HSE-RA-029 Straight and Cut Operation - Rev 0
HSE-RA-029 Straight and Cut Operation - Rev 0
PAGE No 1 of 8
AL SHAFAR GENERAL CONTRACTING LLC. REV 0
DATE 05/01/2017
SAFETY, HEALTH AND ENVIRONMENTAL PROCEDURE
Project Name: Festival Living Stream-02 HSE-RA 029
Job Description: Straight and Cut Operation
Index:
Form 1 Task Analysis Initiation
Form 2 Risk Assessment Process As per Risk Assessment Procedure.
Form 3 Written Safe Work Procedure Result
Compiled by the following team:
NAME DESIGNATION SIGNATURE
Project Manager
Construction Manager
Site Engineer
Safety Officer
Risk Assessment Review 1 Review 2 Review 3 Review 4
Review Date: Date : Date : Date:
AUTHORISATION
Prepared by: Approved by
Signature Date Signature Date
HSE Manager Project Manager
3. Use competent employees only Failure will result in injuries to persons and / Enforce the use of competent persons only
H, S
or property damage
4. Competent supervisor should be appointed for every
activity to monitor the workers.
H, S Work task instruction should be provided for every
Competent supervision Failure will cause injuries to employees and activity.
or property damage
5. Placing Steel on Straight Table Pinch and crush injuries to hands and Ensure proper lifting by competent personnel and correct
S
fingers and feet if dropped use of PPE.
6. Securing steel on straight table Mechanical pinch and crush injuries to S Ensure minimal human interface in mechanical actions,
HSE/QUALITY SYSTEM DOCUMENTATION
DOC No DS/CA006P02/00021
PAGE No 3 of 8
AL SHAFAR GENERAL CONTRACTING LLC. REV 0
DATE 05/01/2017
SAFETY, HEALTH AND ENVIRONMENTAL PROCEDURE
Project Name: Festival Living Stream-02 HSE-RA 029
Job Description: Straight and Cut Operation
Result Classification:
Risk Rating
Critical = 17►15 High = 14►9 Medium = 8►4 Low = 4►0 16
4 Poor Supervision Poor quality of work, chance for Ensure the availability of PE/FM Always
accident /incident or property lost/damage competent supervisor at work
place.
H,S 10 3
Work task instruction should be
provided to the workers prior to
the commencement of activity
5 Placing Steel on Straight Pinch and crush injuries to hands and H 8 Ensure proper lifting by Supervisor Before 3
* RR = Risk Rating
2. PROCEDURE
1. Do pre-use inspection of all equipment to be used and replace or repair faulty items.
2. Use trained competent employees only.
3. Use appropriate Personal Protective Equipment i.e.:
3.1. Hardhat.
3.2. Safety boots.
3.3. Hand gloves
3.4. Overalls.
3.5. Eye protection.
.
Prior to work commencement
1. Must have PPE – safety footwear, gloves, hardhat, goggles, foul weather clothing etc.
2. Must have appropriate tools and equipment in good condition.
3. Must have weatherproof covers for materials and equipment, waste containers, warning tape.
4. Consider risks and hazards in work area. Refer any concerns to supervisor. Are relevant permits in place?
5. Check if it is necessary to secure area adjacent to work. Refer to supervisor if appropriate.
6. Arrange for transport of materials and equipment to site via supervisor.
7. Ensure materials and equipment are secure or removed when site unattended, eg overnight or during breaks.
Hazards
1. Manual handling of materials and equipment – LITE to be considered at all times.
HSE/QUALITY SYSTEM DOCUMENTATION
DOC No DS/CA006P02/00021
PAGE No 8 of 8
AL SHAFAR GENERAL CONTRACTING LLC. REV 0
DATE 05/01/2017
SAFETY, HEALTH AND ENVIRONMENTAL PROCEDURE
Project Name: Festival Living Stream-02 HSE-RA 029
Job Description: Straight and Cut Operation
2. Entanglement.
3. Slips and trips and falls from untidy work area.
4. Impact and cutting
5. Hazards associated with equipment eg. Electric shock, striking of power tools etc.
6. Contact with sharp edges
7. Electrical hazard.
8. Environmental hazard.
Harm
Potential Death, Minor/major cuts and contusions, loss of limbs, fractures, concussion, to fatality, electric shock, environmental damage
Persons in danger
1. Operator
2. Other workers/visitors in vicinity, eg. Passers-by in working area etc.
Control measures
No lone working
1. Ensure minimal human interface in mechanical actions, competent operators and stable work environment. Correct PPE
application.
2. Placing of Proper Machine guards,
3. Emergency stop buttons, competent operators and application of correct PPE.