Professional Documents
Culture Documents
PMQ Q&a V7 DB
PMQ Q&a V7 DB
1
Question 2
Part (a) Describe two benefits of having an embedded project
management office.
Part (b) Explain three differences between the Functional and Matrix
types of organisational structure.
Answer (a)
1)Standardisation. The embedded PMO will set standards for documents,
policies and procedures which are mandatory for all projects, and will
ensure compliance. This improves project performance by removing the
constant need to reinvent the wheel. It also makes it easier for people to
move between projects.
2)Alignment with corporate goals. In large organisations it is often easy for
projects to arise which do not contribute to the overall corporate strategy
and aims. Some projects, even though locally beneficial, may damage
corporate goals. By having a strategic role and a responsibility for
approving all projects the PMO will prevent this.
Answer(b)
1)Project management power. In a functional structure the project manager
is usually subservient to his functional manager. All major decisions are
taken by the functional manager. The project manager can be little more
than a coordinator. In a matrix organisation the project usually spans
several functions and the project manager typically reports into a level
above functional managers and thus has far more power.
2) Staff availability. In a functional structure all or most of the project staff
will belong to the function. Some will be full time and some part time. In
this situation staff can easily be pulled of the project without notice against
the wish of the project manager. In a matrix organisation the staff will
come from all over the organisation and away from the influence of their
parent function.
2
3)Functional conflicts. A matrix organisation is usually employed when a
project covers several functions. This can give rise to disagreement
between the functions which the project manager has to resolve. In a
functional structure this situation cannot occur.
3
Question 3
Part (a) Explain two elements of a procurement strategy and why
these are important.
Part (b) Explain three steps in the supplier selection process for a
project.
Answer (a)
1)Make or Buy. Organisations often have “in house” capability for all or
part of a project so there needs to be a decision on make or buy. When
calculating the cost of each option care must be taken to ensure that all cost
both direct and indirect are taken into account and also the overall effect of
the decision on the organisation e.g. would a decision to make have a
knock on effect on other projects which may require the same resources.
Would a decision to buy put in house facilities at risk?
2)Contract Type. Often in Procurement there is a choice between agreeing
a fixed price for a contract or paying for time and materials consumed. A
fixed price gives certainty and hence has less risk for the buyer, but T&M
could turn out to be cheaper. However if the contract proved more difficult
than first thought there is no limit to the cost thus T&M is riskier for the
buyer.
Answer(b)
1)Define the requirements. The requirements are documented in the
“Invitation to Tender” (ITT). This will detail the requirements in enough
detail for a potential supplier to plan and cost the requirement. The format
of the response will be specified by the buyer so as to facilitate easier
comparison of rival bids
2)Issue Invitation to Tender. The ITT is made available to anyone and
there is a response deadline. It is a mandatory requirement that the
tendering process must be seen to be open and fair to all potential bidders.
This requires that all bidders must be given exactly the same information
4
on which to base their bid. Information given to one must be given to all.
Even with well-prepared bid documents there will be ambiguities and
differences in interpretation. Any such problems can be addressed at a
Bidders Conference where all potential suppliers can attend and ask
questions. If this is impractical the conference could be web based.
3)Evaluate responses. Buyers must have a selection process which is
objective and not subject to personal prejudice. Such a method will also
help to demonstrate that the selection process has been fair and transparent.
A common way of doing this is by using a weighting system. The buyer
develops a list of factors such as cost, financial status and track record.
Each factor is then given a weighting based on its importance then each
bidder is scored, and a total score obtained. The top scorers will constitute
the short list.
5
Question 4 part a. In an iterative life cycle, explain two components of
the project management plan that need to be taken into account when
arriving at the deployment baseline.
Because not all requirements are detailed up front, detailed project
planning as carried out in a linear life cycle is not possible. There will be a
time box created so the first component to consider is the duration of the
time box. This will be an arbitrary value. It should be long enough to
create some usable functionality.
The second consideration is the amount of resources to deploy. This will
then allow for planning what functionality will be deliver by the time box.
Once these are decided then a baseline resource schedule can be created
and a baseline budget determined
part (b) Explain three different methods of estimation in projects.
Choose three from the following: Parametric, Analogous , Analytical and
Delphi
1 Analytical
Also called bottom up, this method is based on the WBS. All the individual
lower level tasks in the WBS are estimated independently and then rolled
up to produce the project estimates. This is a laborious method and its
accuracy is dependent on having a correct WBS. However it is the most
accurate way of estimating. It is sometimes known as the definitive
estimate.
2 Analogous Estimating
This is also called Top Down or Historic estimating. It simply involves
using experience from similar projects carried out in the past. It takes the
overall costs and timescales for similar projects and adjusts them for size
and complexity. The danger is that previous projects may have been
inefficient and/or badly managed. Comparative estimating can also be used
at task level to support bottom up.
6
3 Parametric Estimating
Parametric estimating uses a mathematical model or formulae to produce
project estimates based on input parameters. It is usually based on
historical data. Simple examples are square metres in construction and
lines of code in software development. Quantity Surveyors make extensive
use of parametric estimating.
7
Question 5
part (a) State four sources of conflict within a project.
part (b) Explain three benefits of a communication plan to a project.
Answer(a)
1. misunderstandings arising from unspoken assumptions and
miscommunication
2. personal antagonisms due to such things as stress, fear, jealousy,
culture or different value systems
3. people trying to exert power or impose their views
4. uncertainty and insecurity within the project team
Answer(b)
1. It defines the frequency and form of communication so as to keep
team members informed of what they need to know at the
appropriate times. It will ensure that everyone will receive the
same, accurate, timely information thus helping to avoid mistakes
and delays.
8
Question 6
part (a) Explain two reasons why projects are structured in phases in a
linear project life cycle.
Question part (b) Explain three differences between linear and
iterative life cycles.
Answer(a)
1. Trying to plan an entire project in detail up front is not always
possible. Breaking the project down into smaller phases that are
more manageable in terms of time, cost and specification means
that each phase can be planned and managed as if it were a separate
project
2. Breaking the project into phases allows for the provision of gate
reviews between phases which provides greater management
control and reduces risk
Answer(b)
1. In a linear life cycle all requirements are determined up front. In an
iterative life cycle requirements are determined for only the next
iteration.
2. In a linear life cycle the requirements are the starting point for
determining project schedule and resource requirements. In an
iterative life cycle a timebox is specified which limits the number
of requirement that can be satisfied.
3. In a linear life cycle there is usually no usable product until project
completion whereas for iterative projects each iteration produces
usable product
9
Question 7
part (a) Describe two elements that need to be considered when
allocating resources to a project schedule following a linear life cycle.
part (b) Explain three key differences between resource smoothing
and resource levelling.
Answer(a)
1. Human resource requirements. Each project task has different
human resource requirements. Some require 1 or more people with
similar skills others require a variety of skills, some all the time and
some part of the time. The resource requirements will be dictated
by the desired project end date but may be constrained by resource
availability and budget.
Answer(b)
1. Resource smoothing is time constrained. It tries to even out
resource usage by utilising float. Resource levelling is driven by
resource constraints at the expense of time.
10
Question 8. part (a) Explain two key differences between projects and
business as usual.
1.Projects are Unique. When doing a project, we create something that
did not previously exist. Some projects are totally different whist others
may contain some elements similar to previous projects. Business-as-Usual
usually involves the ongoing provision of specified products or services on
a Repetitive basis.
2.Projects are Temporary. They are endeavours that are Finite or
Timebound. They have a start point and an end point. When the objectives
are met, the project terminates. Busines-as-Usual is an ongoing process
that continues indefinitely.
part (b) Provide one explanation for how project professionals can
assess project context against each of PESTLE, SWOT and VUCA
1.PESTLE is simply a tool for providing some structure to the analysis of
project context. Brainstorming sessions can be made more efficient by
breaking the discussion of context into sections i.e Political- Economic-
Sociological-Technological-Legal-Environmental.
2.SWOT stands for Strengths, Weaknesses, Opportunities and Threats.
SWOT analyses are best carried out by “Brainstorming” using members of
the project team and appropriate stakeholders. SWOT analysis can be
carried out to analyse project context at any level of detail ranging from a
whole organisation to a sub-project or product.
3.VUCA stands for Volatile, Uncertain, Complex and Ambiguous.
Volatility is about the speed of change of project context. Uncertainty is
about our ability to predict the future. Complexity refers to the number
and variety of things we need to consider. Ambiguity refers to things that
we are not sure about
Quantifying all these features will allow an understanding of the overall
risks and uncertainties within. the project context
11
Question 9
Part (a) Describe two characteristics of an effective team.
part (b) Explain three reasons why it might be necessary to change
leadership styles to ensure effective management during a project.
Answer(a)
1. Morale. Team morale and motivation is high. The team works
together, and everyone participates actively team members trust,
help and support each other even to their own detriment.
2. Goals. Both team and individual goals are fully understood and
accepted by all team members. The goals are realistic and attainable
and team members are focused achieving them. All team members
understand how their contribution impacts the project goals
Answer(b)
1. In a crisis it may be necessary to adopt a very Direct or Telling
approach where people are just what to do without argument or
discussion and no dissent is allowed.
2. In a situation where the leader is not quite sure what is the best
thing to do then a more Democratic approach may be appropriate
where the leader encourages discussion and a team consensus is
arrived at.
12
Question 10
Part(a) Select two phases of the project life cycle and explain how the
roles of project manager and project sponsor differ during those two
phases.
1) Concept Phase. In this phase the Sponsor takes the leading. The
sponsor owns the project and is responsible for producing the Business
Case with which to justify the project and obtain the required approvals
and funding. There may not even be a project manager appointed until the
project is approved but if one is present the role to assist in producing the
Business Case and use his expertise to influence the content
2)Execution Phase. During this phase, the Sponsor has delegated full
authority to the project manager. The project manager leads the project
team and decides which problems and decisions are escalated to the
Sponsor who will continue to monitor the project and support the project
manager when necessary. The Sponsor will continue to chair the project
steering committee and gate reviews
Part(b) Select three of the project roles below and describe their
responsibilities throughout the project: Users, Project team members,
Project steering group and Product owner
1)Users. The users will be heavily involved up front in specifying the
requirements and at the same time agreeing acceptance tests. They will be
involved throughout Design and Implementation as requirements evolve
and change. Prior to Handover they will conduct acceptance tests and
eventually accept the system.
2)Project Team Members. Project team members will initially work with
users to define requirements and develop acceptance tests and also to assist
the project manager in developing the project plan. Once the plan has been
agreed their prime responsibility is to execute the work packages assigned
to them by their project manager or team leader.
13
3)Project Steering Group. The Steering Group oversees the project from
initiation to benefits realisation under the chairmanship of the Project
Sponsor. The PM will formally report to the Steering Group at regular
intervals and at “Gate” reviews. It supports the Project Manager
throughout the project especially with regard to Issues that have been
escalated to them by the project manager.
14
Question 11
Part (a) Explain two steps in a configuration management process that
help to manage the scope of a project.
1)Configuration Identification
This involves breaking down the project into individual configuration
items and creating a unique numbering system. The Product Breakdown
Structure forms the basis of the configuration, but the configuration also
includes all documents relating to the products such as requirements,
specifications, designs and plans. Identification of all the individual
configuration items effectively defines the project scope.
2)Configuration Control
During the project, the configuration will grow as the product is being
developed and modified through formal change control. Thus project
scope will continue to be controlled. Configuration control maintains
version control of all configuration items giving a full audit trail from
initial requirements to finished product
part (b) Explain three steps in a requirements management process
that help to establish the scope of a project
1)Capture
Requirements are captured mainly by interviewing relevant stakeholders
especially end users. It is necessary to gain a wide spectrum of opinions to
make sure that all possible requirements are captured. The totality of
requirements is the basis for establishing project scope
2) Analysis
The gathered requirements must be tested for feasibility, validity,
compatibility, acceptability, applicability and consistency. It is often found
that some of the requirements of different stakeholders are mutually
exclusive or are very difficult to provide. All such issues must be cleared
15
before finalising the requirements. If necessary the Sponsor must act as
referee. This process will establish the total desired scope.
3) Prioritise
It is often not possible to include all the requirements into time and budget
constraints. It is therefore usual to prioritise the requirements and exclude
some of them from the initial project scope. Here again the Sponsor may
have to referee. This process further refines the scope and determines the
scope of requirements that form the initial project baseline.
16
Question 12 part (a) Explain how understanding BATNA and ZOPA
can help plan and conduct negotiations.
BATNA is an acronym that stands for Best Alternative To a
Negotiated Agreement. It represents the best course of action that a
negotiating party can take if negotiations fail to reach an agreement. It is
the fallback plan if negotiations are unsuccessful. It is vital that a fall back
plan is in place because if there is no acceptable plan then you may have to
accept an unsatisfactory agreement
ZOPA stands for the Zone of Potential Agreement. Each of the negotiating
parties should have established a firm “Walk Away Point” i.e. No Deal.
The ZOPA will be the overlap between the two walk away points. If there
is no overlap then no agreement can be reached and each party must adopt
their BATNA.
part (b) Explain three ways in which conflicts can be addressed
1 Forcing (or Competing)In this situation one party to the conflict has
authority over the other and has imposed their preferred solution. From the
point of view of the winner the problem has been solved, but at the
expense of the relationship. This is a win-lose situation. Often used When
quick decisive action is vital; (e.g. in emergencies) or on important issues
where unpopular actions need implementing, (e.g. in cost cutting,
enforcing unpopular rules, discipline).
2 Collaboration In this scenario both parties together explore the best
solution to the problem i.e. they confront the issue, not each other. During
this process one or both parties may change their view but they both agree
that the resulting solution is the best and because of this and the fact that
the relationship has been maintained, or even enhanced, this is win-win.
Best used when the problem is too important to just compromise.
3 Avoiding This is the do nothing option. Just ignore the problem. This
shows low concern for both the problem and the ongoing relationship and
is a lose-lose situation because the conflict still exists. However it still may
17
be the best option in some situations such as when the issue is trivial or the
potential effort or disruption outweighs any benefit.
18
Question 13 part (a) Outline four ways in which outputs of knowledge
management informs decision making.
part (b) Explain three reasons why a project may close early.
19
Question 14 part (a) Explain two purposes of quality planning for a
project.
1) Quality Planning identifies all the policies, procedures, processes and
actions needed to ensure that the project will be conducted in
accordance with corporate quality policies
2) Quality Planning enables the specification of Quality Control testing
and monitoring processes which enable identification and correction of
product defects.
Part (b) Explain three key differences between quality control and
quality assurance when managing a project.
1)Quality Assurance is process oriented and is concerned with ensuring
that that the methods and processes designed for the project are being
followed.
Quality Control is reactive in that aims to identify and correct any defects
that do occur during the production process.
20
Question 15 part (a) Outline four reasons why a programme would be
used to deliver strategic change as opposed to using a project.
1 Strategic. The change is strategic and requires visibility and
accountability to the highest levels within the organisation.
2 Size and complexity. The change requires multiple interdependent
projects which must be managed as a whole.
3 Effect on Business-as-Usual. The project has severe implications for
ongoing operations so there is a requirement for ongoing coordination with
BAU which must be managed.
4 Risk. Where the project involves high risk to the parent organisation and
thus requires supervision at senior level
part (b) Explain three ways in which failure to comply with laws and
regulations can impact on project delivery.
21
3 Failure to follow regulations
Examples of this could include proceeding without planning approval and
flouting building regulations. The consequences of lack of planning
approval could vary from a delay whilst retrospective approval is obtained
or even an order to demolish. In the case of building regulations, the work
would have to be made good.
22
Question 16 part (a) Explain how the following two investment
appraisal techniques can be used to assess the validity of a project:
1.Internal Rate of Return (IRR) 2..Net Present Value (NPV)
NPV. Net Present Value (NPV) is defined as “The value today of a future
cash flow stream discounted using a specified interest/discount rate”. It
uses Discounted Cash Flow (DCF) to convert any cash flow into to a
single figure which ascribes a value to the project creating that cash flow.
We can use this to compare the profitability of different projects.
IRR. The limitation of NPV is that it is very sensitive to the interest rate
chosen. Instead of selecting a rate we can work out what the rate would
have to be make the costs and benefits of the project equal to each other.
The discount rate which equates the present value of costs to the present
value of benefits gives an NPV of zero. This value is the Internal Rate of
Return and represents the compound interest rate arising from the money
invested in the project.
part (b) Explain the following three steps in an information
management process: Collection, Storage and Dissemination.
1.Collection This step describes what project information is to be
acquired, its source and the method for collecting it. For instance
information on project performance would be obtained from the Earned
Value Management System based on input from team members carrying
out the work
23
2018 Example Paper
Question 1 part (a) List and describe four external factors that can
affect the timeline of a project.
1) Late delivery A crucial component from an external supplier fails to
arrive on time and hence causes following activities dependant on this
component to slip.
2) Incorrect Quality/Specification
A project deliverable was thought to be completed on time but on
further inspection was found to be the wrong specification or failed to
meet quality parameters
3) Scope Change
After project commencement, the Client/Sponsor changes the project
scope and work content and hence changes the timeline
4) Force Majeure
A major unforeseen event happens which could be natural calamities
such as hurricanes, floods, earthquakes and tornados or manmade
events such as explosions, fires or major traffic accidents.
Part (b) Explain the purpose of using SWOT analysis to assess the
context of a project.
24
Question 2 List and describe five phases in an extended project
life cycle.
Earned Value represents the amount of planned work that has been
completed based on its budgeted cost. For each individual activity
Earned Value equals original budget x % complete. An activity when
complete has Earned Value equal to its budget irrespective of its
actual cost.
1. If we rely just upon the schedule to control our project, then non-
critical items receive less attention. EV measures the whole
project rather than concentrating on the Critical Path so warns us
when non-critical items are slipping and could become critical.
26
Question 4
3. Provider/supplier selection
27
4. Conditions and forms of contract
A supplier must be willing to accept a form of contract acceptable to
the client. Possible forms of contract are :-
Cost reimbursable, Cost plus fixed fee, Cost plus incentive fee and
Firm fixed price
1. Cost based pricing. Here the supplier decides on the profit margin
that is required and adds that to the cost.
2. Demand based pricing. If demand for the product is high then the
supplier can increase the profit margin.
3. Competition based pricing. In this case where there is competition
for supply then it may be necessary to reduce the profit margin to
win the business.
28
Question 5
Scope Management is concerned with all the tools and processes that
ensure that enough work, but no more, is carried out to produce the
project deliverables. It is concerned with controlling the boundaries
of the project and ensuring that all work done is related to project
objectives and that any new work is subject to a formal change
control process. It is also important to clearly establish what is
excluded from the project scope.
29
Part (c) Explain two reasons why the scope of the project
should be baselined.
30
Question 6
3) Norming Once people have well defined roles which they are happy
with and understand the project outcome and how their contribution
fits in with overall project goals then the team starts to gel. People
feel confident and motivated and confidence is high
31
Question 7
Part (a) Explain the prerequisites required for each of the following
three estimating methods:
1.Comparative
2.Bottom up/Analytical
3.Parametric
1) Comparative:
• Your project must have elements that are comparable with
elements of previous projects.
• Actual data from previous project needs to have been
collected and stored for access.
• The circumstances around the previous estimate should have
been recorded to ensure that comparisons are valid.
2) Bottom Up
• There needs to be in place a complete work breakdown
structure that identifies all the work of the project.
• There needs to be an accurate estimate for each lowest level
task or work package.
3) Parametric
• The work to be done must be suitable for parametric
estimating e.g. consisting of elements of scalable work such
as laying bricks or plastering walls.
• There must exist standardised data based on previous actuals
e.g. what is the expected time for a trained bricklayer to lay 100
bricks?
32
Question 7 part (b) State four practical problems of initial estimates
for a project with a long timescale.
33
Question 8 List and describe five activities which the project
sponsor performs during the project life cycle .
Part (b) List and describe four essential sections of a typical Project
Management Plan.
1) Project Schedule
The project schedule is typically represented by a Gantt Chart. It
reflects the structure of the WBS and shows the planned start and end
date of each task/activity and the planned project duration and its
resource requirements. It will show the critical path and which
activities have float. It will also show milestone events where key
activities end or key deliverables are completed.
35
4) Communication Plan
The Communication Plan describes the project information
requirements. It includes the following:-
36
Question 10 List five barriers to communication and describe how
each one may be proactively managed.
1. Organisational
Problems can occur because of a lack of understanding of how
an organisation works. For example, some organisations have
an environment of openness and trust whilst others may
operate on strict hierarchical and “need to know” lines.
Managed by making sure that each individual is made aware
of, and is sensitive to, the way in which the organisation
works.
2. Physical
An example of this is the type of environment that
communication takes place in such as open plan offices where
private conversations are difficult meaning people may feel
inhibited in what they can say.
Managed by making sure that people have access to
convenient locations where private conversations can take
place
4. Jargon
People commonly use acronyms and abbreviations and
assume that everyone else understands them. Coupled with
37
this is an unwillingness by some people to admit lack of
understanding because of fear of appearing stupid.
Managing by minimising the use of jargon, being aware that
other people may need explanations and fostering a climate
where people are not afraid to ask questions
5. Interpersonal
An example of this is where someone’s style of
communication may appear aggressive to others, especially to
people beneath them. This may make them unapproachable.
Managed by being aware of how your communication style
may appear to others and by being prepared to modify your
behaviour when appropriate.
38
Question 11 List and describe five benefits to an organisation of
adopting a formal risk management process.
39
Question 12
Part (a) State two resource loading observations from the given
histogram.
40
Part (b) List and describe four actions that the project manager
might take in response to the resource loading profile in the given
histogram. Include the potential benefit to the project of taking
each action.
4. Projects usually involve risk. Total risk can best be managed and
mitigated by controlling it at programme level rather than at project level.
For instance, a risk to the schedule for an individual project may have no
impact at programme level. This will benefit the Programme
1. Quality planning
2. Quality assurance
3. Quality control
4. Continual improvement
1 Quality Planning
2 Quality Assurance
43
3 Quality Control
4 Continuous improvement
44
Question 15
Question 15 Part (b) List four typical leadership qualities and describe
how each assists in directing or supporting a project team.
1.Lead by example
Effective leaders lead by example and are good role models. People
should look up to them and aspire to be like them and copy their
behaviour. They are seen to be fair and even handed. They have no
favourites and treat everyone equally. They care about their people
and are prepared to take risks on their behalf.
2.Excellent communicators
They are excellent communicators. They can communicate with
people at all levels and by different means. They can communicate
both verbally and in writing, formal and informal. They are good
listeners. Effective communication leads to a more efficient project
and a more motivated team
3.Technically competent
They are good at the technical aspects of project management. As
well as skilful in leading and motivating people they must be
excellent at all the basic PM skills such as planning and organising
but also expert in techniques such as scheduling and earned value
management. Technical efficiency leads to a more efficient project
45
4.Approachable
They will be available and approachable and know what is going on.
Project managers cannot be remote from their team. Team members
must feel they can approach them if they have problems. A good
project manager will get out amongst the team and will always know
what is going on. This leads to early awareness of problems hence a
more efficient project.
46
Question 16 Part (a) Complete the following network and state:-
Part (b) Explain three of the following terms, including why each is
important to the project manager:
▪Critical path
▪Lag
▪Total float
47
Answer (a)
Note: In the exam you can write the numbers on the question paper. Do not draw the
network. Only the 4 answers will be marked.
Part b
1. Critical path
o The longest path through the network
o The shortest possible planned project duration
o The path with least float
2. Lag
When an activity completes, if there is then a delay or wait period
before the next activity starts, this is called lag and the delay is known
48
as the Lag Time. Lag Time is the delay between two consecutive
activities. It is important because not all activities can start
immediately after the previous one is completed. e.g drying or setting
time
3. Total float
49
2015 Example Exam Paper
Question 1
1. Use of overtime
- Asking staff to work longer hours or forego days off is far cheaper
than bringing in extra resource. However, this should not be
considered as a long term tactic as overtime it can impair efficiency.
It is assumed that staff would be willing to do this.
2.Temporary staff
50
assumed that the work can easily be picked up by temporary staff
without excessive learning time.
51
Question 2
Concept-Definition-Implementation-Handover-Closeout
52
point. People also have added concerns concerning
what happens to them on project completion.
53
Question 3
1. Portfolio Direction
All projects within the Portfolio should be aligned with Corporate
goals and objectives. An acid test for the relevance of a project is to
ask in what way is it contributing to the goals of the organisation.
Projects which do not pass this test should not be carried out.
2. Project Sponsorship
All projects should have an appropriate Sponsor to whom the PM
reports and who owns the budget and the business case. Without such
a sponsor the link to Corporate goals is lost and projects can be
allowed to go out of control. Proper sponsorship ensures that projects
are visible to higher management from concept to benefits realisation
54
3. Project Management Effectiveness
Projects should be managed by a person with knowledge, skills and
experience commensurate with the size and complexity of the project.
Project teams should have the skills and competence to achieve
project objectives and be given appropriate tools and resources. There
should be effective delegation.
55
Question 4
(a) Explain the difference between continuous improvement and
project quality planning.
1.Payback
This method calculates how long it takes for cash flow to break even;
i.e. when costs equal benefits. This method ignores cash flows after
break-even point. It can be used to compare projects to see which one
returns the initial investment soonest, thus freeing cash for further
investment. Payback ignores the fact that the value of money
diminishes over time
57
represents the project value in today’s terms. The discount rate that is
used is a function of interest rates, inflation rates, risk and opportunity
cost.
58
Question 6 List five characteristics of projects and describe how
each is different from business-as-usual activities.
1. Unique
A project is a unique undertaking. Every project, to a
greater or lesser extent, will have elements that have
never been done before. Business-as-Usual (BAU) is
typically repetitive, with the same goods/services
produced on a continuous basis
2. Finite
Projects are finite in that they have planned start and
end dates. BAU is normally ongoing and can carry on
indefinitely.
3. Risky
Because of their uniqueness Projects involve activities
of which there may be little or no previous experience.
Hence they involve risk and uncertainty. On the other
hand, performance of BAU is based on cumulative
experience that has the effect of minimising or
eliminating risk.
59
Question 7
1.Project selection.
Projects for potential inclusion within the portfolio should be
carefully selected and a business case prepared. Projects should align
with corporate strategy and contribute to overall corporate goals.
Projects within the portfolio should exhibit an appropriate balance
between risk and return.
2.Resource allocation.
This is concerned with the management of resources across
competing projects and programmes within the portfolio. Resource
issues will occur between projects particular in regard to scarce or
limited resources and capacity bottlenecks. The portfolio manager
must decide on the optimum allocation of resources.
60
presented business case. Best practice is for the eventual
project manager to be heavily involved in assisting in its
production. Involving an experienced project manager
should increase the accuracy of the cost and schedule
estimates.
61
Question 8 This question has two parts:
Part (b) With each of the four quadrants of the matrix labelled A,
B, C and D, explain:
• the potential implications of the stakeholder actions on the
project
• the Project Manager’s approach to managing the
stakeholder.
Quadrant A These people are powerful and have the ability to influence
the project for better or worse so cannot be ignored even though they have
low interest. Put enough work in with these people to keep them satisfied,
but be careful not to antagonise potential Blockers, whilst encouraging
potential Champions to take a more active interest.
62
Quadrant B These are also powerful people but have an interest in the
project and may intend try and influence it. Therefore, you must fully
engage and manage them closely because people with power who are on
your side (Champions) can help you whilst people who are against you
(Blockers) may be in a position to harm you.
Quadrant D These people have a high interest in the project but do not
have the power to significantly affect it. You need to keep these people
adequately informed and monitor them quite closely to ensure that
Detractors are not becoming organised as they can harm you if they
acquire more power. Conversely you should encourage your Supporters to
organise themselves and increase their power.
63
Question 9 Part (a) Explain what is meant by the term project
“closeout”.
Closeout follows handover and is concerned with closing the project down
in a consistent and organised manner. Its main purpose is to ensure that the
project is totally complete and all relevant information archived, there are
no outstanding issues and measures for warranty and future support are in
place.
64
Question 10
Part (a) Within the project context, state the meaning of each of the
following: Committed costs and Accrued costs
Part (b) List and describe four reasons why it is important that the
Project Manager understands committed costs on a project.
1. Legal obligation
If costs have been committed to then it is important for the PM to realise
that that money is subject to legal and moral obligations and reneging may
have repercussions.
4. Danger of Overspending
It is important for the PM to know the amount of committed costs.
Unawareness of the commitment may lead the PM to spend money that is
not available.
65
Question 11
Part (a) List and describe four processes/plans which are included
within the PMP.
1. Quality Plan
The Purpose of the Project Quality Plan is to define these activities and
procedures that will be carried out by the project team in order to deliver
products that will satisfy customer's quality parameters. In other words,
setting standards and how to achieve them. It covers Quality Planning,
Quality Assurance and Quality Control.
3. Communication Plan
The Communication Plan details and describes all the project information
requirements. It includes how information is acquired, how it is stored and
how it is maintained. It will detail formal reporting requirements and
structures and frequency of reporting and to whom reports are sent.
66
Part (b) Explain what is meant by a ‘baselined project management
plan’ and how it is used.
The original project plan as agreed between the Sponsor and the Project
Manager serves as a baseline for the project against which all future
outcomes are compared. Outcomes, in terms of schedule, budget and
quality are monitored to capture deviations from the baseline plan so
appropriate actions can be taken. Formal changes to project scope will
generate incremental changes to the project baseline but the original
baseline and all subsequent changes must be recorded to ensure an audit
trail.
67
Question 12
2. Project Reporting
Project status needs to be reported upwards. This can only be done
efficiently if all projects use a common format allowing project data to be
rolled up to provide a corporate viewpoint
4. Project Governance.
Project Governance requirements rely on the presence of a methodology to
satisfy the need for consistent processes and procedures and defined roles
and responsibilities. Good governance is impossible without a structured
approach.
5. Staff turnover
Most projects will have turnover of staff as well a new people joining the
project throughout the project life cycle. Having a common structure that
everyone is trained in makes handover of responsibilities much easier with
less chance of misunderstandings.
68
Question 13 List and describe five elements that would be performed
as part of an effective configuration management process.
2.Configuration Identification
This involves breaking down the project into individual configuration
items and creating a unique numbering system. Items include all project
documents such as specifications, designs and plans as well as the physical
components of the project deliverables deliverable components.
3.Configuration Control
During the project the configuration will grow as the product is being
developed. After project completion the product will still continue to
evolve. As configuration items are created they are added to the
configuration and their dependencies on other items identified. As the
configuration evolves Configuration Control maintains version control of
all configuration items and the interrelationship between them.
4.Projects usually involve risk. Total risk can best be managed and
mitigated by controlling it at programme level rather than at project level.
For instance, a risk to the schedule for an individual project may have no
impact at programme level. This will benefit the Programme
5.Plan Archiving
Data and information that is no longer current can be archives for future
reference. The Communications Plan will specify when information can be
archived, the method of doing this and how long it must be stored for.
72
Question 16
The table below lists the cumulative values of Project 2079X, a 12-
month project, with values to the end of month 8.
Notes:
PC Planned Cost: What you had planned to spend at a point in the project.
AC Actual Costs: What you had actually spent at a point in the project.
%Comp Percentage Complete: What percentage of the total project is complete at a point
in the project (based on BAC).
BAC Budget at Completion: What the total planned cost of the project.
EV The Earned Value is calculated based upon the amount of the BAC that has been
achieved at the end of each month.
Part (a) What is the Budget at Completion (BAC) and Earned Value at
the end of Month 8.
73
Part (b) What is the Cost Performance Index (CPI) and
Schedule Performance Index (SPI) at the end of Month 8.
Part (c) Looking at the project as a whole, describe the progress of the
project thus far in terms of predicted schedule and cost implications.
For each of these predicted implications (schedule and cost) provide a
statement describing what might have caused it.
Cost are running slightly under budget possibly due to raw materials being
cheaper than planned or less used than planned.
Note: Correct answers will achieve full marks regardless of whether workings are shown.
Incorrect answers, where correct workings are shown, will achieve up to 50% of available marks.
74
2014 Example Exam
Some of the questions have been omitted as they are
repeated in the 2015 sample paper.
Q1 Part a Explain the importance of project reviews.
Project reviews are important because they are the only way that the
Stakeholders can obtain a view as to the actual status of the project. They
are an opportunity to demonstrate that the project is under control. They
give management an opportunity to intervene with problem projects and
generate increased confidence and commitment to projects performing
well. Without reviews projects can go very wrong without management
being aware.
Part b List and describe four different types of review that may be
carried out during a project, and their main purposes.
1. Phase review
This review is carried out at the end of each project Phase. At each
phase end the project manager must report to the project board or
sponsor and ask for authority to proceed to the next phase. The board
will review progress to date against the original baseline plan and any
approved changes. They should also revisit the business case to
ensure it is still viable. Possible outcomes are carry on, carry on with
modifications or terminate the project.
2. Status review
75
The reviews can be carried out either routinely at set intervals or as a
result of a trigger such as a major milestone or project crisis
3. Peer review
76
Question 3 Part a. In the context of Earned Value Management
(EVM), explain the term Earned Value (EV).
1. Holistic view.
The Earned Value for a project is the accumulation of Earned Value
for each individual activity. It thus takes a holistic view of the project
rather than just focusing on the critical path. Just looking at the
schedule will indicate that all is well as long as the critical path is on
plan. However, Earned Value will indicate when non critical
activities are slipping and could eventually become critical.
77
where work is not proceeding to plan so that appropriate corrective
action can be taken.
78
Question 4 List and describe five typical stages in the process for
selection of a supplier via competitive tender.
79
Question 6 Part a. List and describe three advantages, to a
project manager, of a matrix organisation structure when used
in a project environment
2. Discourages sub-optimisation
When a project takes place within a single function the needs of that
function can take precedence over the needs of the organisation. The
solution can thus be sub optimal in that it can be detrimental to the
needs of the organisation. Within a matrix environment it is harder
for a single function to dominate the project so sub optimisation is
much less likely
80
exhibit greater loyalty to their function than to the project.
They may be unduly influenced by their functional manager
and there may be conflict between the different functions,
especially if things go wrong.
2. Communications
Communications in a matrix organisation are always more
complex than in functional or projectised organisations. As
well as communicating vertically within the project and up
to the sponsor the project manager must also communicate
laterally with the functional managers.
81
Question 7 Part a. Explain what is meant by situational
leadership in a project environment
• Supporting
• Coaching
• Delegating
• Directing
(b) List and describe four benefits of adapting leadership styles during
a project.
82
this case would be someone anxious to take responsibility but
not experienced enough to be trusted with a vital task.
83
Question 8 List and describe five important environmental
legislative requirements which the project manager must take into
account when planning a project.
84
5. Pollution and Nuisance
Your construction site must not present a health risk, or a nuisance to
adjoining areas. If something is unreasonable to an average person, a
court might decide that it is a nuisance. Typical examples of statutory
nuisance might include dust, smells, smoke, noise or vibrations.
Anyone affected can ask their local authority to take action.
85
Question 9 Part a. Explain the prerequisites required for each of the
following three estimating methods:
1) Comparative; 2)Bottom up/Analytical; 3) Parametric
1) Comparative:
• Your project must have elements that are comparable with
elements of previous projects.
• Actual data from previous project needs to have been
collected and stored for access.
• The circumstances around the previous estimate should have
been recorded to ensure that comparisons are valid.
2) Bottom Up
• There needs to be in place a complete work breakdown
structure that identifies all the work of the project.
• There needs to be an accurate estimate for each lower level
task or work package.
3) Parametric
• The work to be done must be suitable for parametric
estimating e.g. consisting of elements of scalable work such
as laying bricks or plastering walls.
• There must exist standardised data based on previous actuals
e.g. what is the expected time for a trained bricklayer to lay
100 bricks?
86
3) There may be no standardised data available or future work is not
planned in enough detail to apply parametric estimating.
87
Question10 List and describe five typical contents (e.g. processes,
components, techniques) of a structured project management method.
1. Document templates
The layout and content of all project documents will be
mandated. This will ensure consistency and ease of
communication across all projects. There will be a template
for each project document which defines chapters and
paragraph headings with a description of the expected content
for each.
4. Change control
The methodology will define the mandatory formal change
control process. It will specify how change requests are
generated, how they are assessed, the means by which they
are approved or rejected and how they are assimilated into the
project. It will specify the approval body for each class of
88
change i.e. full change control board, the sponsor, the PM or
individual team members.
5. Risk management
The methodology will detail the process for controlling
project risk (both threats and opportunities). It will define
processes for identifying, assessing, mitigating and managing
possible risk events. It will describe techniques for both
qualitative and quantitative risk measurement and authority
levels for accepting different levels of risk.
89
Question 11 List and describe five activities which the
project sponsor performs during the project life
cycle.
90
5. Carry out Benefits review
The project manager hands over responsibility for the project
deliverables during Handover &
Closeout. Responsibility for achieving the benefits described in the
business case remains with the Sponsor. After a suitable period of
time, typically 6-9 months, the sponsor must demonstrate that the
deliverables have achieved the success criteria laid down in the
business case.
91
Q14 Part a. Explain two reasons why the scope of a project may need
to be changed.
2) Mandatory requirements
As a project progresses there may be changes to legal requirements
such as health & safety, environmental and regulatory controls
which did not exist when the project was planned. This is particularly
true of project with a long time cycle.
(b) Explain three ways that change control can reduce and
manage scope creep on a project.
(c)
1) By having in place a formal change control process it ensures that
all proposed changes are fully assessed for impact. This should
ensure that all changes are beneficial and that inappropriate or
frivolous changes are blocked.
3) When requesting a change, the person making the request often has
little or no idea of the impact that the change will have on the
project. The change control process involves a full evaluation of the
change including its knock on effects not just on time and budget but
on other aspects of the project. The results of this evaluation mean
that many requests will be subsequently withdrawn or refused.
92
Q15 List and describe five benefits to an organisation of
adopting a formal risk management process.
3) Stakeholder confidence
When carrying out a project for a client the project price and contract
type is highly dependent upon the risks involved. For instance it
would be unwise to take on a fixed price contract without a detailed
understanding of what risk events could take place. Risk evaluation
will enable an appropriate risk premium to be negotiated.
93
5) Contingency allowances
94
Q16 Part a. Explain the concept of teamwork.
Part b. From the following team or social roles listed explain how
they contribute to an effective team.
1 Opponent/Challenger/Antagonist
2 Creator/Innovator/Plant
3 Team Builder/Worker _ Completer/Finisher _Collaborator
4 Controller/Inspector/Implementer
1. Creator/Innovator/Plant
95
2. Team Builder/Worker
3. Completer/Finisher
4. Collaborator
96