PRE-CONSTRUCTION SURVEY REPORT

This document lists the following:


 Site Information.
 Propose Site Location.
 Propose Equipment, Electrical and Grounding Location.
 Propose Cable Routing Location.
 Others Miscellaneous.
 Propose Pre-Construction Drawing.

Project Name AMI PHASE 2


BAC Name KLANG
Primary Gateway GW_BKLG03_01_TNB KRCC
Site Name PE TMN SRI GADONG NO2
Site ID EB_BKLG03_088
JALAN BAWAL 1/KS1, KAMPUNG DELEK
Site Address
41250 KLANG, SELANGOR
Contractor Name FGV PRODATA SYSTEMS SDN BHD
Contract TNB-IT No 20/2019
Date of Survey 23/11/2022

PRE-CONSTRUCTION SURVEY REPORT SIGN OFF


CONTRACTOR TNB-ICT

Name

Designation

Contact Number

Date 5/12/2022

Signature

1|Page
PRE-CONSTRUCTION SURVEY REPORT
1. Site Information:
Site Name PE TMN SRI GADONG NO 2
PMU PPU SSU PE y
Site Type (check one)
LV Pole Others, Please specify type of site
s
GW EB Collector
Device Type (check one)
Others Please specify type of device

Site Geo Coordinates Latitude 3.029389°N


(in decimal degrees) Longitude 101.420389°E

Building / Structure Height 4 Meters


Device Mounting location
Rooftop New Pole Wall
(check one)
LV Pole
Proposed Rooftop/Wall Height N/A Meters
Proposed Rooftop Area N/A Sq. Meter/Sq. Feet.

Proposed Pole/Mast Height 20 Meters


Distance of Power Line from
N/A Meters
Pole location
Note: There must be a
minimum clearance of 40
meters from the identified pole
location to path of power line
at PMU sites
Site Access Details Width 3.8 Meters Height 2.5 Meters

Sky Lift Access Available Yes No


Site Power Supply Source Type
AC DC
(check one)
If Power Source Type AC 230V
Location of PSU (check one) Indoor Outdoor
Distance from PSU to Power
9.0 Meters
Source
Distance from PSU to Pole
11.0 Meters
foundation
If Power Source Type DC DC 48V Retifier system
DC Supply (check one) 48 VDC 24 VDC
DC Supply Power N/A Watts

2|Page
PRE-CONSTRUCTION SURVEY REPORT
POE Enclosure N/A
Location of POE Enclosure (check
Indoor Outdoor
one)
Distance from POE Enclosure to
N/A Meters
Power Source
Distance from POE Enclosure to
N/A Meters
Pole foundation
Battery N/A
Battery Backup Available (check
Yes No
one)
POP Details for Gateway This section is applicable only for Gateway
Type of POP Location Fiber based MPLS Network Fiber based SDH Network
MPLS/SDH Port Type RJ 45 SFP
MPLS/SDH Port Number
N/A
(If available)
MPLS/SDH Device Make N/A Model N/A
Distance from MPLS/SDH port to
N/A Meters
POE LAN port
5.7 Remarks (if any)

- ACCESS FOR MACHINERIES ARE NOT AVAILABLE (NARROW ACCESS ROAD)

3|Page
PRE-CONSTRUCTION SURVEY REPORT
2. Site Location

PE TMN SRI GADONG 2

4|Page
PRE-CONSTRUCTION SURVEY REPORT
3. Site View Location
1. PE Signboard Photo

2. Main Entrance Photo

5|Page
PRE-CONSTRUCTION SURVEY REPORT
4. Propose Structure Location
1. Propose structure location with pole and equipment, cable routing & grounding illustration.
EXTENDER
BRIDGE
PROPOSED
LIGHTNING
ARRESTOR
PROPOSED
NAN
ANTENNA

PROPOSED 20m
HEIGHT POLE

PROPOSED
LANTERN ARM

PROPOSED GROUNDING
CHAMBER FOR LIGHTNING
ARESTOR & EQUIPMENTS

PROPOSED CABLE

6|Page
PRE-CONSTRUCTION SURVEY REPORT

PROPOSED
JUNCTION BOX

PROPOSED TO HACK
WALL FOR CABLE
ROUTING

PROPOSED CABLE

7|Page
PRE-CONSTRUCTION SURVEY REPORT
5. Propose Indoor Equipment Location
1. For Extender Bridge.
a. Propose PSU & RF DB enclosure location with illustration.
b. Propose AC power tapping location at existing MCB’s DB panel and cable routing to RF DB.
c. Propose PSU & RF DB enclosure at existing building busbar location with routing and measurement
(leakage and grounding).

PROPOSED TO HACK PROPOSED CABLE


WALL FOR CABLE
ROUTING

RF DB RF PSU

8|Page
PRE-CONSTRUCTION SURVEY REPORT

PROPOSED POWER CABLE RUN


THROUGH PVC CONDUIT TAPPED AT
EXISTING POWER POINT

POWER TAPPED AT
EXISTING POWER
SOURCE

9|Page
PRE-CONSTRUCTION SURVEY REPORT
6. Propose Cable Routing Location
1. Propose structure location with pole and equipment, cable routing & grounding illustration.
a. 40mm HDPE & 50mm GI Pipe.
b. Trenching.
c. Hacking.
d. Cable marker

PROPOSED 4mm ARMOURED


POWER CABLE & 16mm EARTH
CABLE RUN INSIDE 40mm HDPE
PIPE (2800mm)

PROPOSED 2 RUNS OF CAT6


CABLE ROUTING INSIDE 40mm
HDPE PIPE (2800mm)

PROPOSED CAT 6, SERIAL CABLE


RUN INSIDE 40mm HDPE THROUGH
50mm GI PIPE LAY UNDER GREEN
SLAB UNDERGROUND (4800mm) BY
TRENCHING METHOD

PROPOSED 4mm ARMOURED POWER


CABLE & 16mm EARTH CABLE RUN
INSIDE 40mm HDPE THROUGH 50mm
GI PIPE LAY UNDER GREEN SLAB
UNDERGROUND (4800mm) BY
TRENCHING METHOD

10 | P a g e
PRE-CONSTRUCTION SURVEY REPORT

PROPOSED 4mm ARMOURED


POWER CABLE & 16mm EARTH
CABLE RUN INSIDE 40mm HDPE
PIPE (2800mm)

PROPOSED 2 RUNS OF CAT6


CABLE ROUTING INSIDE 40mm
HDPE PIPE (2800mm)

11 | P a g e
PRE-CONSTRUCTION SURVEY REPORT

PROPOSED CAT 6 & SERIAL CABLE


RUN INSIDE GREEN METAL
TRUNKING (3000mm)

PROPOSED 4mm ARMOURED


POWER CABLE & 16mm EARTH
CABLE ROUTING TO RF DB RUN
INSIDE ORANGE METAL TRUNKING
(3000mm) RF DB RF PSU

PROPOSED POWER CABLE RUN


THROUGH PVC CONDUIT TAPPED AT
EXISTING POWER POINT (8500mm)

POWER TAPPED AT
EXISTING POWER
SOURCE

12 | P a g e
PRE-CONSTRUCTION SURVEY REPORT
2. Propose Grounding Location
1. Propose chamber location for equipment and lighting arrestor location.
2. Propose existing chamber location for grounding tapping with leakage measurement (clamp meter).
3. Propose earthing cable routing from new chamber location at structure to proposed existing chamber
location for grounding tapping.

PROPOSED GROUNDING
CHAMBER FOR LIGHTNING
ARESTOR & EQUIPMENTS

PROPOSED GROUNDING
ROUTING

13 | P a g e
PRE-CONSTRUCTION SURVEY REPORT
3. Others Photo

TOOLBOX SAFETY MEETING

UNDERGROUND MAPPING

14 | P a g e
PRE-CONSTRUCTION SURVEY REPORT

LAND SURVEY

15 | P a g e