Professional Documents
Culture Documents
MS For The Arrangement of Pilot Road at Ch. 4+300 4+400 GPAR (Add Sub)
MS For The Arrangement of Pilot Road at Ch. 4+300 4+400 GPAR (Add Sub)
Method Statement for Remove & Replace Peat with Boulders, RUC 4at Km 14+400 by Underwater Excavation
___________________________________________________________________________________________
Method Statement for Remove & Replace Peat with Boulders, RUC 4 at Km
14+400 by Underwater Excavation
Ch. 14+400
2.0 Equipment
The major equipment to be used for the wet excavation, but not limited to the
following:
3.0 Materials
3
Southern Transport Development Project
Method Statement for Remove & Replace Peat with Boulders, RUC 4at Km 14+400 by Underwater Excavation
___________________________________________________________________________________________
The major materials to be used for the above work include, but are not
limited to the following:
A Site Engineer will be assigned throughout the working period for the
safety and supervision work.
The operational conditions of the equipment and dump trucks to be
used for this work have to be thoroughly examined before the actual
start of work.
The physical conditions of the crews, especially the operators of
equipments and truck drivers should also be physically fit, healthy and
alert.
All operators and workers will be properly briefed / oriented beforehand
with the procedures to be undertaken for familiarization and ease of
execution.
Shape monitoring of HES87N at Km 14+370 has already started on 19 th
November 2009 and carrying out once a week. The monitoring will be
continued until completion of the backfilling of proposed RCBC three
times a week. (Appendix C)
The survey points will be established and the monitoring of the cut slope
through the fill between the excavation to remove unsuitable soil and the
adjacent HES structure will be carried out 3 times a week and the
records will be maintained. (Appendix D)
Rock materials shall be carefully loaded and unloaded to and from
trucks.
There should be proper display of warning signs in the area.
Suitable personal protective equipment shall be worn by workers at all
times when working, such as safety shoes, safety helmets, gloves,
safety belt, etc.
Qualified helper or signalman shall be employed in the operation of the
backhoe and unloading of rock onto the soft ground.
No equipment shall be allowed to go into the soft ground without proper
assessment and stability check by a competent supervisor.
A strict compliance with the daily safety checklist for all equipment and
trucks shall be undertaken.
Secure the excavated slope with barricade as a safety measure in soil
case collapse happened.
Competent flagman will be arranged at all times on the pilot road
when dump trucks are operating.
4
Southern Transport Development Project
Method Statement for Remove & Replace Peat with Boulders, RUC 4at Km 14+400 by Underwater Excavation
___________________________________________________________________________________________
The methods and procedures for the removal and replacement of peat with
boulders + RUC 4 materials by wet excavation are as follows:
The designated area for remove and replace by underwater excavation will be
properly marked using survey instruments. The area involved is Km 14+400.
(Area marked in the drawing No. STDP-KG-(MS025)-EXC-001 (Rev C))
Selected Boulders and RUC4 Materials will be transported to the site by means of
the dump trucks.
5
Southern Transport Development Project
Method Statement for Remove & Replace Peat with Boulders, RUC 4at Km 14+400 by Underwater Excavation
___________________________________________________________________________________________
The Engineer’s inspection will be carried out to determine the depth of removal of
unsuitable material at this area. Long Arm Excavator EX210 or equivalent will be
used to excavate unsuitable materials under the existing bottom level of the body
of water. In order to assure that the required depth as assumed by trial pits, are
attained, the arm of the excavator shall be paint marked on the corresponding
metres length. This shall be jointly undertaken by the Engineer and the
Contractor. The span of excavation will be limited to the reach of backhoe arm. It
is approximately 5 metres. Excavation will be done half width by half width and
zone by zone as shown in the drawing No. STDP-KG-(MS025)-EXC-001 (Rev C).
(Appendix B) and replacement will be made accordingly using the shot rock
<0.45m (80%) and 10 ~ 20 mm aggregate (20%).
Disposed material is quite wet, therefore disposal dike will be required to prevent
muddy water from coming out to public drainage at disposal area. In case it is
required, a drying up yard for wet disposal materials will be prepared near
unsuitable excavation site. Presently unsuitable materials will be dumped at
previous pilot road at 15+900 ~ 16+200 RHS.
Once the excavation is completed, boulder materials shall be immediately
dumped up to +1.5m MSL. This rock fill will form part of the permanent structure.
After completing shot rock filling with 10 ~ 20 mm aggregate level it up and
allow of traffic of the trucks and equipment. Then further filling of shot rock
and 10 ~ 20 mm aggregate materials will continue up to required level and at
the same time move on to the other section for removing and replacing unsuitable
peat.
The contractor will forwarded the Inspection requests to the Engineer for the
following hold points.
8.0 Appendix
6
Southern Transport Development Project
Method Statement for Remove & Replace Peat with Boulders, RUC 4at Km 14+400 by Underwater Excavation
___________________________________________________________________________________________