KOC Commissioning HSE Checklist 29-11-2017
KOC Commissioning HSE Checklist 29-11-2017
KOC Commissioning HSE Checklist 29-11-2017
Generator Package
Lights insufficient secondary retention
Dynamic Brake Resistor no secondary retention
GPA Light package and PA system no secondary retention
Hand rails no cotter/ securing cotter pin
Cable support loose on south wall
Recommendation: All bolts securing equipment to
have Norlock washers or Nylock type nuts installed.
Mud Pumps
Mud Pits
No Hand rail cotter/securing pins
Bridging Link No cotter/securing pins
Agitator Start Panel requires secondary retention
Shaker Area
Support for Flow line inlet too Shakers loose
nuts and Bolts
Lights insufficient secondary retention
Access Hatch cotter/securing pins
Loose Debris to be Removed
Electrical Support Bracket and Plug cover
requires secondary retention
Stairs to Drill Floor No securing pins installed
Drill Floor
2 Part Shackles in use ( Tongs , Cat Eye ,
Top Drive, winches)
Lights insufficient secondary retention.
Work / inspection basket flame cut Pad eyes
Sub Structure
4 To verify all lifting gears bear valid colour coding and ✓ Closed 98%
certificates. KOC Contract calls for all lifting gears to have
valid colour coding and certification Need to be colour coded
Closed
9 To function check Fire detection system with all manual ✓ Extinguishers inventory at both Camp & Rig Side Closed
call points, sounders, room fire detectors and the fail to meet KOC contractual requirements.
control panel as per contract in both Rig and main
camp. Whilst BWD do have extinguishers on location
10 To ensure that Fire pump and fire water network in rig ✓ Closed
and main camp are as per the requirement. List and Extinguishers inventory at both Camp & Rig Side
place of fire extinguishers with KOC inspection tags fail to meet KOC contractual requirements.
with all fire extinguishers.
Whilst BWD do have extinguishers on location
PRVs
Serial No ? Tag no PSV- 352 Calibration in date
Serial No ? Tag no PSV- 353 Calibration in date
Serial No ? Tag no PSV- 354 Calibration in Date
Serial No – 50853 – Calibration in date
Serial No – 50851/17 – Calibration in date
Serial No – 50852/17 – Calibration in date
Misc Valves
Pump Pressure Gauge – 0737825 Calibration in date
Flange Type Pressure Gauge – 56198 Calibration in date
Tong Torque Gauge – 1802004- Calibration in date
Weight Indicator SN No 1504895 Calibration in date
Pressure Gauge – Tag No PG 980 - Calibration in date
Stand Pipe Gauge – Serial No 55448- Calibration in date
Stand Pipe Gauge – Serial No 55449- Calibration in date
18 To verify Sign boards and its placements, rig route and ✓ Closed
route signage. Upon Inspection it was uncovered that
the below signage was not on location to the
Specified contractual quantity.
19 To check the availability of Paging system, Wind socks, ✓ Not As per Contract Closed
Spill kit, Fire pump and fire water network in rig and
main camp. Upon Inspection it was revealed
20 To verify Certificates and load test for all winches and ✓ Not As Per Contract Closed
BOP trolleys/winches are available.
No Certificates and load tests for all winches and BOP trolleys/winches
on location are available on
Location to Verify
Date Contract Company Rig Drilling Supervisor HSE Eng. HSE Supervisor Well
28/9/17 Burgan 130 Scott, Perdeep Alan n/a