Headquarters Office,
Baroda House
New Delhi
As subjected above, the Draft Revised (2022) Maintenance Manual for LHB AC &
Non AC Coaches Electrical has been examined and following comments are made
1. Issues related to Coach Description:
Para 6.2.2: All types of coaches are not defined.
Para 6.5.1.1: Servomotor for fresh air damper is indicated, however, it is obsolete
now.
Note:
1) All efforts should be made to avoid over maintenance, since over maintenance not
only results in wastage of man power but also prone to the premature failures due to
loose connections/mishandling
i) This Maintenance Manual should be open for revision in future since new IT based
equipments are being proliferated in coaching stock. Also, Rly. Bd. guidelines &
RDSOILKO's SMI/MS from time to time should be included/updated.
in) A meeting with Zonal Railways before finalizing this manual for brain storming and
including the experiences will be appreciated.
DA/-as above,
(Veena Sinha)24|2
Chief Electrical Services Engineer
Copy/
PCME/NR for kind inf. please
2 Director/Elect./CAMTECH/
Gwalior for inf. & necessary action please.
2
261/493
895731/2022/O/o Dy.CEE/Chg/HQ/NR
Annexure-II 262/493
Comments on Maintenance Schedules
895731/2022/O/o Dy.CEE/Chg/HQ/NR
Para 8.17.1 Alternator: (9) These activities are currently being carried out during
D & E check of diesel engines.
Para 8.17.6 Power Panel/Control Panel: Maintenance instructions are required
on HOG Contactors, HOG control transformer
Para 8.17.7 Radiator, Radiator Pipeline and Radiator Chamber: (2) Add
“Remove internal scaling if any, with the help of suitable descaling agent. Activity
to be added in SS-2 also.
(8) To be deleted since covered in (2).
Para 8.17.11 Fuel Tank: (5) To be deleted since not provided in LHB power
cars.
Para 8.17.12 Safety System: Calibration/Replacement should be Calibration/
Replacement on Conditional basis.
Item no 10 to be included for RFR (Radiator Fan Relay), Circuit checking during
D1, D2, D3, SS1 & Calibration/ Replacement on Conditional basis during SS2.
Para 8.18 & 8.19: Maintenance schedules of diesel engines: To be updated
as per Rly.Bd.’s guidelines.
Para 8.20 List of Must Change Items for Power Cars: For engine items for
Must change items, the periodicity should be in sync with C/D/E checks rather
than 1st & 2nd POH.
Para 10.1.2 Battery: (e) Activity should be carried out in SS-2 Schedule.
Clause 10.1.3 REBC:
(4) Air pressure/blower shall be used in place of Vacuum cleaner.
(8) Air pressure/blower shall be used in place of Vacuum cleaner.
Clause 10.1.6: Step Down Transformer 100 VA, 750/415V is given, it should be
100/200VA
a. This activity shall be deleted from T1 (D1) (as not possible in every trip
maintenance schedule).
b. This activity shall be deleted from T1 (D1) (as not possible in every trip
maintenance schedule).
c. This activity shall be deleted from T1 (D1) & M (D2) (as not possible in every
trip maintenance schedule and is also very earlier in Monthly schedule).
d. Instead of 1 A write as 2A as per latest RDSO guidelines.
e. Make wise nominal values of Winding Resistance 100 VA & 200 VA are also
to be mentioned for reference.
Clause 10.1.7 RC Filter:
a. This activity shall be deleted from T1 (D1) (as not possible in every trip
maintenance schedule).
b. This activity shall be deleted from T1 (D1) (as not possible in every trip
maintenance schedule).
c. Check value of capacitor by LCR meter, If the value is low, replace the RC
filter should be as Check value of capacitor and resistance by LCR meter, If
the value is low, replace the RC filter.
This activity shall be carried out in IOH (SS1) and POH (SS2) Schedules only
and deleted from D3..
Clause 10.1.8 Z.S. Coupler on non-vestibule side for attachment in
Locomotive:
c. How to check proper mating of IV Couplers with thermo-vision device is not
clear. So, clarity with proper procedure to carry out this activity is required
before including it in this maintenance schedule.
Clause 10.1.9 Isolating Contactors:
a. This activity shall be written as “Cleaned with blower/Compressed air and
checked for any loose connection”
-Page1-
263/493
d. This
895731/2022/O/o activity shall be carry out in POH (SS2) Schedules only.
Dy.CEE/Chg/HQ/NR
This should be as Check condition of contacts by measuring the Contact area,
mili-volt drop, closing & opening time etc. Replace them on condition basis if
fails in test.
Limits for Contact area, mili volt drop are to be defined.
Clause 10.1.11 Miscellaneous Equipments:
Feeder Cable
b Check proper clamping arrangement should be as Check proper clamping
arrangement and healthiness of rubber hose connector pipe.
Under frame
A new item should be added as (b) Check condition of feeder junction boxes.
Ensure proper sealing to avoid water ingression (D1, D2, D3, SS1 & SS2)
Earthing
b. This activity shall be as check earthing connections of disconnecting and
earthing switch (since replacement of disconnecting and earthing device
complete rotary switch is covered in 10.2.1 Switch Board Cabinet part- n)
d. This activity is to be deleted as covered in 10.2.1 Switch board cabinet part - q
One more activity DC positive & negative insulation failure checking is to
be added in SS1 & SS2 Schedule
Clause 10.2.1 Switch Board Cabinet:
c. This activity shall be as Clean the panel with blower/Compressed air and
checked for any loose connection “
l. This activity shall be as “Replace MPCBs/MCBs for blower motor, condenser
motor, compressor, heater, exhaust fan, pantry equipment and pumps”.
m.Limits need to be defined for contact area, mili volt drop.
n. Replace disconnecting & earthing device complete rotary switch should be as
Check the condition of disconnecting & earthing device complete rotary switch,
replace if required.
r. Delete this item since obsolete.
s. This activity shall be as “Replace contactor for K01, K02, K44 and
compressors”.
t. Delete this activity since external modules are not used in existing contactors
used in latest spec.
-Page 3-
265/493
895731/2022/O/o Dy.CEE/Chg/HQ/NR
Annexure-III
LIST OF MUST CHANGE ITEMS FOR LHB AC COACHES
1st 2nd
SN Items
POH POH
1 Switch Board Cabinet:
a* MCBs for Pantry Equipments F-16, F-18, F-19, F-20 Y
b* MCBs for Pump Controller F-36 Y
c* MPCBs for Compressors F-03, F-05, F-09, F-11 Y
d* MPCB for Pumps F-21 & F-22 Y
e Contactor for Compressor K-33, K-34, K-38, K-39 Y
f Contactor for Blower Fan Motor K-26, K-28 Y Y
g Contactor for Condenser Fan Motor K-31, K-32, K-36, K-37 Y
h Contactor for Heater K-35, K-40 Y
i Contactor for Output of 60KVA Transformer, K-44 Y Y
j* Timer for External Power Supply/LMS, K-18 Y
k* Timer for Light ON/OFF, K-17 Y
l* Minimum Voltage Relay (MVR),U-2.3 Y
m* Rotary Switch for Disconnecting & Earth Device, A-2 Y
DC to DC converter (110V/24V) for Pump control & Sanitary
n* Y
control, U-2.1
o* Rotary Switch Power Supply ON/OFF, S-01 Y
p* Rotary Selector Switch Net-1,Net-2 & LMS, S-02 Y
Interlock Contactor for Change over of Coach light supply from
q Y
110VAC to 110V DC & Vice versa, K-48 (Obsolete)
r* Measuring & Monitoring Relay MMRs, K-03 & K-04 Y
s Main Feeder Contactors, K-01 & K-02 Y
t Electronic Module for Contactors, K-01, K-02 (Obsolete) Y
u Door for complete Switch Cabinet unit Y
2 Light Fittings
a Lavatory Light Fitting Y
b Lavatory Exhaust Fan Y
c Diffuser for Rajdhani Exp Coaches Y
d Mobile Switch Socket complete Y
3 Pantry Equipment
a* 3 Pin Sockets/MCBs for operation of equipment Y
b Hot Water Boiler/Geyser Y
c Heating Element assembly complete with Blower unit rotary Y Y
switch, thermostat & indicator for Hot cases
d Filter of Electric Chimney Y
e Pantry Exhaust Fan Y
4 Roof Mounted AC Package Unit
a Canvas Duct for Return Air Y
b Canvas Duct for Supply Air Y
c Canvas Duct for Fresh Air Y
d Anti Vibration Mounting Pad Y Y
e Filter media mix air Y
f Filter cassette Fresh air Y
g ESTI cartridge Bulb Y
h Over Heat Protection Switch Y
* Conditional replacement item
266/493
895731/2022/O/o Dy.CEE/Chg/HQ/NR
1st 2nd
SN Items
POH POH
i NTC sensors Y Y
j Thermal Insulation Sheet Y
K* Earthing Shunt Y
l* Rotary Switch ON/OFF for AC plant Y
m Fresh Air Filter Assembly Y
n FRP Blade for Condenser Fan Blade Y
5 ZS Coupling
a* Contact Pin assembly for Phases, Neutral & Earth with Springs Y
b* Connector Female assembly Phases, Neutral & Earth with Y
Springs
c* Ratchet arrangement for coupling sockets assembly Y
d* Insulating Base with fixing screw kit for coupling socket Y
e* Insulating Base with fixing screw kit for Jumper Plug assembly Y
f* Hinged cover assembly for Blind socket Y
g* Ratchet arrangement for Blind socket assembly Y
h PMA protective sleeve for cables Y
i Conduit seal ring & all type gaskets Y
j* Coupling socket housing assembly Y
k* Lever Tie Bow RH & LH Y
l* Connecting link lever arm Y
m* Rivet Pin link long Y
Complete ZScoupling with ratchet sockets assembly & Blind
n Y
socket
6 Monoblock Pump
a Complete Mono block Pump unit Y
7 Battery Fuse Box
a* Positive Battery Fuse Box Complete Y
b* Negative Battery Fuse Box Complete Y
8 Additional Proposed New Must Change Items
a PACIL Fitting Y
b Limit Switch used for Socket Assembly Feeder Junction Box Y
c WC engagement Light Y
d Capacitor Bank Y
e Rodent control glands, sockets, wire mesh etc Y
* Conditional replacement item
267/493
ANNEXURE-IV
895731/2022/O/o Dy.CEE/Chg/HQ/NR
OPERATONAL TESTING OF SWITCH BOARD CABINET
Page 1 of 4
268/493
895731/2022/O/o Dy.CEE/Chg/HQ/NR
Relay rating Applied voltage Tripping time
750V AC 690V AC 7sec
Single phasing tripping test on MMR:-Variable supply of 3ф 750V AC provided to voltage phase control relay of
750V AC. To check single phasing tripping test. Disconnect any phase of relay, Single phasing indication will display
on relay and output supply will disconnected. Observation is as under:-
Page 2 of 4
269/493
895731/2022/O/o Dy.CEE/Chg/HQ/NR
S1X1-259
Compressor unit 2.1 S1F09 S1K38 S1X1-260 3 Ø 415 Volts O.K.
S1X1-261
S1X1-263
Compressor unit 2.2 S1F11 S1K39 S1X1-264 3 Ø 415 volts O.K.
S1X1-265
S1X1-273
Condenser Fan 2.1 S1F12 S1K36 S1X1-274 3 Ø 415 Volts O.K.
S1X1-275
S1X1-276
Condenser Fan 2.2 S1F13 S1K37 S1X1-277 3 Ø 415 Volts O.K.
S1X1-278
S1X1-267
Electrical heater 2 S1F14 S1K40 S1X1-268 3 Ø 415 Volts O.K.
S1X1-269
S1X1-279
Exhaust Fan S1F15 S1K29 S1X1-280 3 Ø 415 Volts O.K.
S1X1-281
Over voltage tripping test on MMR415VAC:-Variable supply of 3ф 415V AC provided to voltage phase control relay
of 415V AC. To check over voltage tripping test, set relay at 10% setting, than increase supply voltage up to 10% of
rated supply voltage of relay. During increasing voltage, relay will trip. Observation are as under:-
Single phasing tripping test on MMR415VAC:-Variable supply of 3ф 415V AC provided to voltage phase control
relay of 415V AC. To check single phasing tripping test. Disconnect any phase of relay, Single phasing indication will
display on relay and output supply will disconnected. Observation are as under:-
Page 3 of 4
270/493
895731/2022/O/o Dy.CEE/Chg/HQ/NR
withstood the result:
6) Test for verification of insulation resistance as per clause 8.3.4 of IS: 8623:
The auxiliary relay connected with circuit shall be disconnected from main supply and kept Earthing Device switched
on with all fuse in circuit. Now applied 500 VDC supply between each phase & panel body. Observation are as under:-
8) Checking for satisfactory operation of Rotary switches by rotating 10 times clockwise and 10 times
anticlockwise:
All the Rotary Switches are checked by rotating 10 times clockwise and 10 times anti-clockwise. The result found to
be satisfactory.
Page 4 of 4
271/493
a
895731/2022/O/o Dy.CEE/Chg/HQ/NR
Annexure
SN Activityy Perlodicity
1 Thermal screening of power panel equlpment D2 schedule.
including D&ED rotary terminals.
2Thermal screening of power Harting connector at D2 schedule.
roof.
3 Thermal D2 schedule.
screening of ZS coupler plug assembly.
4Thermal screening of ZS coupler/wrachet terminal D3 schedule.
junction box.
5Thermal screening of 60/19/5 KVA Transformer D3 schedule.
terminal plate connections
6 Thermal screening of power ESTI Connector & heater D3 schedule &
assembly connection terminal. during winter
drive.
7 Thermalscreening of Cells coupling. D3 schedule.
8 Thermal screening of Blower motor ,condenser D3 schedule.
motorcompressor motor and water mono block
pump terminal box
9 Thermal screening of under slung constant voltage, D3 schedule.
regulated cum emergency battery charger terminals
connections.
10 Thermal screening of Pantry Equipments like water D3 schedule.
boiler & hot case connection terminals.
B. Equipment Details
1 AC Unit Make
CP-1.1 CP-2.1
Compressor
2
(07-10 Amps)
CP- 1.2 CP-2.2
CD-1.1 CD-2.1
Condensor Motor
3
(1.5 – 2.1 Amps)
CD-1.2 CD-2.2
Blower Motor
4
(1.5-2.5 Amps)
6 D&ED
Unit-I Unit-II
CP 1.1 CP1.2 CP 2.1 CP1.2
Make- tripping Make- tripping pressure:- Make- tripping Make- tripping
17 HP Cutout Tripping at 415 psi pressure:- pressure:- pressure:-
Sensor name RT-I RT-II AT-I AT-II ST1 ST2 HYGROSTAT 1 HYGROSTAT 2
19 NTC Sensor
location
20 Heater Current
25 ZS Ratchet Coupler
26 Junction Box
27 Dummy Plug
28 Coach Light
29 Berth Light
30 Call bell
36 Power Bank
ESTI-1 wheather it is in
circuit/bypass
Heating mode testing (Check the ESTI-2 wheather it is in
40 tripping of heaters i.e. OHP. The circuit/bypass
OHP setting is 65°C. OHP-1(tripping time)
OHP-2(tripping time)
41 Air Flow
42 Underframe Fastner
43 Cable trench
44 Canvas Duct
Pantry Equipments:-
45 Hot Case-1
46 Bottle Cooler
47 Deep Freezer 1 2
1
48 Chimney 2
3
1
49 Water Boiler 2
3
50 Refrigerator
51 Hot Plate
Date of attended
Date of Failure Equipment Detail Make & S. no. Reason of Failure Detail of Action taken & joints with the firm
by firm
Signature of supervisor