELAKSANA PEKERJAAN

(SUPARYONO) (ROSARILA DWI JAYANT) (DIMAS ABHIARDHANA)


LAPORAN MINGGUAN
Pekerjaan : PEKERJAAN PENAMBAHAN MONITORING PADA PERALATAN AHU TERMINAL 3
BANDARA SOEKARNO-HATTA
No SPP/ SPK : PJJ.14.01/01/02/2023/0164
Tanggal SPP/ SPK : 02/02/2023
Dep/ Instansi : Mechanical Facility Terminal 3 Tanggal : 23 Februari s/d 1 Maret
Pelaksana : PT. ARTA VICTORI ATMAJA Minggu ke :4

NO URAIAN PEKERJAAN Volume Bobot Last Progres This Progres Bobot Progres
1 2 3 4 5 6 7
A Pekerjaan Persiapan 1 lot 2.19% 0.67% 0.01% 0.68%

B Hardware
1 PLC (Logic Controller) 8 unit 10.79% 5.93% 0.0% 5.93%
Modbus Analog Input Module 8 ch
2 12 unit 12.54% 0.00% 0.0% 0.00%
(4/20mA)
Modbus Analog Input Module 8 ch
3 12 unit 12.54% 0.00% 0.0% 0.00%
(PT 100)
4 Converter Serial to Ethernet 8 unit 5.01% 0.00% 0.0% 0.00%
5 Switch Manageable 24 port 3 unit 5.18% 0.00% 0.0% 0.00%
6 Rack Wallmount 4U 3 unit 1.62% 0.00% 0.0% 0.00%
7 MCB 1P 16a 3 pcs 0.07% 0.00% 0.0% 0.00%
8 Stop Kontak 3 Lubang 3 pcs 0.03% 0.00% 0.0% 0.00%
9 Pipa Conduit 325 pcs 1.73% 0.00% 0.0% 0.00%
10 Panel With Accesoris 8 unit 9.76% 4.88% 0.0% 4.88%
11 Power Supply 24VDC 8 unit 3.23% 1.61% 0.0% 1.61%
12 Kabel NYAF 1x1,5 mm 12 roll 1.39% 0.70% 0.0% 0.70%
13 Kabel NYY 3x2,5 mm (100m) 6 roll 3.42% 1.71% 0.0% 1.71%
14 Kabel UTP Cat 6 (300m) 3 roll 2.12% 1.06% 0.0% 1.06%
15 Accesoris (Dynabolt skun kabel) 8 set 2.29% 1.14% 0.0% 1.14%

C Pekerjaan dan Jasa 0.00%


1 Assembling dan Download 6.79%
Program 1 lot 0.00% 0.0% 0.00%
2 WEB Base Development 1 lot 5.38% 0.00% 0.27% 0.27%
Instalasi dan Konfigurasi Switch
3 Manageable 1 lot 0.61% 0.00% 0.0% 0.00%
4 Penarikan Kabel NYY 3x2,5 1 lot 2.91% 0.00% 0.0% 0.00%
5 Penarikan Kabel UTP 1 lot 3.66% 0.00% 0.0% 0.00%

D TESTING & COMMISIONING 0.00%


Testing & Site Accaptence Test
1 (Commisioning) 1 lot 5.88% 0.00% 0.0% 0.00%
2 Training 1 lot 0.85% 0.00% 0.0% 0.00%

Jumlah Seluruh Pekerjaan 100% 17.98%

PT. ANGKASA PURA II PT. JAKARTA PROCESS AUTOMATION


PENGAWAS PELAKSANA PEKERJAAN

(SUPARYONO) (ROSARILA DWI JAYANT) (DIMAS ABHIARDHANA)


LAPORAN MINGGUAN
Pekerjaan : PEKERJAAN PENAMBAHAN MONITORING PADA PERALATAN AHU TERMINAL 3
BANDARA SOEKARNO-HATTA
No SPP/ SPK : PJJ.14.01/01/02/2023/0164
Tanggal SPP/ SPK : 02/02/2023
Dep/ Instansi : Mechanical Facility Terminal 3 Tanggal : 2 Maret s/d 8 Maret
Pelaksana : PT. ARTA VICTORI ATMAJA Minggu ke :5

NO URAIAN PEKERJAAN Volume Bobot Last Progres This Progres Bobot Progres
1 2 3 4 5 6 7
A Pekerjaan Persiapan 1 lot 2.19% 0.68% 1.42% 2.10%

B Hardware
1 PLC (Logic Controller) 8 unit 10.79% 5.93% 0.0% 5.93%
Modbus Analog Input Module 8 ch
2 12 unit 12.54% 0.00% 0.0% 0.00%
(4/20mA)
Modbus Analog Input Module 8 ch
3 12 unit 12.54% 0.00% 0.0% 0.00%
(PT 100)
4 Converter Serial to Ethernet 8 unit 5.01% 0.00% 0.0% 0.00%
5 Switch Manageable 24 port 3 unit 5.18% 0.00% 0.0% 0.00%
6 Rack Wallmount 4U 3 unit 1.62% 0.00% 0.0% 0.00%
7 MCB 1P 16a 3 pcs 0.07% 0.00% 0.0% 0.00%
8 Stop Kontak 3 Lubang 3 pcs 0.03% 0.00% 0.0% 0.00%
9 Pipa Conduit 325 pcs 1.73% 0.00% 0.0% 0.00%
10 Panel With Accesoris 8 unit 9.76% 4.88% 0.0% 4.88%
11 Power Supply 24VDC 8 unit 3.23% 1.61% 0.0% 1.61%
12 Kabel NYAF 1x1,5 mm 12 roll 1.39% 0.70% 0.0% 0.70%
13 Kabel NYY 3x2,5 mm (100m) 6 roll 3.42% 1.71% 0.0% 1.71%
14 Kabel UTP Cat 6 (300m) 3 roll 2.12% 1.06% 0.0% 1.06%
15 Accesoris (Dynabolt skun kabel) 8 set 2.29% 1.14% 0.0% 1.14%

C Pekerjaan dan Jasa


1 Assembling dan Download 6.79%
Program 1 lot 0.00% 0.0% 0.00%
2 WEB Base Development 1 lot 5.38% 0.27% 1.35% 1.62%
Instalasi dan Konfigurasi Switch
3 Manageable 1 lot 0.61% 0.00% 0.0% 0.00%
4 Penarikan Kabel NYY 3x2,5 1 lot 2.91% 0.00% 0.0% 0.00%
5 Penarikan Kabel UTP 1 lot 3.66% 0.00% 0.0% 0.00%

D TESTING & COMMISIONING


Testing & Site Accaptence Test
1 (Commisioning) 1 lot 5.88% 0.00% 0.0% 0.00%
2 Training 1 lot 0.85% 0.00% 0.0% 0.00%

Jumlah Seluruh Pekerjaan 100% 20.75%

PT. ANGKASA PURA II PT. JAKARTA PROCESS AUTOMATION


PENGAWAS PELAKSANA PEKERJAAN

(SUPARYONO) (ROSARILA DWI JAYANT) (DIMAS ABHIARDHANA)


LAPORAN MINGGUAN
Pekerjaan : PEKERJAAN PENAMBAHAN MONITORING PADA PERALATAN AHU TERMINAL 3
BANDARA SOEKARNO-HATTA
No SPP/ SPK : PJJ.14.01/01/02/2023/0164
Tanggal SPP/ SPK : 02/02/2023
Dep/ Instansi : Mechanical Facility Terminal 3 Tanggal : 9 Maret s/d 15 Maret
Pelaksana : PT. ARTA VICTORI ATMAJA Minggu ke :6

NO URAIAN PEKERJAAN Volume Bobot Last Progres This Progres Bobot Progres
1 2 3 4 5 6 7
A Pekerjaan Persiapan 1 lot 2.19% 2.10% 0.01% 2.11%

B Hardware
1 PLC (Logic Controller) 8 unit 10.79% 5.93% 0.0% 5.93%
Modbus Analog Input Module 8 ch
2 12 unit 12.54% 0.00% 0.0% 0.00%
(4/20mA)
Modbus Analog Input Module 8 ch
3 12 unit 12.54% 0.00% 0.0% 0.00%
(PT 100)
4 Converter Serial to Ethernet 8 unit 5.01% 0.00% 0.0% 0.00%
5 Switch Manageable 24 port 3 unit 5.18% 0.00% 0.0% 0.00%
6 Rack Wallmount 4U 3 unit 1.62% 0.00% 0.0% 0.00%
7 MCB 1P 16a 3 pcs 0.07% 0.00% 0.0% 0.00%
8 Stop Kontak 3 Lubang 3 pcs 0.03% 0.00% 0.0% 0.00%
9 Pipa Conduit 325 pcs 1.73% 0.00% 0.0% 0.00%
10 Panel With Accesoris 8 unit 9.76% 4.88% 0.0% 4.88%
11 Power Supply 24VDC 8 unit 3.23% 1.61% 0.0% 1.61%
12 Kabel NYAF 1x1,5 mm 12 roll 1.39% 0.70% 0.0% 0.70%
13 Kabel NYY 3x2,5 mm (100m) 6 roll 3.42% 1.71% 0.0% 1.71%
14 Kabel UTP Cat 6 (300m) 3 roll 2.12% 1.06% 0.0% 1.06%
15 Accesoris (Dynabolt skun kabel) 8 set 2.29% 1.14% 0.0% 1.14%

C Pekerjaan dan Jasa


1 Assembling dan Download 6.79%
Program 1 lot 0.00% 0.0% 0.00%
2 WEB Base Development 1 lot 5.38% 1.62% 1.35% 2.97%
Instalasi dan Konfigurasi Switch
3 Manageable 1 lot 0.61% 0.00% 0.0% 0.00%
4 Penarikan Kabel NYY 3x2,5 1 lot 2.91% 0.00% 0.0% 0.00%
5 Penarikan Kabel UTP 1 lot 3.66% 0.00% 0.0% 0.00%

D TESTING & COMMISIONING


Testing & Site Accaptence Test
1 (Commisioning) 1 lot 5.88% 0.00% 0.0% 0.00%
2 Training 1 lot 0.85% 0.00% 0.0% 0.00%

Jumlah Seluruh Pekerjaan 100% 22.11%

PT. ANGKASA PURA II PT. JAKARTA PROCESS AUTOMATION


PENGAWAS PELAKSANA PEKERJAAN

(SUPARYONO) (ROSARILA DWI JAYANT) (DIMAS ABHIARDHANA)


LAPORAN MINGGUAN
Pekerjaan : PEKERJAAN PENAMBAHAN MONITORING PADA PERALATAN AHU TERMINAL 3
BANDARA SOEKARNO-HATTA
No SPP/ SPK : PJJ.14.01/01/02/2023/0164
Tanggal SPP/ SPK : 02/02/2023
Dep/ Instansi : Mechanical Facility Terminal 3 Tanggal : 16 Maret s/d 22 Maret
Pelaksana : PT. ARTA VICTORI ATMAJA Minggu ke :7

NO URAIAN PEKERJAAN Volume Bobot Last Progres This Progres Bobot Progres
1 2 3 4 5 6 7
A Pekerjaan Persiapan 1 lot 2.19% 2.11% 0.01% 2.12%

B Hardware
1 PLC (Logic Controller) 8 unit 10.79% 5.93% 0.0% 5.93%
Modbus Analog Input Module 8 ch
2 12 unit 12.54% 0.00% 0.0% 0.00%
(4/20mA)
Modbus Analog Input Module 8 ch
3 12 unit 12.54% 0.00% 0.0% 0.00%
(PT 100)
4 Converter Serial to Ethernet 8 unit 5.01% 0.00% 0.00% 0.00%
5 Switch Manageable 24 port 3 unit 5.18% 0.00% 1.73% 1.73%
6 Rack Wallmount 4U 3 unit 1.62% 0.00% 0.54% 0.54%
7 MCB 1P 16a 3 pcs 0.07% 0.00% 0.02% 0.02%
8 Stop Kontak 3 Lubang 3 pcs 0.03% 0.00% 0.01% 0.01%
9 Pipa Conduit 325 pcs 1.73% 0.00% 0.58% 0.58%
10 Panel With Accesoris 8 unit 9.76% 4.88% 0.0% 4.88%
11 Power Supply 24VDC 8 unit 3.23% 1.61% 0.0% 1.61%
12 Kabel NYAF 1x1,5 mm 12 roll 1.39% 0.70% 0.0% 0.70%
13 Kabel NYY 3x2,5 mm (100m) 6 roll 3.42% 1.71% 0.0% 1.71%
14 Kabel UTP Cat 6 (300m) 3 roll 2.12% 1.06% 0.0% 1.06%
15 Accesoris (Dynabolt skun kabel) 8 set 2.29% 1.14% 0.0% 1.14%
0.00%
C Pekerjaan dan Jasa 0.00%
1 Assembling dan Download 6.79%
Program 1 lot 0.00% 0.0% 0.00%
2 WEB Base Development 1 lot 5.38% 2.97% 1.35% 4.32%
Instalasi dan Konfigurasi Switch
3 Manageable 1 lot 0.61% 0.00% 0.0% 0.00%
4 Penarikan Kabel NYY 3x2,5 1 lot 2.91% 0.00% 0.0% 0.00%
5 Penarikan Kabel UTP 1 lot 3.66% 0.00% 0.0% 0.00%

D TESTING & COMMISIONING


Testing & Site Accaptence Test
1 (Commisioning) 1 lot 5.88% 0.00% 0.0% 0.00%
2 Training 1 lot 0.85% 0.00% 0.0% 0.00%

Jumlah Seluruh Pekerjaan 100% 26.35%

PT. ANGKASA PURA II PT. JAKARTA PROCESS AUTOMATION


PENGAWAS PELAKSANA PEKERJAAN

(SUPARYONO) (ROSARILA DWI JAYANT) (DIMAS ABHIARDHANA)


LAPORAN MINGGUAN
Pekerjaan : PEKERJAAN PENAMBAHAN MONITORING PADA PERALATAN AHU TERMINAL 3
BANDARA SOEKARNO-HATTA
No SPP/ SPK : PJJ.14.01/01/02/2023/0164
Tanggal SPP/ SPK : 02/02/2023
Dep/ Instansi : Mechanical Facility Terminal 3 Tanggal : 23 Maret s/d 29 Maret
Pelaksana : PT. ARTA VICTORI ATMAJA Minggu ke :8

NO URAIAN PEKERJAAN Volume Bobot Last Progres This Progres Bobot Progres
1 2 3 4 5 6 7
A Pekerjaan Persiapan 1 lot 2.19% 2.12% 0.01% 2.13%
0.00%
B Hardware 0.00%
1 PLC (Logic Controller) 8 unit 10.79% 5.93% 0.0% 5.93%
Modbus Analog Input Module 8 ch
2 12 unit 12.54% 0.00% 0.0% 0.00%
(4/20mA)
Modbus Analog Input Module 8 ch
3 12 unit 12.54% 0.00% 0.0% 0.00%
(PT 100)
4 Converter Serial to Ethernet 8 unit 5.01% 0.00% 0.00% 0.00%
5 Switch Manageable 24 port 3 unit 5.18% 1.73% 1.73% 3.46%
6 Rack Wallmount 4U 3 unit 1.62% 0.54% 0.54% 1.08%
7 MCB 1P 16a 3 pcs 0.07% 0.02% 0.02% 0.04%
8 Stop Kontak 3 Lubang 3 pcs 0.03% 0.01% 0.01% 0.02%
9 Pipa Conduit 325 pcs 1.73% 0.58% 0.58% 1.16%
10 Panel With Accesoris 8 unit 9.76% 4.88% 0.0% 4.88%
11 Power Supply 24VDC 8 unit 3.23% 1.61% 0.0% 1.61%
12 Kabel NYAF 1x1,5 mm 12 roll 1.39% 0.70% 0.0% 0.70%
13 Kabel NYY 3x2,5 mm (100m) 6 roll 3.42% 1.71% 0.0% 1.71%
14 Kabel UTP Cat 6 (300m) 3 roll 2.12% 1.06% 0.0% 1.06%
15 Accesoris (Dynabolt skun kabel) 8 set 2.29% 1.14% 0.0% 1.14%
0.00% 0.00%
C Pekerjaan dan Jasa 0.00% 0.00%
1 Assembling dan Download 6.79%
Program 1 lot 0.00% 0.0% 0.00%
2 WEB Base Development 1 lot 5.38% 4.32% 1.06% 5.38%
Instalasi dan Konfigurasi Switch
3 Manageable 1 lot 0.61% 0.00% 0.0% 0.00%
4 Penarikan Kabel NYY 3x2,5 1 lot 2.91% 0.00% 0.0% 0.00%
5 Penarikan Kabel UTP 1 lot 3.66% 0.00% 0.0% 0.00%
0.00%
D TESTING & COMMISIONING 0.00%
Testing & Site Accaptence Test
1 (Commisioning) 1 lot 5.88% 0.00% 0.0% 0.00%
2 Training 1 lot 0.85% 0.00% 0.0% 0.00%

Jumlah Seluruh Pekerjaan 100% 30.30%

PT. ANGKASA PURA II PT. JAKARTA PROCESS AUTOMATION


PENGAWAS PELAKSANA PEKERJAAN

(SUPARYONO) (ROSARILA DWI JAYANT) (DIMAS ABHIARDHANA)


LAPORAN MINGGUAN
Pekerjaan : PEKERJAAN PENAMBAHAN MONITORING PADA PERALATAN AHU TERMINAL 3
BANDARA SOEKARNO-HATTA
No SPP/ SPK : PJJ.14.01/01/02/2023/0164
Tanggal SPP/ SPK : 02/02/2023
Dep/ Instansi : Mechanical Facility Terminal 3 Tanggal : 30 Maret s/d 5 April
Pelaksana : PT. ARTA VICTORI ATMAJA Minggu ke :9

NO URAIAN PEKERJAAN Volume Bobot Last Progres This Progres Bobot Progres
1 2 3 4 5 6 7
A Pekerjaan Persiapan 1 lot 2.19% 2.13% 0.01% 2.14%
0.00%
B Hardware 0.00%
1 PLC (Logic Controller) 8 unit 10.79% 5.39% 5.39% 10.78%
Modbus Analog Input Module 8 ch
2 12 unit 12.54% 0.00% 0.00% 0.00%
(4/20mA)
Modbus Analog Input Module 8 ch
3 12 unit 12.54% 0.00% 0.00% 0.00%
(PT 100)
4 Converter Serial to Ethernet 8 unit 5.01% 0.00% 0.00% 0.00%
5 Switch Manageable 24 port 3 unit 5.18% 3.46% 1.73% 5.19%
6 Rack Wallmount 4U 3 unit 1.62% 1.08% 0.54% 1.62%
7 MCB 1P 16a 3 pcs 0.07% 0.04% 0.02% 0.06%
8 Stop Kontak 3 Lubang 3 pcs 0.03% 0.02% 0.01% 0.03%
9 Pipa Conduit 325 pcs 1.73% 0.01% 0.58% 0.59%
10 Panel With Accesoris 8 unit 9.76% 4.88% 4.88% 9.76%
11 Power Supply 24VDC 8 unit 3.23% 1.61% 1.61% 3.22%
12 Kabel NYAF 1x1,5 mm 12 roll 1.39% 0.70% 0.70% 1.40%
13 Kabel NYY 3x2,5 mm (100m) 6 roll 3.42% 1.71% 1.71% 3.42%
14 Kabel UTP Cat 6 (300m) 3 roll 2.12% 1.06% 1.06% 2.12%
15 Accesoris (Dynabolt skun kabel) 8 set 2.29% 1.14% 1.14% 2.28%
0.00%
C Pekerjaan dan Jasa 0.00%
1 Assembling dan Download 6.79%
Program 1 lot 0.00% 0.00% 0.00%
2 WEB Base Development 1 lot 5.38% 5.38% 0.00% 5.38%
Instalasi dan Konfigurasi Switch
3 Manageable 1 lot 0.61% 0.00% 0.00% 0.00%
4 Penarikan Kabel NYY 3x2,5 1 lot 2.91% 0.00% 0.00% 0.00%
5 Penarikan Kabel UTP 1 lot 3.66% 0.00% 0.00% 0.00%
0.00%
D TESTING & COMMISIONING 0.00%
Testing & Site Accaptence Test
1 (Commisioning) 1 lot 5.88% 0.00% 0.00% 0.00%
2 Training 1 lot 0.85% 0.00% 0.00% 0.00%

Jumlah Seluruh Pekerjaan 100% 29% 47.99%

PT. ANGKASA PURA II PT. JAKARTA PROCESS AUTOMATION


PENGAWAS PELAKSANA PEKERJAAN

(SUPARYONO) (ROSARILA DWI JAYANT) (DIMAS ABHIARDHANA)


LAPORAN MINGGUAN
Pekerjaan : PEKERJAAN PENAMBAHAN MONITORING PADA PERALATAN AHU TERMINAL 3
BANDARA SOEKARNO-HATTA
No SPP/ SPK : PJJ.14.01/01/02/2023/0164
Tanggal SPP/ SPK : 02/02/2023
Dep/ Instansi : Mechanical Facility Terminal 3 Tanggal : 6 April s/d 12 April
Pelaksana : PT. ARTA VICTORI ATMAJA Minggu ke : 10

NO URAIAN PEKERJAAN Volume Bobot Last Progres This Progres Bobot Progres
1 2 3 4 5 6 7
A Pekerjaan Persiapan 1 lot 2.19% 2.14% 0.01% 2.15%

B Hardware
1 PLC (Logic Controller) 8 unit 10.79% 10.78% 0.00% 10.78%
Modbus Analog Input Module 8 ch
2 12 unit 12.54% 0.00% 4.18% 4.18%
(4/20mA)
Modbus Analog Input Module 8 ch
3 12 unit 12.54% 0.00% 4.18% 4.18%
(PT 100)
4 Converter Serial to Ethernet 8 unit 5.01% 0.00% 1.67% 1.67%
5 Switch Manageable 24 port 3 unit 5.18% 5.19% 0.00% 5.19%
6 Rack Wallmount 4U 3 unit 1.62% 1.62% 0.00% 1.62%
7 MCB 1P 16a 3 pcs 0.07% 0.06% 0.00% 0.06%
8 Stop Kontak 3 Lubang 3 pcs 0.03% 0.03% 0.00% 0.03%
9 Pipa Conduit 325 pcs 1.73% 0.01% 0.0% 0.00%
10 Panel With Accesoris 8 unit 9.76% 9.76% 0.0% 9.76%
11 Power Supply 24VDC 8 unit 3.23% 3.22% 0.0% 3.22%
12 Kabel NYAF 1x1,5 mm 12 roll 1.39% 1.40% 0.0% 1.40%
13 Kabel NYY 3x2,5 mm (100m) 6 roll 3.42% 3.42% 0.0% 3.42%
14 Kabel UTP Cat 6 (300m) 3 roll 2.12% 2.12% 0.0% 2.12%
15 Accesoris (Dynabolt skun kabel) 8 set 2.29% 2.28% 0.0% 2.28%

C Pekerjaan dan Jasa


1 Assembling dan Download 6.79%
Program 1 lot 0.00% 0.0% 0.00%
2 WEB Base Development 1 lot 5.38% 5.38% 0.00% 5.38%
Instalasi dan Konfigurasi Switch
3 Manageable 1 lot 0.61% 0.00% 0.0% 0.00%
4 Penarikan Kabel NYY 3x2,5 1 lot 2.91% 0.00% 0.0% 0.00%
5 Penarikan Kabel UTP 1 lot 3.66% 0.00% 0.0% 0.00%

D TESTING & COMMISIONING


Testing & Site Accaptence Test
1 (Commisioning) 1 lot 5.88% 0.00% 0.0% 0.00%
2 Training 1 lot 0.85% 0.00% 0.0% 0.00%

Jumlah Seluruh Pekerjaan 100% 29% 57.44%

PT. ANGKASA PURA II PT. JAKARTA PROCESS AUTOMATION


PENGAWAS PELAKSANA PEKERJAAN

(SUPARYONO) (ROSARILA DWI JAYANT) (DIMAS ABHIARDHANA)


LAPORAN MINGGUAN
Pekerjaan : PEKERJAAN PENAMBAHAN MONITORING PADA PERALATAN AHU TERMINAL 3
BANDARA SOEKARNO-HATTA
No SPP/ SPK : PJJ.14.01/01/02/2023/0164
Tanggal SPP/ SPK : 02/02/2023
Dep/ Instansi : Mechanical Facility Terminal 3 Tanggal : 13 April s/d 19 April
Pelaksana : PT. ARTA VICTORI ATMAJA Minggu ke : 11

NO URAIAN PEKERJAAN Volume Bobot Last Progres This Progres Bobot Progres
1 2 3 4 5 6 7
A Pekerjaan Persiapan 1 lot 2.19% 2.15% 0.01% 2.16%
0.00%
B Hardware 0.00%
1 PLC (Logic Controller) 8 unit 10.79% 10.78% 0.00% 10.78%
Modbus Analog Input Module 8 ch
2 12 unit 12.54% 4.18% 4.18% 8.36%
(4/20mA)
Modbus Analog Input Module 8 ch
3 12 unit 12.54% 4.18% 4.18% 8.36%
(PT 100)
4 Converter Serial to Ethernet 8 unit 5.01% 1.67% 1.67% 3.34%
5 Switch Manageable 24 port 3 unit 5.18% 5.19% 0.00% 5.19%
6 Rack Wallmount 4U 3 unit 1.62% 1.62% 0.00% 1.62%
7 MCB 1P 16a 3 pcs 0.07% 0.06% 0.00% 0.06%
8 Stop Kontak 3 Lubang 3 pcs 0.03% 0.03% 0.00% 0.03%
9 Pipa Conduit 325 pcs 1.73% 0.00% 0.00% 0.00%
10 Panel With Accesoris 8 unit 9.76% 9.76% 0.00% 9.76%
11 Power Supply 24VDC 8 unit 3.23% 3.22% 0.00% 3.22%
12 Kabel NYAF 1x1,5 mm 12 roll 1.39% 1.40% 0.00% 1.40%
13 Kabel NYY 3x2,5 mm (100m) 6 roll 3.42% 3.42% 0.00% 3.42%
14 Kabel UTP Cat 6 (300m) 3 roll 2.12% 2.12% 0.00% 2.12%
15 Accesoris (Dynabolt skun kabel) 8 set 2.29% 2.28% 0.00% 2.28%
0.00%
C Pekerjaan dan Jasa 0.00%
1 Assembling dan Download 6.79%
Program 1 lot 0.00% 0.00% 0.00%
2 WEB Base Development 1 lot 5.38% 5.38% 0.00% 5.38%
Instalasi dan Konfigurasi Switch
3 Manageable 1 lot 0.61% 0.00% 0.00% 0.00%
4 Penarikan Kabel NYY 3x2,5 1 lot 2.91% 0.00% 0.00% 0.00%
5 Penarikan Kabel UTP 1 lot 3.66% 0.00% 0.00% 0.00%
0.00%
D TESTING & COMMISIONING 0.00%
Testing & Site Accaptence Test
1 (Commisioning) 1 lot 5.88% 0.00% 0.00% 0.00%
2 Training 1 lot 0.85% 0.00% 0.00% 0.00%

Jumlah Seluruh Pekerjaan 100% 29% 67.48%

PT. ANGKASA PURA II PT. JAKARTA PROCESS AUTOMATION


PENGAWAS PELAKSANA PEKERJAAN

(SUPARYONO) (ROSARILA DWI JAYANT) (DIMAS ABHIARDHANA)


LAPORAN MINGGUAN
Pekerjaan : PEKERJAAN PENAMBAHAN MONITORING PADA PERALATAN AHU TERMINAL 3
BANDARA SOEKARNO-HATTA
No SPP/ SPK : PJJ.14.01/01/02/2023/0164
Tanggal SPP/ SPK : 02/02/2023
Dep/ Instansi : Mechanical Facility Terminal 3 Tanggal : 20 April s/d 26 April
Pelaksana : PT. ARTA VICTORI ATMAJA Minggu ke : 12

NO URAIAN PEKERJAAN Volume Bobot Last Progres This Progres Bobot Progres
1 2 3 4 5 6 7
A Pekerjaan Persiapan 1 lot 2.19% 2.16% 0.01% 2.17%
0.00%
B Hardware 0.00%
1 PLC (Logic Controller) 8 unit 10.79% 10.78% 0.00% 10.78%
Modbus Analog Input Module 8 ch
2 12 unit 12.54% 8.36% 4.18% 12.54%
(4/20mA)
Modbus Analog Input Module 8 ch
3 12 unit 12.54% 8.36% 4.18% 12.54%
(PT 100)
4 Converter Serial to Ethernet 8 unit 5.01% 3.34% 1.67% 5.01%
5 Switch Manageable 24 port 3 unit 5.18% 5.19% 0.00% 5.19%
6 Rack Wallmount 4U 3 unit 1.62% 1.62% 0.00% 1.62%
7 MCB 1P 16a 3 pcs 0.07% 0.06% 0.00% 0.06%
8 Stop Kontak 3 Lubang 3 pcs 0.03% 0.03% 0.00% 0.03%
9 Pipa Conduit 325 pcs 1.73% 0.00% 0.00% 0.00%
10 Panel With Accesoris 8 unit 9.76% 9.76% 0.00% 9.76%
11 Power Supply 24VDC 8 unit 3.23% 3.22% 0.00% 3.22%
12 Kabel NYAF 1x1,5 mm 12 roll 1.39% 1.40% 0.00% 1.40%
13 Kabel NYY 3x2,5 mm (100m) 6 roll 3.42% 3.42% 0.00% 3.42%
14 Kabel UTP Cat 6 (300m) 3 roll 2.12% 2.12% 0.00% 2.12%
15 Accesoris (Dynabolt skun kabel) 8 set 2.29% 2.28% 0.00% 2.28%
0.00% 0.00%
C Pekerjaan dan Jasa 0.00% 0.00%
1 Assembling dan Download 6.79%
Program 1 lot 0.00% 1.36% 1.36%
2 WEB Base Development 1 lot 5.38% 5.38% 0.00% 5.38%
Instalasi dan Konfigurasi Switch
3 Manageable 1 lot 0.61% 0.00% 0.00% 0.00%
4 Penarikan Kabel NYY 3x2,5 1 lot 2.91% 0.00% 0.00% 0.00%
5 Penarikan Kabel UTP 1 lot 3.66% 0.00% 0.00% 0.00%
0.00% 0.00%
D TESTING & COMMISIONING 0.00% 0.00%
Testing & Site Accaptence Test
1 (Commisioning) 1 lot 5.88% 0.00% 0.00% 0.00%
2 Training 1 lot 0.85% 0.00% 0.00% 0.00%

Jumlah Seluruh Pekerjaan 100% 29% 78.88%

PT. ANGKASA PURA II PT. JAKARTA PROCESS AUTOMATION


PENGAWAS PELAKSANA PEKERJAAN

(SUPARYONO) (ROSARILA DWI JAYANT) (DIMAS ABHIARDHANA)


LAPORAN MINGGUAN
Pekerjaan : PEKERJAAN PENAMBAHAN MONITORING PADA PERALATAN AHU TERMINAL 3
BANDARA SOEKARNO-HATTA
No SPP/ SPK : PJJ.14.01/01/02/2023/0164
Tanggal SPP/ SPK : 02/02/2023
Dep/ Instansi : Mechanical Facility Terminal 3 Tanggal : 27 April s/d 3 Mei
Pelaksana : PT. ARTA VICTORI ATMAJA Minggu ke : 13

NO URAIAN PEKERJAAN Volume Bobot Last Progres This Progres Bobot Progres
1 2 3 4 5 6 7
A Pekerjaan Persiapan 1 lot 2.19% 2.17% 0.01% 2.18%

B Hardware
1 PLC (Logic Controller) 8 unit 10.79% 10.78% 0.00% 10.78%
Modbus Analog Input Module 8 ch
2 12 unit 12.54% 12.54% 0.00% 12.54%
(4/20mA)
Modbus Analog Input Module 8 ch
3 12 unit 12.54% 12.54% 0.00% 12.54%
(PT 100)
4 Converter Serial to Ethernet 8 unit 5.01% 5.01% 0.00% 5.01%
5 Switch Manageable 24 port 3 unit 5.18% 5.19% 0.00% 5.19%
6 Rack Wallmount 4U 3 unit 1.62% 1.62% 0.00% 1.62%
7 MCB 1P 16a 3 pcs 0.07% 0.06% 0.00% 0.06%
8 Stop Kontak 3 Lubang 3 pcs 0.03% 0.03% 0.00% 0.03%
9 Pipa Conduit 325 pcs 1.73% 0.00% 0.00% 0.00%
10 Panel With Accesoris 8 unit 9.76% 9.76% 0.00% 9.76%
11 Power Supply 24VDC 8 unit 3.23% 3.22% 0.00% 3.22%
12 Kabel NYAF 1x1,5 mm 12 roll 1.39% 1.40% 0.00% 1.40%
13 Kabel NYY 3x2,5 mm (100m) 6 roll 3.42% 3.42% 0.00% 3.42%
14 Kabel UTP Cat 6 (300m) 3 roll 2.12% 2.12% 0.00% 2.12%
15 Accesoris (Dynabolt skun kabel) 8 set 2.29% 2.28% 0.00% 2.28%

C Pekerjaan dan Jasa


1 Assembling dan Download 6.79%
Program 1 lot 1.36% 2.26% 3.62%
2 WEB Base Development 1 lot 5.38% 5.38% 0.00% 5.38%
Instalasi dan Konfigurasi Switch
3 Manageable 1 lot 0.61% 0.00% 0.37% 0.37%
4 Penarikan Kabel NYY 3x2,5 1 lot 2.91% 0.00% 0.00% 0.00%
5 Penarikan Kabel UTP 1 lot 3.66% 0.00% 0.00% 0.00%

D TESTING & COMMISIONING


Testing & Site Accaptence Test
1 (Commisioning) 1 lot 5.88% 0.00% 0.00% 0.00%
2 Training 1 lot 0.85% 0.00% 0.00% 0.00%

Jumlah Seluruh Pekerjaan 100% 29% 81.52%

PT. ANGKASA PURA II PT. JAKARTA PROCESS AUTOMATION


PENGAWAS PELAKSANA PEKERJAAN

(SUPARYONO) (ROSARILA DWI JAYANT) (DIMAS ABHIARDHANA)


LAPORAN MINGGUAN
Pekerjaan : PEKERJAAN PENAMBAHAN MONITORING PADA PERALATAN AHU TERMINAL 3
BANDARA SOEKARNO-HATTA
No SPP/ SPK : PJJ.14.01/01/02/2023/0164
Tanggal SPP/ SPK : 02/02/2023
Dep/ Instansi : Mechanical Facility Terminal 3 Tanggal : 4 Mei s/d 10 Mei
Pelaksana : PT. ARTA VICTORI ATMAJA Minggu ke : 14

NO URAIAN PEKERJAAN Volume Bobot Last Progres This Progres Bobot Progres
1 2 3 4 5 6 7
A Pekerjaan Persiapan 1 lot 2.19% 2.18% 0.01% 2.19%

B Hardware
1 PLC (Logic Controller) 8 unit 10.79% 10.78% 0.00% 10.78%
Modbus Analog Input Module 8 ch
2 12 unit 12.54% 12.54% 0.00% 12.54%
(4/20mA)
Modbus Analog Input Module 8 ch
3 12 unit 12.54% 12.54% 0.00% 12.54%
(PT 100)
4 Converter Serial to Ethernet 8 unit 5.01% 5.01% 0.00% 5.01%
5 Switch Manageable 24 port 3 unit 5.18% 5.19% 0.00% 5.19%
6 Rack Wallmount 4U 3 unit 1.62% 1.62% 0.00% 1.62%
7 MCB 1P 16a 3 pcs 0.07% 0.06% 0.00% 0.06%
8 Stop Kontak 3 Lubang 3 pcs 0.03% 0.03% 0.00% 0.03%
9 Pipa Conduit 325 pcs 1.73% 0.00% 0.00% 0.00%
10 Panel With Accesoris 8 unit 9.76% 9.76% 0.00% 9.76%
11 Power Supply 24VDC 8 unit 3.23% 3.22% 0.00% 3.22%
12 Kabel NYAF 1x1,5 mm 12 roll 1.39% 1.40% 0.00% 1.40%
13 Kabel NYY 3x2,5 mm (100m) 6 roll 3.42% 3.42% 0.00% 3.42%
14 Kabel UTP Cat 6 (300m) 3 roll 2.12% 2.12% 0.00% 2.12%
15 Accesoris (Dynabolt skun kabel) 8 set 2.29% 2.28% 0.00% 2.28%

C Pekerjaan dan Jasa


1 Assembling dan Download 6.79%
Program 1 lot 3.62% 2.26% 5.88%
2 WEB Base Development 1 lot 5.38% 5.38% 0.00% 5.38%
Instalasi dan Konfigurasi Switch
3 Manageable 1 lot 0.61% 0.37% 0.24% 0.61%
4 Penarikan Kabel NYY 3x2,5 1 lot 2.91% 0.00% 1.75% 1.75%
5 Penarikan Kabel UTP 1 lot 3.66% 0.00% 0.00% 0.00%

D TESTING & COMMISIONING


Testing & Site Accaptence Test
1 (Commisioning) 1 lot 5.88% 0.00% 0.00% 0.00%
2 Training 1 lot 0.85% 0.00% 0.00% 0.00%

Jumlah Seluruh Pekerjaan 100% 29% 85.78%

PT. ANGKASA PURA II PT. JAKARTA PROCESS AUTOMATION


PENGAWAS PELAKSANA PEKERJAAN

(SUPARYONO) (ROSARILA DWI JAYANT) (DIMAS ABHIARDHANA)


LAPORAN MINGGUAN
Pekerjaan : PEKERJAAN PENAMBAHAN MONITORING PADA PERALATAN AHU TERMINAL 3
BANDARA SOEKARNO-HATTA
No SPP/ SPK : PJJ.14.01/01/02/2023/0164
Tanggal SPP/ SPK : 02/02/2023
Dep/ Instansi : Mechanical Facility Terminal 3 Tanggal : 11 Mei s/d 17 Mei
Pelaksana : PT. ARTA VICTORI ATMAJA Minggu ke : 15

NO URAIAN PEKERJAAN Volume Bobot Last Progres This Progres Bobot Progres
1 2 3 4 5 6 7
A Pekerjaan Persiapan 1 lot 2.19% 2.19% 0.01% 2.20%

B Hardware
1 PLC (Logic Controller) 8 unit 10.79% 10.78% 0.00% 10.78%
Modbus Analog Input Module 8 ch
2 12 unit 12.54% 12.54% 0.00% 12.54%
(4/20mA)
Modbus Analog Input Module 8 ch
3 12 unit 12.54% 12.54% 0.00% 12.54%
(PT 100)
4 Converter Serial to Ethernet 8 unit 5.01% 5.01% 0.00% 5.01%
5 Switch Manageable 24 port 3 unit 5.18% 5.19% 0.00% 5.19%
6 Rack Wallmount 4U 3 unit 1.62% 1.62% 0.00% 1.62%
7 MCB 1P 16a 3 pcs 0.07% 0.06% 0.00% 0.06%
8 Stop Kontak 3 Lubang 3 pcs 0.03% 0.03% 0.00% 0.03%
9 Pipa Conduit 325 pcs 1.73% 0.00% 0.00% 0.00%
10 Panel With Accesoris 8 unit 9.76% 9.76% 0.00% 9.76%
11 Power Supply 24VDC 8 unit 3.23% 3.22% 0.00% 3.22%
12 Kabel NYAF 1x1,5 mm 12 roll 1.39% 1.40% 0.00% 1.40%
13 Kabel NYY 3x2,5 mm (100m) 6 roll 3.42% 3.42% 0.00% 3.42%
14 Kabel UTP Cat 6 (300m) 3 roll 2.12% 2.12% 0.00% 2.12%
15 Accesoris (Dynabolt skun kabel) 8 set 2.29% 2.28% 0.00% 2.28%

C Pekerjaan dan Jasa


1 Assembling dan Download 6.79%
Program 1 lot 5.88% 0.91% 6.79%
2 WEB Base Development 1 lot 5.38% 5.38% 0.00% 5.38%
Instalasi dan Konfigurasi Switch
3 Manageable 1 lot 0.61% 0.61% 0.00% 0.61%
4 Penarikan Kabel NYY 3x2,5 1 lot 2.91% 1.75% 1.16% 2.91%
5 Penarikan Kabel UTP 1 lot 3.66% 0.00% 2.20% 2.20%

D TESTING & COMMISIONING


Testing & Site Accaptence Test
1 (Commisioning) 1 lot 5.88% 0.00% 0.00% 0.00%
2 Training 1 lot 0.85% 0.00% 0.00% 0.00%

Jumlah Seluruh Pekerjaan 100% 29% 90.06%

PT. ANGKASA PURA II PT. JAKARTA PROCESS AUTOMATION


PENGAWAS PELAKSANA PEKERJAAN

(SUPARYONO) (ROSARILA DWI JAYANT) (DIMAS ABHIARDHANA)


LAPORAN MINGGUAN
Pekerjaan : PEKERJAAN PENAMBAHAN MONITORING PADA PERALATAN AHU TERMINAL 3
BANDARA SOEKARNO-HATTA
No SPP/ SPK : PJJ.14.01/01/02/2023/0164
Tanggal SPP/ SPK : 02/02/2023
Dep/ Instansi : Mechanical Facility Terminal 3 Tanggal : 18 Mei s/d 24 Mei
Pelaksana : PT. ARTA VICTORI ATMAJA Minggu ke : 16

NO URAIAN PEKERJAAN Volume Bobot Last Progres This Progres Bobot Progres
1 2 3 4 5 6 7
A Pekerjaan Persiapan 1 lot 2.19% 2.20% 0.01% 2.21%

B Hardware
1 PLC (Logic Controller) 8 unit 10.79% 10.78% 0.00% 10.78%
Modbus Analog Input Module 8 ch
2 12 unit 12.54% 12.54% 0.00% 12.54%
(4/20mA)
Modbus Analog Input Module 8 ch
3 12 unit 12.54% 12.54% 0.00% 12.54%
(PT 100)
4 Converter Serial to Ethernet 8 unit 5.01% 5.01% 0.00% 5.01%
5 Switch Manageable 24 port 3 unit 5.18% 5.19% 0.00% 5.19%
6 Rack Wallmount 4U 3 unit 1.62% 1.62% 0.00% 1.62%
7 MCB 1P 16a 3 pcs 0.07% 0.06% 0.00% 0.06%
8 Stop Kontak 3 Lubang 3 pcs 0.03% 0.03% 0.00% 0.03%
9 Pipa Conduit 325 pcs 1.73% 0.00% 0.00% 0.00%
10 Panel With Accesoris 8 unit 9.76% 9.76% 0.00% 9.76%
11 Power Supply 24VDC 8 unit 3.23% 3.22% 0.00% 3.22%
12 Kabel NYAF 1x1,5 mm 12 roll 1.39% 1.40% 0.00% 1.40%
13 Kabel NYY 3x2,5 mm (100m) 6 roll 3.42% 3.42% 0.00% 3.42%
14 Kabel UTP Cat 6 (300m) 3 roll 2.12% 2.12% 0.00% 2.12%
15 Accesoris (Dynabolt skun kabel) 8 set 2.29% 2.28% 0.00% 2.28%

C Pekerjaan dan Jasa


1 Assembling dan Download 6.79%
Program 1 lot 6.79% 0.00% 6.79%
2 WEB Base Development 1 lot 5.38% 5.38% 0.00% 5.38%
Instalasi dan Konfigurasi Switch
3 Manageable 1 lot 0.61% 0.61% 0.00% 0.61%
4 Penarikan Kabel NYY 3x2,5 1 lot 2.91% 2.91% 0.00% 2.91%
5 Penarikan Kabel UTP 1 lot 3.66% 2.20% 1.46% 3.66%

D TESTING & COMMISIONING


Testing & Site Accaptence Test
1 (Commisioning) 1 lot 5.88% 0.00% 2.35% 2.35%
2 Training 1 lot 0.85% 0.00% 0.00% 0.00%

Jumlah Seluruh Pekerjaan 100% 29% 93.88%

PT. ANGKASA PURA II PT. JAKARTA PROCESS AUTOMATION


PENGAWAS PELAKSANA PEKERJAAN

(SUPARYONO) (ROSARILA DWI JAYANT) (DIMAS ABHIARDHANA)


LAPORAN MINGGUAN
Pekerjaan : PEKERJAAN PENAMBAHAN MONITORING PADA PERALATAN AHU TERMINAL 3
BANDARA SOEKARNO-HATTA
No SPP/ SPK : PJJ.14.01/01/02/2023/0164
Tanggal SPP/ SPK : 02/02/2023
Dep/ Instansi : Mechanical Facility Terminal 3 Tanggal : 25 Mei s/d 31 Mei
Pelaksana : PT. ARTA VICTORI ATMAJA Minggu ke : 17

NO URAIAN PEKERJAAN Volume Bobot Last Progres This Progres Bobot Progres
1 2 3 4 5 6 7
A Pekerjaan Persiapan 1 lot 2.19% 2.21% 0.01% 2.22%

B Hardware
1 PLC (Logic Controller) 8 unit 10.79% 10.78% 0.00% 10.78%
Modbus Analog Input Module 8 ch
2 12 unit 12.54% 12.54% 0.00% 12.54%
(4/20mA)
Modbus Analog Input Module 8 ch
3 12 unit 12.54% 12.54% 0.00% 12.54%
(PT 100)
4 Converter Serial to Ethernet 8 unit 5.01% 5.01% 0.00% 5.01%
5 Switch Manageable 24 port 3 unit 5.18% 5.19% 0.00% 5.19%
6 Rack Wallmount 4U 3 unit 1.62% 1.62% 0.00% 1.62%
7 MCB 1P 16a 3 pcs 0.07% 0.06% 0.00% 0.06%
8 Stop Kontak 3 Lubang 3 pcs 0.03% 0.03% 0.00% 0.03%
9 Pipa Conduit 325 pcs 1.73% 0.00% 0.00% 0.00%
10 Panel With Accesoris 8 unit 9.76% 9.76% 0.00% 9.76%
11 Power Supply 24VDC 8 unit 3.23% 3.22% 0.00% 3.22%
12 Kabel NYAF 1x1,5 mm 12 roll 1.39% 1.40% 0.00% 1.40%
13 Kabel NYY 3x2,5 mm (100m) 6 roll 3.42% 3.42% 0.00% 3.42%
14 Kabel UTP Cat 6 (300m) 3 roll 2.12% 2.12% 0.00% 2.12%
15 Accesoris (Dynabolt skun kabel) 8 set 2.29% 2.28% 0.00% 2.28%

C Pekerjaan dan Jasa


1 Assembling dan Download 6.79%
Program 1 lot 6.79% 0.00% 6.79%
2 WEB Base Development 1 lot 5.38% 5.38% 0.00% 5.38%
Instalasi dan Konfigurasi Switch
3 Manageable 1 lot 0.61% 0.61% 0.00% 0.61%
4 Penarikan Kabel NYY 3x2,5 1 lot 2.91% 2.91% 0.00% 2.91%
5 Penarikan Kabel UTP 1 lot 3.66% 3.66% 0.00% 3.66%

D TESTING & COMMISIONING


Testing & Site Accaptence Test
1 (Commisioning) 1 lot 5.88% 2.35% 3.53% 5.88%
2 Training 1 lot 0.85% 0.00% 0.85% 0.85%

Jumlah Seluruh Pekerjaan 100% 29% 98.27%

PT. ANGKASA PURA II PT. JAKARTA PROCESS AUTOMATION


PENGAWAS PELAKSANA PEKERJAAN

(SUPARYONO) (ROSARILA DWI JAYANT) (DIMAS ABHIARDHANA)


LAPORAN MINGGUAN
Pekerjaan : PEKERJAAN PENAMBAHAN MONITORING PADA PERALATAN AHU TERMINAL 3
BANDARA SOEKARNO-HATTA
No SPP/ SPK : PJJ.14.01/01/02/2023/0164
Tanggal SPP/ SPK : 02/02/2023
Dep/ Instansi : Mechanical Facility Terminal 3 Tanggal : 25 Mei s/d 31 Mei
Pelaksana : PT. ARTA VICTORI ATMAJA Minggu ke : 17

NO URAIAN PEKERJAAN Volume Bobot Last Progres This Progres Bobot Progres
1 2 3 4 5 6 7
A Pekerjaan Persiapan 1 lot 2.19% 2.22% 0.01% 2.23%

B Hardware
1 PLC (Logic Controller) 8 unit 10.79% 10.78% 0.00% 10.78%
Modbus Analog Input Module 8 ch
2 12 unit 12.54% 12.54% 0.00% 12.54%
(4/20mA)
Modbus Analog Input Module 8 ch
3 12 unit 12.54% 12.54% 0.00% 12.54%
(PT 100)
4 Converter Serial to Ethernet 8 unit 5.01% 5.01% 0.00% 5.01%
5 Switch Manageable 24 port 3 unit 5.18% 5.19% 0.00% 5.19%
6 Rack Wallmount 4U 3 unit 1.62% 1.62% 0.00% 1.62%
7 MCB 1P 16a 3 pcs 0.07% 0.06% 0.00% 0.06%
8 Stop Kontak 3 Lubang 3 pcs 0.03% 0.03% 0.00% 0.03%
9 Pipa Conduit 325 pcs 1.73% 0.00% 0.00% 0.00%
10 Panel With Accesoris 8 unit 9.76% 9.76% 0.00% 9.76%
11 Power Supply 24VDC 8 unit 3.23% 3.22% 0.00% 3.22%
12 Kabel NYAF 1x1,5 mm 12 roll 1.39% 1.40% 0.00% 1.40%
13 Kabel NYY 3x2,5 mm (100m) 6 roll 3.42% 3.42% 0.00% 3.42%
14 Kabel UTP Cat 6 (300m) 3 roll 2.12% 2.12% 0.00% 2.12%
15 Accesoris (Dynabolt skun kabel) 8 set 2.29% 2.28% 0.00% 2.28%

C Pekerjaan dan Jasa


1 Assembling dan Download 6.79%
Program 1 lot 6.79% 0.00% 6.79%
2 WEB Base Development 1 lot 5.38% 5.38% 0.00% 5.38%
Instalasi dan Konfigurasi Switch
3 Manageable 1 lot 0.61% 0.61% 0.00% 0.61%
4 Penarikan Kabel NYY 3x2,5 1 lot 2.91% 2.91% 0.00% 2.91%
5 Penarikan Kabel UTP 1 lot 3.66% 3.66% 0.00% 3.66%

D TESTING & COMMISIONING


Testing & Site Accaptence Test
1 (Commisioning) 1 lot 5.88% 5.88% 3.53% 9.41%
2 Training 1 lot 0.85% 0.85% 0.00% 0.85%

Jumlah Seluruh Pekerjaan 100% 29% 101.81%

PT. ANGKASA PURA II PT. JAKARTA PROCESS AUTOMATION


PENGAWAS PELAKSANA PEKERJAAN

(SUPARYONO) (ROSARILA DWI JAYANT) (DIMAS ABHIARDHANA)