This document outlines target dates for electrical meter and street lighting work by contractor Voon Electrical. It provides 8 items with descriptions, original targets, durations, responsible parties, and remarks for TNB meter work; 2 items for TIME network work; and 2 items for street lighting work. The overall work is scheduled to be completed in phases from Q3 2021 through Q2 2023 according to the outlined target dates and durations.
This document outlines target dates for electrical meter and street lighting work by contractor Voon Electrical. It provides 8 items with descriptions, original targets, durations, responsible parties, and remarks for TNB meter work; 2 items for TIME network work; and 2 items for street lighting work. The overall work is scheduled to be completed in phases from Q3 2021 through Q2 2023 according to the outlined target dates and durations.
This document outlines target dates for electrical meter and street lighting work by contractor Voon Electrical. It provides 8 items with descriptions, original targets, durations, responsible parties, and remarks for TNB meter work; 2 items for TIME network work; and 2 items for street lighting work. The overall work is scheduled to be completed in phases from Q3 2021 through Q2 2023 according to the outlined target dates and durations.
TNB Electrical Meter Target Dates (Contractor - Voon Electrical)
No Form Ref. No. Description Original Target Duration Action Remarks
1 PIAT Handover TNB room for Precommissioning Inspection and Testing (PIAT) Q3 2021 1 month PPC/LiZ PIAT defects/comments rectification
2 Contribution Obtain contribution charges amount and pay
charges 3 Equipment Mobilization of equipment and installation 6-18 months LiZ/PPD delivery 4 Bulk meter Obtain the bulk meter deposit amount and pay deposit 5 Energization Energization and installation of bulk meter Q1 2023 At least 1 month before Bomba for T&C 6 Unit meter Obtain the unit meter deposit amount and pay PPD deposit 7 Unit meter Installation of unit meter PPD At least 1 week (depends on meter installation delivery) 8
TIME Target Dates (Contractor - Voon Electrical)
No Form Ref. No. Description Original Target Duration Action Remarks