NO LR 22406
BILL NO 2: ACCESS ROAD AND PARKING
Construction
300 mm base : handpacked stone filling graded and compacted to falls , CM 1521.9 2500
cross falls and slopes. Include filling of voids with quary dust:
compact by rolling to falls and cross falls
Amount
3804750
3,804,750.00
PROJECT: PROPOSED CONSTRUCTION OF ACCESS ROADS TO SERVE SUBDIVISION OF NAIROBI BLOCK 137, PLOT
NO LR 22406
BILL NO 2: ACCESS ROAD AND PARKING
Item Description Unit Qty Rate Amount
KERBS ONLY
Excavate for, provide and place 250 x 125 mm class 25/20 precast
concrete raised or ramped kerbs Including 350x325mm x 100mm
thick class 15/20 concrete bed and haunch, mortar jointed in support to
carriageway and any necessary formwork as directed by the Engineer.
Ditto, but 250 x 125 mm kerb and 125 x 100mm channel, including
450x350mm, ditto.
FOOTPATH
A Excavate to formation level, depth n.e 0.75m average depth 0.5m. CM 402 700 281400
B Ditto, but 1.0m deep in black cotton soils CM 608 900 547200
C Return fill and ram selected excavated materials CM 390 450 175500
D . Cart away from site surplus ecavated materials CM 620 700 434000
E Extra over for excavation in rock CM 10 1500 15000
F Provide, lay and compact approved filling matrials in layers not CM 300 350 105000
exceeding 150mm thick.
G Provide, lay and compact 100mm thick approved murram. SM 1142 878 1002676
H Provide and apply persistent herbicide. SM 1142 300 342600
OPEN STORM WATER DRAIN
A Excavate trench for 450 x 225mm external dimension Pcc IBD not CM 310 700 217000
exceeding 1.0m, including trimming sides to slope and disposal of
surplus material.
B Ditto, but depth not exceeding 1.5m,ditto. CM 774 900 696600
C Extra over for excavation in rock class I. CM 5 900 4500
D Provide, lay and compact 100mm thick approved marram bed and on SM 2182 878 1915796
slopping sides of the ibd to details(50) 5329 B
E Provide, lay and joint 450x225x600mm external dimensions Pcc IBD LM 868 2200 1909600
to detail (50) 5326.
F Extra over Item F for one side slab on each side to detail (50) 5329’B’. LM 30 1000 30000
G Extra over Item F for two sides slabs on each side to detail (50) 5329 LM 322 2000 644000
‘B’.
H Extra over Item F for three sides slabs on each side to detail (50) 5329 LM 516 3000 1548000
‘B’.
J Demolition of existing open drainage channel, (IBDs & side slabs; LM 304 450 136800
including disposal of materials from site.
Culverts
Excavate in trench for 300mm diameter precast concrete pipes, backfill CM 35 700 24500
and compact after laying of pipes and cart away surplus
material.average depth 1.0m
Provide all materials and stone pitch the edge of the storm drain and SM 250 2200 550000
other sloping surfaces as directed by the Engineer.
1718000
TOTAL CARRIED TO COLLECTION PAGE EW/2
COLLECTION
7,102,296.00
FROM PAGE EW/1
1718000
FROM PAGE Above
SUMMARY PAGE
3 FOOTPATHS 2,903,376.00