N DESIGNATION Qté U

------------------------------------------------------------------------------------------- ----------------- --
I FONDATION
I1 BETON DE PROPRIETE ----------------- --
I1-1 Sacs de ciment 33
I1-2 sable 4,37 t
I1-3 gravier 5,56 t
I2 CHAINAGE BAS ----------------- --
I2-1 Sac ciment 24 --
I2-2 Sable 2,65 t
I2-3 Gravier 4 t
I2-4 Acier HA10 3bot-3bar --
I2-5 Acier HA6 2bot-4bar --
I3 MUR DE SOUBASSEMENT ----------------- --
I3-1 Brique plaine 900 --
I3-2 Sacs de ciment 6 --
I1-2 sable 817,89 Kg

II ELEVATION
II1 MUR D’ELEVATION ----------------- --
II1-1 Brique creux 1500 --
II1-2 Sacs de ciment 9 --
II1-3 sable 1,20 t
II2 POTEAU ----------------- --
II2-1 Ciment 13 --
I2-2 Sable 1,44 t
II2-3 Gravier 2,16 t
II2-4 Acier HA10 2bot-4bar --
II2-5 Acier HA6 1bot-14bar --
II3 POUTRE ----------------- --
II3-1 Sac ciment 24 --
II3-2 Sable 2,65 t
II3-3 Gravier 4 T
II3-4 Acier HA10 3bot-3bar --
II3-5 Acier HA6 2bot-4bar --

III DALLAGE ----------------- --


III1-1 Sacs de ciment 141 --
III1-2 sable 18,80 t
III1-3 gravier 28,19 t