Professional Documents
Culture Documents
86220080204
86220080204
Abstract: Presence of risks and uncertainties inherent in project development and implementation plays
significant role in poor project performance. Thus, there is a considerable need to have an effective risk
analysis approach in order to assess the impact of different risks on the project objectives. A powerful risk
analysis approach may consider dynamic nature of risks throughout the life cycle of the project, as well as
D
accounting for feedback loops affecting the overall risk impacts. This paper presents a new approach to
construction risk analysis in which these major influences are considered and quantified explicitly. The
proposed methodology is a system dynamics based approach in which different risks may efficiently be
modeled, simulated and quantified in terms of time, cost and quality by the use of the implemented object
SI
oriented simulation methodology. To evaluate the performance of the proposed methodology it has been
employed in a bridge construction project. Due to the space limitations, the modeling and quantification
process for one of the identified risks namely “pressure to crash project duration” is explained in detail.
a failure inherent in all stages of project (i.e., objectives are assessed. Analysis of
planning, bidding, contracting and construction consequences may also aid us to identify the most
stages). Thus, there is a considerable need to important influencing factors on project
incorporate the risk management concepts into performance to take appropriate timely response
construction practice in order to enhance the in facing with them.
Ar
they do not consider such a systemic nature. laboratory and their full impacts can be
considered effectively.
- Traditional risk analysis techniques have not the
capability to quantify the full impact of different
risks, as they do not consider the indirect effects System Dynamics Approach
of risks.
System dynamics is a methodology for studying
- While potential risk events may have major and management of dynamically complex
influences on project cost, time and quality, systems by building and applying simulation
conventional risk analysis techniques can only models [11]. System dynamics (SD) was
assess risk consequences based on their impacts developed in the late 1950s for analysis of
either on the project cost or project time. industrial systems [12]. SD has been successfully
applied to issues, ranging from social, industrial
- Most of the traditional risk management and environmental to project management
techniques deal with the risk analysis process systems.
from a qualitative point of view [10].
System dynamics modeling is useful for
This research presents a new risk analysis managing and simulation of processes with two
approach, which explicitly accounts for all the major characteristics: (1) they involve changes
shortcomings associated with the commonly over time and (2) they allow feedback-the
practiced approaches. The proposed transmission and receipt of information [13].
methodology is a system dynamics (SD) based Much of the art of system dynamics modeling is
approach in which all different risks may discovering and representing the feedback
efficiently be modeled and simulated by the use processes, which along with stock and flow
of the implemented object oriented simulation structures, time delays and nonlinearities,
methodology. With the proposed methodology all determine the dynamics of a system [14]. Stocks
of systemic natures of risks could be considered and flows are used to model the flow of work and
explicitly. resources through a project [15] (Fig1). Stocks
represent stored quantities and characterize the
In the proposed methodology, different risks state of the system and generate the information
could be modeled as feedback loops and their upon which decisions are based. Flows are the
impacts on project objectives can be quantified in rate of increase or decrease in stocks [14].
terms of time, cost and quality efficiently. In Information feedback loops are used to model
comparison to the conventional risk analysis decisions and project management policies [15].
approaches, the SD approach has the capability to SD modeling can be applied adequately to
quantify the full impact of different risks by construction domain problems. The reason is that
considering both direct and indirect effects of Construction projects:
each risk through the feedback loop analysis. The
proposed SD simulation model provides a - Are extremely complex , consisting of multiple
powerful tool, by which the impact of various interdependent components
risks on project objectives can be quantified prior - Are highly dynamic
to their occurrence by creating a learning - Involve multiple feedback processes
<Time>
<equipment perceived <labor perceived <remaining work
productivity> initial work
productivty> considering rework>
Project
change in project Duration
duration
Project
<lack of working area Quality
change in quality
on quality effect>
<fatigue on quality
effect> initial quality
- Involve nonlinear relationships foundation from the model proposed by Ford and
- Involve both hard (quantitative) and soft Sterman [11], [17] which was originally
(qualitative) data. [16] developed for product development projects. So,
some augments have been made in their original
SD is suited to handle these situations more than model, to suit it to the construction projects. After
any other modeling process [15]. preparation of qualitative model of the project,
the interrelationships between different variables
of the identified feedback loops are assessed by
Dynamic Risk Analysis appropriate mathematical functions and the
quantitative model of the project is built.
As a preliminary stage and before starting the risk
analysis process, the construction project process The model structure should successfully capture
must be modeled and simulated, acting as a the complexity of the project management
baseline during the risk analysis phase. The process while being easily comprehendible.
deficiency of conventional project management Therefore, sub models are used in the CPPSM.
techniques and tools arising from the multiple The sub models used in this research are called
feedback processes involved in construction sectors. The CPPSM has the following sectors:
projects and also the highly dynamic nature of
construction process, has motivated some The cost sector, schedule sector, quality sector,
scholars to seek for a complementary tool. resources sector, productivity sector and process
System dynamics approach is a powerful structure sector. The developed construction
alternative enabling us to account for these project process simulation model (CPPSM) is
characteristics. extensively large and due to the space limitation,
two small sectors of the overall model are
Hence, in this research the construction project presented here. Researchers may contact the
process simulation model (CPPSM) is built by senior author for further information. For
system dynamics approach. For this purpose, all descriptive purposes, the schedule and quality
dynamics and feedback loops involved in a sector and cost sector of this model has been
construction project are captured and modeled presented in Figs (2) and (3). As it can be seen in
and qualitative model of the project is built. The these figures, the schedule, quality and cost
proposed model employs the system dynamics sector aid us to determine the project
modeling approach and borrows its conceptual performance measures through the time.
total labor
cost Project Cost
labor cost
<workforce considering <remaining work>
labor unit cost
monetary sources>
<implemented ww to
normal ww>
total equipment
cost
equipment cost
After preparation of the CPPSM, the proposed constitute the feedback loops will be defined by
SD approach methodology is implemented to adequate mathematical functions. Then the
perform risk analysis (Both qualitative and prepared CPPSM will be simulated for a scenario
quantitative). where the risk occurs. Since the risk event act as
a positive loop, negative loop or some external
For this purpose, first the main risks of factors on the CPPSM, the model behavior will
construction project must be identified. Potential be changed from the base run, due to the
risk events affecting the project can be identified existence of risks. The impact of each risk event
by the use of proposed System Dynamics based on different project objectives can be quantified
approach. These risks can be identified by by the comparison of system behavior resulting
influence diagrams as events resulting from from CPPSM with and without risk elements.
positive (or self-reinforcing) loops, negative (or CPPSM simulates the project outcomes in terms
self-correcting) loops or some external factors. of time, cost and quality. Hence, the impact of
In positive loops, the growth of system will be each risk on every project performance criteria
continued due to the positive impacts resulting may be quantified.
from the loop and the problem will be
exacerbated over the time. But in negative loops The achieved results are more reliable than all
the growth will be finally stopped due to the other traditional risk analysis approaches as the
negative impacts resulting from these loops. [14] systemic nature of risks affecting the overall risk
After identification of potential risk events as impacts is accounted for through the recognized
feedback loops, their consequences on project cause and effect feedback loops.
objectives may be analyzed effectively using This approach provides a learning laboratory, in
proposed system dynamics methodology. At the which one can simulate the consequences of
first stage, the impact of each risk event can be different risks on project performance before
analyzed qualitatively. For this purpose the their occurrence in a virtual environment.
probability and impact of each risk event can be
assessed through analyzing different feedback
loops affecting each risk event. Application of proposed Methodology
At the second stage, the risk events will be To evaluate the performance of the proposed
analyzed quantitatively. For this purpose, the methodology, it was employed to quantify the
interrelationships between different variables consequences of identified risks in a bridge
No Risk
2 Inflation
7 Change orders
17 Construction errors due to faulty design but not checked in time by contractor
construction project. There are 19 risks identified duration of highway mega project, it is
for this project based on the interviews being anticipated that there would be a request from the
done be the experts being involved in this project main contractor to crash the preliminary duration
and the other similar projects. These risks have of bridge project to bear some part of the external
been quantified by the proposed SD approach pressure. This risk may cause major negative
(Table1). Due to the space limitations, one of the impacts on project objectives in terms of cost
identified risks namely "pressure to crash project overrun, project delay and poor quality. In this
duration", has been selected for detail section the reason for such a failure is
consideration. investigated by considering and modeling all
feedback loops affecting this risk as shown in
Modeling risk of "Pressure to Crash Project Fig.4. In the next section, these negative effects
Duration" (PCPD)
are simulated, analyzed and quantified by the use
The pressure to crash project duration is one of of proposed SD methodology.
the essential risks inherent in construction
projects. In this project case example, a transition Conceptual diagram and associated feedback
bridge is being constructed on a lake. This project loops affecting the risk of PCPD is presented In
is part of a bigger mega project which is a Fig.4. Three alternative actions are introduced to
highway project across through the lake. Since it crash project duration in order to fulfill it
has been asked by the client to crash the original demanded crashed time.
productivity
project duration
project cost
These actions include use of overtime labor hours, it would have negative side effects on
policy, modification in labor/equipment policy, or productivity and quality due to the labors fatigue.
changing construction method. Depending on the Furthermore, labor fatigue will cause some
trend and habits of parties involved in a project, rework as the fatigue will increase the probability
one or combination of the above actions may be of flaw accordingly. Detailed modeling of over
selected in different projects to crash project time labor policy to gain required workweek and
duration by increasing the project productivity. fatigue impact is presented in Fig.5.
However, each of these actions has some
simultaneous negative side effects on project Modification in Labor/Equipment Policy
productivity which may consequently lead to The second possible action which may be
project delay, cost overrun and poor quality. implemented to crash project duration is to
These side effects have also been incorporated modify the number of labor/equipment assigned
into the model by some arcs, which accounts for to the project. The Detailed model of
fatigue, lack of working area and unfamiliarity modification in labor/equipment policy is
with new technique respectively. presented in Figs.(6) and(7), which allows
determination of the construction
Overtime Labor Policy labor/equipment required to perform a specific
The first possible action which may be activity in the required duration. As it can be
implemented to crash project duration is use of seen, the amount of current labor/equipment is
overtime labor policy. In this case, the value of adjusted to the required labors/equipment by
workweek increase from 44 hours per week hiring new labor/equipment. In this modeling
(relative to a normal workweek) based on the structure, the amount of labor/equipment is
impacts of schedule workweek effect. The increased based on the fraction of original project
schedule workweek effect is defined by the duration to requested crashed duration. However
fraction of original project duration (time if the labor/equipment exceeds a case dependent
remaining to completion) to requested crashed maximum value, it will have negative impacts on
duration (time available to completion). productivity and quality due to lack of working
According to the schedule workweek effect, the area.
required workweek is determined.
Change in Construction Method
However if the workweek hours exceed from 44 The third possible action which may be
<requested crashed
duration> <remained time>
<Time> work week
change in work
week
implemented ww to
normal ww
<single labor
perceived
productivity> <Labor
required labor adjustment time>
<Time>
Construction
<remaining work> Labor
change in labor
<requested crashed
duration> labor maximum
value
fraction of labor to
maximum adequate
workforce
fraction of equipment to
maximum adequate
eqipment
normal
productivity
<fatigue on
perceived
productivity effect>
productivity
Fuzzy representation of
input risk event
Fuzzy representation of
risk consequences
, 0 .5
Where X=range of possible values; and Since there are many uncertainties inherent in the
Ps(x) = membership function taking values from evaluation of probability distribution function of
[0, 1], specifying to what degree x belongs to the the requested crashed duration at earlier stages of
fuzzy set S. A fuzzy number must have a unique a project, fuzzy set theory has been employed to
model value, be convex, and piecewise model these uncertainties.
continues.
As explained before, in this project case example,
In fuzzy sets theory, an D -cut of a fuzzy set is a it is anticipated that there would be a request
set containing members with membership values from the client to crash the preliminary duration
greater than or equal to a specified 0<D O1. In of bridge project. In Fig.10, the anticipated
fact, a fuzzy set can be represented through its requested crashed duration is presented by a
D -cuts which all are crisp sets. In other words, trapezoidal fuzzy number considering the project
D -cuts of a fuzzy set, which are fuzzy subsets governing conditions and past behavior of the
whose elements membership grades are equal to owner. According to this figure, the requested
or greater than 0<D O1, can uniquely represent crashed duration varies between 5 to 10 months.
that fuzzy set [20]. According to this figure, the most likely crashed
duration is between 9 to 10 months which has a
The D-cut level set or D-level cut of A is the set: membership function of 1 and the least likely
crashed duration is anticipated as 5 months which
SD ^x, P ( x)t D x X `
s D >0,1@ has a membership function of 0. A range of other
crashed durations is also possible which receive
Where SD is an ordinary subset of A. different membership functions between 0 to1.
Based on the D-cut concept, an uncertain variable To evaluate the consequences of PCPD risk, five
1 10 7000000 7000000 1 1
1 1
Membership Function
M em bership Function
0.75 0.75
OTP MLEP OTP MLEP
0.5 0.5
0.25 0.25
0 0
6.8 7 7.2 7.4 7.6 7.8 8 8.2 8.4 0.75 0.8 0.85 0.9 0.95 1 1.05
Project Cost (Millions of Dollars) Project Qulaty
Fig.11 Fuzzy number of "PCPD" risk consequences on Fig.12 Fuzzy number of "PCPD" risk consequences on
project cost project quality
D -cut levels of 1, 0.75, 0.5, 0.25 and 0 were used. Consequences of the PCPD risk on cost and
The achieved crisp values of crashed project quality of the project for two different response
duration were determined as (10, 9), 8, 7, 6 and 5 policies is presented in table 2. The consequences
months respectively. of this risk have been analyzed and compared in
the case of implementation of overtime labor
The crisp values of crashed durations will be policy (OTP) and modification in
given as an input to the proposed system labor/equipment policy (MLEP). Since change in
dynamics approach and their consequences on construction method policy had minor
the project objectives are quantified by contribution to crash the duration of this project
simulation of system behavior resulting from case example, it has been ignored.
CPPSM. Solution to the SD simulation model
with defined crisp values associated with Results from OTP and MLEP responses are
different D -cuts, yields the overall impact of the presented in Figs.11 and 12 as fuzzy numbers for
risk on the project. Since the crisp inputs to the project cost and quality respectively. As it can be
SD model depend on the selected D -cut, the seen in Figs.11&12, "PCPD" risk, has resulted in
resulted output is valid for the same value of cost overrun and poor quality in the case of
D -cut. Simulation of consequences for all the implementation of both OTP and MLEP. In this
crisp points, makes the output of the model as a case example, the overtime labor policy (OTP)
fuzzy number. results in more pronounced increase in cost