NH CAPM - 6.10 Slides Student

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 415

CAPM® Exam 

Preparation
PDU Course Number: OLLNHLSCAPMPREP6TH; ILTNHLSCAPMPREP6TH
PDUs: 28; PMI® R.E.P. Number: 1341
Author: Brian Salk, PhD, PMP®, PMI‐ACP®

Materials in this class are based on the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) ‐ Sixth Edition, Project Management Institute, Inc., 2017. PMI, PMP, 
CAPM, OPM3, PMI‐SP, PMI‐RMP, PMI‐ACP, and PMBOK Guide are registered trademarks of the Project Management Institute, Inc.
CAPM® Exam Preparation
Version: 6.06

2
2
CAPM® Exam Preparation Course Objectives
• Lecture, discussions, and guided questions to help 
participants to identify project management terms, 
concepts, and common practices as expressed by the Project 
Management Body of Knowledge (PMBOK)® Guide Sixth 
Edition.

3
CAPM® Exam Preparation Course Topics
• Lesson 1: Project Management Introduction  Page 12
• Lesson 2: The Environment in Which Projects Operate Page 41
• Lesson 3: The Role of the Project Manager Page 66
• Lesson 4: Initiating Processes Page 79
• Lesson 5: Planning Processes Page 94
• Lesson 5: Planning Processes, Section A – Management Plans Page 95
• Lesson 5: Planning Processes, Section B – Scope, Schedule, Resource, 
and Cost Processes Page 168
• Lesson 5: Planning Processes, Section C – Risk Processes Page 229
• Lesson 6: Executing Processes Page 264
• Lesson 7: Monitoring and Controlling Processes Page 317
• Lesson 8: Closing Processes Page 392
• Appendices Page 410

4
Exam: What to Expect, How 
to Prepare

5
5
PMP®/CAPM® Exam Details
PMP® CAPM®
Number of Multiple Choice 200 150
Questions (1 Correct Answer)
Exam Hours Four (plus 15 minutes for tutorial) Three (plus 15 minutes)
Price PMI Member: US $405 PMI Member: US $225
Non‐member: US $555 Non‐member: US $300
Prerequisites (leading and directing  Secondary degree: 7,500 hours/  Secondary degree
projects.) 5 years PM Experience AND
Note: Secondary degree includes  OR
high school diploma, associate’s  Four‐year degree: 4,500 hours/  23 hours PM education 
degree or the global equivalent 3 years PM Experience OR
1,500 hours of project experience
35 hours of PM education
To maintain your certification Earn 60 professional development 
6 PDUs
units (PDUs) every three years.
Overview of the Application Process
Become a PMI Member (optional)

Create an account, complete the application, and submit the application

PMI Review and Payment

Possible Audit

Take Exam within a Year

Maintain Your Certification

7
Exam Registration and Environment: Scoring

• As of January, 2008, PMI has adopted industry 
best practices and issues exam results of pass or 
fail and, in the five sub‐domains, exam results of 
proficient, mildly proficient, or lacking 
proficiency.  Our suggestion when doing exam 
simulation is to be in the 80%+ range to create 
some extra padding when taking the real exam. 

8
Exam Registration and Environment:  Exam Objectives 

• The exam consists of 150 questions, all of which you will want to 
answer.  Only 135 are scored.  The remaining questions, which 
are inserted randomly in the examination, are considered pre‐
test questions and are used to test the validity of future 
questions.

• You have 3 hours to complete the exam.

• On average, you have 72 seconds per question.

9
Exam Breakdown, Refer to PMI Website

Certified Associate in Project Management (CAPM)® Exam Content 
Outline | PMI

10
Exam Registration and Environment:
Question Formats

• The exam uses a number of question formats.  Some of the questions 
use multiple formats.  Understanding the formats helps you dissect 
the question and the available answers.  Here are some formats:

Select Chicken or the egg (sequence)
Select NOT/EXCEPT Situational
All (or a combination of) the above Calculation
None of the above

11
Exam Registration and Environment: Exam Questions
Question Formats (Cont.)

Question  Description Example


Format
Select  This is likely the most  A milestone has what duration?  
straightforward question  A. 1 day
format on the exam.  It simply  B. 0 (no duration) (Correct)
asks you to select the best 
C. 1 hour
answer.  Be aware, however, 
D. 8 hours
because it can also include 
other question formats, 
including the Chicken or the 
Egg format questions. 

12
Exam Registration and Environment: Exam Questions
Question Formats (Cont.)
Question Format Description Example

Select NOT/EXCEPT For this the type of question, you must  All the following are areas of 


select the answer that does not apply.   communications management except… 
Generally, this question type is not a big  A. Manage 
deal unless you have already hit “the  communications
wall” that we discussed in the exam  B. Control communications
environment part of this book.  The key  C. Perform quantitative  
to handling this type of question is to  risk analysis  (Correct)
determine which three answer 
D. Plan communications
selections have something in common.  
The fourth answer selection is the 
exception and the answer to choose.  

13
Exam Registration and Environment: Exam Questions
Question Formats (Cont.)

Question Format Description Example

All (or a  With this question format, all  Which of the following are areas of 


Combination of)  ‐‐ or a combination ‐‐ of the  risk management?
the Answers answers are acceptable.  The  A. Identify risks 
main thing to consider is that  B. Perform quantitative
there isn’t a bad choice.  The  risk analysis
odds are that if two of the 
C. Plan risk responses 
answers (other than “All the 
D. All the answers (Correct)
answers”) look good, so will 
the third.  

14
Exam Registration and Environment: Exam Questions
Question Formats (Cont.)

Question Format Description Example


Situational  This question format is probably the most  You’ve taken over an existing project and 
challenging, and the exam will include at least  discover that it has suffered major scope creep 
75 questions using this format, some in  because the former project manager couldn’t 
combination with other formats.  This  say “no” to the sponsor, and it lacked enough 
question format expects you to leverage your  supporting documentation.  What document do 
PM experience and understanding of the  you first want to see (or create if it doesn’t 
PMBOK Guide and the PMI way of thinking.   exist) about the project foundation?  
Typically, you will see a Chicken or the Egg  A. Risk list
(what comes first) ‐‐ with whom do you  B. Project charter (Correct)
communicate regarding a project, or what is  C. Communications plan
your next action on the project.  Keys to 
D. Budget
success in this area are to understand the 
processes table in section 3.8.1 of this book, 
plus the key role players in the methodology.  
15
Exam Registration and Environment: Exam Questions
Question Formats (Cont.)

Question Format Description Example

Chicken or the Egg With this format, more than one  What comes before sequence activities?


answer is acceptable.  The key is  A. Estimate activity
to understand the order ‐‐ what  durations
comes first, last, before  B. Estimate costs 
something, or after  C. Define activities (Correct)
something.  In this case, look at  D. Develop project 
what the question is asking and  management
determine the best answer based  plan
on the timeline of the answers.  

16
Exam Registration and Environment: Exam Questions
Question Formats (Cont.)

Question  Description Example


Format
Calculation  This question format typically falls under the Select or the  What is the CPI for the 
None of the Above (sometimes “not enough information”)  following data?  AC=$200, 
formats.  If you know the formulas for the exam, you  PV=$400, EV=$200, 
shouldn’t have a problem with calculation questions.  In  BAC=$1,000
some, you could encounter possible answers that “add up”  A. $200
correctly if you don’t know the formula, but attempt to  B. ‐$200
reverse‐engineer the question.  An example: you are to 
C. 1.0 (Correct)
calculate CPI (divide EV by AC).  You have incorrect answers 
D. 0.5
that total other calculations as well (SP, SPI, CV, or others).  
It is not uncommon for the exam to have questions that do 
not give you enough data, such as future value or present 
value.  Therefore, it is important that you know all the 
components of a formula.  
17
Exam Registration and Environment:
Question Characteristics Intended to Throw You Off

• There are different characteristics and 
components you must recognize when 
interpreting questions, especially the situational 
ones.  They include distracters, common 
terminology, too much information, and wrong 
area/point in time.  
• If you recognize them in the questions, you may 
determine more easily what the question is 
actually asking.  

18
Exam Registration and Environment: Exam Questions
Question Characteristics and Components (Cont.)

Question Type Explanation
Distracter We use this word to reference information that has no value 
or bearing in a question.  We call it a distracter because it is 
content that has been inserted to distract you in the exam 
environment.  We also call such content “noise.”
Common  The exam typically uses PMI terminology.  A question could 
Terminology have one possible answer commonly connected with the 
question but not PMI terminology. Another possible answer 
uses the PMI terminology for the common description (e.g., 
budget at completion vs. budget).  In this example, if you 
answered “budget” because you weren’t familiar with the 
true definition of “budget at completion,” you are technically 
wrong because “budget at completion” is the better answer.  

19
Exam Registration and Environment: Exam Questions
Question Characteristics and Components (Cont.)

Question Type Explanation
Too Much Information  The exam could present questions that contain a great deal of information.  
(TMI) For example, you might encounter a situational question in which a number 
of variables are included, such as time, cost, scope, and quality.  Look at 
each variable and see how it relates to what the question is asking.  For 
example, if you are given reasonable variables associated with time, quality, 
and scope, but the cost variable shows that you are over budget, then the 
cost variable is likely the one you that should concern you.  

Wrong Area, or Wrong  The exam could present questions that have an answer or answers that are 
Point in Time from the incorrect knowledge area or are from the correct knowledge area 
but occur too early or too late in the process to be acceptable.  The 
questions could also ask you to determine process or activity sequence (e.g., 
which of the following activities would you perform first?).  

20
Exam Registration and Environment:
Preparing for Exam Day 

Practice Exams Practice tests help you become familiar with the environment, as well as the 


question layout and timing.  
When taking practice tests, focus on the speed at which you complete the 
questions. Your mind will be accustomed to processing questions at a pace 
that is above normal, and to recognize the questions types and characteristics.
Study Read the PMBOK guide cover to cover
Read the student guide provided in this course

Might I also recommend the app called PocketPrep for CAPM: 
http://www.pocketprep.com/exams/pmi‐capm/

21
Exam Registration and Environment: General Tips

• ****The exam tests your understanding of the PMBOK Guide and 
PMI processes across all knowledge areas, as well as the ability to 
know how to deal with these processes in situational questions.  
• Know the formulas that are in the PMBOK.  
• Know the terms and definitions.
• Know the acronyms that PMI uses.
• Be familiar with documents purposes, and when they are inputs vs. 
outputs.  You won’t be asked to create them, nor will there be details 
on how they should look etc.
• The CAPM Examination can include questions with absolute words 
such as ALWAYS, NEVER, COMPLETELY, and gray words, such as 
SOMETIMES, SHOULD, COULD, GENERAL, and MAY.  
• Be very sensitive to these words because absolute words compared to 
gray words can significantly change the meaning of a question.  
22
Exam Registration and Environment: More General Tips

•Study often: aim for 1 to 3 hours per work day and 4 to 8 
hours each weekend day. 
• Spaced practice and study is better than pure cramming. 

•Study consistently: the volume of material makes it harder 
if you wait too long between study sessions. 

• Test sooner rather than later: the volume of material 
makes it harder to pass the exam if you wait months to 
take the exam.
23
Exam Registration and Environment:  Preparing for Exam Day
Scheduling and  Schedule your exam for a time when you are most alert. Try not to 
the Day Before schedule your exam to follow a day's work.  A good night's sleep the night 
before the exam and eating well a few days before will help greatly.  
Cramming the day before is not a bad idea.  It can help you detect any 
final subject areas that need last minute study.  

Brain Dump A brain dump is important information that you write down as you begin 
your CAPM Examination.  We recommend that you write down your brain 
dump during the tutorial of the exam.  This tutorial occurs in the first 
fifteen minutes before your three hours actually start.  Ensure that you 
can do this cold in fifteen minutes or less before you take the test. 
***I recommend you memorize the Process Group and Knowledge Area 
Mapping table on page 25 of your PMBOK.

24
Exam Registration and Environment: Exam Day
What to Take:  The following are required: 
Required  Your eligibility letter with the authorization number on it  
 A photo ID and two other forms of ID (credit card, etc.)
Verify that the names on the IDs and the letter are identical.  For example, 
Anthony and Tony could cause problems.  
What to Take:  • Dress in layers so you can be comfortable in the room environment whether it be 
Recommended cold, warm, or unstable.  A t‐shirt with a sweater is a good combination.  
• Although you may take food and drink, you must leave them in the provided locker.  
• You may take the locker key plus the provided pencils and paper into the test room.
• May be “white board” and dry erase markers – ask for fine tipped.
• The lockers can be small.

25
Exam Registration and Environment: Exam Day (Cont’d)

Marking  The exam lets you mark questions and return later to review them.  


Questions for Studies show that your initial response to a question is usually the 
right answer. While we suggest marking questions you are unsure 
Later about, and perhaps math questions, we recommend that you don't 
mark too many questions, and make sure you put an answer down 
even if you mark it for review … better to have something than 
nothing if you run out of time.

Typically, our classroom students who score well on the exam mark
about ten to fifteen questions.  

26
Online Proctored Exams are Now Available
• You can find out more here:
• https://www.pmi.org/certifications/types/certified‐
associate‐capm/exam‐prep/online

27
Lesson 1: Project 
Management Introduction
Learning Objective: Based on Chapters 1‐3 of the PMBOK® Guide 
Sixth Edition.

28
28
Lesson 1 Topics: Project Management 
Introduction
• Defining Projects (1.2.1) • Project Management 
• The Importance of Project  Knowledge Areas
Management (1.2.2) • Project Data, Information, and 
• Project, Program, Portfolio and  Reports
Operations Management  • Tailoring
(1.2.3) • Project Management Business 
• Key Components (1.2.4) Documents (1.2.6)
• Project Management Process  • Success Measurements
Groups

29
Defining Projects (1.2.1)
• Developing a unique product, service, or result
• Temporary endeavor
• Definitive beginning and end
• Incorporating repetitive elements, as necessary

30
The Importance of Project Management 
(1.2.2)
• Effective project management increases the probability of 
• Successful project execution 
• The creation of tangible and intangible value
• The accomplishment of organizational goals
• Poor project management increases the probability of 
• Wasted effort, materials, facilities and/or money
• Missed opportunities
• Failure to avoid or mitigate internal and external risks

31
Project, Program, Portfolio and Operations 
Management (1.2.3)
Mission statement or 
vision statement

Strategic plan

Portfolio

Mega 
Operations Program 1 Program 2
Project 1

Project 1 Project 2 Project 3 Project 4

32
Portfolio vs. Program – Real World Example

City Center in Las Vegas, Nevada, originally owned by MGM Resorts International, is 5 hotels combined into one area.

The program took 5 years from conception, and included at least 5 projects.  From left to right: Mandarin Oriental, Crystals, 


Aria, Veer Towers, and Vdara.

MGM Resorts International’s Portfolio includes other casino resorts being planned/built internationally.
33
33
Key Components (1.2.4) (1 of 2)
• Project life cycle 
• Predictive: plan ahead completely and then execute, usually for a 
well known opportunity/problem and solution
• Iterative: cycles of planning, executing, and client evaluations
• Incremental: adding additional scope (e.g. features) over time
• Adaptive (e.g., agile): can use iterative and incremental approaches
• Hybrid: using predictive lifecycles for predictable elements and agile 
lifecycles for less well‐defined elements

34
Types of Life Cycles‐ Predictive Life Cycle

• Predictive life cycles are also known as waterfall or plan 
driven approaches.  
• In the predictive life cycle the scope, schedule, and budget 
are established as early as possible in the project. 
• This approach is often used when the work is well 
understood by the performing organization.

35
Types of Life Cycles‐ Iterative, Incremental, Hybrid Life Cycles
• Iterations develop the product through a series of repeated cycles

• Increments successively add to the functionality of the product

• In iterative or incremental life cycles, project scope is identified 
early in the project, but schedule and budget are adjusted as the 
team learns more about the project work.  Iteration durations and 
team members may change based on project need.  
• This approach is typically used when the goal is to minimize 
complexity and risk, or when partial project delivery can benefit 
some of the stakeholders.
36
Types of Life Cycles‐ Adaptive Life Cycles

• Adaptive life cycles are also known as agile methods 
and are generally thought of as a change‐driven 
approach to project management.  
• This approach has rapid iterations, typically 2‐4 
weeks long with fixed time and resources, and 
requires significant stakeholder/customer 
involvement.  
• This approach is often used in rapidly changing 
project environments where the scope is difficult to 
define in advance.

37
Key Components (1.2.4) (2 of 2)
• Project phases within Project Life Cycle
• Each phase represents a logical element or component of the overall project. For example, 
an organization could us a project life cycle consisting of the phases Analysis, Design, 
Develop, Implement, and QA to guide their work.
• Phase gate
• A review process, typically conducted at the end of a project phase, to decide whether to 
keep going on the project, or to “kill” it. For example, the project team might require 
permission from the sponsor or customer before they can begin the work of the next project 
phase. 
• Project management processes
• Often, but not always, project management processes convert data or information (inputs) 
into useful documents (outputs). 
• There are 49 processes to represent the actions required to conduct the project!
• The majority of the PMBOK revolves around these processes and organizes them into 
Process Groups and Knowledge Areas.

38
Project Management Life Cycle:
Process Groups and Knowledge Areas
Monitoring and 
Knowledge Areas Initiating Process  Planning Process  Executing Process  Closing Process 
Closing Process 
Group Group Group Group
Group
4. Project  4.1 Develop Project  4.2 Develop Project  4.3 Direct and  4.5 Monitor and  4.7 Close Project or 
Integration  Charter Management Plan Manage Project  Control Project  Phase
Management Work Work
4.4. Manage Project  4.6 Perform 
Knowledge Integrated Change 
Control
5. Project Scope  5.1 Plan Scope  5.5 Validate Scope
Management Management 5.6 Control Scope
5.2 Collect 
Requirements
5.3 Define Scope
5.4 Create WBS
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) ‐ Sixth Edition, Project Management 
Institute, Inc., 2017, page 25.

39
Project Life Cycle vs. Project Management Life Cycle 

Analysis Phase Design Phase Develop Phase


Initiating Initiating Initiating
Planning Planning Planning
Executing Executing Executing
Monitoring &  Monitoring &  Monitoring & 
Controlling Controlling Controlling
Closing Closing Closing

40
Project Management Life Cycle

41
42
Project Data, Information, and Reports

Reports

Work Performance  “Activity A cost $10 less than planned, and this is favorable” 
Information

Data Analysis (Tool or Technique)

Work Performance Data “Activity A cost $100” 

43
Exercise: Data, Information, and Reports
• Answer the following questions:
1. Is, “We’re ahead of schedule by 1 day” data or information?
2. Is, “We found two quality defects” data, information?
3. Generally, would a highly useful report contain primarily data or 
information?
4. True or false: project reports should optimally include all work 
performance information so stakeholders can determine for 
themselves what’s important.
44
Exercise Answers: Data, Information, and 
Reports
1. “Ahead of schedule by 1 day” is information. 
2. “Two quality defects” is data. 
3. Generally, a highly useful report contains primarily 
information. 
4. False 

45
Tailoring (1.2.5)
• PMBOK® Guide not a methodology
• Several project management methodologies from many 
sources ( Specifics not a requirement for CAPM exam)
• E.g. Agile, Six Sigma, Waterfall, Scrum
• Tailoring project management methodologies for each 
project can increase team’s efficiency and likelihood of 
project success.

46
Project Management Business Documents 
(1.2.6) (1 of 2) These 3 documents are considered “pre‐project work” 
• Needs assessment: examines the gaps between an organization’s 
current state and desired state
• Usually conducted prior to formally authorizing a project with a project 
charter
• Project business case: documents the expected benefits of a project; 
often used to approve a project prior to more detailed planning and 
subsequent execution
• Potentially included as part of the needs assessment
• Project benefits management plan: describes the process for creating, 
maximizing, and sustaining the project’s expected business benefit
• Can describe the alignment of targeted, measurable project benefits to 
business benefits, expected timeframe to achieve the benefits, and benefits 
owner

47
Project Management Business Documents 
(1.2.6) (2 of 2)
• Project charter: formally authorizes the project and 
empowers the project manager (see section 4.1 of the 
PMBOK® Guide)
• Project management plan: describes how the project 
management team will execute, monitor and control, and 
close the project (see section 4.2 of the PMBOK® Guide)
• Many other plans will be made throughout the project life cycle, 
called subsidiary plans.

48
Lesson 1 Review: Project Management 
Introduction
• PMP®/CAPM® Test‐Worthy  • Project Management 
Topics: Project Management  Knowledge Areas
Introduction • Project Data, Information, and 
• Defining Projects  Reports
• The Importance of Project  • Tailoring
Management • Project Management Business 
• Project, Program, Portfolio and  Documents
Operations Management  • What Are Your Questions?
• Key Components
• Project Management Process 
Groups
49
Lesson 2: The Environment in 
Which Projects Operate
Learning Objective: based on Chapters 1‐3 of the PMBOK® Guide 
Sixth Edition.

50
50
Lesson 2 Topics: The Environment in Which 
Projects Operate
• PMP®/CAPM® Test‐Worthy Topics: The Environment in Which 
Projects Operate
• Enterprise Environmental Factors (2.2)
• Organizational Process Assets (2.3)
• Organizational Systems (2.4)
• Governance Frameworks (2.4.2)
• Management Elements (2.4.3)
• Organizational Structure Types (2.4.4)
• Project Management Office

51
Enterprise Environmental Factors (2.2)
Factors beyond the team’s control, and these factors can help or hinder the project

Organizational
Marketplace
Culture

Human  Physical /  Social & 


Geography
Resources Environmental Cultural
Internal External

Commercial  Regulations & 
Technology Infrastructure
Databases Standards

52
Organizational Process Assets (2.3)
Assets specific to the organization performing the project that can both help and constrain the project team

Policies Financial

Methods Procedures
Structural 
or Project Knowledge Lessons 
Docs Learned
Governance Base
Factors
Guidelines Processes

Issues & 
Templates Defects

53
Exercise: Enterprise Environmental Factors 
and Organizational Process Assets
Identify whether each of the following options is an enterprise environmental 
factor or an organizational process asset, and which type (i.e. Internal, 
External, Structural, Knowledge Base).
1. The steps and passing score for an internal project quality audit
2. Sagging market demand for certain types of products
3. Regulations regarding financial reporting
4. Actual costs of a previous project within our organization
5. The status reporting process
6. The decision‐making authority typically given to project managers
7. IT systems that provide project schedule functionality
8. Project life cycle templates

54
Exercise Answers: Enterprise Environmental 
Factors and Organizational Process Assets
1. The steps and passing score for an internal project quality audit. OPA (Structural) 
2. Sagging market demand for certain types of products EEF (External)
3. Regulations regarding financial reporting EEF (External)
4. Actual costs of a previous project within our organization OPA (Knowledge Base)
5. The status reporting process OPA (Structural)
6. Decision‐making authority frequently given to project managers EEF (Internal)
7. IT systems that provide project schedule functionality EEF (Internal)
8. Project life cycle templates OPA (Structural) 

55
Governance Frameworks (2.4.2)
• Governance/Structural elements strive to direct employee 
and management behavior towards organizational goals. 
Examples include (Note that many of these elements include 
enterprise environmental factors and organizational process 
assets).
• Processes
• Rules
• Policies
• Procedures
• Systems (e.g., automated)

56
Management Elements (2.4.3)
• Management elements also direct employee and 
management behaviors towards organizational goals. 
Examples include
• Grouping employees with specialized skills
• Providing them with appropriate resources
• Delegating authority to make decisions
• Specifying who makes specific types of decisions
• Clarifying that organizational goals override departmental goals, 
which override individual goals
• Compensating and treating people fairly

57
Organizational Structure Types (2.4.4)
• Organizational structure type refers to the arrangement of 
people into groups and reporting responsibilities.
• Aligning the organizational structure to the nature of the 
organization’s industry, mission, vision, and overall culture 
(e.g., views of leadership) increases the likelihood of 
achieving project and organizational goals.
• Many types of organization structures exist, including:
• Organic, functional, matrix, project‐oriented, PMO, and hybrid.

58
Organizational Structure Types (2.4.4)
Organizational structures organized to show which provides the least to the most amount of power and 
authority to project managers
Organic, 
functional, and 
multi‐divisional 
(little or none)
Weak matrix 
(low)

Balanced matrix and virtual 
(low to moderate) 

Strong matrix 
(moderate to high )

Project‐oriented, and PMO 
(high to almost total)
59
Organizational Structure Types: Organic
Involves people working together flexibly to accomplish common goals. A small, family‐owned organization 
could be an example of an organic organization.

Project 
Owner Employee
coordinator

Project 
Employee
coordinator
60
Organizational Structure Types: Functional
Generally departmentalize similar types of resources (e.g., engineering, manufacturing, accounting), and most resources 
work on functional or operational activities the majority of the time. The role of a traditional project manager generally 
doesn’t exist within a functional organization, as this type of organization runs few projects, and those projects generally run 
within a single department. An organization that performs mostly repetitive activities, such as a restaurant or department 
store, could organize itself functionally.
CEO

HR Manager Sales Manager

Project 
Employee
coordinator

Project 
Employee
coordinator

Employee Employee
Note: coordinators also have functional responsibilities 61
Organizational Structure Types: Multidivisional
Essentially, a multidivisional organization consists of two or more functional organizations, with great independence 
between those organizations (i.e. geographic locations, product types). Like the functional organization, a 
multidivisional organization rarely employs full‐time project managers, and most projects occur within a single 
department.

CEO

Division  Division 
Manager Manager

Sales  Sales 
HR Manager HR Manager
Manager Manager

Project 
Employee Employee Employee
coordinator

Project 
Employee Employee Employee
coordinator
Note: coordinators also have functional responsibilities
62
Organizational Structure Types: Weak Matrix
Perform a small number of projects and a large volume of repetitive, operational activities. Most employees provide 
functional or operational services. Employees running projects such as project coordinators likely have minimal power, 
authority, and control over project human resources or funds. Communication is most complex in a Matrix.

CEO

Manager Manager Manager

Employee Employee Project 


Coordinator

Project 
Employee Employee
Coordinator
Note: coordinators also have functional responsibilities
63
Organizational Structure Types: Balanced Matrix
Organizations that create a moderate number of new products per year as well as support those products. Project 
managers and departmental managers generally possess equal power, as projects and operations provide relatively 
equal benefit to the organization. Communication is most complex in a Matrix.

CEO

Manager Manager Manager

Project 
Employee Employee
Manager

Project 
Employee Employee
Manager
Note: employees are assigned to projects as needed
64
Organizational Structure Types: Strong Matrix
Good fit for organizations that create many new products or services per year. Most employees work on projects, and 
projects account for most of the organization’s expenditures. Project managers tend to have more power than 
functional or operational managers due to the volume and importance of projects to the organization. Communication 
is most complex in a Matrix.

CEO

Manager of Project 
Manager Manager Managers

Employee Employee Project Manager

Employee Employee Project Manager

Note: employees are assigned to projects as needed
65
Organizational Structure Types: PMO
PMO provides structure and governance for projects and coordinates resources and information between projects. For 
clarity, the graphics used for this topic and the preceding Strong Matrix topic are virtually identical, with the minor difference 
of renaming the Strong Matrix’s “Manager of Project Managers” as “PMO Manager.” It’s not uncommon for a department 
with a Manager of Project Managers to organize itself as a PMO.

CEO

Manager Manager PMO Manager

Project 
Employee Employee
Manager

Project 
Employee Employee
Manager
Note: employees are assigned to projects as needed
66
Project Management Office
• Organizational group that
• Ensures strategic alignment of projects and the actual delivery of the 
organizational benefits
• Standardizes project management methodology, tools, and techniques, and 
provides training on these assets
• Shares project human resources, technology resources, and lessons learned
• Varying degree of control and influence
• Supportive (low): shares best practices, tools, templates
• Controlling (moderate): requires the use of tools and templates
• Directive (high): directs the projects; project managers report to the PMO
67
Organizational Structure Types: Project‐Oriented
Organizations likely perform a very large number of complex projects. Most human resources work on projects, and projects 
account for most organizational spending. Project managers, accordingly, have large degrees of power and authority. 
Commonly, these organizations have PMOs (not shown in the graphic) to oversee all project managers and provide 
consistency between projects. Functional departments usually perform supporting roles. A project‐oriented organization can 
experience significant turnover as projects end.

CEO

Project Manager  Project Manager Project Manager


A B C

Project Team  Project Team  Project Team 


Member Member Member

Project Team  Project Team  Project Team 


Member Member Member
68
Organizational Structure Types: Virtual
A virtual organization consists of geographically distributed resources. Realistically, a virtual organization 
might have any of the organizational structure types mentioned previously.  This graphic shows a 
balanced or strong matrix with a combination of managers, project managers, employees, and team 
members. 

Mexico Canada

Employee Team Member
USA USA

Employee HR Manager CEO Project Manager Team Member

Employee Team Member

69
Exercise: Organizational Structure Types
Assign the correct type: organic, functional, multidivisional, matrix, virtual, or project‐oriented.
1. Most of the organization’s activities involve performing highly specialized temporary and 
unique endeavors, and project team members might have no “home” when the project 
concludes. 
2. Operational policies and procedures are highly refined, and employees find the work 
predictable and stable, though the volume of work may change day to day.
3. Communication is the most complex. 
4. North American‐based project leaders have difficulties collaborating with European project 
leaders due to differing policies, processes, and documents. 
5. Establishing and coordinating with project team members can be difficult due to 
geographically dispersed and highly specialized employees who work on a variety of 
different initiatives.
6. Though project team members get cross‐departmental experience, they may have more 
difficulty getting visibility in their departments when they are working on projects. 
7. Team members work together flexibly and sometimes inefficiently to achieve both project 
and operational goals as few formal operational policies and procedures exist. 
70
Answers – Organizational Structure Types
1. Most of the organization’s activities involve performing highly specialized temporary and 
unique endeavors, and project team members might have no “home” when the project 
concludes. Project‐oriented
2. Operational policies and procedures are highly refined, and employees find the work 
predictable and stable, though the volume of work may change day to day. Functional
3. Communication is the most complex. Matrix
4. North American‐based project leaders have difficulties collaborating with European project 
leaders due to differing policies, processes, and documents. Multidivisional
5. Establishing and coordinating with project team members can be difficult due to 
geographically dispersed and highly specialized employees who work on a variety of different 
initiatives. Virtual
6. Though project team members get cross‐departmental experience, they may have more 
difficulty getting visibility in their departments when they are working on projects. Matrix
7. Team members work together flexibly and sometimes inefficiently to achieve both project 
and operational goals as few formal operational policies and procedures exist. Organic

71
Lesson 2 Review: The Environment in Which 
Projects Operate
• PMP®/CAPM® Test‐Worthy Topics: The Environment in Which 
Projects Operate
• Enterprise Environmental Factors (2.2)
• Organizational Process Assets (2.3)
• Organizational Systems (2.4)
• Governance Frameworks (2.4.2)
• Management Elements (2.4.3)
• Organizational Structure Types (2.4.4)
• Project Management Office

72
Lesson 3: The Role of the 
Project Manager
Learning Objective: Based on Chapters 1‐3 of the PMBOK® Guide 
Sixth Edition.

73
73
Lesson 3 Topics: The Role of the Project 
Manager
• PMP®/CAPM® Test‐Worthy Topics: The Role of the Project Manager
• Overview (3.1)
• The Project Manager’s Sphere of Influence (3.3)
• Project Management Competencies (3.4)
• Comparison of Leadership and Management (3.4.5)
• Leadership Styles (3.4.5)
• Performing Integration (3.5)
• PMP®/CAPM® Practice Questions
• What are your questions?

74
Role of the Project Manager: Overview (3.1)
• Responsible for achieving project’s objective and leadership of 
team to accomplish organization’s objectives
• Provides leadership, planning, and coordination
• PMs role and responsibilities vary by organization: may be 
involved before the project formally initiated (e.g., help craft 
business case) and after the project closed (e.g., determine 
actual business benefits) 
• Can work with business leaders who provide project team 
members
• Doesn’t have to be a technical expert, but familiarity with the 
work important
75
The Project Manager’s Sphere of Influence 
(3.3)
The organization The industry
• works with/influences a wide variety of  • works with/learns from other professionals 
organizational stakeholders to continually gain industry‐specific 
knowledge, skills, and best practices

The project

Professional discipline Across disciplines
• continually learn/share evolving project  • advocate the value of project management 
management best practices to a wide variety of professionals in a variety 
of settings

76
Project Management Competencies (3.4)
Project, program, and portfolio knowledge 
Knowledge of the industry and the  and skills. Understanding/applying the 
organization’s vision, strategy, and  project management processes found in the 
goals. This involves a variety of 
Strategic  Technical  PMBOK® Guide, as well as choosing the 
knowledge/skills, such as general  and  project  appropriate project methodology (e.g. agile) 
business practices, and organization‐ Business  mgt. for a given project. 
specific factors (e.g., products,  Mgt.
services, departments, competitors, 
suppliers, market factors). This 
enables the project manager to  Leadership
work with internal and external 
stakeholders.
Guiding, motivating, and directing a team 
to accomplish an organization’s goals. Skills 
in this area can include negotiating, 
communicating, problem solving, critical 
thinking, and interpersonal skills.
77
Comparison of Management and Leadership(3.4.5)
Management Leadership
Direct using positional power Guide, influence, and collaborate using relational 
power
Maintain Develop
Systems and structures Relationships with people
Rely on control Inspire trust
Focus: near‐term goals Focus: long‐range goals
Ask how and when Ask what and why
Focus on bottom line Focus on the horizon
Accepts status quo Challenges status quo
Efficiency: doing things right Effectiveness: doing the right things
Focus: operations and problem solving Focus: vision, alignment, motivation, inspiration
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) ‐ Sixth Edition, Project Management 
Institute, Inc., 2017, page 64.
78
Leadership Styles (3.4.5)
Laissez‐faire
• team make its own 
Interactional decisions; minimal 
oversight/guidance Transactional
• combination of 
transactional,  • Based on behavior of 
transformational,   team, reward/correct 
charismatic leadership appropriately

Leadership 
Styles
Charismatic
Servant Leadership
• demonstrating high 
energy and  • serve team needs 
confidence to inspire  first and leading the 
the team Transformational team second 

• demonstrating idealized 
attributes and 
characteristics

79
Performing Integration (3.5)
• Combining parts into a whole; involves systems thinking
• Project management examples
• Developing and releasing a product, service, or result that helps 
the organization achieve its strategic goals
• Managing and leading team members and stakeholders with 
differing backgrounds, skills, and motivations 
• Understanding project management process interdependencies
• Incorporating new and changing environmental factors and trends 
(e.g., new technologies, social networks, multicultural 
organizations and teams, and virtual teams)

80
Test‐Worthy Agile Project Management Topics
• This slide may be inaccurate.  Let’s look at the CAPM handbook from PMI (page 6, first paragraph).
• About PMI’s Credentials
• Looking in the PMBOK Index, there are 13 pages that mention Agile out of 756 pages.
• And yet, 6th edition exam seems a bit “Agile‐heavy” according to some test takers.
• To make up for this “disparity”, this means during the exam you’ll need to understand the driving needs in Agile Environments so you can better 
answer unexpected Agile questions on the exam.
• OR… you can study the heck out of all the “extra” Agile Topics presented here in Pinnacle and in the “Agile Practice Guide” just in case.

• When preparing for the exam, be familiar with the following agile project management terms and concepts.
• Agile values and principles
• Lean perspective
• Life cycles; iterations and increments
• Roles and skills of agile project manager (servant leader; coach) versus traditional project manager
• Roles and skills of team members 
• Roles and skills of product owner (customer) 
• Collocation; face‐to‐face communications
• For more information on these agile topics and the location of agile practice questions, see below.

81
Lesson 3 Review: The Role of the Project 
Manager
• PMP®/CAPM® Test‐Worthy Topics: : The Role of the Project Manager
• Overview (3.1)
• The Project Manager’s Sphere of Influence (3.3)
• Project Management Competencies (3.4)
• Comparison of Leadership and Management (3.4.5)
• Leadership Styles (3.4.5)
• Performing Integration (3.5)
• PMP®/CAPM® Practice Questions
• What are your questions?

82
PMP®/CAPM® Practice Questions: Lessons 1‐3
• Open the file PMP and CAPM Practice Questions. 
• Using the Table of Contents, navigate (using CTRL+Click) to 
the entry Lessons 1‐3: Framework Questions. 
• Answer the odd questions (1,3,5 etc) and check your 
answers. The answers follow the questions.
• Time to complete this exercise: 10‐15 minutes

83
Lesson 4: Initiating 
Processes
Learning Objective: Based on the PMBOK® Guide Sixth Edition 
Initiating processes.

84
84
Lesson 4 Topics: Initiating Processes
•PMP®/CAPM® Test‐Worthy Topics: Initiating Processes
•Initiating Process Group Overview
•Develop Project Charter (4.1)
•Identify Stakeholders (13.1)
•PMP®/CAPM® Practice Questions

85
Initiating Process Group Overview
• Consists of the processes to formally authorize a new project or phase 
of a project that addresses the organization’s strategic plan
• Clarifies the stakeholders affected by the project and their 
corresponding interests, levels of power, and involvement
• Involves high‐level planning
• Occurs more than once for high‐risk projects; usually at the beginning 
of each phase of the project life cycle
• Typically leads to planning the project work in detail, not to executing 
the work
• While the Project Charter ultimately affects most documents in project 
management to some degree, pay attention to when the PMBOK lists it 
explicitly as an input:  For example, it is an input into the Develop Project 
Management Plan process
86
Develop Project Charter Process
(PMBOK® Guide 4.1)
• Signed by significant stakeholders, the project charter describes the 
high‐level details of the project, shows the organization’s commitment 
to the project, and provides the project manager with authority.
• Important considerations:
• The project sponsor should contribute heavily to the drafting and approval 
of the project charter.
• The sponsor should possess sufficient political power to avoid or overcome 
potential political problems later in the project.
• The intended project manager and relevant stakeholders should help draft 
the project charter. 
• The project charter should incorporate lessons learned from past projects, 
which provide the foundation for the project’s high‐level implementation 
strategy.
• Stakeholders should be informed once the project charter is approved.
87
Develop Project Charter: Key Output
Purpose, 
success criteria Key requirements, 
Project exit criteria deliverables, and 
boundaries

High‐level 
Sponsor Project Charter schedule and 
budget

Project manager Overall risk

Key stakeholders

88
Develop Project Charter: Key Inputs, Tools 
and Techniques, Outputs 

Expert judgment
Business case  Project
Data gathering methods
Agreements charter
Interpersonal and team skills

Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) ‐
Sixth Edition, Project Management Institute, Inc., 2017, page 75.

89
Identify Stakeholders (PMBOK® Guide 13.1)
• Identifying the individuals, groups, and organizations affected or 
impacted by or who can impact the project, and determining their 
interests, involvement, interdependencies, and potential impact on 
the project
• Sets the foundation for engaging those stakeholders.  
• Following the Identify Stakeholders process, there is the Plan Stakeholder 
Engagement process in which the Stakeholder Engagement Plan is created to 
map out how to keep the key stakeholders involved and supportive.  (More on 
this in another lesson).
• Begins very early in the project, and performed at least once when 
initiating a new project as a whole, and potentially when initiating 
each new phase of the project
• Stakeholders may or may not be actively involved.
90
Identify Stakeholders: Key Outputs
• Stakeholder register, consisting of the following types of 
information:
• Stakeholder identification information
• Stakeholder assessment information
• Stakeholder classification
• Change requests (e.g., All considered vendors charge more than 
our original cost estimate, so we ask for more of project budget)
• Updates to the project management plan for any approved 
changes
• Updates to other project documents like the risk register or the 
assumptions log related to these stakeholders

91
Identify Stakeholders: Key Inputs, Tools and 
Techniques, Outputs

Data gathering methods 
Business case & 
(e.g., brainstorming, Nominal Group, questionnaires)  Stakeholder register
benefits mgt. plan
Data Representation  Change requests
Project charter
(e.g., Power/Interest Grid, Updates Project Plan 
Agreements
Salience model, 2‐D charts, 3‐D stakeholder cube) Updates other docs
Project mgt. plan
Stakeholder Analysis

Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) ‐ Sixth 
Edition, Project Management Institute, Inc., 2017, page 507.

92
Example of Power/Interest Grid

93
Example of Power and Interest Chart 
Power and Interest Grid
5

4.5
4 Sponsor
3.5
3
Project 
Power

Manager
2.5

1.5
End
Users
1

0.5

0
0 0.5 1 1.5 2 2.5 3 3.5 4 4.5 5

Interest

94
Example of Salience Model
Power: Is the ability project stakeholders has to 
influence the outcome of an organization, deliverables, 
or a project 

Legitimacy: Is the authority and level of involvement 
project stakeholders have on a project. 

Urgency: Is the time expected by project stakeholders 
for responses to their expectations. 

95
Salience Model: Deeper Dive
1. Dormant
1 2 2. Discretionary

Power 4 Legitimacy
3. Demanding
4. Dominant
7
5 6 5. Dangerous
6. Dependent
Urgency 7. Definitive
8. Non‐
8 stakeholder
3

(Sharma, 2010) 
96
Test‐Worthy Agile Project Management Topics
• Again, this slide may not be accurate.  Instead, refer to the PMI 
Handbook and the PMBOK:
• https://www.pmi.org/certifications/types/certified‐associate‐
capm/exam‐prep

• When preparing for the exam, be familiar with the following agile 
project management terms and concepts.
• Product (or project) vision statement or elevator speech
• Entire team assigned during the Initiating Process Group
• For more information on these agile topics and the location of 
agile practice questions, see below.

97
Lesson 4 Review: Initiating Processes
•PMP®/CAPM® Test‐Worthy Topics: Initiating Processes 
•Initiating Process Group Overview
•Develop Project Charter (4.1)
•Identify Stakeholders (13.1)
•PMP®/CAPM® Practice Questions
•What are your questions?

98
PMP®/CAPM® Practice Questions: Initiating 
Processes
• Open the file PMP and CAPM Practice Questions. 
• Using the Table of Contents, navigate (using CTRL+Click) to 
the entry Lesson 4: Initiating Processes Questions.  
• Answer the odd questions and check your answers. The 
answers follow the questions.
• Time to complete this exercise: 15‐20 minutes

99
Lesson 5: Planning 
Processes
Learning Objective: Based on the PMBOK® Guide Sixth Edition 
Planning processes.

100
100
Lesson 5: Planning Processes, 
Section A – Management Plans 
Overview

101
101
Lesson 5: Planning Processes, Section A Topics –
Management Plans
• PMP®/CAPM® Test‐Worthy Topics:  • Plan Communications 
Initiating Processes  Management (10.1)
• Planning Process Group Overview • Plan Risk Management (11.1)
• Develop Project Management Plan  • Plan Procurement Management 
(4.2) (12.1)
• Subsidiary Management Plans • Plan Stakeholder Engagement 
• Plan Scope Management (5.1) (13.2)
• Plan Schedule Management (6.1) • Change Management Plan and 
Configuration Management Plan 
• Plan Cost Management (7.1) (4.2)
• Plan Quality Management (8.1) • PMP®/CAPM® Practice Questions 
• Plan Resource Management (9.1)
102
Planning Process Group Overview
• Consists of the processes that define the scope, schedule, 
cost, quality, and other factors of the project
• Describes how the team will accomplish the high‐level 
objectives and solution described in the Initiating Process 
Group
• Culminates in the approval of a detailed project 
management plan, consisting of
• Four baselines (scope, schedule, cost, and performance 
measurement) 
• Subsidiary management plans
103
Develop Project Management Plan Process 
(PMBOK® Guide 4.2)
• Involves the creation of an integrated project management 
plan that defines all aspects of the project work
• As mentioned, consists of four baselines (scope, schedule, 
cost, and performance measurement) and subsidiary 
management plans
• **Requires the completion of many other Planning Process 
Group processes to finalize the baselines and the subsidiary 
management plans

104
Develop Project Management Plan: Detailed Inputs/ Outputs
Scope Mgt. Plan Communication Mgt. Plan 
Requirements Mgt. Plan Risk Mgt. Plan
Schedule Mgt. Plan Subsidiary Mgt.  Procurement Mgt. Plan
Cost Mgt. Plan Plans Stakeholder Engagement Plan
Quality Mgt. Plan Change Mgt. Plan
Resource Mgt. Plan Configuration Mgt. Plan

Project Mgt. Plan

Performance 
Baselines Scope
Measurement

Cost Schedule

This is obviously not created by one person – the PM and the team should create 
this together – though the PM assumes accountability for creating a realistic plan.
105
Subsidiary Management Plans
Change Mgt. 
Plan
Stakeholder  4.2.3.1 Configuration 
Mgt. Plan Mgt. Plan
13.1.3.1 4.2.3.1

Procurement 
Scope Mgt. Plan
Mgt. Plan
5.1.3.1
12.1.3.1

Subsidiary  Requirements 
Risk Mgt. Plan
Mgt. Plan
11.1.3.1 Mgt. Plans 5.1.3.2

Commun. Mgt.  Schedule Mgt. 
Plan Plan
10.1.3.1 6.1.3.1

Resource Mgt. 
Cost Mgt. Plan
Plan
7.1.3.1
9.1.3.1 Quality Mgt. 
Plan
8.1.3.1

106
Develop Project Management Plan: Key 
Inputs, Tools and Techniques, Outputs

Expert judgment
Project charter Data gathering
Outputs of  Interpersonal and team skills Project 
other processes Management Plan
Meetings
OPAs
(Kickoff Meetings signify end of Planning Process Group on 
big projects)

Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) ‐
Sixth Edition, Project Management Institute, Inc., 2017, page 82.

107
Plan Scope Management Process
(PMBOK® Guide 5.1)
• Part of the Project Scope Management Knowledge Area, which 
includes the processes that help the project team define and control the 
work and deliverables included in (as well as excluded from) the project. 
• Plan Scope Management involves the creation of the scope 
management plan and the requirements management plan that 
describe how the team will perform all other processes in the Project 
Scope Management Knowledge Area, including:
Initiating Planning Executing Monitoring &  Closing
Controlling
Collect Requirements (5.2) Validate Scope (5.5)
Define Scope (5.3) Control Scope (5.6)
Create WBS (5.4)

108
Project Scope Management Key Concepts 
(PMBOK® Guide 5)
• Product scope: the features and functions that characterize a 
product, service, or result; 
completion measured against the product requirements
• Project scope: the work performed to deliver a product, 
service, or result with the desired features and functions; 
completion measured against the project management plan
• For predictive life cycles, scope generally locked down during 
planning to minimize unnecessary downstream changes, false starts, 
and rework
• For agile life cycles, scope progressively elaborated during the 
planning portion of each iteration
109
Project Scope Management Key Concepts 
(PMBOK® Guide 5) 
• Requirements: measurable and testable characteristics of a 
product, service, or process
• Deliverables: tangible work products or capabilities to perform a 
service
• Requirements drive deliverables!

110
Plan Scope Management: Key Outputs
Documents how subsequent processes in the 
Knowledge Area Project Scope Management 
will be performed. Documents decisions such 
as:
Scope mgt.  • How and when will scope statement and 
plan WBS be documented
• Who will document scope and WBS
• How will completed deliverables be 
approved
Plan Scope  • How will team control possible changes
Management 
outputs
Documents how team will manage numerous 
requirements over life of project. Documents 
decisions such as
• How and when will requirements be  Requirements 
documented mgt. plan
• Who will document requirements
• How will requirements be approved
• How will team control possible changes 111
Plan Scope Management: Key Inputs, Tools, 
and Techniques, Outputs

Project charter Expert Judgement  Scope mgt. plan


Data Analysis Requirements mgt. 
Project mgt. plan Meetings plan

Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) ‐ Sixth Edition, 
Project Management Institute, Inc., 2017, page 130.

112
Plan Schedule Management Process
(PMBOK® Guide 6.1)
• Part of the Project Schedule Management Knowledge Area, which 
includes the processes that help the project team create and control a 
realistic and optimized timeline to complete the agreed‐upon work. 
• The first process in this knowledge area, Plan Schedule Management, 
involves the creation of the schedule management plan that describes 
how the team will perform all other Project Schedule Management 
processes, including:
Initiating Planning Executing Monitoring &  Closing
Controlling
Define Activities (6.2) Control Schedule (6.6)
Sequence Activities (6.3)
Estimate Activity Durations (6.4)
Develop Schedule (6.5)

113
Project Schedule Management Key Concepts 
(PMBOK® Guide 6) (1 of 2)

Scheduling  Schedule  Schedule 


method baseline presentation
Scheduling  • Locked‐down
• CPM  • Gantt
• Agile method
tool • No changes  • Network 
without change  diagram
control
• Milestone chart

114
Project Schedule Management Key Concepts 
(PMBOK® Guide 6) (2 of 2)
Plan‐driven or  Scope 
Resource  Learning 
agile  complexity 
experience curve
approach and risk

Realistic  Reporting 
Incentives
Schedule requirements

Work hours,  Quantity of 
Resource  Scheduling 
productivity,  resources and 
availability quality, morale
technology
productivity

115
Plan Schedule Management: Key Output
• Documents how subsequent processes in the Project Schedule 
Management Knowledge Area will be performed. Documents 
decisions such as:
• Who will create schedule.
• What tools will be used to create schedule.
• What sources of historical information available to create 
schedule.
Plan  • How will team control possible changes.
Schedule  Schedule  • Will team choose a plan‐driven or an agile approach. 
Management  mgt. plan
• Who will review schedule progress to determine schedule 
output
performance, and how often will this be done.
• What are important measurement units for controlling 
schedule, such as monitoring hours of effort, duration, 
and/or milestones.
• What are thresholds related to controlling schedule, and 
what are the corrective actions required when schedule 
exceeds thresholds.
116
Plan Schedule Management: Key Inputs, Tools 
and Techniques, Outputs

Project charter Expert Judgement 
Data Analysis Schedule mgt. plan
Project mgt. plan Meetings

Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) ‐ Sixth Edition, 
Project Management Institute, Inc., 2017, page 174.

117
Plan Cost Management Process
(PMBOK® Guide 7.1)
• Part of the Project Cost Management Knowledge Area, which includes 
the processes that help the project team create and control a realistic 
and optimized cost baseline and cost budget to complete the agreed‐
upon work.
• The first process in this knowledge area, Plan Cost Management, 
involves the creation of the cost management plan that describes how 
the team will perform all other processes in the Project Cost 
Management Knowledge Area, including:
Initiating Planning Executing Monitoring &  Closing
Controlling
Estimate Costs (7.2) Control Costs (7.4)
Determine Budget (7.3)

118
Project Cost Management Key Concepts 
(PMBOK® Guide 7) (1 of 3)
Estimating 
project costs
Estimating  Securing 
Return On  internal and/or 
Investment  external 
funding
Project Cost 
Mgt.
Optimizing  Incorporating 
project costs  reporting 
vs. operational  standards and 
costs regulations 
Controlling 
costs 

119
Project Cost Management Key Concepts 
(PMBOK® Guide 7) (2 of 3)
• Cost baseline
• Approved project costs plus contingency reserves (for known risks)
• Part of the project management plan
• Cannot change without approved change request
• Project budget: 
• Cost baseline plus management reserves (for unknown risks) 

• Agile projects can estimate costs for each iteration
• A cost‐constrained project may not produce all scope
120
Project Cost Management Key Concepts 
(PMBOK® Guide 7) (3 of 3)
• Estimating and managing cost considerations include: 
• scope complexity
• risk
• plan‐driven or agile approach
• reporting requirements
• availability of cost tools
• relationship between quality and cost
• resource availability
• learning curve impact
• impact of incentives on performance
• … and more …
121
Plan Cost Management: Key Output
• Documents how subsequent processes in the Project Cost 
Management Knowledge Area will be performed. Documents 
decisions such as:
• Who will estimate project costs.
• What tools will be used to create project cost 
estimates/budget.
• What is process to lock down cost baseline and project 
budget with project sponsor.
Plan Cost 
Cost mgt.  • What sources of historical information are available to 
Management  estimate costs, including labor, materials, supplies, facilities, 
plan
outputs inflation, currency fluctuations, and other factors. 
• How will team control possible changes.
• Who will review actual project spending and funding to 
determine cost performance, and how often.
• What is the level of detail required for controlling and 
reporting project costs, such as tracking costs to the nearest 
thousands of dollars, hundreds of dollars, dollars, or pennies.

122
Plan Cost Management: Key Inputs, Tools and 
Techniques, Outputs

Project charter Expert Judgement 
Data Analysis Cost mgt. plan
Project mgt. plan Meetings

Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) ‐ Sixth Edition, 
Project Management Institute, Inc., 2017, page 232.

123
Plan Quality Management (PMBOK® Guide
8.1)
• Part of the Project Quality Management Knowledge Area that includes 
the processes that help the project team achieve overall stakeholder 
satisfaction by meeting stakeholders’ product and project requirements. 
It also involves continuous project, product, and process improvement. 
• This first process, Plan Quality Management, involves the creation of 
the
• Quality metrics: measurable attributes that indicate stakeholder satisfaction 
(e.g., number of defects, downtime per month, customer satisfaction scores)
• Quality management plan: describes how the team will perform all other 
processes in the Project Quality Management Knowledge Area, including:

Initiating Planning Executing Monitoring &  Closing


Controlling
Manage Quality (8.2) Control Quality (8.3)
124
Plan Quality Management: Key Concepts

Quality 
objectives

Deliverables  Quality roles 
testing plans and 
responsibilities
Quality Mgt. 
Plan
Continuous 
improvement  Quality OPAs
and audit plans

Quality EEFs

125
Plan Quality Management: Key Inputs, Tools 
and Techniques, Outputs

Benchmarking
(Comparing our planned result against comparable entities)
Data gathering methods Quality 
Project charter
Data analysis  metrics
Project mgt. plan
(Cost/Benefit Analysis, Cost of Quality(Conformance and Nonconformance)
Other planning  Decision making Quality 
documents
(Multicriteria Decision Analysis)
mgt. plan
Data representation
(Flowcharts, Matrix Diagrams, Mind Mapping)

Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) ‐
Sixth Edition, Project Management Institute, Inc., 2017, page 75.

126
Cost of Quality (COQ)

Cost of Conformance Cost of Nonconformance
• Project money spent to avoid  • Project and operational money 
failures spent because of failures
• Prevention (build) costs  • Internal failure costs 
(e.g., training, documentation,  (found by the project team; e.g., 
equipment) rework and scrap)
• Appraisal (assessment) costs  • External failure costs 
(e.g., testing, destructive test loss,  (often found by the customer; e.g., 
inspections) liabilities, warranty work, loss of 
business)

127
Multicriteria Decision Analysis
Criteria
Possible Solution Addresses Entire  Schedule to  Cost to Implement Risk to Implement Total
Problem? Implement (1‐5) (1‐5)
(1‐10) (1‐8)

Solution 1 4 8 4 3 19
Solution 2 5 7 3 2 17
Solution 3 7 3 1 5 16
Solution 4 10 4 4 2 20
Note: Higher scores indicate desirability. Thus, a solution that addresses the entire problem receives a 10 out 
of 10. Similarly, a solution with a short schedule, a low cost and a low risk are desirable, and thus, it receives 
higher scores for these criteria.  Solution 4, with a total score of 20, is the most desirable solution.

128
Flowcharts (a.k.a. Process Maps)
Side Note:  Be aware of SIPOC flowcharts.
Customer calls customer service
SIPOC (Suppliers, Inputs, Process, Outputs, Customers) 
A particular type of flowchart, describes the entire 
Agent determines problem and  system flow from supplier to end customers, though it 
provides solution emphasizes understanding customer needs first, then 
working upstream to the suppliers to ensure the 
system meets customer needs.
Customer 
Satisfied? While it could be helpful for finding risks to quality, it is 
Yes more often use to judge a process, or identify scope.

Service complete

129
Matrix Diagrams
Matrix diagrams show relationships between a variety of quality factors, such as requirements, 
specifications, features, customer importance, risks, development costs, and development priorities. 
Below is a simplified example that only pits Customer Requirements with Product Features.

Intended Features/Components
Customer  Feature 1 Feature 2 Feature 3 Feature 4 Feature 5
Requirement

Requirement 1 X X
Requirement 2
Requirement 3 X X
Requirement 4 X X

130
Mind Mapping

131
Plan Resource Management Process 
(PMBOK® Guide 9.1)
• Part of the Project Resource Management Knowledge Area, which includes the 
processes that help to identify, acquire, develop, manage, and control the resources 
(e.g., human, equipment, facilities) needed to complete the project work. 
• The first process in this knowledge area, Plan Resource Management involves the 
creation of two key outputs: the resource management plan and the team charter. The 
resource management plan describes how the project management team will perform all 
other processes in the Project Resource Management Knowledge Area, including:

Initiating Planning Executing Monitoring &  Closing


Controlling
Estimate Activity  Acquire Resources (9.3) Control Resources (9.6)
Resources (9.2) Develop Team (9.4)
Manage Team (9.5)

132
Project Resource Management Key Concepts 
(PMBOK® Guide 9)
PM required skills for physical  PM required skills for human 
resources resources
• Just In Time (JIT) inventory management  • Assessing team skills
• Order as needed • Conducting team building activities
• Because having more inventory than needed 
introduces unnecessary costs associated with  • Coaching and motivating team 
inventory storage, obsolescence, and shrinkage members
• Theory of Constraints (Goldratt & Cox, 1992) • Recognizing and incorporating 
• Involves locating and removing bottlenecks that  cultural differences
limit throughput • Working with virtual teams
• Can be ideal for projects that involve the design 
and development of operational products or  • Negotiating, resolving conflict, and 
services (e.g., manufacturing goods, call center  employing politics
operations)
• Incorporating HR regulations and 
• Critical Chain (Goldratt, 1997) constraints
• Similar to Theory of Constraints, only applied to 
the project workflow
133
Plan Resource Management: Key Outputs (1 of 2)
How to identify 
and acquire project 
resources types 
and quantities  Roles, authorities, 
Team member 
rewards and  responsibilities, 
recognition plans and competencies
Resource Mgt. 
Plan
Physical  Project reporting 
resources policies  relationships 
and practices
Team resource 
management 
information 

134
Plan Resource Management: Key Outputs (2 of 2)

Team values

Communication 
Team agreements guidelines

Team Charter

Meeting  Decision making 
guidelines processes
Conflict resolution 
processes

135
Plan Resource Management: Key Inputs, Tools 
and Techniques, Outputs

Data representation techniques, including:
Project charter
1. Hierarchical charts  Resource 
Project mgt. plan mgt. plan
(e.g., OBS, RBS, Project Organizational Charts)
Project  Team charter
2. Responsibility Assignment Matrices
documents
(RAM: e.g. RACI charts)

Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) ‐ Sixth Edition, 
Project Management Institute, Inc., 2017, page 312.

136
Organizational Breakdown Structures (OBS)
Shows deliverables, work packages, or activities, organized by the individuals (internal or 
external) responsible for performing the work.

Project

IT Finance

Develop  Provide 
Systems Requirements

Test Systems Provide Sign‐off

137
Resource Breakdown Structure (RBS)
Shows all project resources in graphic form. An RBS generally provides reporting relationships between 
human resources, but it also includes information related to other resources such as materials, 
facilities, equipment, etc.
Project 
Resources

People Materials Facilities Equipment

IT Finance Paper Test Lab Test Server

Conference  High‐speed 
Technicians Manager Ink Cartridges
Rooms Printer

Developers Finance SME

138
Project Organizational Charts
Shows authority levels and reporting relationships between project stakeholders. 

Sponsor

Project 
Manager

IT Team  Finance 
Lead Team Lead

Technicians Analyst

Financial 
Developers
139 Planner
Responsibility Assignment Matrix (RAM);
RACI (Responsible/Accountable/Consulted/Informed)
Work Package Responsible Accountable Consulted Informed

Provide  Business Analyst Lead Business Finance Manager Project Manager


Requirements Analyst

Develop System IT Technicians IT Manager  External IT Analyst Project Manager, 


Finance Manager Finance Manager

Test System Quality Control Quality Control  N/A Project Manager


Manager

** Having 2+ people “Accountable” for the same work package usually a bad idea (confusion, conflict, blame game)

140
Plan Communications Management Process 
(PMBOK® Guide 10.1)
• Part of the Project Communications Management Knowledge 
Area, which includes the processes that help ensure the effective 
flow of communications between project stakeholders. Effective 
communications greatly improve the likelihood of project 
success. 
• The first process in this knowledge area, Plan Communications 
Management, involves the creation of the communications 
management plan. This document describes how the project 
management team will perform all other processes in the Project 
Communications Management Knowledge Area, including:
Initiating Planning Executing Monitoring & Controlling Closing
Manage Communications (10.2) Monitor Communications (10.3)

141
Project Communications Management Key 
Concepts (PMBOK® Guide 10)
Important PM 
Communication Dimensions communications skills
• Internal and external • Writing
• Formal and informal • Listening
• Horizontal and vertical • Public speaking
• Official and unofficial • Diversity
• Stakeholder expectation setting
• Motivating and coaching
• Persuading  and negotiating
• Resolving conflict
• Social networking

142
Plan Communications Management: Key 
Concepts
Information 
communicated
Time and cost of  Reason or benefit 
communications

Communications 
mgt. plan
When and how  From whom
often

To whom

***The communications management plan may also specify particulars such as:
escalation paths, a glossary of common terms, and methods to update the communications 
management plan itself. 143
Plan Communications Management: Key 
Inputs, Tools and Techniques, Outputs

Expert judgment
Communications requirement analysis
Project charter
Communications technology
Project mgt. plan Communications
Communications model
Project  mgt. plan
Communications methods
documents
Interpersonal and team skills
Data representation

Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) ‐ Sixth 
Edition, Project Management Institute, Inc., 2017, page 366.

144
Communications Requirement Analysis: 
Number of Communication Channels= N(N‐1)/2 (Where N = # of stakeholders)

3 Stakeholders; 3 channels 4 Stakeholders; 6 channels
N (N‐1)/2        3*(2)/2 = 3 N (N‐1)/2       4*(3)/2 = 6

145
Communications Model
Feedback
Loop
Sender Receiver

Idea Encoding Message Decoding Meaning

Noise

Perceptual Differences:
Words, Culture, Judgments, 
Values, Emotions, 
Personalities
146
Communication Methods
The methods utilized to share information among stakeholders can be 
divided into three primary methods:

• Interactive: exchange of information between multiple parties and 
fosters a common understanding between participants
I I

• Push: distribute information but does not ensure that the information  I
was received or understood

• Pull: provide information in a centrally accessible location such as the 
Internet I

147
Plan Risk Management Process
(PMBOK® Guide 11.1)
• Part of the Project Risk Management Knowledge Area, which includes 
the processes that help to identify, analyze, respond to, and control 
project uncertainties.
• This first process in this knowledge area, Plan Risk Management involves 
the creation of the risk management plan that describes how the 
project management team will perform all other processes in the Project 
Risk Management Knowledge Area, including:
Initiating Planning Executing Monitoring &  Closing
Controlling
Identify Risks (11.2)  Implement Risk  Monitor Risks 
Perform Qualitative Risk Analysis (11.3) Responses (11.6) (11.7)
Perform Quantitative Risk Analysis (11.4) 
Plan Risk Response (11.5)

148
Project Risk Management Key Concepts 
(PMBOK® Guide 11) (1 of 2)
• Project risk management involves evaluating and responding to risks in a 
controlled fashion, and optimizing the time and cost of risk management
activities against the expected project rewards.
• Project risk activities should vary based on the specific project’s 
magnitude, complexity, and development approach.
• Risks represent uncertainty (potentially desirable and undesirable events.)
• “Known unknowns” = Risks we successfully anticipate
• “Unknown unknowns” = Risks we didn’t anticipate
• Project risk management examines individual risks, the sources of risk, and 
the overall project risk rating.
• ***The project management team should reevaluate all risks at least once 
per phase of the project life cycle (plan‐driven projects) or once per 
iteration/sprint (agile projects.) 
149
Project Risk Management Key Concepts 
(PMBOK® Guide 11) (2 of 2)
• A positive risk is an opportunity; a negative risk is a threat.

• An example of a positive risk event is accommodating the growth 
that results when the sales of a new product exceed expectations.

• An example of a negative risk is the reliance on a piece of software 
that is not available when needed or as planned, forcing the team 
to come up with an alternative.  

150
Project Risk Management Emerging Trends 
(PMBOK® Guide 11) • Non‐event risks involve the examination of 
favorable/unfavorable events or decisions that may occur 
during the project. 
Non‐event  • Variability Risks: aspect of a planned task is uncertain
risks • Ambiguity Risks: lack of knowledge
• Emergent Risks: limitations in our conceptual 
frameworks or world‐view (“unknown unknowns”)
• Project resilience entails preparing the project and the 
project team to more effectively accommodate “unknown 
Emerging  unknowns” through methods such as allocating additional 
trends reserve time/money, and empowering the team to make 
decisions.
Integrated  Project  • Integrated risk management involves the development of 
risk mgt. resilience organization‐wide, coordinated, systematic, and consistent 
risk management processes, policies, and procedures. 

151
Plan Risk Management: Key Concepts

Strategy and 
methodology 
Reporting,  Funding and 
tracking, auditing,  timing 
improving
Risk Mgt. Plan

Terms, scales, 
and scale  Risk categories
definitions
Stakeholder risk 
appetites / 
thresholds

152
Risk Appetites

Type Description

Risk‐averse Risk‐averse is a mentality of risk avoidance. Selecting the 


low risk item or the sure thing is typical in this case.  

Risk seeker Risk seeker is a mentality of looking for risk, or worse case, 


not being afraid of it.  This is typically the early adopter of 
new products, or the person or company that is willing to go 

for an all or nothing approach to an initiative.  

Risk‐neutral Risk‐neutral is a middle ground mentality toward risk.  It can 
shift toward either seeker or averse, depending upon the 
situation but usually falls in the middle.  

153

Risk Breakdown Structure (RBS)
Provides a method to visually display project risks by category. The simplified graphic on 
this page shows three categories of risk: scope, schedule, and business risks. Hundreds of 
categories of risk exist.

Project risks

Scope risks Schedule risks Business risks

1.1 Unclear  2.1 Material  3.1 New 


requirements delays competitors

3.2 Changing 
1.2 Lack of  2.2 Decision 
consumer 
team expertise delays
tastes

154
One Way to Identify Risks:  Fishbone Diagram 
(a.k.a. Cause and Effect, a.k.a. Ishikawa Diagram)

Also good for finding root 
cause of problems, and 
other uses

155
Probability and Impact Assessment; 
Probability and Impact Chart
Probability and Impact 
Assessment Probability and Impact Chart
Risk Probability Impact Rating High
(1‐5) (1‐5) (P * I)
Risk 1 3 4 12
Risk 2 2 3 6
Probability

Low
Low Impact High

156
Plan Risk Management: Key Inputs, Tools and 
Techniques, Outputs

Project charter
Expert judgment
Project mgt. plan Risk
Data analysis
Other project  mgt. plan
Meetings
documents

Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) ‐
Sixth Edition, Project Management Institute, Inc., 2017, page 401.

157
Plan Procurement Management Process 
(PMBOK® Guide 12.1)
• Part of the Project Procurement Management Knowledge Area, 
which includes the processes that help the project management 
team or other relevant stakeholders to obtain products and 
services from outside the organization. 
• This first process in this knowledge area, Plan Procurement 
Management, involves the creation of numerous outputs. One of 
these outputs, the procurement management plan, describes 
how the project management team will perform the other 
processes in the Project Procurement Management Knowledge 
Area, including:
Initiating Planning Executing Monitoring & Controlling Closing
Conduct Procurements (12.2) Control Procurements (12.3)

158
Project Procurement Management Key 
Concepts (PMBOK® Guide 12)
• General procurement concepts apply to legally binding contracts, Service Level 
Agreements (SLAs), Memorandums of Understanding (MOA), and purchase 
orders. 
• Procurement introduces complexities and risks for the organization and the 
project team.
• Departments (e.g., purchasing, legal, or contracting) ensure that the contract 
addresses all requirements, risks, and regulations. The contracting officer works 
with the project manager to obtain external goods and services. The 
contracting officer has the authority to enter into legally binding contracts and 
make contract modifications. 
• Organizations can have two major approaches:
• Centralized purchasing: specific department that handles all procurement activities
• Decentralized purchasing: delegate procurements to the project manager

159
Project Procurement Management Emerging Trends and Practices
New technology tools have increased 
procurement efficiencies. For 
Organizations hire contractors under a  example, online portals that link 
trial engagement to gauge whether  buyers and vendors help to 
the contractor has the ability to  standardize and streamline the 
successfully provide the desired  Technology tools acquisition, delivery, and closure of 
products and services (online portals) contracts

Trial 
engagements Risk 
Emerging trends management
(contractors)
Increased procurement accountability and 
More refined approaches to 
transparency to stakeholders. For example, 
Accountability  defining and allocating risks 
USASpending.gov provides general public 
and  between buyers and 
with information related to amount of 
transparency  vendors
money that agencies have spent on 
initiatives and the organizations that have 
provided those products and services 160
Plan Procurement Management: Key Outputs
Procurement  Procurement 
Change requests
mgt. plan strategy

Plan 
Independent 
Procurement  Bid documents
cost estimates
Mgt.

Make or buy  Source selection  Procurement 


decision criteria SOW

161
Fixed‐Price Contract Payment Type

Firm‐Fixed Price 
(FFP; lump sum)

Fixed Price 
Purchase order Fixed Price Types Incentive Fee 
(FPIF)

Fixed Price 
Economic Price 
Adjustment 
(FPEPA)

162
Fixed‐Price Contract Payment Type
• Firm‐Fixed‐price (lump sum): a set price for well‐known deliverables with few expected changes.
• Fixed‐Price Incentive Fee: a fixed‐price contract that provides a financial incentive for one or 
more criteria. For example, a vendor performing road maintenance for a fixed price might earn 
an additional $2,000 for every day they finish ahead of schedule.
• Fixed‐Price Economic Price Adjustment (FP‐EPA): generally used for well‐defined, lengthier 
projects. This type of contract payment permits price fluctuations for items like wages or 
commodities. Typically, these contracts fix quantities, such as number of labor hours or the 
number of components or the volume of materials purchased, but the price per item charged 
fluctuates using an agreed‐upon index (e.g., a steel index). 
• Purchase order: a unilateral (signed by the buyer only) contract, typically for commodities. The 
definition of purchase order can vary greatly by organization. However, it’s somewhat common 
for an organization to enter into a contract with a vendor for a specific commodity for a 
certain time period at a specific fixed price per item (e.g., $30.00 for 10 reams of a specific type 
of paper). When the organization needs to acquire additional quantities, the organization 
creates (and potentially signs) a purchase order, and routes it to the vendor for fulfillment. 
163
Cost‐Plus Contract Payment Type

Cost

Cost Plus Award  Cost Sharing
Fee

Cost plus types

Cost Plus  Cost Plus 
Incentive Fee  Percentage of 
(CPIF) Cost (CPPC)
Cost Plus Fixed 
Fee (CPFF)

164
Cost‐Plus Contract Payment Type
• Cost Contract (Garrett, 1997): the organization pays the vendor’s actual costs with no profit. 
Government partnering with universities can use this type of contract.
• Cost‐Sharing Contract (Garrett, 1997): the organization pays only a portion of the vendor’s cost 
with no profit. If the vendor benefits from the development of a product or service (e.g., it can be 
sold to other customers), the vendor might be willing to absorb some of the development costs.
• Cost‐Plus‐Percentage‐of‐Cost (CPPC) contract (Garrett, 1997): the vendor up charges a specific 
percentage of the actual costs as profit. This type of contract poses great risk to the buyer, as 
unethical vendors have an incentive to prolong projects and acquire the most expensive resources. 
• Cost Plus Fixed Fee (CPFF): the vendor receives a fixed monetary (e.g., dollars) amount of profit, 
regardless of actual project costs. For example, a software development vendor may charge the 
client $20,000 as a fixed fee (unchanging profit). If actual costs amount to $100,000, the buyer pays 
this $100,000, plus the fixed fee of $20,000.
• Cost Plus Incentive Fee (CPIF): the vendor and buyer agree on a high‐level cost target for the 
project work, and then agree to share the cost savings or the cost overruns.  For example, they 
agree to share any savings and cost overruns using a 30%/70% (buyer/vendor) ratio. 
• Cost Plus Award Fee (CPAF): in addition to actual costs, the buyer pays the vendor a potential 
profit (the award fee) based on the buyer’s satisfaction with subjective performance criteria. This 
type of contract poses great risk to the vendor.
165
Time and Materials Contract Payment Type
• Often used for staff acquisition, hiring experts, and where 
precise work is unknown
• Therefore the vendor charges for all costs like labor and materials 
using predetermined prices. 
• Time and materials payment type contains elements of 
• Fixed‐price payment: labor rates, materials, and other factors use set 
prices (unchanging unit prices)
• Cost‐reimbursable payment: both the work and the final costs are 
open ended
• Time and materials places a burden on the organization to 
ensure that assigned human resources have both sufficient 
work and supervision.
166
Plan Procurement Management: Key Outputs 
(Reminder)
Procurement  Procurement 
Change requests
mgt. plan strategy

Plan 
Independent 
Procurement  Bid documents
cost estimates
Mgt.

Make or buy  Source selection  Procurement 


decision criteria SOW

167
Make or Buy Calculation
(x = daily cost)
Buy (an asset)    Lease (an asset)
$1,000,000 + $1,000X            $5,000X       
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
$1,000,000 + $1000(4)           $5,000(4)
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐ ‐‐‐‐‐‐‐‐‐‐‐‐‐ 4 days actual cost comparison
$1,004,000                              $20,000
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
$1,000,000/$5000‐$1000 = 250 days 
(Break Even Point, taking into account the $1,000 daily maintenance fee)

168
Source Selection Analysis
• Provides prospective vendors with a description of how the organization will choose the vendor:
oLeast cost: the lowest cost, technically acceptable vendor is generally offered the work.
oQualifications only: the organization shortlists a small number of potential vendors and offers the work to the 
vendor who possesses the best qualifications, experience, references, or similar criteria.
oQuality‐based/highest technical proposal score: the vendor with the best technical proposal. Provided the buyer 
and vendor can negotiate an agreeable price, the organization offers the work to this vendor.
oQuality and cost‐based: the organization considers the quality, cost, and potentially other factors of the vendors 
submitting proposals, and offers the work to the vendor who provides the most applicable solution. The 
organization can use weighting and screening criteria to determine the most suitable vendor.
oSole source: where only one vendor could possibly provide the product or service, such as when a vendor holds 
a patent or highly specialized knowledge. In these cases, the vendor holds considerable leverage over the buyer.
oSingle source: the buyer chooses a particular vendor to provide standard products and services, generally for a 
fixed time period through a master contract. These can provide benefits to the organization (e.g., lower prices, 
faster acquisition of products and services, consistent quality) and to the vendor (consistent work and revenue 
with reduced procurement‐related work.)
oFixed budget: the organization specifies the maximum amount of money available and describes the desired 
scope. Vendors provide responses on the quantities of products and services they can provide within the cost 
constraint. 169
Plan Procurement Management: Key Inputs

Business  Project 
Project  mgt. 
documents
charter plan

Other 
project 
documents

Procurement Mgt. Plan
Procurement Strategy
Other outputs

170
Plan Procurement Management: Key Tools 
and Techniques

Expert judgment Procurement mgt. 
Project charter
Data gathering  plan
Business  Procurement 
documents (Market Research) strategy
Project mgt. plan Data analysis Bid documents
Procurement SOW
Project  Source selection analysis Other outputs
documents
Meetings

Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) 
‐ Sixth Edition, Project Management Institute, Inc., 2017, page 466.

171
Plan Stakeholder Engagement Process
(PMBOK® Guide 13.2)
• Part of the Project Stakeholder Management Knowledge Area, which includes the 
processes that help to identify the individuals, groups, and organizations affected by 
the project; determine their requirements, and determine how to engage them 
throughout the project to ensure their support. 
• This second process in this knowledge area, Plan Stakeholder Engagement involves the 
creation of a stakeholder engagement plan that describes the activities that will be 
performed to keep stakeholders involved, interested, and supportive of the project. This 
document also describes how the project management team will perform all other 
processes in the Project Stakeholder Management Knowledge Area, including:

Initiating Planning Executing Monitoring & Controlling Closing


Manage Stakeholder  Monitor Stakeholder 
Engagement (13.3) Engagement (13.4)

172
Plan Stakeholder Engagement: Key Concepts

Current and desired 
Process for  engagement levels
Planned strategies
updating the plan

Stakeholder 
engagement plan
Expected project 
impact on  Stakeholder 
stakeholders interrelationships
(and their reactions)

173
Plan Stakeholder Engagement: Key Inputs, 
Tools and Techniques, Outputs

Expert judgment
Project charter Data gathering
Data analysis Stakeholder 
Project mgt. plan
Decision making engagement 
Project  plan
Data representation
documents
(Stakeholder Engagement Assessment Matrix)
Meetings
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) ‐ Sixth Edition, 
Project Management Institute, Inc., 2017, page 516.

174
Stakeholder Engagement Assessment Matrix
Stakeholder Unaware Resistant Neutral Supportive Leading

Sponsor D, C

Customer C D

Functional  C D
Manager 1

D= Desired level of engagement 
C = Current level of engagement
175
Change Management Plan and Configuration Management Plan 
(Additional Components to Project Management Plan)
(PMBOK® Guide 4.2.3.1)
• **Change management plan
• Specifies the process for evaluating and potentially incorporating project 
changes that affect one or more of the project’s baselines
• Helps minimize scope creep, gold plating, late delivery, and cost overruns
• **And yet, NOT a process in the PMBOK process groups and knowledge areas
• **Configuration management plan
• Describes the project products, product documentation, and what product 
information will be identified, recorded, verified, and audited.
• Benefits: identifying recalled components, documenting methods to quickly 
resolve incidents, identifying maintenance schedules, etc.
• Works hand‐in‐hand with project change management systems: requested 
changes often affect and create configuration items
• **And yet, NOT a process in the PMBOK process groups and knowledge areas
176
Lesson 5: Planning Processes, Section A Review –
Management Plans
• PMP®/CAPM® Test‐Worthy Topics:  • Plan Resource Management (9.1)
Lesson 5, Section A – Management  • Plan Communications Management 
Plans  (10.1)
• Planning Process Group Overview • Plan Risk Management (11.1)
• Develop Project Management Plan  • Plan Procurement Management 
(4.2) (12.1)
• Subsidiary Management Plans • Plan Stakeholder Engagement (13.2)
• Plan Scope Management (5.1) • Change Management Plan and 
• Plan Schedule Management (6.1) Configuration Management Plan (4.2)
• Plan Cost Management (7.1) • PMP®/CAPM® Practice Questions
• Plan Quality Management (8.1) • What are your questions?

177
PMP®/CAPM® Practice Questions: Planning 
Processes, Section A
• Open the file PMP and CAPM Practice Questions. 
• Using the Table of Contents, navigate (using CTRL+Click) to 
the entry Lesson 5: Planning Processes Section A: 
Management Plans Questions. 
• Answer the odd‐numbered questions and check your 
answers. The answers follow the questions.
• Time to complete this exercise: 15‐20 minutes

178
Lesson 5: Planning Processes, 
Section B – Scope, Schedule, 
Resource, and Cost Processes
Learning Objective: Based on the planning processes described in the 
PMBOK® Guide Sixth Edition, Planning processes.

179
179
Lesson 5: Planning Processes, Section B Topics – Scope, 
Schedule, Resource, and Cost Processes
• PMP®/CAPM® Test‐Worthy Topics:  • Resource Planning Processes 
Lesson 5, Section B: Scope,  Overview
Schedule, and Cost Processes • Define Activities (6.2)
• Scope, Schedule, Resource, and  • Sequence Activities (6.3)
Cost Processes Overview
• Scope Planning Processes  • Estimate Activity Resources (9.2)
Overview • Estimate Activity Durations (6.4)
• Collect Requirements (5.2) • Develop Schedule (6.5)
• Define Scope (5.3) • Cost Planning Processes Overview
• Create WBS (5.4) • Estimate Costs (7.2)
• Schedule Planning Processes  • Determine Budget (7.3)
Overview • PMP®/CAPM® Practice Questions
180
Scope, Schedule, Resource, and Cost Planning 
Processes Overview
• This section of the course describes in detail all the remaining 
planning processes for the Project Scope, Schedule, Resource, 
and Cost Knowledge Areas processes.
• Some project management books describe scope, schedule, and 
cost as the “triple constraints.”
• It’s a long‐running truism (and perhaps somewhat of a joke) that if the 
customer locks down the scope, schedule, and cost without input from 
the project management team, the project manager can respond, 
“Good, fast, or cheap. Pick two!” 
• Resource types, quantities, and experience/grade directly affect 
schedule and cost.
181
Scope Planning Processes Overview
• Plan Scope Management (discussed earlier in this course)
• Collect Requirements (Planning Process Group; PMBOK® Guide 5.2): 
determining, documenting, and managing stakeholder needs and 
requirements to meet project objectives.
• Define Scope (Planning Process Group; PMBOK® Guide 5.3): 
developing a project scope statement that provides a detailed 
description of the project work and product, and which also specifies 
the work and deliverables excluded from the project. 
• Create WBS (Planning Process Group; PMBOK® Guide 5.4): subdividing 
project deliverables and project work into smaller, more manageable 
components and finalizing the scope baseline
182
Collect Requirements (PMBOK® Guide 5.2)
• Requirements: measurable, testable, and complete conditions or 
capabilities of a product, service, or result that address the needs 
and expectations of stakeholders
• Examples:
• The project will generate a minimum return on investment of 10%.
• The system will achieve a throughput of at least 50 items per hour.
• The system’s planned downtime for maintenance will not exceed 20 minutes per day.
• Requirements drive the solution (deliverables and work), which 
drives the project’s schedule, cost, quality, risk, and other factors.

183
Collect Requirements: Key Outputs
Business Requirements Traceability 
revenue, cost 
Matrix
savings
Description
Quality
Stakeholder
testing, certification Rationale

Requirements  Project objective
Documentation
Project Solution Deliverables
milestone dates,  functional requirements 
contractual  (product behavior)               Design & 
obligations and non‐functional  development
(reliability, security)
Transition and 
readiness Test plan
training

184
Collect Requirements: Key Inputs

Project  Project 
Project 
charter mgt. plan
documents
Business 
docs

Agreements

Requirements documentation 
Requirements Traceability Matrix

185
Collect Requirement: Key Tools and 
Techniques
Expert judgment
Data gathering
Data analysis
Project charter
Decision making Requirements 
Project mgt. plan documentation
(Unanimity, Majority etc.)
Project documents
Data representation Requirements 
Business documents
Agreements
Interpersonal and team skills Traceability Matrix
(Nominal Group Technique)
Context diagrams
Prototypes
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) ‐ Sixth 
Edition, Project Management Institute, Inc., 2017, page 138. 186
Decision Making Techniques

• Unanimity:  all parties support the requirement 
• Majority: over 50% support the requirement
• Plurality:  largest block of votes even if less than 50%; used 
when more than two options available
• Autocratic:  one party with authority decides

187
Nominal Group Technique
• Structured form of brainstorming:
• Anonymous generation of ideas
• A moderator‐led discussion of these ideas
• Voting on these ideas 

188
Define Scope Process
(PMBOK® Guide 5.3)
• Producing a project scope statement that further defines the work and 
deliverables of the project described in the approved project charter
• Ensuring the design will meet the requirements defined in the requirements 
documentation and requirements traceability matrix
• Determining exclusions: work or deliverables not included in the project to 
help manage stakeholder expectations and reduce the likelihood of scope 
creep (unmanaged scope changes)
• For predictive plan‐driven projects, scope defined and refined many times 
during planning, but generally locked down at the conclusion of planning
• For agile projects, prioritized deliverables (features; characteristics) 
determined and potentially revised at the beginning of each sprint (iteration)

189
Define Scope: Key Concepts

Product scope  Requirements 
description documentation

Project 
Project  Stakeholder  Document  Traceability 
Scope  Deliverables
exclusions register updates matrix
Statement

Acceptance  Assumptions 
criteria log

190
Define Scope: Key Inputs, Tools and 
Techniques, Outputs
Expert judgment
Project charter Data analysis Project scope 
statement
Project mgt. plan Decision making
Project document 
Project documents Interpersonal and team skills updates
Product analysis*

**Examples of product analysis beyond the scope of this course include: product 
breakdown, requirements analysis, systems analysis, systems engineering, value 
analysis, value engineering, and instructional systems design.

Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) ‐ Sixth Edition, 
Project Management Institute, Inc., 2017, page 150. 191
Create WBS Process
(PMBOK® Guide 5.4)
• Work Breakdown Structure (WBS)
• Decomposing the deliverables and work in the project scope statement 
into smaller, manageable work packages
• Provides the foundation for all other project aspects like schedule, 
cost, quality, and resources 
• The WBS becomes part of the scope baseline: a key component of the 
project management plan, and a key input for every process in the 
Planning, Executing, Monitoring and Controlling, and Closing Process 
Groups.
• Each work package represents a group of activities that will be further 
decomposed in the Project Schedule Management Process called 
Define Activities.

192
Work Packages, Activities and Control 
Accounts
• *The lowest level of WBS lists the work packages, not the 
activities themselves. The team decomposes work packages into 
activities later in planning in the process called “Define 
Activities”.
• Work packages should be detailed “enough” to enable the team 
to generate a list of activities later in planning. 
• When creating a WBS, the team must consider at what level of 
detail that key stakeholders, such as the sponsor, finance, or 
accounting, will require scope, schedule, and cost reporting.
• Control accounts in the WBS represent the elements where the team 
will report performance. Generally, one control account represents two 
or more work packages. 

193
WBS Example – Organized by Phase
Project Name (0)

Phase (1) Phase (2)

Deliverable 4 
Deliverable  (1.1) Deliverable  (1.2) Deliverable (2.1)
(2.2)

Design Work  Work package  Work package  Work package 


Package(1.1.1) (1.2.1) (2.1.1) (2.2.1)

Prototype Specs 
Work package  Work package  Work package 
Work 
(1.2.2) (2.1.2) (2.2.2)
Package(1.1.2)
Note: the numbers in parentheses represent the WBS number
194
WBS Example – Organized by Deliverable
Project Name 
(0)

Deliverable  Deliverable 
(1) (2)

Component   Component 2  
Feature (2.1) Feature (2.2)
(1.1) (1.2)

Work package  Work package  Work package  Work package 


(1.1.1) (1.2.1) (2.1.1) (2.2.1)

Work package  Work package  Work package  Work package 


(1.1.2) (1.2.2) (2.1.2) (2.2.2)
Note: the number in parentheses represent the WBS number
195
Create WBS: Key Output
Describing a wide 
variety of very 
detailed information  Project scope 
for each element of  statement
the WBS, such as 
deliverable or work 
descriptions, along 
with schedule, cost, 
quality, resource, and 
agreements. Scope baseline

WBS dictionary WBS

196
Create WBS: Key Inputs, Tools and 
Techniques, Outputs

Project mgt. plan Scope baseline
Decomposition Project document 
Project documents updates

Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) ‐ Sixth 
Edition, Project Management Institute, Inc., 2017, page 156.

197
Schedule Planning Processes Overview
• Plan Schedule Management (Planning Process Group; PMBOK® Guide 6.1; discussed earlier in 
this course)
• Define Activities (Planning Process Group; PMBOK® Guide 6.2): determining, and 
documenting specific activities needed to be performed to meet project objectives and 
produce deliverables.
• Sequence Activities (Planning Process Group; PMBOK® Guide 6.3): determining, and 
documenting the order in which activities will be performed and the relationship between 
them. 
• Estimate Activity Durations (Planning Process Group; PMBOK® Guide 6.4): estimating the 
amount of time needed to complete each activity with the estimated available resources.
• Develop Schedule (Planning Process Group; PMBOK® Guide 6.5): analyzing schedule 
parameters like the sequence of activities, their durations and resource requirements, and 
associated constraints in order to derive an optimum schedule to carry out project work.

198
Define Activities Process(PMBOK® Guide 6.2)
• Identifying and listing the actions to produce the project 
deliverables to meet the project objectives
• Identifying milestones (significant events with 0 duration)
• Activities represent the work effort required to complete 
the work package, and they provide a basis for scheduling, 
cost estimating, monitoring and controlling.

199
Define Activities: Key Outputs Activity attributes 
describe detailed 
parameters of each 
activity, such as 
duration, cost, 
resources, required 
skill sets, schedule 
Project  Activity list time and date(s), 
management plan  Activity attributes tracking IDs, and 
updates other information. It 
requires information 
typically not available 
at the beginning of a 
project, thus the 
Define Activities team progressively 
elaborates these 
details as the project 
progresses.
Change requests Milestone list

200
Define Activities: Key Inputs, Tools, and 
Techniques

Expert judgment
Project  Activity list
Decomposition
management  Activity attributes
plan Rolling wave planning
Milestone list
Meetings

Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) ‐
Sixth Edition, Project Management Institute, Inc., 2017, page 183.

201
Sequence Activities Process
(PMBOK® Guide 6.3)
• Activities are ordered to be performed in sequence or parallel.
• Every activity, except the starting and finishing activities, has at 
least one activity performed before it (predecessor) and after it 
(successor). 
• The schedule network diagram visually displays the resulting 
sequence. 
• Coupled with activity durations, activity resources, and other 
factors, the network diagram leads to the creation of the 
project schedule (during the process Develop Schedule, 
discussed in detail later in the course).
202
Sequence Activities: Key Inputs, Tools, and 
Techniques

Precedence diagramming 
method (PDM)
Dependency determination  Project schedule 
Project mgt. plan network diagrams
and integration
Project documents Project documents 
Leads and lags updates
Project mgt. information 
system

Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) ‐ Sixth 
Edition, Project Management Institute, Inc., 2017, page 187.

203
Sequence Activities: Key Outputs
Project Schedule Network Diagram

FS+10
B D

Start A F Finish

C E

204
Path Divergence and Convergence

Divergence Convergence
FS+10
B D

Start A F Finish

C E

Project Schedule Network Diagram

205
PDM Relationship Types, Lags and Leads

https://blogs.msdn.microsoft.com/project/2008/07/28/back‐to‐basics‐understanding‐task‐dependencies/
206
Resource Planning Processes Overview
• Plan Resource Management (Planning Process Group; 
PMBOK® Guide 9.1; discussed earlier in this course)
• Estimate Activity Resources (Planning Process Group; 
PMBOK® Guide 9.2): determining and documenting types 
and quantities of specific resources needed – both human 
and physical – to perform project work and meet project 
objectives

207
Estimate Activity Resources Process
(PMBOK® Guide 9.2)
• Determining the types, quantities, and attributes of human 
and physical resources required to perform the project. 
• Working in close conjunction with the Project Schedule 
Management and the Project Cost Management processes
• Estimate Activity Resources is heavily integrated with the 
previous process, Plan Resource Management process. 
Particularly, elements such as activity resource 
requirements, RACI charts, and project organizational 
charts.

208
Estimate Activity Resources: Key Outputs
Basis of Estimates: 
describes how the resource 
Resource  requirements were 
requirements derived. This document 
may include the method
used to develop the 
estimate, the range for the 
Project  Basis of  estimate if required, an 
Estimate Activity 
documents  estimates indication of the level of 
Resources
updates confidence in the 
estimates, and additional 
factors that were 
Resource  considered while 
breakdown  estimating including the 
structure constraints, risks, and 
assumptions.

209
Estimate Activity Resources: Key Inputs, Tools, 
and Techniques
Expert judgment
Analogous estimating Resource 
Parametric estimating requirements
Project management  Basis of estimates
plan Bottom‐up estimating
Resource breakdown 
Project documents Data analysis structure
Project management  Project documents 
information system updates

Meetings
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) ‐ Sixth Edition, 
Project Management Institute, Inc., 2017, page 321.

210
Estimating
• Analogous estimating:
• With limited information, the project team may use the quick and 
inexpensive approach of using resource estimates from similar past projects. 
• Parametric estimating:
• Making use of formulas and algorithms to compute the estimate. For 
example, a requirement to produce 6,000 parts per hour would require two 
machines that each produces 3,000 parts per hour. Like all estimates, the 
accuracy of a parametric estimate depends on the quality of the data and the 
robustness of the estimating model used.
• Bottom‐up estimating
• Used when the work is too large to be estimated with a reasonable degree 
of confidence. In such cases, the team divides the work into smaller 
components (e.g., activities) that could be estimated for resources with a fair 
degree of confidence. These estimates are then aggregated to the work 
package level, control account level, and the project level.

211
Estimate Activity Durations Process
(PMBOK® Guide 6.4)
• Activity durations are estimated by people who specialize / are 
knowledgeable in the activity to be estimated.
• Depends on the availability of resources and skills and other 
factors, including:
Number of resources Motivation of staff
Increasing resources may or may not reduce the time to  Parkinson’s Law: work expands to fill time available for 
complete the activity; must also consider learning curve,  its completion. Additionally, procrastination must be 
knowledge transfers, and increase in administration and  considered by estimating durations. 
risk.
Law of diminishing returns Advances in technology
As activity resources are increased, a point will arrive  Use of latest technology, which may be more efficient and 
when adding additional resources results in diminishing  have a higher throughput, could potentially impact 
increases in productivity.  resource needs and subsequently the duration. 

212
Estimate Activity Durations: Key Outputs

Duration 
estimates

Estimate Activity 
Durations

Basis of 
estimates

213
Estimate Activity Durations: Key Inputs

Schedule  Lessons  Activity  Risk register Resource 


Scope  management  learned  list
baseline plan register Resource  calendars
Project team  Milestone  breakdown
Resource  structure
assignments list requirements
Assumption 
log Activity 
attributes

Duration estimates
Basis of estimates
214
Estimate Activity Durations: Key Tools and 
Techniques
Expert judgment
Analogous estimating
Parametric estimating
Duration 
Project mgt. plan Three‐point estimating estimates
Project documents Bottom‐up estimating Basis of 
estimates
Data analysis
Decision making
Meetings
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) ‐
Sixth Edition, Project Management Institute, Inc., 2017, page 195.
215
Three‐Point Estimating
• Three Point Estimate (tE) Involves the range of three estimates (best, 
worst and most likely scenarios) to accomplish an activity, phase or the 
entire project. Three‐point estimating incorporates varying degrees of 
uncertainty to arrive at a single, final estimate. 
• Most likely (tM) estimate is based on the scenario that makes realistic 
assumptions of resource availability, productivity, dependencies on 
influencing factors and constraints.
• Optimistic (tO) estimate is based on assumptions of a best‐case scenario
• Pessimistic (tP) estimate is based on assumptions of a worst‐case scenario
• Triangular distribution formula is used to compute the expected 
duration:
(tE) is tE = (tO + tM + tP) / 3 (6 + 8 + 13) / 3 = 9
216
Develop Schedule Process
(PMBOK® Guide 6.5)
• Incorporating outputs of many other processes to create the 
project schedule and the finalized schedule baseline
• The project schedule: 
• Can change daily during the Executing Process Group as reality unfolds
• Used to manage the actual work
• The schedule baseline
• Key component of the project management plan 
• Cannot change without an approved change request 
• Compared against the actual project schedule during the Monitoring 
and Controlling Process Group to determine schedule variances

217
Develop Schedule: Key Outputs 

Schedule baseline
Project 
documents  Project schedule
updates

Develop Schedule Schedule data
Project 
management plan  • alternative 
schedules, schedule 
updates reserves

Change requests Project calendars

218
Develop Schedule: Key Inputs

Schedule  Lessons  Activity 


learned  Risk register
Scope  management plan list Resource 
baseline register Project schedule  calendars
Milestone list Activity  network diagrams
attributes Resource 
Project team 
assignments Duration  requirements
Assumption  estimates Basis of 
log estimates
Agreements

Schedule baseline
Project schedule
Schedule data
Project calendars
219
Develop Schedule: Key Tools and Techniques 

Schedule network analysis
Critical path method Schedule 
Project mgt. plan Leads and lags baseline
Project  Resource optimization Project schedule
documents Data analysis Schedule data
Agreements Schedule compression Project calendars
Project management  Change requests
information system

Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) ‐
Sixth Edition, Project Management Institute, Inc., 2017, page 205.

220
Determine Critical Path

Activity A (on critical path)
5 Days

Activity B (on critical path)
Start Finish
5 Days

Activity C (not on critical path)
7 Days 3 days of total slack

221
Exercise: Create a Network Diagram to 
Determine Critical Path
Activity/Milestone Duration Predecessors
Start 0 N/A
A 5 Start
B 5 A
C 10 A
D 15 B,C
Finish 0 D

222
Answer: Create a Network Diagram to 
Determine Critical Path

223
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) ‐

Critical Path Analysis Sixth Edition, Project Management Institute, Inc., 2017, page 210. (6.5.2.2)

Analyze a Network 
Diagram 
1. How many paths run through 
the network diagram? 
Calculate the durations for all 
paths (assuming duration in 
days).
2. What is the critical path?
3. How long is the critical path? 
4. If any activities are not on the 
critical path, how many days 
could they be delayed before 
they would become critical as 
well?

• Time to complete this 
exercise: 5 minutes

224
Exercise Answers: Create a Network Diagram 
to Determine Critical Path
1. How many paths run through the network diagram? Two: 
ABD (25 days) and ACD (30 days)
2. What is the critical path? ACD
3. How long is the critical path? 30 days
4. If any activities are not on the critical path, how many days 
could they be delayed before they would become critical as 
well? B is not on the critical path. It could be delayed by 
five days (or take five days longer than expected) before it 
would become critical.

225
Additional Critical Path Exercises
• Note: there are additional critical path exercises, included 
in the appendices of this manual. 
• They are likely harder than the ones you will see on the 
exam, as they entail more activities. However, answering 
these questions correctly will give you confidence if (or 
when) you see these types of questions on the exam.

226
Resource Optimization
• Adjust the project schedule to reflect real‐world resource 
limitations. Optimizing resources for these limitations can 
involve two similar methods:
• Resource leveling 
• "A technique in which start and finish dates are adjusted based 
on resource constraints with the goal of balancing demand for 
resources with the available supply.“ (PMBOK Definition)
• Resource smoothing 
• Provides the same leveling goal described above, though it 
prohibits delaying the schedule end date. Thus, it only levels over‐
allocated and under‐allocated resources on non‐critical activities. 

227
Schedule Compression
• Techniques that reduce the duration of activities on the critical 
path while not changing the desired scope or quality of those 
activities. Specific schedule compression techniques include:
• Crashing
• increasing the quality or quantity of activity resources (e.g., hiring or 
assigning more human or physical resources, selecting more experienced 
resources or faster machines). Crashing generally increases the cost and 
the risk of the project: higher quality resources generally cost more 
money, and managing more resources involves higher risk.
• Fast tracking 
• performing multiple critical activities simultaneously as opposed to 
sequentially. Though fast tracking generally shortens the schedule, it 
increases risk and rework.

228
Cost Planning Processes Overview
• Plan Cost Management (Planning Process Group; PMBOK® Guide
7.1; discussed earlier in this course)

• Estimate Costs (Planning Process Group; PMBOK® Guide 7.2): 
estimating the financial resources required to complete project 
work with the available resources.

• Determine Budget (Planning Process Group; PMBOK® Guide 7.3): 
consolidating the estimated costs to perform project work and 
creating an understanding of how funds will be expended over 
the course of the project.
229
Estimate Costs Process
(PMBOK® Guide 7.2)
• Estimates the monetary resources required to accomplish 
each activity and project work in general.
• Includes cost considerations such as the potential costs of 
outsourcing resources, financing, inflation, and currency 
fluctuations
• Cost estimates are generally provided with ranges or 
margins of error
• Rough Order of Magnitude (ROM) range (‐25% to +75%)
• Definitive range (‐5% to +10%)

230
Estimate Costs: Key Outputs

Cost 
estimates

Estimate 
Costs
Project 
Basis of 
documents 
estimates
updates

231
Direct vs. Indirect Costs
• Direct Cost:
• Labor
• Materials, equipment, services, and facilities
• Information technology
• Cost of financing (including interest charges)
• Inflation allowances, exchange rates
• Contingency reserves

• Indirect Cost:
• Administration
• Marketing
• Many overhead costs
232
Estimate Costs: Key Inputs

Quality  Cost 
Scope  management  management  Risk 
baseline plan plan register
Lessons 
learned  Resources 
register requirements
Project 
schedule

Cost estimates
Basis of estimates

233
Estimate Costs: Key Tools and Techniques 

Expert judgment
Analogous estimating
Parametric estimating
Cost estimates
Project management plan Bottom‐up estimating
Basis of estimates
Project documents Three‐point estimating
Project documents 
Data analysis updates
Project management 
information system
Decision making
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) ‐ Sixth Edition, 
Project Management Institute, Inc., 2017, page 204.

234
Determine Budget Process (PMBOK® Guide 7.3)
• The project budget, in addition to being an aggregation of cost 
estimates, also establishes the points in time when these costs 
would come to bear (funding requirements).
• Funding requirements:
• When the project will require funds to pay for project expenditures, 
typically either at designated dates (or perhaps milestones). 
• When the project will disburse funds, like human resources paying 
employees  and outside organizations receiving payment for physical 
resources upon transfer.
• Not having adequate funds to pay for resources can lead to significant 
problems such as low morale and delays.
• It establishes the quantum of expenditure expected to be incurred 
in carrying out project work and producing deliverables. 

235
Determine Budget: Project Budget 
Components

Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) ‐ Sixth Edition, 
Project Management Institute, Inc., 2017, page 255.
236
Determine Budget: Key Outputs

Cost  Remember: Cost baselines 
baseline include contingency reserves, 
NOT management reserves!

Determine 
Budget

Project  Project 
documents  funding 
updates requirements

237
Determine Budget: Key Inputs, Tools and 
Techniques, Outputs

Expert judgment
Cost aggregation
Project management 
Data analysis Cost baseline
plan
Historical information review Project funding 
Project documents requirements
Funding limit reconciliation
Business documents (Work may have to be rescheduled in order to align 
Project documents 
expenses with funding limits)  updates
Agreements
Financing
(May include debt, equity, internal/external sources)

Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) ‐ Sixth Edition, 
Project Management Institute, Inc., 2017, page 248.
238
Lesson 5: Planning Processes, Section B Review – Scope, 
Schedule, Resource, and Cost Processes
• PMP®/CAPM® Test‐Worthy Topics: Lesson  • Sequence Activities (6.3)
5, Section B: Scope, Schedule, Resource,  • Estimate Activity Resources (9.2)
and Cost Processes
• Scope, Schedule, Resource, and Cost  • Estimate Activity Durations (6.4)
Processes Overview • Develop Schedule (6.5)
• Scope Planning Processes Overview • Cost Planning Processes Overview
• Collect Requirements (5.2) • Estimate Costs (7.2)
• Define Scope (5.3) • Determine Budget (7.3)
• Create WBS (5.4) • PMP®/CAPM® Practice Questions
• Schedule Planning Processes Overview • What are your questions?
• Resource Planning Processes Overview
• Define Activities (6.2)

239
PMP®/CAPM® Practice Questions: Planning 
Processes, Section B
• Open the file PMP and CAPM Practice Questions. 
• Using the Table of Contents, navigate (using CTRL+Click) to 
the entry Lesson 5: Planning Processes Section B: Scope, 
Schedule, Resource, and Cost Questions.
• Answer the odd‐numbered questions and check your 
answers. The answers follow the questions.
• Time to complete this exercise: 10 minutes

240
Lesson 5: Planning Processes, 
Section C – Risk Processes
Learning Objective: Based on the planning processes described in the 
PMBOK® Guide Sixth Edition, Planning processes.

241
241
Lesson 5: Planning Processes, Section C Topics – Risk 
Processes
• PMP®/CAPM® Test‐Worthy Topics: Lesson 5: Planning 
Processes Section C: Risk Processes
• Risk Planning Processes Overview
• Identify Risks (11.2)
• Perform Qualitative Risk Analysis (11.3)
• Perform Quantitative Risk Analysis (11.4)
• Plan Risk Responses (11.5)
• PMP®/CAPM® Practice Questions

242
Risk Planning Processes Overview
• Plan Risk Management (Planning Process Group; PMBOK® Guide 11.1; 
discussed earlier) 
• Identify Risks (Planning Process Group; PMBOK® Guide 11.2): 
determining, and documenting risks to project objectives.
• Perform Qualitative Risk Analysis (Planning Process Group; PMBOK® 
Guide 11.3): assessing the probability and impact of identified risks and 
then prioritizing them.
• Perform Quantitative Risk Analysis (Planning Process Group; PMBOK® 
Guide 11.4): assessing the impact of all risks on overall project 
objectives.
• Plan Risk Responses (Planning Process Group; PMBOK® Guide 11.5): 
determining action plans to deal with risks.

243
Identify Risks Process (PMBOK® Guide 11.2)
• The team and all relevant stakeholders identify the 
uncertainties (risks) that can threaten or benefit the project 
constraints and objectives.
• Risks may impact the project scope, schedule, budget, 
quality, resources, and procurements, among other factors.
• Identifying these uncertainties, and subsequently analyzing 
and responding to those uncertainties, leads to a much 
more predictable project with a greater likelihood of 
success.

244
Identify Risks: Key Outputs

Risk  Risk Report depicts 
register summary information about 
the overall project 
exposure.

At the conclusion of the 
Identify  project, the risk report 
Risks provides a coherent 
document that helps 
Project  stakeholders understand 
documents  Risk report how effectively risks were 
updates managed on the project, 
which can guide future 
actions.
245
Risk Register
• Project risks identified by the project team and relevant stakeholders. 
• Description of each identified risk
• Each risk’s causes or triggers (events or conditions that indicate that a 
risk is about to occur)
• Risk category/categories (e.g., technical risk, resource risk, business risk, 
scope risk, schedule risk, safety risk)
• Risk’s current status
• Effects it may have on project objectives and specific WBS elements. 
• Potential risk owners
• Risk timing information (e.g., when the risk might occur, when a 
response must be implemented if the risk occurs). 

246
Identify Risks: Key Inputs, Tools, and 
Techniques

Project  Expert judgment
management plan
Data gathering
Risk register
Project 
Data analysis Risk report
documents
Interpersonal and team skills Project documents 
Agreements updates
Prompt lists
Procurement 
documentation Meetings

Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) ‐
Sixth Edition, Project Management Institute, Inc., 2017, page 409.

247
Prompt Lists
• Prompt lists that provide the team with lists or frameworks of 
pre‐determined categories of risks or impact areas that could 
be used to identify specific project risks. Common frameworks 
to determine overall project risks include:
• PESTLE (Political‐Economic‐Social‐Technological‐Legal‐Environmental)
• VUCA (Volatility‐Uncertainty‐Complexity‐Ambiguity)
• TECOP (Technical‐Environmental‐Commercial‐Operational‐Political)

248
Perform Qualitative Risk Analysis Process
(PMBOK® Guide 11.3)
• The project team and relevant stakeholders assess all risks in 
the risk register to determine their probabilities of 
occurrence and their impact on project objectives.
• Determining the probabilities and impacts of risks requires 
soliciting people’s opinions, which can introduce biases. 
Hence, it’s a subjective (qualitative) method. 
• The probabilities and impact values may be combined with 
other assessment factors, to derive a cumulative risk score.

249
Perform Qualitative Risk Analysis: Key Output

Risk Register

A log used to document and track 
issues
Project 
Issues log document  Risk Report
updates

Assumptions  A document used to record all 
log assumptions and constraints throughout  
the project life cycle

250
Perform Qualitative Risk Analysis: Key Inputs, 
Tools, and Techniques

Expert judgment
Data gathering
Project management  Data analysis
plan Project documents 
Interpersonal and team skills updates
Project documents
Risk categorization
Data representation
Meetings
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) ‐ Sixth 
Edition, Project Management Institute, Inc., 2017, page 419.

251
Probability and Impact Matrix; Probability and 
Impact Chart
Probability and Impact Matrix Probability and Impact Chart
Risk Probability Impact Rating
(1‐5) (1‐5) (P X I) High

Risk 1
Risk 2
Probability

Low
**The result of Qualitative Risk Analysis  Low Impact High
end up in the Risk Register that lists all 
risks. 252
Updated Risk Register
Risk Prob. Impact  Risk Rating Risk Response Risk Owner
1 (low)‐5 (high) 1 (low)‐5 (high) (P X I) Strategy
Sponsor leaving  3 4 12 Include likely  Project Manager
company new sponsor in 
communications

Not enough  2 3 6 Dedicated  Project Manager


people resource, hire 
contractors

253
Perform Quantitative Risk Analysis Process
(PMBOK® Guide 11.4)
• A quantitative analysis of risks numerically assesses risks to 
determine their cumulative impact on project objectives. A 
quantitative analysis of risks provides a more definitive way to 
determine the actual impact of project risks.
• Involves the assessment of overall project risks on the project. 
• Generally makes use of a computer simulation analyses to 
determine the effect of risks on project outcomes.
• May not be required to be performed on projects that are small 
or easier to execute or of lower significance.
254
Perform Quantitative Risk Analysis: Key 
Outputs

Perform 
Project documents 
Quantitative Risk 
updates
Analysis

255
Perform Quantitative Risk Analysis: Key 
Inputs, Tools, and Techniques
Expert judgment
Data gathering
Project  Interpersonal and team skills
management plan Representations of uncertainty Project documents 
Project  updates
(Probability Distributions, 
documents Statistical Correlation)
Data analysis
(Monte Carlo)

Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) ‐
Sixth Edition, Project Management Institute, Inc., 2017, page 428.
256
Tornado Diagrams
• Rank risk variables that affect schedule, cost, or quality, helping 
the project manager focus on the variables that potentially 
impact the project.
• Frequently use optimistic, most likely, and pessimistic scenarios.
• Use variables in isolation; keep all other factors at their most 
likely value and then create bars based on best case and worst 
case.
• Provide the foundation for further research to verify 
assumptions and to investigate risk response strategies.
257
Tornado Diagram: Effect of Risks on Schedule in Days
70 75 80 85 90 95 100 105 110 115

Labor availability

Weather

Optimistic
Labor experience Pessimistic

Working hours/day

Job site conditions

https://www.youtube.com/watch?v=grPcreRG‐lY
258
Influence Diagrams
• Provide a graphic of a system with causal influences, time 
ordering of events, and relationships between variables.
• Can provide a depiction of project risks and potential risk 
response strategies.
• With quantitative information, can provide the foundation 
for decision trees.

259
Example: Influence Diagram

Vendor Shipping
Distance + Travel time ‐ Expediting Fees

+
Probability of
Arrival at
on‐time
Job Site
delivery
+
Vendor  Manufacturing Manufacturing
Capacity
‐ time ‐ Expediting Fees

260
Expected Monetary Value (EMV) Analysis
• Calculates the average outcome for future events that may 
or may not happen.
• The probability of an event times the “quantified output.”  
For example, assume a project has a threat with a 10% 
chance of causing a $1,000 loss.
• $1,000*0.1=$100
• The expected monetary value of this risk is $100. This $100 
could be set aside as contingency reserves, along with 
reserves of all other threats.

261
Exercise: Expected Monetary Value
• Calculate the Expected Monetary Value for the activities on this 
project. What is the total EMV of this project?
• 20% of past projects have suffered from poorly‐defined requirements, which 
adds an average, additional cost of $2,000 per project.
• 25% of past projects have been able to secure highly‐skilled resources, 
which reduces the cost of the average project by $500.
• 40% of past projects have suffered from fluctuating customs fees, which add 
an average, additional cost of $800 per project.

262
Exercise Answers: Expected Monetary Value
Risk Probability Impact Expected 
Monetary Value
Poorly‐defined  20% $2,000 $400
requirements 
Highly‐skilled  25% ($500) ($125)
resources
Fluctuating  40% $800  $320
customs fees
Total Expected Monetary Value  $595
(Contingency Reserves*)

263
Exercise: Decision Trees Using Expected Monetary Value
• Calculate the Expected Monetary Value for each of these 
projects.
• Project A
• 80% chance of EARNING $100,000 GAIN = ??
• 20% chance of LOSING $50,000 LOSS = ??
• EMV = ??
• Project B
• 50% chance of EARNING $160,000 GAIN = ??
• 50% chance of LOSING $40,000 LOSS = ??
• EMV =??
• If the organization could only fund one of these projects, which 
would it fund?
264
Exercise Answers: Decision Trees Using Expected Monetary Value
• Project A
• 80% chance of EARNING $100,000 GAIN = $80,000
• 20% chance of LOSING $50,000 LOSS =  ($10,000)
• EMV = $70,000

• Project B
• 50% chance of EARNING $160,000 GAIN = $80,000
• 50% chance of LOSING $40,000 LOSS =  ($20,000)
• EMV = $60,000

Project A is more desirable, as it has a higher EMV
265
Monte Carlo
• Can simulate project schedule, cost, or other constraints
• Often uses optimistic, most likely, and pessimistic estimates 
for task as inputs 
• Simulates the project by randomly choosing different 
numbers for many iterations
• Creates a probability distribution of expected schedule, 
cost, etc.

266
Plan Risk Responses (PMBOK® Guide 11.5)
• High priority risks would have responses planned for them.
• Responses may not be planned for those risks that may not 
significantly impact the project or aren’t likely to materialize. 
These risks are monitored.
• Major risks would be addressed depending on the nature of 
the risk – opportunity or threat.
• Project cost, time, and resources would be planned for use, 
to implement responses

267
Risk:  Risk Response Strategies

• The following strategies are those recommended 
by PMI to use in planning risk responses.  We 
recommend that you memorize each response 
type and be able to recognize it in a situation.  
• Mnemonic:
• SEE (share, exploit, enhance) Opportunities
• ATM (avoid, transfer, mitigate) Threats

268
Risk:  Risk Response Strategies (Cont.)
Risk Response Strategies for Positive Risks or Opportunities

Risk Response Tool Description Example

The share strategy splits the  The technology company formed a 
responsibility (and benefit) of the risk  partnership with a marketing company to 
Share
with a third party (or parties) to  launch a sales campaign to support the 
maximize an opportunity.   new product being developed.  

The exploit strategy takes steps to  The new project had the best resources 
Exploit ensure the success and the risk of the  assigned to maximize the probability of 
event or project.   success.  
The enhance strategy takes steps to  When sales were exceeding projections, 
improve the size or capacity of the risk  the company hired more sales people to 
Enhance event by determining the key  ensure that as many customers as 
components of the risk and maximizing  possible knew of their products.
those components.   269
Risk:  Risk Response Strategies (Cont.)
Risk Response Strategies for Negative Risks or Threats

Risk Response Tool Description Example


Avoid involves modifying the plan so  Selecting alternative potential vendors will keep 
Avoid risk doesn’t have to be dealt with.  To  you from running out of inventory.  
get rid of the problem.
Transfer reassigns risk exposure to  Example #1:  Hiring an outside company to do 
another party. In doing this, you do  something instead of doing it yourself  (contract 
Transfer not necessarily eliminate all risk, but  out risk) 
likely minimize some and create  Example #2: Buying insurance for something 
additional risk as well. (contractually underwrite cost of risk)

Mitigate is to proactively change the  Eliminating outside sources and doing work 


Mitigate plan to minimize the impact or  internally mitigates your risk if another company 
probability of the risk occurring. failed to meet the deliverables on your project.
270
Risk:  Risk Response Strategies (Cont.)
Risk Response Strategies for both Positive and Negative Risks
Risk Response Tool Description Example
Acceptance tolerates the risk and deals with  Determining that, if a union goes on 
Accept it.  It is a valid option if there are no other  strike, the project will have to stop until 
options available.  the strike is settled.  

When the project team and/or project  While working on a new residential 
manager agree that the risk is outside the  construction project, the project manager 
scope of the project, or that the response  catches wind of a neighboring parcel of 
Escalate exceeds the project manager’s authority.   land, zoned for commercial use only, is 
Often escalated to program level or portfolio  recently listed for sale.  This may be an 
level, or other parts of the organization. opportunity, but is outside the scope of 
the current project.

271
Plan Risk Responses: Key Outputs

Change 
requests

Plan Risk 
Responses

Project  Project 
documents  management 
updates plan updates

272
Plan Risk Responses: Key Inputs
Risk report Cost  Resource 
Risk  Resource  baseline management plan
register
calendars
Stakeholder 
register Lessons learned  Risk management 
register plan
Project 
schedule Project team 
assignments

Change requests

273
Plan Risk Responses: Key Tools and Techniques
Expert judgment
Data gathering
Interpersonal and team skills
Strategies for threats
(ATM) Change requests
Project management  Strategies for opportunities Project management 
plan plan updates
(SEE)
Project documents Project documents 
Contingent response strategies
updates
(when risk responses fail to have the 
anticipated effect)
Strategies for overall project risk
Data analysis
Decision making
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) ‐
274 Sixth 
Edition, Project Management Institute, Inc., 2017, page 437.
Lesson 5: Planning Processes, Section C Review – Risk 
Processes
• PMP®/CAPM® Test‐Worthy Topics: Lesson 5: Planning Processes 
Section C: Risk Processes
• Risk Planning Processes Overview
• Identify Risks (11.2)
• Perform Qualitative Risk Analysis (11.3)
• Perform Quantitative Risk Analysis (11.4)
• Plan Risk Responses (11.5)
• PMP®/CAPM® Practice Questions
• What are your questions?

275
Test‐Worthy Agile Project Management Topics
• Again, this slide may not be accurate.  Instead, refer to the PMI Handbook and the PMBOK:
• https://www.pmi.org/certifications/types/certified‐associate‐capm/exam‐prep

• For simplicity, all agile concepts related to the Planning Process Group have been collected here.
• When preparing for the exam, be familiar with the following agile project management terms and 
concepts.
• Product backlog, release backlog, iteration backlog
• Product roadmap
• Aspects/Elements of release planning and iteration planning
• Stories and epics
• Verification and validation criteria
• Story points, ideal days, affinity estimating
• Velocity/capacity
• For more information on these agile topics and the location of agile practice questions, see below.

276
PMP®/CAPM® Practice Questions: Planning 
Processes, Section C
• Open the file PMP and CAPM Practice Questions. 
• Using the Table of Contents, navigate (using CTRL+Click) to 
the entry Lesson 5: Planning Processes Section C: Risk 
Questions. 
• Answer the odd questions and check your answers. The 
answers follow the questions.
• Time to complete this exercise: 15 minutes

277
Lesson 6: Executing 
Processes
Learning Objective: Based on the PMBOK® Guide Sixth Edition 
Executing processes.

278
278
Lesson 6 Topics: Executing Processes
• PMP®/CAPM® Test‐Worthy Topics:  • Manage Communications (10.2)
Executing Processes • Implement Risk Responses (11.6)
• Executing Process Group Overview • Conduct Procurements (12.2)
• Direct and Manage Project Work  • Manage Stakeholder Engagement 
(4.3) (13.3)
• Manage Project Knowledge (4.4) • PMP®/CAPM® Practice Questions
• Manage Quality (8.2)
• Acquire Resources (9.3)
• Develop Team (9.4)
• Manage Team (9.4)
279
Executing Process Group Overview
• The Executing Process Group consists of the processes that carry out 
project work
• The execution of plans results in the creation of deliverables that create 
value for the organization, add new capabilities to the organizations 
existing capacity, which help the organization realize its strategic 
objectives enlisted in the project charter, and the business case in the 
project’s business documents
• Spending on a project is at its highest when executing project work
• Execution generally is the most complex part of a project, because of 
the numerous interactions between competing demands, project 
stakeholders, and changing dynamics – within the project, organization 
and beyond.

280
Direct and Manage Project Work Process
(PMBOK® Guide 4.3)
• Accomplishing all planned work on the project
• Implementing the project management plan and its 
subsidiary plans to guide execution of project work
• Performing activities and producing deliverables
• Identifying and documenting issues in a structured manner
• Generating work performance data

281
Direct and Manage Project Work: Key Outputs
Issue log typically 
contains an issue
Deliverables description, the issue
Organization  effects, the date when 
process asset  Work performance  the team identified the 
updates data issue, the targeted 
resolution date, and 
possible solutions. Each
Direct and Manage  issue typically has an 
Project Work owner, identified in the 
Project documents  Issue log
updates issue log, who has the 
responsibility of 
monitoring the issue, and 
Project  working to resolve or 
management plan  Change requests control it.
updates

282
Direct and Manage Project Work: Key Inputs, 
Tools, and Techniques

Deliverables
Expert judgment Work performance data
Project 
management plan Project  Issue log
management  Change requests
Project documents
information  Project management plan updates
Approved change  system Project documents updates
requests
Meetings Organizational process assets 
updates
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) ‐ Sixth 
Edition, Project Management Institute, Inc., 2017, page 90.

283
Manage Project Knowledge Process
(PMBOK® Guide 4.4)
• **New to PMBOK 6th Edition 
• Creating, collecting, distributing and integrating knowledge 
and information on the project
• Project performance relies on the availability and best use 
of knowledge and information
• Using knowledge management tools and techniques to 
motivate the project team and create ways and means to 
share their knowledge and learn from others’ knowledge.

284
Manage Project Knowledge: Key Outputs

Lessons learned 
register

Manage 
Project 
Knowledge
Organizational  Project 
process assets  management 
updates plan updates

285
Manage Project Knowledge: Key Inputs, Tools, 
and Techniques

Lessons learned 
Project  Expert judgment register
management plan Project 
Knowledge management management plan 
Project  updates
documents Information management
Organizational 
Deliverables Interpersonal and team skills process assets 
updates

Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) ‐ Sixth 
Edition, Project Management Institute, Inc., 2017, page 98.

286
Knowledge vs. Information
• Knowledge management:
• is the use of tools and techniques to create, gather, disseminate and 
integrate knowledge. (More of interactive communication style)
• Examples: networking with people and communities at trade shows, 
conferences, fairs, and workshops, along with work shadowing, and training
• Information management:
• is the use of tools and techniques to generate information and 
connecting people to it. (More of push or pull communications style)
• Examples: contributing or referring to the lessons learned register, adding data to  
project management information systems, reading and discovering information 
through online searches, and interacting with subject matter experts

287
126

Manage Quality Process
(PMBOK® Guide 8.2)
• Quality can be achieved by:
• ensuring that the product is of desired quality levels by building it 
correctly the first time
• iteratively improving quality through identification and resolution of 
defects.
• This process deals with being right, the first time
• Costs of activities performed in this process fall under the cost 
of conformance in the cost of quality framework
• The project team assures that stated quality objectives would be 
met by following due process, improving processes, and 
designing the result to meet the requirements in scope

288
Manage Quality: Key Outputs

Change requests
Test and 
Quality reports,  evaluation  Project 
containing information documents management plan 
measurements and  updates
readings taken of 
process and product  Manage Quality
quality, summarizing 
the level of quality 
achieved and, if 
Quality reports Project documents 
necessary, 
updates
recommending steps 
to be taken to elevate 
quality to desired 
levels.  289
Manage Quality: Key Inputs

Quality 
management plan Quality control
measurements
Risk report
Quality 
Lessons  metrics
learned 
register

Quality reports
Test and evaluation documents
Change requests
290
Manage Quality: Key Tools and Techniques

Data gathering
(Checklists) Quality reports
Data analysis Test and evaluation 
documents
Decision making
Project management  Change requests
plan Data representation
Audits Project 
Project documents management plan 
Design for X
updates
(focus developmental efforts on one req)
Project documents 
Problem solving updates
Quality improvement methods

Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) ‐ Sixth 
Edition, Project Management Institute, Inc., 2017, page 288.

291
Acquire Resources Process
(PMBOK® Guide 9.3)
• Confirming the availability and acquiring physical and 
human resources
• In matrix organizations, negotiating with a department 
head, or a functional manager to acquire resources
• Preassigning specialized resources when crafting the project 
charter or writing a proposal for a prospective client
• Acquiring resources internally or externally through 
vendors, contractors, and staffing agencies

292
Acquire Resources: Key Outputs
OPA update examples: Physical 
• Documentation  resource 
related to acquiring,  Organizational  assignments Project team 
assigning and  process assets  assignments
allocating resources updates

EEF update examples: Enterprise 
Acquire  Resource 
• Resource availability  environmental  calendars
Resources
in the organization factors updates
• Amount of 
organization’s 
Project  Change 
consumables used documents  requests
updates Project 
management 
plan updates

293
Acquire Resources: Key Inputs, Tools, and 
Techniques
Physical resource 
assignments
Project team assignments
Decision 
Resource calendars
making
Change requests
Project management  Interpersonal 
plan Project management plan 
and team skills updates
Project documents
Pre‐assignment Project documents updates
Virtual teams Enterprise environmental 
factors updates
Organizational process 
assets updates
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) ‐ Sixth 
Edition, Project Management Institute, Inc., 2017, page 328.

294
Develop Team Process
(PMBOK® Guide 9.4)
• Developing the team through 
• Open communication
• Trust building behaviors and exercises
• Working collaboratively
• Providing regular constructive feedback
• Rewarding high performance
• Assessing the team’s performance on factors such as 
individual skills, collective competencies, knowledge sharing, 
collaboration, and staff attrition
295
Develop Team: Key Outputs
Team 
performance 
assessments
Organizational 
process assets  Change 
updates requests

Develop Team

Enterprise  Project 
environmental  management 
factors updates plan updates
Project 
documents 
updates

296
Develop Team: Key Inputs

Resource  Project team 
Team 
management 
charter assignments
plan
Project 
schedule Resource 
calendars
Lessons 
learned 
register

Team performance assessments
Change requests

297
Develop Team: Key Tools and Techniques
Team performance 
Colocation assessments
Virtual teams Change requests
Project management 
Project  Communication technology plan updates
management  Interpersonal and team skills Project documents 
plan updates
Project  Recognition and rewards
Enterprise 
documents Training environmental 
factors updates
Individual and team assessments
Organizational 
Meetings process assets 
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) ‐ Sixth  updates
Edition, Project Management Institute, Inc., 2017, page 336.

298
Manage Team Process
(PMBOK® Guide 9.5)
• Tracking performance, providing feedback, resolving issues, and 
managing team changes to help the team become more self‐
directing and high‐performing
• Optimizing project performance while engendering project team 
growth and morale
• Coaching the team so they can eventually manage themselves
• Reviewing the team performance assessment and work 
performance reports, followed by using a variety of 
interpersonal skills, team skills, leadership skills, to help the team 
improve their communications, conflict resolution skills, and 
overall performance

299
Manage Team: Key Outputs

Change requests

Enterprise  Project 
environmental  Manage Team management 
factors updates plan updates

Project 
documents 
updates

300
Manage Team: Key Inputs

Team performance
Resource  Project team 
management plan assessments assignments
Lessons  Work performance 
learned  reports
register
Team  Issue 
charter log

Change requests

301
Manage Team: Key Tools and Techniques

Change requests
Project management 
plan Project management 
plan updates
Project documents Interpersonal and team skills
Project documents 
Work performance  Project management information  updates
reports system
Enterprise 
Team performance 
environmental 
assessments
factors updates

Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) ‐ Sixth 
Edition, Project Management Institute, Inc., 2017, page 345.

302
Manage Team: Key Tools and Techniques –
Conflict Management
• The Manage Team process includes the tool and technique, 
“interpersonal and team skills”, which covers a variety of 
important skills the project manager should possess. 
• In particular, this tool and technique describes conflict 
management techniques. 
• Common conflict management techniques include 
• Collaborate/problem solve 
• Withdraw/avoid
• Smooth/accommodate
• Compromise/reconcile
• Force/direct

303
Conflict Resolution (Cont.)
Conflict Resolution  Description Example
Technique
Collaborating/ Problem  Collaborating/problem solving is an  If it’s taking too long for a team member 
Solving effort in which attempts are made to  to create status reports, maybe buy 
work out the actual problem.  It is the  better reporting software and devise 
best type of conflict resolution. better ways to collect the data.
Compromising/ Compromising/reconciling is a  If we can get labor to give in on benefits a 
Reconciling negotiation attempt to get everyone  little, and management to increase their 
involved to give (concede) a little to  raise a little, I think we can find 
find a common ground and resolution. agreement that both sides can live with.  
It is sometimes viewed as undesirable 
because when everyone gives 
something up, there is a potential that 
the solution might fail to meet 
anyone’s needs.  

304
Conflict Resolution (Cont.)
Conflict Resolution  Description Example
Technique
Forcing/  Forcing/directing is an action in which a direct  You will stop using that software and switch 
Directing order to resolve something is given.  It is  to the authorized version or you will not be 
typically the worst type of conflict resolution.  around here for long.  
Smoothing/  Smoothing/accommodating is an attempt to  Look at how well the requirements on the 
Accommodating focus on the positive and distract the attention  project went.  We just have to apply that 
from the negative.  same view to this phase of the project as 
well.  
Withdrawing/  In withdrawing/avoiding, the project manager  I know he is a pain to work with, and takes 
Avoiding ignores the problem and hopes it either fixes  longer to do his work than we like, but 
itself or disappears.  Typically, withdrawal is  maybe if we let him be, he will just quit and 
not viewed by PMI as a conflict resolution  take a new job. 
technique because it’s not a proactive 
approach to resolving conflict. 
305
Exercise: Conflict Management Techniques
The team is evaluating whether they should use Technology X or Technology Y. 
For each of the following scenarios, indicate whether the approach involves 
collaborating/problem solving, withdrawing/avoiding, smoothing/accommodating, 
compromising/reconciling, or forcing/directing:
1.The project manager wants to postpone the decision until senior management 
announces the yearly budget, which will determine how much money will be available 
to acquire the needed technology, which could influence the decision.
2.The team suggests using Technology X for one portion of the work, and Technology Y 
for a second portion of the work. The technologies will not interfere with one another.
3.The project manager informs the team that an existing contract requires the team to 
use Y.
4.The team suggests testing both technologies in prototypes to determine which 
performs better.
5.The project manager decides to use Technology X, as a senior team member strongly 
favors this technology. Choosing Technology Y would inevitably result in strong 
resentment and pushback from this senior team member.
306
Exercise: Conflict Management Techniques
1.The project manager wants to postpone the decision until senior 
management announces the yearly budget, which will determine how 
much money will be available to acquire the needed technology, which 
could influence the decision. Withdrawing/avoiding
2.The team suggests using Technology X for one portion of the work, and 
Technology Y for a second portion of the work. The technologies will not 
interfere with one another. Compromising/reconciling
3.The project manager informs the team that an existing contract 
requires the team to use Y. Forcing/directing
4.The team suggests testing both technologies in prototypes to determine 
which performs better. Collaborating/problem solving
5.The project manager decides to use Technology X, as a senior team 
member strongly favors this technology. Choosing Technology Y would 
inevitably result in strong resentment and pushback from this senior 
team member. Smoothing/accommodating
307
Manage Communications Process
(PMBOK® Guide 10.2)
• The process Manage Communications involves implementing the 
communication management plan and the stakeholder engagement plan to 
produce project communications that inform and involve stakeholders, and 
to enable decision making.
• A full‐time project manager often spends the majority of time communicating. 
Accordingly, the project manager must strive to continuously improve 
his/her communication and interpersonal skills, including 
• Providing feedback
• Making presentations
• Interpreting non‐verbal communications
• Building trusted relationships
• Communicating effectively depends on understanding the changing needs of 
stakeholders. 

308
Manage Communications: Key Outputs

Project 
communications

Organizational  Project 
Manage  management 
process assets 
Communications plan updates
updates

Project 
documents 
updates

309
Project Communication Examples
• Progress reports • Post‐its • Slouching
• Meeting minutes • Emails • Sighs
• Presentations • IMs • Raised Voice
• Records • Plans • Flyers
• Reports • Voicemail • Training Manuals
• Memos • Phone calls • Labels
• Posts online • Charts • Posters
• Passing comments • Smiles • Calendars
• Meetings • Frowns • Head in hands
• Video Conferencing • Rolling Eyes • Handshake

We care because communication has long‐lasting, far‐reaching, big‐impacting 
effect!  For example, project communications may be archived for future 
reference and/or used as templates and assets for the organization.
310
Manage Communications: Key Inputs
Issue log Work  Resource 
Change  Quality 
performance  management 
log report
reports plan
Stakeholder 
register Lessons learned  Stakeholder 
register engagement plan
Risk  Communications 
report management 
plan

Project communications

311
Manage Communications: Key Tools and 
Techniques
Communication technology
Communication methods Project communications
Project management  Communication skills Project management 
plan plan updates
Project management 
Project documents Project documents 
information system
Work performance  updates
reports Project reporting Organizational process 
Interpersonal and team skills assets updates

Meetings
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) ‐ Sixth 
Edition, Project Management Institute, Inc., 2017, page 379.

312
Implement Risk Responses Process
(PMBOK® Guide 11.6)
• ***New to PMBOK Sixth Edition
• Ensuring that agreed‐upon risk responses are implemented by risk 
owner and relevant stakeholders with the goal of maintaining the 
project at an acceptable level of risk
• Planning risk responses doesn’t guarantee the execution of those 
responses: the project manager may need to influence stakeholders 
and risk owners to execute the agreed‐upon risk responses.
• Implementing risk responses not only addresses the project’s overall risk 
exposure, but also strengthens the performing organization’s resilience 
to risks by creating a culture that proactively manages risks.

313
Implement Risk Responses: Key Outputs

Change requests

Implement Risk 
Responses

Project 
documents 
updates

314
Implement Risk Responses: Key Inputs, Tools, 
and Techniques

Project  Expert judgment
management  Interpersonal and  Change requests
plan team skills Project documents 
Project  updates
Project management 
documents information system

Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) ‐ Sixth 
Edition, Project Management Institute, Inc., 2017, page 449.

315
Conduct Procurements Process
(PMBOK® Guide 12.2)
1. Publishing the Request For Quote/Request For Proposal and 
the procurement statement of work
2. Advertising and seeking responses from interested and 
qualified vendors
3. Evaluating bids/proposals on numerous, predetermined 
weighting and screening criteria to determine suitable vendors
4. Negotiating with these shortlisted vendors
5. Making an offer to the desired seller 
6. Entering into an agreement (e.g., contract, service level 
agreement, memorandum of understanding) with the external 
organization
316
Procurement:  Procurement Documents
Document Typical Purpose Description Example
Type
Request for  Typically used to solicit  A document requesting  A request from a state 
Information •
information to learn  information on a service  government to see if a consulting 
(RFI) •
more about a company  provider’s qualifications  company has the appropriate 
that could provide service  so a buyer can review  experience in an area to bid for a 
for a buyer them project
Request for  Typically used to solicit  A document requesting a  A request for prospective sellers 
Quote •
proposals for a small  price for a standard item wishing to provide pricing for 
(RFQ) dollar amount or used for  There is a general  customer‐established server 
commodity type of  assumption that  criteria: Quantity 50 XYZ Servers 
products that do not  negotiation is not  with 1G RAM, 200G hard drive to 
require a great degree of  associated with this type  be purchased within 90 days of 
customization of procurement  submittal.
document.
317

Procurement:  Procurement Documents (Cont.)
Document Typical Purpose Description Example
Type
Request for  Typically used to solicit  A document that requests  A request for a proposal to 

Proposal proposals for bigger,  an approach, price, and  prospective sellers for design, 


(RFP)  higher priced, customized  significant detail about  implementation, and training for 


sometimes called  services or products how the seller proposes  a data warehouse to consolidate 
Request for  (Generally, the seller  to do the requested work five different enterprise 
Tender (RFT) describes the detailed  The general assumption is  databases at a fortune 500 

approach for the solution  that negotiations occur  company named Widgets, Inc.


to the buyer, including  based on scope, time, 
previous experience in  and cost of what the 
the area.)   buyer requested and 
what the seller 
suggested.  
318

Conduct Procurements: Other Concepts
• Five elements of a binding contract include:
• Offer
• Acceptance 
• Consideration (something of value received by both parties)
• Legal capacity (separate legal parties, empowered by their 
organization, competent parties)
• Legal age
• Words in contracts generally given more weight than 
numbers if there is a dispute. For example
• “The seller will be paid fifty dollars ($5.00).”
319
Conduct Procurements: Key Outputs

Selected 
vendors
Organizational 
process assets  Agreements
updates
Conduct 
Procurements
Project 
documents  Change 
updates requests
Project 
management 
plan updates

320
Conduct Procurements: Key Inputs
Communications  Procurement 
Configuration  management plan documentation Procurement 
management plan management plan
Risk management plan Requirements 
documentation Scope 
Requirements  management 
Lessons  Seller 
management plan plan
Stakeholder  learned  proposals
register register
Risk register
Cost  Project 
baseline schedule

Selected sellers
Agreements

321
Conduct Procurements: Key Tools and 
Techniques
Selected vendors
Expert judgment Agreements
Project management  Advertising Change requests
plan
Project documents Bidder  Project management 
conferences plan updates
Procurement  Project documents 
documentation Data analysis updates
Vendor proposals Interpersonal and  Organizational 
team skills process assets 
updates
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) ‐ Sixth 
Edition, Project Management Institute, Inc., 2017, page 482.

322
Bidder Conferences
• Special meetings held prior to the submission of proposals that 
the purchasing organization conducts with all interested sellers. 
• Aim to answer all seller questions related to the procurement, 
ensuring that the all sellers have the same understanding of the 
requirements, and that no particular seller receives favored 
treatment.
• On the other hand, the procuring organization must strive to 
minimize the likelihood of collusion. 
• Collusion involves the illegal collaboration between competing 
vendors. For example, if only two firms have the capabilities to provide 
a particular service, those firms may agree to inflate their prices in their 
proposals, with tacit agreements that the firm that wins the contract 
will subcontract part of the work to the other firm.
323
Manage Stakeholder Engagement Process
(PMBOK® Guide 13.3)
• Communicating and working with stakeholders, as outlined in 
the stakeholder engagement plan, to meet their needs and 
expectations, address their issues, and to continually foster 
their support
• Involving stakeholders in decision making 
• Negotiating with negative stakeholders 
• The project manager provides an indispensable role in generating 
and maintaining support and engagement, and project success 
often depends on receiving support from powerful and 
influential stakeholders
324
Manage Stakeholder Engagement: Key 
Outputs
Change 
requests

Manage 
Stakeholder 
Engagement
Project  Project 
documents  management 
updates plan updates

325
Manage Stakeholder Engagement: Key Inputs, 
Tools, and Techniques

Expert judgment
Communication skills Change requests
Project  Project management 
management plan Interpersonal and 
plan updates
team skills
Project documents Project documents 
Ground rules updates
Meetings

Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) ‐ Sixth 
Edition, Project Management Institute, Inc., 2017, page 516.

326
Test‐Worthy Agile Project Management Topics
• Again, this slide may not be accurate.  Instead, refer to the PMI Handbook and the PMBOK:
• https://www.pmi.org/certifications/types/certified‐associate‐capm/exam‐prep

• For simplicity, all agile concepts related to both the Executing Process Group and the 
Monitoring and Controlling Process Group have been collected here.
• When preparing for the exam, be familiar with the following agile project management 
terms and concepts.
• Wireframes, storyboards, and protypes
• Fist of fives
• Standup meetings/daily scrums
• Tracking best practices; Information radiators and refrigerators
• Continuous integration, test‐driven development, refactoring
• Backlog grooming
• Product reviews (demonstrations)
• Iteration, release, and product retrospectives
• For more information on these agile topics and the location of agile practice questions, see 
below.
327
Lesson 6 Review: Executing Processes
• PMP®/CAPM® Test‐Worthy Topics:  • Manage Communications (10.2)
Executing Processes • Implement Risk Responses (11.6)
• Executing Process Group Overview • Conduct Procurements (12.2)
• Direct and Manage Project Work  • Manage Stakeholder Engagement 
(4.3) (13.3)
• Manage Project Knowledge (4.4) • PMP®/CAPM® Practice Questions
• Manage Quality (8.2) • What are your questions?
• Acquire Resources (9.3)
• Develop Team (9.4)
• Manage Team (9.4)
328
PMP®/CAPM® Practice Questions: Executing 
Processes
• Open the file PMP and CAPM Practice Questions. 
• Using the Table of Contents, navigate (using CTRL+Click) to 
the entry Lessons 6: Executing Processes Questions.  
• Answer the odd‐numbered questions and check your 
answers. The answers follow the questions.
• Time to complete this exercise: 15 minutes

329
Lesson 7: Monitoring and 
Controlling Processes
Learning Objective: Based on the PMBOK® Guide Sixth Edition 
Monitoring and Controlling processes.

330
330
Lesson 7 Topics: Monitoring and Controlling 
Processes
• PMP®/CAPM® Test‐Worthy Topics:  • Control Schedule (6.6)
Monitoring and Controlling  • Control Costs (7.4)
Processes
• Monitoring and Controlling Process • Control Quality (8.3)
Group Overview • Control Resources (9.6)
• Monitor and Control Project Work  • Monitor Communications (10.3)
(4.5) • Monitor Risks (11.7)
• Perform Integrated Change Control • Control Procurements (12.3)
(4.6)
• Monitor Stakeholder Engagement 
• Validate Scope (5.5) (13.4)
• Control Scope (5.6) • PMP®/CAPM® Practice Questions

331
Monitoring and Controlling Process Group 
Overview
• Ensures that the actual work performed aligns to the project 
management plan and other planning documents
• Emphasizes a proactive approach to both performance and issues
• Recommends the necessary actions and steps to maximize the 
likelihood of project success
• Ensures that the organization and the project team follow a 
standardized process to evaluate all requested changes
• Performed throughout the project lifecycle
• The project manager is accountable for ensuring the project meets the 
business and project objectives and conforms to the project’s approved 
scope, schedule, and cost baselines. 

332
Monitor and Control Project Work Process
(PMBOK® Guide 4.5)
• Tracking the project’s performance and generating work 
performance reports that identify variations between 
planned results and actual results
• Recommending corresponding preventive and corrective 
actions to improve project performance

333
Monitor and Control Project Work: Key 
Outputs
Reports that show progress, 
Work 
forecasts, charts, KPIs, issues and 
performance 
risks.
reports

Project  Monitor and 
documents  Control Project  Change requests
updates Work

Project 
management plan 
updates
334
Monitor and Control Project Work: Key Tools 
and Techniques

Project management  Work performance 
plan Expert judgment reports
Project documents Data analysis Change requests
Project management plan 
Work performance  Decision making updates
information Meetings Project documents 
Agreements updates

Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) ‐ Sixth 
Edition, Project Management Institute, Inc., 2017, page 105.

335
Perform Integrated Change Control Process
(PMBOK® Guide 4.6) (1 of 2)
• Involves the evaluation by relevant stakeholders (e.g., 
project manager, sponsor, Change Control Board) of 
proposed changes to controlled project items (e.g., project 
management plan elements, deliverables, controlled 
documents), and managing those changes efficiently and 
effectively
• For agile projects ‐ welcoming all value‐added changes, 
even late in the project
• Preventing unnecessary change and protecting the project 
objectives
336
Perform Integrated Change Control Process
(PMBOK® Guide 4.6) (Continued) (2 of 2)
• This process is mandatory when a proposed change affects any 
element of the project management plan (e.g., scope, schedule, and 
cost baselines; any subsidiary management plans) and any document 
the organization deems important enough to control.
• **The change management plan and the configuration management 
plan specify which documents require the formal change control 
process. 
• Generally, integrated change control is not required prior to finalizing 
the project management plan, or if reserves are available for specific 
risks and events.
• The project manager accountable for requiring all proposed changes 
follow the Integrated Change Control process.

337
Exercise: Integrated Change Control Steps
Using your experience and judgment, rearrange the following steps related to 
processing a requested change into the correct order.
• Approve or deny the change
• Assess and evaluate the proposed change
• Close the change record
• Create the Request For Change (RFC)
• Implement the change
• Inform relevant stakeholders
• Record the Request For Change (RFC)
• Review the implemented change
• Review the Request For Change (RFC) for completeness
• Update relevant documents

338
Answers: Integrated Change Control Steps
Create the  Review the  Assess and 
Record the  evaluate the 
Request For  RFC for  proposed 
RFC
Change (RFC) completeness change

Inform  Update  Approve or 


Implement 
relevant  relevant  deny the 
the change
stakeholders documents change

Review the  Close the 
implemented  change 
change record

339
Perform Integrated Change Control: Key 
Outputs
Approved 
change 
requests

Perform 
Integrated 
Change 
Control
Project  Project 
documents  management 
updates plan updates

340
Perform Integrated Change Control: Key 
Inputs, Tools, and Techniques

Expert judgment
Project 
management plan Change control tools Approved change 
requests
(Change Log)
Project documents Project management 
Data analysis
Work performance  plan updates
Decision making
reports Project documents 
Meetings updates
Change requests (Change Control Board, CCB)

Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) ‐
Sixth Edition, Project Management Institute, Inc., 2017, page 113.

341
Validate Scope Process (PMBOK® Guide 5.5)
• Conducting a formal review of completed deliverables by the 
customer or the sponsor with the goal of obtaining approval of 
those deliverables
• Validating that deliverables:
• meet the customer’s expectations 
• (fitness for use)
• meet product requirements 
• (conformance to requirements/specifications)
• Initiating appropriate actions (e.g., change requests, lessons 
learned) if the customer or sponsor declines to approve 
deliverables

342
Validate Scope: Key Outputs
Work 
performance 
information

Project  Accepted 
document  Validate Scope deliverables
updates

Change requests

343
Validate Scope: Key Inputs, Tools, and 
Techniques

Project management  Accepted deliverables
plan Inspection Work performance 
Project documents (Demos, walkthroughs,  information
reviews) Change requests
Verified deliverables
Decision making Project document 
Work performance data updates

Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) ‐ Sixth 
Edition, Project Management Institute, Inc., 2017, page 163.

344
Control Scope Process (PMBOK® Guide 5.6)
• Ensuring the team creates all agreed‐upon deliverables and perform all agreed‐
upon work listed in the most recent scope baseline
• Managing changes to the scope baseline and associated documentation by 
routing all proposed scope changes through the process of Integrated Change 
Control
• Updating relevant documentation (e.g., requirements documentation, project 
scope statement, WBS)
• Eliminating unmanaged scope, such as scope creep and gold plating 
• Gold Plating: the team adding features with the hopes of surprising and delighting the 
customer
• ***Uncontrolled changes cause many projects to fail, or at a minimum, they 
negatively impact other project objectives, such as cost, schedule, resources, 
quality, and risk.
• Thus, effective scope control greatly influences project success, and increases the 
likelihood that the project will deliver the intended benefits.
345
Control Scope: Key Outputs
Work 
performance 
information

Project 
document  Control Scope  Change requests
updates

Project 
management 
plan updates

346
Control Scope: Key Inputs, Tools, and 
Techniques

Work performance 
Project management  information
plan Data analysis Change requests
Project documents Project management 
(Variance Analysis) plan updates
Work performance data Project document 
updates

Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) ‐ Sixth 
Edition, Project Management Institute, Inc., 2017, page 167.

347
Control Schedule Process (PMBOK® Guide 6.6)
• Ensuring the team completes deliverables and performs work according to 
the most recent, agreed‐upon schedule
• Comparing the project’s actual schedule performance (e.g., actual start dates, 
finish dates, and hours of effort) with the planned schedule to determine 
schedule‐related work performance information. 
• Using earned value analysis, performance reviews, and schedule forecasts.
• If applicable, submitting change requests to improve schedule performance. 
• Managing changes to the schedule baseline and associated documentation by 
routing these requests through the process Integrated Change Control
• Employing a variety of schedule‐oriented techniques such as: 
• using schedule compression (crashing and/or fast tracking)
• adjusting leads and lags
• applying resource optimization techniques (resource smoothing and leveling)
• Continually reviewing the project’s critical path activities to determine 
performance, assess risks, and respond to issues
348
Control Schedule: Key Outputs

Work performance 
Project  information
documents  Schedule forecasts
updates

Control Schedule

Project 
management plan  Change requests
updates

349
Control Schedule: Key Inputs
Schedule  Schedule 
Lessons learned  management plan baseline Resource calendars
register
Schedule  Performance 
Project  data measurement baseline
schedule Scope baseline
Work 
performance 
data Project 
calendars

Schedule forecasts
Work performance information
Change requests
350
Control Schedule: Key Tools and Techniques

Data analysis
Critical path method Work performance information
Project management 
Schedule forecasts
plan Project management 
information system Change requests
Project documents
Project management plan 
Work performance  Resource optimization updates
data
Leads and lags Project document updates
Schedule compression
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) ‐ Sixth 
Edition, Project Management Institute, Inc., 2017, page 222.

351
Control Costs (PMBOK® Guide 7.4)
• Comparing baseline versus actual expenditures and funding at 
the activity, work package, deliverable, and project levels to 
produce cost‐related work performance information, including 
cost forecasts.
• Investigate the reasons behind any variances and generating 
change requests and/or corrective actions to bring future 
performance in line with planned performance
• Ensuring that actual expenditures lead to the creation of 
deliverables that meet quality expectations
• Ensuring that no changes to the cost baseline occur without 
proper routing through the process Integrated Change Control

352
Control Costs: Key Outputs

Work performance 
Project document  information
Cost forecasts
updates

Control Costs

Project 
management plan  Change requests
updates

353
Control Costs: Key Inputs

Cost management  Cost baseline Lessons learned 


plan register
Project 
funding  Work performance 
requirements data

Change requests

354
Control Costs: Key Tools and Techniques

Expert judgement Work performance 
Data analysis information
Project management plan
Cost forecasts
Project documents (Earned Value, Reserve)
Change requests
Project funding  To‐complete 
requirements Project management 
performance index plan updates
Work performance data
Project management  Project document 
information system updates

Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) ‐
Sixth Edition, Project Management Institute, Inc., 2017, page 257.

355
Earned Value Analysis (EVA)
• Involves the examination and comparison of

against

planned schedule and cost  actual schedule and cost metrics 

to determine overall project performance.
356
Earned Value: Key Metrics
• Budget At Completion (BAC): the cost baseline – the amount of 
money expected to be spent on the project, including contingency 
reserves. 
• Assume BAC = $100,000
• Planned Value (PV): the baseline value of the work that should have 
been completed, as of the reporting date. 
• Assume PV = $40,000
• Earned Valued (EV): the baseline value for the work that was
accomplished, as of the reporting date. 
• Assume EV = $30,000 
• behind schedule; $10,000 work not completed
• Actual Cost (AC): the actual amount of money spent on the work that 
was accomplished, as of the reporting date. 
• Assume AC = $35,000 
• overbudget; spent $5,000 more than expected for completed work
357
Earned Value: Variances, Indices, Interpretations
• Schedule Variance (SV) = EV ‐ PV. In this example, SV = $30,000 ‐ $40,000 = ($10,000). 
• An SV < $0 means behind schedule; an SV > $0 means ahead of schedule.
• The team failed to complete work with a baseline cost of $10,000.
• Schedule Performance Index (SPI) = EV/PV. In this example, SPI= $30,000/$40,000 = .75. 
• An SPI < 1 means behind schedule; an SPI > 1 means ahead of schedule.
• The team created only 75% of the planned work deliverables.
• Cost Variance (CV) = EV ‐ AC. In this example, CV = $30,000 ‐ $35,000 = ($5,000). 
• A CV < $0 means the project is over budget; a CV > $0 is under budget.
• The team spent $5,000 more than expected on the completed work.
• Cost Performance Index = EV/AC. In this example, CPI = $30,000/$35,000 = .857. 
• A CPI < 1 means over budget; a CPI > 1 means under budget. 
• Thus, the team is only receiving 85.7 cents of value for every dollar they are spending.
• Note: variances (SV and CV) use subtraction, and indices (SPI and CPI) use division.
• All four formulas begin with EV. 358
Earned Value: Forecasts
• Estimate At Completion (EAC): expected total project cost based on current 
performance. Though there are three different formulas, the team chooses the 
one that most accurately reflects their current performance.
1. EAC = AC + Bottom‐up (new) ETC
• Actual costs different than planned. Assume new ETC equals $75,000. In this case, EAC = 
$110,000 = ($35,000 + $75,000). 
2. EAC = AC  + (BAC ‐ EV)
• The current cost variance will not influence future performance. In this case, EAC = 
$105,000 = $35,000 + ($100,000‐$30,000)
3. EAC = BAC/CPI 
• Current spending expected to continue. In this case, EAC = $116,686 = $100,000/.857 
(rounded).
• Estimate To Completion (ETC) = EAC ‐ AC. The expected remaining amount of 
money to complete the work. For the values of EACs listed above
1. ETC = $110,000 ‐ $35,000 = $75,000 
2. ETC = $105,000 ‐ $35,000 = $70,000
3. ETC = $116,686 ‐ $35,000 = $81,686
359
Earned Value: Variance At Completion (VAC)
• The expected cost variance for the entire project based on current 
performance
• VAC = BAC ‐ EAC
• A VAC less than $0 means the project is expected to cost more than planned; 
a VAC greater than $0 means the project is expected to cost less than planned.

• Based on the values of EAC on the previous slide of $110,000, $105,000, and 
$116,686:
1. VAC = $100,000 ‐ $110,000 = ($10,000)
2. VAC = $100,000 ‐ $105,000 = ($5,000)
3. VAC = $100,000 ‐ $116,686 = ($16,686)
• Using the three values of VAC, above, the project is expected to exceed the 
original budget by $10,000, $5,000, and $16,686 respectively.

360
Earned Value: To‐Complete Performance 
Index (TCPI)
• Provides a measure of how efficiently the team must manage their 
remaining project money to complete the remaining work
• TCPI = (BAC ‐ EV)/(BAC ‐ AC)
• in other words: Remaining Project Work/Remaining Project Money
• Based on the values from previous slides, 
• Remaining work = $70,000 = BAC ‐ EV = $100,000 ‐ $30,000
• Remaining money = $65,000 = BAC ‐ AC= $100,000 ‐ $35,000 
• Thus, TCPI = $70,000/$65,000 = 1.077 (rounded)
• Meaning: for every $1 of money remaining, the team must find a way to earn 
$1.077 to correct the current $5,000 variance.
• TCPI greater than 1.00 means the project is currently overbudget, and the 
team will need to earn more than $1 of value for every $1 left in the budget. 
• A TCPI less than 1.00 means the project is currently under budget.

361
Earned Value: S‐Curves
Earned Value
2500

Gap between EV and PV 
2000 indicates a schedule variance.

1500

1000

500 Gap between EV and AC 
indicates a cost variance.
0
Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8

EV PV AC

362
Earned Value Management (EVM) (Cost Analysis Only)

• Perhaps the easiest way to understand EVM and Cost Analysis is to look at the 
components and formulas within the context of a home building project.  
• To determine EARNED VALUE and perform COST and SCHEDULE analysis, you need 
to know the total project value and, at a distinct point in time, the completion 
percentage, the amount of work that should have been completed, and the 
amount that has been spent. 
• For our example:
• The overall planned value of the project is $100,000.
• At the end of the day today (a specific point in time):
• The house is 40% completed, thus $40,000 in work done so far
• The amount of work that should have been completed is $60,000
• The amount that has been spent is $80,000
363
Earned Value Management (EVM)
Determining Earned Value

Component


Definition Calculation/Amount
Budget at Completion (BAC) The amount you expect the project to  Total the costs of each project work 
cost package without regard to 
completion status: $100,000

**May have to be done per activity

Planned Value (PV)  The value of the work that should have  Total the value of each project 


been completed at a specific point in  activity scheduled for completion at 
time, excluding any work started ahead  a specific point in time: $60,000
• of schedule

Actual Cost (AC) The cost of the work that has been  Total all the project costs at a 



completed at a specific point in time,  specific point in time:
including any work started ahead of  $80,000

schedule 364
Earned Value Management (EVM)

Determining Earned Value (Cont.)

Component Definition Calculation/Amount

Earned Value (EV) A measurement of the  BAC multiplied by 


progress of a project and the  percentage complete 
basis for cost analysis,  (40%):
including any work started  $100,000*40%=$40,000
ahead of schedule **This is often done per
activity up to this point in 
time.

365
Cost:  Earned Value Management (EVM) – (Cont.)
Performing Cost Analysis (Cont.)

Index/Variance Formula/Result Result Interpretation

Cost Variance (CV) EV‐AC A variance indicator that denotes the difference between the 


$40,000 ‐ $80,000 = ($40,000) value of the work completed
and cost of the work completed.
Be able to calculate EV or AC if 
given CV and EV or AC.   If the result is 0, the project is on track.
For example:  If the result is greater than 0, the project is under budget.
AC + CV = EV  If the result is less than 0, the project is over budget.
or 
EV – CV = AC In this case, the result is less than 0; 
therefore the project is over budget by $40,000.

366
Earned Value Management (EVM) – (Cont.)

Performing Cost Analysis

Index/Variance Formula/Result Result Interpretation

Cost  EV / AC An efficiency indicator that denotes the return on each dollar spent at a single 


Performance  $40,000 / $80,000 = 0.5 point in time.
Index (CPI) If the result is 1.0, the return on the project at a single point in time is on track.
Be able to calculate EV  If the result is greater than 1.0, the return on the project is under budget.
or AC if given CPI and  If the result is less than 1.0, the return on the project is over budget.
EV or AC.  
For example: 
A CPI of .5 means that the project is getting 50 cents of 
AC x CPI = EV 
work done for every dollar spent.
or 
EV/CPI = AC

367
Cost:  Forecasts
Forecasts are estimates or predictions of the future state of the project based on past 
performance and expected future performance.
Cost  Formula* Description
Forecast Varied Approaches

Estimate at  EAC=BAC/CPI The estimate at completion (EAC) represents the current projected 


Completion Or  final cost based on the current spending efficiency (CPI).  
(EAC) $100,000/0.5 If you have a CPI greater than one (>1), the number will be less than 
***Remember,  =$200,000 the BAC, meaning that the project will likely finish under budget.  
there are 3 possible  ***This formula is if we 
If you have a CPI of less than one (<1), the number will be greater 
formulas here based  expect the current 
than the BAC, meaning that the project will finish over budget.  
on what caused the  spending to continue
past variance and if  If the CPI equals 1, the project will finish on budget.  
we expect that 
cause to continue. EAC: $200,000 (This is on pace to come in over the BAC 
of $100,000 in our example on the previous pages.) 

368
Cost:  Forecasts (Cont.)
Cost  Formula* Description
Forecast

Estimate to  ETC=EAC‐AC The estimate to complete (ETC) represents the amount needed to finish the 


Complete Or  project based on the current spending efficiency of the project.  This figure is 
(ETC) $200,000‐$80,000= the EAC without the actual cost to date. 

$120,000 ETC: $120,000 (It is on pace to exceed the BAC amount when factoring in what 
has already been spent in our example in the previous pages.) 

Variance at  VAC=BAC‐EAC The variance at completion (VAC) is the difference between the budget at 


Completion  Or  completion (BAC) and the estimate at completion (EAC).  This difference tells 
(VAC) $100,000 ‐200,000 = how much over or under budget the project might finish.

($100,000) VAC: $100,000 (This figure is the projected over budget amount, based on the 
current spending efficiency of the project in our example on the previous 
pages.) 

369
Cost:  Forecasts (Cont.)
Cost  Formula* Description
Forecast

To‐complete  TCPI= An efficiency indicator that denotes the efficiency needed from the remaining 


Performance Index  (BAC ‐EV)/ resources to meet the cost goals of the project and finish the project on budget.
(TCPI) (BAC ‐ AC) 
Or In other words, the To Complete Performance Index (TCPI) is the estimate of the 
($100k ‐ $40k) /  future cost performance that you may need to complete the project within the 
($100k ‐ $80k) approved budget (which is either the initial approved budget (BAC), or a newly 
=3.0 calculated budget/estimate at completion (EAC)).

It’s like saying “if we want to stay on budget, we’ll have to continue with a 
future Cost Performance Index of x.

In this scenario, it’s like saying from now on we’ll have to 
get 3 times the amount of work per planned dollar!
370
Earned Value: Summary of Formulas Discussed
• EV: BAC*% Completed work
• SV: EV ‐ PV
• SPI: EV/PV
• CV: EV ‐ AC 
• CPI: EV/AC

• EAC = AC + ETC (Most common and accurate; uses Management ETC: adding expected costs of all remaining 
activities)
• EAC = AC + (BAC ‐ EV) (Past cost performance may have differed, but future cost performance expected to 
align with planned)
• EAC = BAC/CPI (Past cost performance expected to continue)

• ETC: (BAC ‐ EV)/CPI  or  EAC ‐ AC


• VAC = BAC ‐ EAC
• TCPI = (BAC ‐ EV)/(BAC ‐ AC)

371
Exercise: Earned Value
Answer the following questions. Refer to the formulas on the previous page if necessary.
A project has total expected development costs of $50,000. The project manager determines the following on status reporting day:
Activity A has an expected development cost of $5,000. It should be 100% complete. It’s currently 100% complete, has an actual cost of $6,000
Activity B has an expected development cost of $8,000. It should be 100% complete. It’s currently 60% complete, has an actual cost of $5,500
Questions:
1. What is AC for the project?
2. What is EV for the project?
3. What is PV for the project?
Double‐check your work for Questions 1‐3 before you begin the remaining questions.  Make sure you’ve done the math correctly.
4. What is SV for the project? 
5. Based on the value of SV, what can you determine about the project?
6. What is CPI for the project? 
7. Based on the value of CPI, what can you determine about the project?
****The current cost performance is attributed to the cost of raw material being more expensive than expected, and the remaining activities 
require the same types and quantities of resources.
8. What is EAC for the project?
9. What is VAC for the project?
10. What does the VAC mean for the project?
11. What is ETC for the project?

372
Exercise Answers: Earned Value
1. AC = $11,500 ($6,000 + $5,500)
2. EV = $9,800 ($5,000 + $8,000*.6) = ($5,000 + $4,800)
3. PV = $13,000 ($5,000 + $8,000)
4. SV = ‐$3,200 ($9,800 ‐ $13,000)
5. Behind schedule (less than $0)
6. CPI = .852 (rounded; $9,800/$11,500)
7. Overbudget (less than 1; only getting 85.2 cents for every dollar spent)
8. EAC = $58,685 ($50,000/.852)
9. VAC = ‐$8,685 ($50,000 ‐ $58,685)
10. At this moment, the project is expected to cost $8,685 more than expected.
11. ETC = $47,185 ($58,685 ‐ $11,500)

Remember to practice schedule formulas as well!
373
Control Quality Process
(PMBOK® Guide 8.3)
• Producing quality‐related work performance information, such as 
whether the project deliverables comply with planned standards, 
regulations, requirements, and specifications, typically listed in the 
quality management plan and requirements documentation 
• Ensuring that the project produces complete and correct outputs
• Recording defects, investigating root cause(s) and potentially 
recommending change requests
• Performing population testing or statistical sample testing
• Optimally, achieving the goal of “verified deliverables”: those tested 
deliverables that successfully meet all relevant requirements (an input 
to the process Validate Scope, discussed earlier)
374
Control Quality: Key Outputs

Quality control 
measurements
Project 
documents  Verified 
updates deliverables

Control Quality

Project  Work 
management  performance 
plan updates information
Change 
requests

375
Control Quality: Key Inputs

Quality management plan
Lessons learned  Test and evaluation
register documents
Quality metrics

Deliverables Approved 
Work  change  
performance  requests
data

Quality control measurements
Verified deliverables
Work performance information
Change requests
376
Control Quality: Key Tools and Techniques

Data gathering Quality control 
(Check Sheets, Surveys) measurements
Project management plan Data analysis Verified deliverables
Project documents Inspection Work performance 
Approved change requests Testing/product evaluations information
Deliverables Data representation Change requests
Work performance data (Control, Pareto, Histogram  Project management plan 
and Scatter Charts, Ishikawa)  updates
Meetings Project documents updates
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) ‐ Sixth 
Edition, Project Management Institute, Inc., 2017, page 298.

377
Check Sheets
Check sheets help gather data about the attributes or defects in deliverables

Morning Shift Afternoon Shift Total


Wrong Shape 5 4 9
Wrong Color 2 0 2
Wrong Weight 3 4 7
Wrong Height 9 8 17
Wrong Width 3 3 6
Totals 22 19 41

378
Pareto Charts
Pareto charts help organizations focus on eliminating the most significant cause first, the second most 
significant cause next, etc.

Causes of Scrapped Products
100 100%
90
80
70
60
50 50%
40
30
20
10
0 0%
Machine Calibration Poor Raw Materials Improper Storage Shipping Damage

379
Control Charts
Provide an indication of whether a process produces acceptable or “out of control” outputs. This chart 
shows an average (mean) of 100% schedule performance. This implies that the organization runs the 
average projects at 100% schedule performance. The organization has set Lower Control Limits (LCL) and 
Upper Control Limits (UCL) at 97% and 103%, respectively. 

Schedule Performance
<100% implies behind schedule

108% UCL, 103%
Mean, 100%
100% LCL, 97%
Out of Control, 
92% 96%
Week 1 Week 2 Week 3 Week 4 Week 5 Week 6

380
Histograms
Histograms provide a graphical representation of data in bar chart format. Histograms can lead 
to more detailed quantitative (and/or qualitative) investigation, such as finding statistical 
correlations or root causes. For the process Control Quality, histograms can display the number 
of defects discovered related to specific products, components, project phases, or any other 
relevant aspect.

Types of Defects
30

25

20

15

10

Missing components Wrong Components Extra Components Defective Components

381
Generally show the potential 
Scatter Diagrams correlation between variables. For 
the process Control Quality, they 
could show the potential correlation 
X axis = Weeks of PM training between work hours and defects, or 
Y axis = Schedule Performance between training and morale.
110% Briefly, scatter diagrams explore 
whether variables are related 
100% (correlation), not whether one 
variable causes the other (causality). 
90% As an often‐cited example, consider 
these two statements:
80%
1. Ice cream consumption and 
70% drowning deaths are related. On 
days when people eat more ice 
60% cream, there are more drowning 
deaths (correlation).
50% 2. Eating ice cream increases the 
0 1 2 3 4 5 chances of drowning (causality).

382
Exercise: Control Quality Tools and Techniques
Match each quality control scenario with an appropriate tool or technique that could adequately 
address that scenario. 
Tools and techniques: check sheets, checklist, control charts, cause‐and‐effect diagrams, 
histograms, questionnaires and surveys, scatter diagrams
• The team needs to measure products (e.g., height, weight, density, torque) or service outcomes 
(e.g., service times) where they have well‐defined ranges for successful and unsuccessful 
outcomes. 
• The team member performing a test must indicate the number of defects and the types of 
defects (e.g., wrong size, dented components, missing components) found during testing. 
• The team wants to know whether schedule performance (amount of work completed 
successfully) is related to the temperature within the office. 
• The team needs to perform a test with 10 specific steps in a very specific order.
• The team wants to determine whether customers are satisfied with their product in the 
operational environment.
• The team wants to visually display the number of defects found in each phase of the project life 
cycle (or the number of defects attributable to various departments, products, or other factors). 
• The team wants to display the root causes that lead to a particular outcome (e.g., scrap, defects, 
warranty claims)
383
Exercise Answers: Control Quality Tools and Techniques
• The team needs to measure products or service outcomes (e.g., service time, height, weight, 
density, torque) where they have well‐defined ranges for successful and unsuccessful 
outcomes. Control charts
• The team member performing a test must indicate the number of defects and the types of 
defects (e.g., wrong size, dented components, missing components) found during testing. 
Check sheets or histograms
• The team wants to know if schedule performance (amount of work completed successfully) is 
related to the temperature within the office. Scatter diagrams
• The team needs to perform a test with 10 specific steps in a very specific order. Checklist
• The team wants to determine whether customers are satisfied with their product in the 
operational environment. Questionnaires and surveys
• The team wants to visually display the number of defects found in each phase of the project 
life cycle (or the number of defects attributable to various departments, products, or other 
factors). Histograms
• The team wants to display the root causes that lead to a particular outcome (e.g., scrap, 
defects, warranty claims) Cause‐and‐effect diagrams (Ishikawa diagrams; fishbone 
diagrams)

384
Control Resources Process
(PMBOK® Guide 9.6)
• ***New to the PMBOK Sixth Edition
• Focusing on the effective assignment and use of physical resources (e.g., 
equipment, materials, facilities)
• Ensuring that stakeholders who control physical resources provide those 
resources according to plan: in the correct types, quantities, and at the correct 
locations
• Comparing actual utilization to planned utilization to generate resource‐related, 
work performance information and potential unacceptable variances
• Ensuring the team uses physical resources as planned to maximize efficiencies
• Predicting shortages and overages, communicating resource issues to relevant 
stakeholders, initiating corrective and preventative actions 
• Submitting change requests related to physical resources to the process 
Integrated Change Control
385
Control Resources: Key Outputs
Work 
performance 
information

Project 
Control  Change requests
document 
Resources
updates

Project 
management 
plan updates

386
Control Resources: Key Inputs
Resource  Physical resource 
management plan assignments Resource 
Lessons learned 
register requirements
Issue log Risk register

Project schedule Resource breakdown
structure
Work performance 
data
Agreements

Work performance information
Change requests

387
Control Resources: Key Tools and Techniques

Data analysis
Work performance 
(Performance Reviews,  information
Project management plan Trend Analysis)
Change requests
Project documents Problem solving
Project management plan 
Work performance data Interpersonal and team  updates
Agreements skills
Project documents 
Project management  updates
information system

Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) ‐ Sixth 
Edition, Project Management Institute, Inc., 2017, page 352.

388
Monitor Communications Process
(PMBOK® Guide 10.3)
• Monitoring communications and producing communications‐
related work performance information by evaluating whether:
• the project provides the specified communications as defined in the 
communications management plan and the stakeholder management 
plan 
• the project communications effectively and efficiently inform and 
engage stakeholders by sending the right information to the right 
audience at the right time using the right channels
• Submitting change requests, as appropriate, with the intent of 
continually improving communications and engagement
389
Monitor Communications: Key Outputs
Work 
performance 
information

Project 
Monitor  Change requests
document 
Communications
updates

Project 
management 
plan updates

390
Monitor Communications: Key Tools and 
Techniques

Expert Judgement Work performance 
Project management plan Data Representation information
Project documents Interpersonal and team  Change requests
Work performance data skills Project management plan 
EEFs Project management  updates
OPAs information system Project documents 
Meetings updates

Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) ‐ Sixth 
Edition, Project Management Institute, Inc., 2017, page 388.

391
Monitor Risks Process
(PMBOK® Guide 11.7)
• Monitoring the:
• overall level of project risk 
• effectiveness of risk management processes
• Performing activities, such as
• Monitoring the implementation and effectiveness of risk responses
• Tracking known risks, and updating the risk register and the risk report to 
reflect changing details
• Monitoring low‐ranking risks
• Identifying and analyzing new risks and retiring risks
• Monitoring reserves, and recommending applicable changes
• Generating work performance information, such as determining the level of 
compliance to risk policies and procedures and the effectiveness of those policies 
and procedures
• Generating lessons learned and recommending changes to improve 
effectiveness or efficiency
392
Monitor Risks: Key Outputs
Work 
performance 
information

Project 
document  Monitor Risks Change requests
updates

Project 
management 
plan updates

393
Monitor Risks: Key Inputs, Tools, and 
Techniques

Work performance 
Project management plan information
Data analysis
Project documents Change requests
(Reserve Analysis)
Work performance data Audits Project management plan 
updates
Work performance  Meetings Project documents 
reports updates

Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) ‐ Sixth 
Edition, Project Management Institute, Inc., 2017, page 453.

394
Control Procurements Process
(PMBOK® Guide 12.3)
• Managing the procurement relationship, making payments, 
making applicable corrections, and eventually closing contracts
• Monitoring seller performance, communicating to build effective 
working relationships, performing procurement audits, and 
recommending beneficial changes
• Resolving claims through (in desired order):
• negotiation, mediation, binding arbitration and litigation 
• Generally, performed by SMEs from departments such as 
contracting, legal, purchasing, or procurements, though the 
project management team should optimally understand all 
particulars

395
Control Procurements: Key Outputs
Must close both successful and 
unsuccessful procurements. 
Closed 
procurements
Project  Work 
document  performance 
updates information
Control 
Procurements
Project  Procurement 
management  documentation 
plan updates updates
Change 
requests

396
Control Procurements: Key Inputs

Requirements  Lessons  Approved 


learned  change  Risk register Change 
Schedule  management plan
register requests Procurement  management 
baseline Procurement  plan
Quality  Milestone list management 
reports documentation plan
Risk management plan Work  Requirements 
Assumption  performance  documentation
log data Stakeholder 
Requirements 
register
traceability matrix
Agreements

Closed procurements
Work performance information
Change requests
397
Control Procurements: Key Tools and 
Techniques

Closed procurements
Project management plan Expert judgment Work performance 
Project documents Claims  information
Agreements administration Procurement 
Procurement  documentation updates
Data analysis
documentation Change requests
Approved change requests Inspection Project management plan 
Work performance data Audits updates
Project documents updates
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) ‐ Sixth 
Edition, Project Management Institute, Inc., 2017, page 492.

398
Claims Administration
• Involves the process of managing and resolving conflicting opinions on 
applicable charges and expenses between the buyer and seller. 
• Generally, the agreement between the parties specifies the procedures for 
performing claims administration to resolve the claims. 
• If both parties cannot resolve the claim through the objective interpretation 
of the agreement, they should attempt to resolve the claim through 
negotiations with a win‐win orientation. 
• If this fails, the agreement may specify Alternative Dispute Resolution (ADR)
procedures, such as resolving the dispute through mechanisms such as 
mediation, binding arbitration, and (lastly) litigation. 

399
Monitor Stakeholder Engagement Process
(PMBOK® Guide 13.4)
• Generating work performance information by examining the 
compliance to agreed‐upon engagement strategies and 
evaluating the effectiveness of those strategies 
• Recommending alternative strategies that could produce higher 
levels of stakeholder involvement and support
• Using a variety of tools and techniques such as communication 
skills, interpersonal skills, and political skills, among others
• Performing root cause analysis and alternatives analysis to 
propose activities that should foster more favorable stakeholder 
relationships
400
Monitor Stakeholder Engagement: Key 
Outputs
Work 
performance 
information

Project  Monitor 
document  Stakeholder  Change requests
updates Engagement 

Project 
management 
plan updates

401
Monitor Stakeholder Engagement: Key Inputs
Resource  Project 
Lessons learned  management plan communications Stakeholder 
register Stakeholder  engagement plan
Issue log Risk register
register

Work  Communications 
performance  management 
data plan

Work performance information
Change requests

402
Monitor Stakeholder Engagement: Key Tools 
and Techniques

Data analysis
Work performance 
Decision making information
Project management plan Data representation Change requests
Project documents Communication skills Project management plan 
Work performance data updates
Interpersonal and 
Project documents 
team skills updates
Meetings
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) ‐ Sixth 
Edition, Project Management Institute, Inc., 2017, page 530.

403
Test‐Worthy Agile Project Management Topics
• Again, this slide may not be accurate.  Instead, refer to the PMI Handbook and the PMBOK:
• https://www.pmi.org/certifications/types/certified‐associate‐capm/exam‐prep

• For simplicity, all agile concepts related to both the Executing Process Group and the Monitoring and 
Controlling Process Group have been collected here.
• When preparing for the exam, be familiar with the following agile project management terms and 
concepts.
• Wireframes, storyboards, and protypes
• Fist of fives
• Standup meetings/daily scrums
• Tracking best practices; Information radiators and refrigerators
• Continuous integration, test‐driven development, refactoring
• Backlog grooming
• Product reviews (demonstrations)
• Iteration, release, and product retrospectives
• For more information on these agile topics and the location of agile practice questions, see below.

404
Lesson 7 Review: Monitoring and Controlling 
Processes
• PMP®/CAPM® Test‐Worthy Topics:  • Control Quality (8.3)
Monitoring and Controlling Processes • Control Resources (9.6)
• Monitoring and Controlling Process  • Monitor Communications (10.3)
Group Overview
• Monitor and Control Project Work  • Monitor Risks (11.7)
(4.5) • Control Procurements (12.3)
• Perform Integrated Change Control  • Monitor Stakeholder Engagement 
(4.6) (13.4)
• Validate Scope (5.5) • PMP®/CAPM® Practice Questions
• Control Scope (5.6) • What are your questions?
• Control Schedule (6.6)
• Control Costs (7.4)

405
PMP®/CAPM® Practice Questions: Monitoring 
and Controlling Processes
• Open the file PMP and CAPM Practice Questions. 
• Using the Table of Contents, navigate (using CTRL+Click) to 
the entry Lesson 7: Monitoring and Controlling Processes 
Questions.  
• Answer the odd‐numbered questions and check your 
answers. The answers follow the questions.
• Time to complete this exercise: 15 minutes

406
Lesson 8: Closing Processes
Learning Objective: Based on the PMBOK® Guide Sixth Edition Closing 
process.

407
407
Lesson 8 Topics: Closing Processes
• PMP®/CAPM® Test‐Worthy Topics: Lesson 8: Closing 
Processes
• Closing Process Group Overview
• Close Project or Phase (4.7)
• PMP®/CAPM® Practice Questions

408
Closing Process Group Overview
• Finalizing all work of the project, phase, or contract 
• Updating and archiving documentation
• Releasing physical and human resources
• Transitioning information from the project lessons learned log to 
the organization’s information repositories
• Writing and filing the final project report
• ***The Closing Process “Group” consists of only a single 
process (Close Project or Phase), but the PMBOK® Guide uses 
the word “Group,” as organizations may have additional 
processes they perform while closing a project phase, project, 
or contract.
409
Close Project or Phase Process (PMBOK® Guide 4.7)
• Transitioning project products, services, or results to operations or to the next project 
phase
• Performing a variety of required administrative activities.
• Confirming acceptance from relevant  • Evaluate key project parameters 
stakeholders • Measuring stakeholder satisfaction
• Closing project accounts (e.g., work hours, costs) • Releasing project resources for other 
• Archiving information and documents organizational uses 
• Creating the project’s final report

• Collecting final lessons learned and transferring them to the organization’s knowledge 
repository
• Performing similar activities for procurements (e.g., confirming acceptance of seller’s 
deliverables, processing final payments, finalizing open claims, collecting lessons learned, 
and archiving procurement)
• An organization must close projects, project phases, and procurements, whether they are 
successful or unsuccessful. 410
Close Project or Phase: Key Outputs
Final Report: summarizing the project’s 
or phase’s performance on key 
parameters like scope, schedule, cost, 
quality, and risk. The final report 
highlights variances, the root causes and  Project documents 
associated lessons learned.  updates

It also describes the degree to which the 
phase’s or project’s result meets planned 
objectives and delivers the anticipated 
benefits.  Close Project or 
Phase
In the event of early termination of the 
phase or the project, the report would  Final product, 
also contain reasons for termination,  Final report service, or result 
lessons learned, and recommendations  transition
for the management and use of any 
partially completed product, service or 
result. 411
Close Project or Phase: Key Inputs
Project  Lessons  Risk  Risk register
Project  management plan learned  report Project communications
charter Basis of estimates register Quality control  Change log
Quality  Issue 
Milestone list log measurements
reports
Business case Procurement  Requirements 
Assumption  documentation documentation
log Benefits 
Accepted  management 
deliverables plan
Agreements

Final product, service, or result transition
Final report
412
Close Project or Phase: Key Tools and 
Techniques
Project charter
Project management plan
Project documents Project documents updates
Accepted deliverables Expert judgment Final product, service, or 
Business documents result transition
Data analysis
Agreements Final report
Meetings Organizational process 
Procurement 
documentation assets updates
Organizational process 
assets
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) ‐ Sixth 
Edition, Project Management Institute, Inc., 2017, page 121.

413
Lesson 8 Review: Closing Processes
• PMP®/CAPM® Test‐Worthy Topics: Closing Process
• Closing Process Group Overview
• Close Project or Phase
• PMP®/CAPM® Practice Questions
• What are your questions?

414
PMP®/CAPM® Practice Questions: Closing 
Processes
• Open the file PMP and CAPM Practice Questions.
• Using the Table of Contents, navigate (using CTRL+Click) to 
the entry Lesson 8: Closing Processes Questions.
• Answer the odd questions and check your answers. The 
answers follow the questions.
• Time to complete this exercise: 5 minutes

415

You might also like