Document No.

EAT/0011/PDIR
Revision No. 0
Pre- Delivery Inspection Report Date of PDI 02/04/2023

Location of PDI ECORISER


Part Name W clamp Material Grade Nylon 6
Part code E/WC/018 Batch No E/WC/01/0323

Date of Production 31/03/2023 Sample size (Pcs) 10


Customer code EAT/HEMPL Drawing code
S No Name of Inspection Observations
Remarks
Sample No. 1 2 3 4 5 6 7 8 9 10
1 Visual Test OK OK OK OK OK OK OK OK OK OK

2.1 Dimensional Test (D1) ok ok ok ok ok ok ok ok ok ok


2.2 (D2)

2.3 (D3)

2.4 (D4)

2.5 (D5)

3 Functional Test ok ok ok NA NA NA NA NA NA NA

4 Water Ingress Test ok ok ok ok ok ok ok ok ok NA

5 Other Remarks
*Visual test conduct under full white light on flat smooth testing bench .
*Dimensional test conduct with Digital vernier caliper /Digital micrometer /measuring tape.
Note:-
*Functional test conduct as per customer part testing process.
*Water Ingress test conduct with room temperature (35-40 Degree celsius).
Prepared By ANIL KUMAR Quality Checked By KULDEEP JANGID

Date & Sign Date & Sign