Item Wise Rate Tender

Date: 14/12/2020

Labor Work Rates

Sr Item Unit Rate


No.
1 Earthwork
a. Excavation Up To 6’ Depth From G.L Cft. 9.00
b. 6’ To 10’ Depth Cft. 10.00
c. Above 10’ Depth Cft. 11.00

2 P.C.C. (1:4:8) Sft. 16.00


a. Up To 4” Thick Sft. 18.00
b. 4” To 6” Thick Sft. 22.00
c. More Than 6” To 9” Thick

3 P.C.C. With Light Reinforcement


a. 4" Thick (Single Mesh of Steel) Sft. 20.00
b. 4" To 6” Thick ( -Do- ) Sft. 25.00
c. 6" Tk. To 9 " Tk. Raft Slab with Double Mesh Steel Sft. 40.00
4 Rubble Soling Works with Sand Filling

a. 9” Thick Sft. 20.00

5 Footing Works
a. Simple Cft. 120.00
b. Eccentric Cft. 140.00
c. Special (I.E., Box, Raft & Combined) Cft. 150.00
d. Footing Up to Size (4’ X 4’) Nos 2000.00
6 Filling Of Earth
a. Excavated Earth Refilling Cft. 4.00
b. Earth From Outside Cft. 5.00
c. Road Compacting with Hammering (Up To 6" Tk) Sft. 16.00

7 R.C.C. Works for Column


Regular Cft. /Rft/Sq.Ft 150.00
Round Or Special or L Shape Cft. /Rft 200.00
Expose Round Column (With All Formwork Costs) Cft. /Rft 400.00
Expose Regular Column (With All Formwork Costs) Cft. /Rft/Sq.Ft 250.00
Expose Column L Shape Cft. /Rft/Sq.Ft 400.00
Note: - Column Width Less Than 9” Measurement Will
Be Calculated In Sq. Ft
Lead @ 10% Per Floor Will Be Charged Extra
8 Augar(M20 Grade)
a. 9” Dia Rft 100.00
b. 12” Dia Rft 130.00
c. Bulb Nos 300.00
9 R.C.C. Works for Beams
a. Simply Supported (10' Ht) Cft. / Rft 150.00
b. Cantilever / Inverted Cft. / Rft 160.00
c. Expose Beam with Laminated Ply Only (With Cft. / Rft / Sq. 250.00
All Formwork Cost) Ft
d. Partition Beam (10' Ht.) 41/2"K & 6"Tk Sft 150.00
e. Expose Partition Beam (10'ht) 4 1/2" & 6" Tk Sft 300.00
f. Expose Partition Beam (10'ht) 4 1/2" & 6" Tk Sft / Cft / Rft 130.00
g. Hidden Beam Rft. 55.00
h. After 10' Each Height (Lead) Per Floor 10%
Extra For Curved or Any Other Shape of The Beam Cft / Rft / 100.00
Sq.Ft
10 Staircase
a. Regular Tappa: Riser-7" Trade-10" (Landing Rft. 400.00
Considering in Sq. Ft)
b. Kadi Tappa Riser-6 Trade-12" ( -Do- ) Rft. 550.00
c. Extra For Exposed Finish or Curved Stair Works in Rft. 200.00
Above Rates
11 R.C.C. Work for Pardi
a. 4” Thick Single or Double Shuttering Sft. 100.00
b. 4” To 6" Thick Single or Double Shuttering Sft. 120.00
c. 6" To 9" Tk (-Do-) Sft. 150.00
d. Drop Pardi (10'ht.) Sft. 150.00
e. Expose Pardi (Up To 6" Thick) (With All Formwork
Costs with Plain Finish)
Two Side Expose or One Side Expose. Plain Finish in Sft. 300.00
Laminated Ply Only
f. Expose Wall (Tk 6" To 12*) Plain Finish in Laminated Sft. 350.00
Ply Only
Lead @ 10% Per Floor for Every 10' Height Will Be
Charged Extra
g. Extra For the Curved Expose R.C.C. Wall, Beam, Sft / Cft / Rft 100.00
Column
12 R.C.C Slab
a. Simple
One-Way Or Two-Way (Up To 4” Thick) Sft. 100.00
Expose One Way or Two-Way Slab In A Pattern (Up To Sft. 250.00
4” Thick)
One-Way Or Two Way (4" To 6' Thick) Sft. 125.00
Expose Slab One Way or Two Way (4" To 6" Thick) Sft. 280.00
P.T Slab with Double Mesh or Single Mesh Up To 1' Tk Sft. 175.00
Expose P.T Slab with Double Mesh or Single Mesh Up Sft. 400.00
To 1'tk
b. Slopping Slab (Up To 6'tk) Sft. 200.00
c. Expose RCC Slab with Laminated Ply (More Then1' Tk) Cft. 300.00
d. Slab With Inverted Bean Sft. 130.00
e. Staging For the Slab for Every 10 Ht. Staging. Sft. 100.00
Note: Expose Works in Laminated Ply Plain Finish
Only. For Design Works
Formwork Will Be Supplied by The Owner and Labor
Will Be Charged for Extra
Lead @ 10% Per Floor for Every 10' Height Will
Be Charged Extra
13 R.C.C. Work for Lintel or D.P.C.
a. 4" Thick Rft. 60.00
b. 6" Thick Rft. 70.00
c. 3" To 4" Rcc Cornice Rft. 80.00
d. Exposed Lintels Rft. 350.00
14 RCC Chajja (10’ Ht.) Each 1’ Rs. 50 Extra Sft. 80.00
R.C.C. Exposed Chajja Sft. 350.00
15 R.C.C. Work for A Loft Sft. 80.00
R.C.C. Exposed Loft Sft. 350.00
16 Brick Masonry Works
a. 4.50” Thick Sft. 25.00
b. 9” Thick Sft. 35.00
c. More Than 9” Thick Sft. / Cft. 50.00
d. Pillar 12” X 12”.9” X 9” Rft. 60.00
e. Brick Tappa Rft. 70.00
f. Expose Brickworks (9” Tk) Sq.Ft/Cft 130.00
Expose Brickworks (4.5”) Tk Sq.Ft 100.00
g. Block Work Sft 30.00
h. Cement Jali Fixing Nos 200.00
i. Cement Thambli Fixing Nos 60.00
j. Pointing Works to The Exposed Brickworks Or Rubble Sq.Ft 50.00
Works On Each Side
k. Expose Rubble Masonry Works Cft. 120.00
17 Cement Plaster
a. Smooth Plaster Single Coat (Tari) Inside Sft. 22.00
b. Mala Plasters Single Coat (Inside) Sft. 25.00
c. Tari Patta Upto 6* Thick (Inside) Rft. 22.00
d. On Open Beams, Columns, Ceiling, Pardi, etc. Sft. 26.00
e. Smooth Outside Single Coat Sft. 27.00
f. Double Coat Mala L/S Or O/S Sponge Plaster. Sft. 35.00
For Roller Finish Charged an Extra 5 Rs/Sqft In Given
Rates)

g. Single Coat Rough (Inside) Extra 2 Rs/Sft for Out-Side Sft. 24.00
h. Kadi Tappa Stair Plaster Rft. 26.00
i. Chhajja Plaster Sft. 25.00
j. Patta Upto 6" Thick (Outside) Rft. 24.00
k. Ghisi Rft. 20.00
l. Roller Finish Plaster (Single Coat) Sft. 30.00
m. Gun Plaster (Single Coat) Sft. 26.00
n. Vatta Rft. 20.00
o. Tapak In Slab Rft. 25.00

18 Water Proofing Works Sft. 35.00

19 Fixing Hook Nos. 100.00

20 Fixing Kada Nos. 100.00

21 Tancha Of Rcc Sft. 4.00

22 Door / Window Fitting Sft. 20.00

23 Ventilator Fitting Nos 200.00


24 Nalia Fixing Sft. 40.00

25 Water Tank (U.G.) & For 0.H Water Tank Lead 10% Litre 7.00
/ Floor Consider
Extra
26 Fixing Steel Grill Sft 20.00

27 Fixing Of Chicken Mesh (With Fiber Mesh) Rft 14.00

28 Expose Groove Works in The Exposed Surface of Rft 30.00


Wall Slab, Column, Beams

29 Expose Surface Cutouts in Beam, Slab Wall, Nos 1000.00


Columns

30 Expose Rendering Works with All Material Cost Sft. 50.00

31 M.S. Plate (With Hold Fast) Fixing In R.C.C Without Nos 500.00
Welding Works (Labor)

32 Fixing Of Foundation Bolts in R.C.C. (Labor Only). Nos 300.00


Up To 20 Mm Bolt

20 Min To 32 Mm Dia. Bolt Nos 400.00

33 Making Pockets in R.C.C. For The Fixing of Plates or Nos 300.00


Bolts (Labor)

34 Ferro Crete Wall Works Sq.Ft 200.00

35 Rebar Works (Hilti or Fischers)


8 Mm Nos 100.00
10 Mm Nos 125.00
12 Mm Nos 150.00
16 Mm Nos 200.00
20 Mm Nos 250.00

29 Dismantling Works by Breaker Machine


a. R.C.C. Hours 150.00

30 Departmental Labors
a. Carpenter/ Fitter Day 800.00
b. Helper Day 600.00
c. Mason Day 1000.00
d. Male Labor Day 500.00
e. Female Labor Day 475.00

31 Filling Of Holes by Plastic Datta and G.P. Grout Nos. 20.00


(12mm Dia & Wall 6” Thick)
Terms & Conditions:
1. Insurance for labor should be barred by the owner.
2. Arrangement for labor accommodation, w.c, policy, water & electricity facility also
provides by for the labor.
3. Dewatering and breaking work from the foundation should be carried out at the
owner’s coat.
4. The above rates are for labor work only.
5. Government tax is not Included in the above rates so it will be charged extra.
6. GST: 18% on labor as per the government norms.

7. Payment against the bill for the work done shall be made within 5 days, falling in it
Contractor shall not be responsible for delay in completion of the work.
8. The owner should store necessary material near the site within 50 feet Range.
9. Water, watchman, and Electrification arrangements shall be provided at the site by the
owner.
10. Rates for the extra items shall be negotiated with the advice of the architect.
11. The above rates are valid for 12 months from the date of submitting the same.
12. Measurement of slab & R.C.C. wall shall be taken full and thickness of slab or wall
shall not be deducted from the depth of beam or column.
13. Arrangements for curing and watchman for 24 hr. shall be arranged by the owner.
14. In the above rates (10 % / Floor/10' HT) lead will be charged extra.
15. During the construction work, all labor is staying on-site till the work will be
complete or provide an optional area for accommodation.
16. All work will be carried out at the owner’s risk & cost so all expenses regarding
damages, site maintenance costs any penalties, and remedies work should be carried
out at the owner’s cost.
17. For exposed work touching work for the RCC member will be carried out by the
owner, touching work cost for the exposed work should be charged extra.
18. Concreting work Quantity more than 50 C.M.shell be carried out by R.M.C Only and
for that, no deduction in rate shall be entertained.

Owner's sign. Architects sign. Contractor’s sign.