Analisis Pekerjaan

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 2

HARGA ANALISIS

SPESIFIKASI TANGKI SOLAR (BOTEM CEMBUNG)


Merk : Jaya Tank
Model : Horizontal Cylinder
Kapasitas : 24.000 liter
Dimensi : 2340 x 5490 mm
Material : Mildsteel SS400
T.Plat : 6 mm
C/W : Manhole, Kaki,Tangga,Outlet Nozzle, Inlet Nozzle
Drain Nozzle, Ventilation, Level Indikator

ANALISA 1
Pembongkaran beton bertulang
16.3340 Upah Tukang @ Rp. 89,000.00 = Rp. 1,453,726.00
0.1000 Upah Mandor @ Rp. 115,000.00 = Rp. 11,500.00
Jumlah = Rp. 1,465,226.00

ANALISA 2
Galian tanah (tanah biasa) sedalam 1 m
0.7500 Upah Tukang @ Rp. 89,000.00 = Rp. 66,750.00
0.0750 Upah Mandor @ Rp. 115,000.00 = Rp. 8,625.00
Jumlah = Rp. 75,375.00

ANALISA 3
Urugan tanah kembali
0.5000 Upah Tukang @ Rp. 89,000.00 = Rp. 44,500.00
0.0500 Upah Mandor @ Rp. 115,000.00 = Rp. 5,750.00
Jumlah = Rp. 50,250.00

ANALISA 4
Pengurugan dengan pasir urug
1.3500 M3 Pasir urug @ Rp. 87,000.00 = Rp. 117,450.00
0.3500 Upah Tukang @ Rp. 89,000.00 = Rp. 31,150.00
0.2000 Upah Mandor @ Rp. 115,000.00 = Rp. 23,000.00
Jumlah = Rp. 171,600.00

ANALISA 5
Pasangan batu belah/ kali campuran 1PC : 3PP
1.2000 M3 Batu Kali/Batu Belah (Sungai/Gunung) @ Rp. 265,000.00 = Rp. 318,000.00
6.5000 zak Semen @ Rp. 68,000.00 = Rp. 442,000.00
0.6850 M3 Pasir Pasang @ Rp. 125,000.00 = Rp. 85,625.00
0.0850 Upah Mandor @ Rp. 115,000.00 = Rp. 9,775.00
0.7500 Upah Tukang @ Rp. 100,000.00 = Rp. 75,000.00
0.0750 Upah Kepala Tukang @ Rp. 133,000.00 = Rp. 9,975.00
1.5000 Upah Pekerja @ Rp. 89,000.00 = Rp. 133,500.00
Jumlah = Rp. 1,073,875.00

ANALISA 6
Pasangan batu kosong (Aanstamping)
1.2000 M3 Batu Kali/Batu Belah (Sungai/Gunung) @ Rp. 265,000.00 = Rp. 318,000.00
0.4850 M3 Pasir Urug @ Rp. 87,000.00 = Rp. 42,195.00
0.0390 Upah Mandor @ Rp. 115,000.00 = Rp. 4,485.00
0.7800 Upah Tukang @ Rp. 100,000.00 = Rp. 78,000.00
0.0390 Upah Kepala Tukang @ Rp. 133,000.00 = Rp. 5,187.00
0.3900 Upah Pekerja @ Rp. 89,000.00 = Rp. 34,710.00
Jumlah = Rp. 482,577.00

ANALISA 7
Membuat beton mutu f'c = 14,5 Mpa (K-225)
10.6000 M3 Semen @ Rp. 68,000.00 = Rp. 720,800.00
0.6980 M3 Pasir Beton @ Rp. 125,000.00 = Rp. 87,250.00
1.0470 M3 Kerikil @ Rp. 125,000.00 = Rp. 130,875.00
0.2150 Ltr Air @ Rp. 1,000.00 = Rp. 215.00
0.1230 Upah Mandor @ Rp. 115,000.00 = Rp. 14,145.00
0.3750 Upah Tukang @ Rp. 100,000.00 = Rp. 37,500.00
0.0580 Upah Kepala Tukang @ Rp. 133,000.00 = Rp. 7,714.00
1.6500 Upah Pekerja @ Rp. 89,000.00 = Rp. 146,850.00
Jumlah = Rp. 1,145,349.00

ANALISA 8
Pasangan besi 1 Kg/ M'
1.1667 Kg Besi Beton Polos @ Rp. 14,500.00 = Rp. 16,916.67
0.0167 Kg Kawat Besi @ Rp. 30,000.00 = Rp. 500.00
0.0004 Upah Mandor @ Rp. 115,000.00 = Rp. 51.11
0.0078 Upah Tukang @ Rp. 100,000.00 = Rp. 777.78
0.0008 Upah Kepala Tukang @ Rp. 133,000.00 = Rp. 103.44
0.0078 Upah Pekerja @ Rp. 89,000.00 = Rp. 777.78
Jumlah = Rp. 19,126.78

ANALISA 9
Pasangan bekisting untuk 2x pakai/ M2
0.0450 M3 Kayu Klas III @ Rp. 5,225,000.00 = Rp. 235,125.00
0.3000 Kg Paku Kayu @ Rp. 17,000.00 = Rp. 5,100.00
0.1000 Ltr Minyak Bekisting @ Rp. 50,000.00 = Rp. 5,000.00
0.0260 Upah Mandor @ Rp. 115,000.00 = Rp. 2,990.00
0.2600 Upah Tukang @ Rp. 100,000.00 = Rp. 26,000.00
0.0260 Upah Kepala Tukang @ Rp. 133,000.00 = Rp. 3,458.00
0.5200 Upah Pekerja @ Rp. 89,000.00 = Rp. 26,000.00
Jumlah = Rp. 303,673.00

ANALISA 10
Pekerjaan Sloof (40X50) Besi 8Ø12 begel Ø10-15 / M'
0.5333 M2 Pasangan bekisting untuk 2x pakai/ M2 @ Rp. 303,673.00 = Rp. 161,958.93
14.3748 Kg Pasangan besi 1 Kg/ M' @ Rp. 19,126.78 = Rp. 274,943.61
0.2000 M3 Membuat beton mutu f'c = 14,5 Mpa (K-225) @ Rp. 1,145,349.00 = Rp. 229,069.80
Jumlah = Rp. 665,972.34

ANALISA 11
Pekerjaan (50X50) Besi 8Ø12 begel Ø10-15 / M'
1.2000 M' Pasangan bekisting untuk 2x pakai/ M2 @ Rp. 303,673.00 = Rp. 364,407.60
16.7187 Kg Pasangan besi 1 Kg/ M' @ Rp. 19,126.78 = Rp. 319,774.86
0.2500 M3 Membuat beton mutu f'c = 14,5 Mpa (K-225) @ Rp. 1,145,349.00 = Rp. 286,337.25
Jumlah = Rp. 970,519.71