BUKR1

BOMBA Target Dates (Contractor - Menang Technic)

No Form Ref. No. Description Original Target Duration Action Remarks


1 Bomba inspection Passive & Active inspection April 2023 PPC/LiZ/BEP

IWK Target Dates (Contractor - SYP)

No Form Ref. No. Description Original Target Duration Action Remarks


1 PDC 6 Notice of commencement of sewerage works/septic tank works Q1 2023

2 PDC 7 Notice of intermediate inspection of sewerage works Q1-Q2 2023

3 PDC 8 Notice of final inspection Q2 2023

JKKP Target Dates (Contractor - Shinyou Elevators)

No Form Ref. No. Description Original Target Duration Action Remarks


1 Bomba lift Obtain PMA no. for bomba lift Q3 2022 3 months for 1 nos lift installation 2-4
weeks for 1 nos PMA
2 Passenger lift Obtain PMA no. for passenger lift Q1 2023 1 month for T&C + JKKP inspection

MPK Target Dates (Contractor - )

No Form Ref. No. Description Original Target Duration Action Remarks


1 R&D Road & drainage Q2 2023

2 Landscape Softscape & hardscape Q2 2023