dcdc

PROGRESS REPORT

SITE PREPARATION, SITE BUILD AND EQUIPMENT INSTALLATION,


COMMISSIONING & TESTING FOR TNB-IT’S ADVANCED METERING
INFRASTRUCTURE (AMI) COMMUNICATION PROJECT

SITE NAME : P/E TAMAN KG MEDAN


SITE ID : EB_BKLG04_122

No Remarks
1
2
3
4
5
6

Checked & Submitted by : Checked & Received by :

Please sign here Please sign here

Name : Muhammad Al-Qassim Bin Ahmad Name : Rabi'ah Binti Mohd Nordin
Designation : State Project Manager, Lembah Designation : Project Manager, AMI, Theta
Klang AG Global Venture Sdn Bhd Technologies
Date : 10/02/2023 Date :
dcdc

SITE NAME MAXIS PERO

SITE ID EB_BRWG01_005_3

1) PROGRESS WORK
a) PLINTH INSTALLATION
dcdc

b) ERECTION POLE
dcdc

c) ELECTRICAL WORK
dcdc

d) GROUNDING
dcdc

2) SITE COMPLETE
a) BOOM FLOOR AND SECURITY CAGE INSTALLATION
dcdc

b) POLE ERECTION
dcdc

c) ELECTRICAL WORK
dcdc

d) GROUNDING