1a. Annexure 1 - WMS
1a. Annexure 1 - WMS
Method
Description of Activity
Statement No
01 Method Statement For Survey & Setting works
02 Method Statement for Clearing and Grubbing
Construction of Embankment, Sub grade and Shoulder
03
with soil
04 Construction of Embankment with Fly ash
Method Statement for Sub grade Construction with Fly
05
ash + Sand
Method Statement For Backfilling Behind Abutment &
06
Around Structures
Method Statement for the Construction of Granular Sub
07
Base
Method Statement for the Construction of Cement
08
Treated Sub-Base/Base
Method Statement for the Construction of Wet Mix
09
Macadam
10 Method Statement for Prime Coat/Tack Coat
Method Statement for the Construction of Dense
11
Bituminous Macadam
Method Statement for the Construction of Bituminous
12
Concrete
13 Method Statement for Mastic Asphalt Construction
Method Statement For Construction of Dry Lean
14
Concrete
Method Statement for Construction of Pavement
15
Quality Concrete
16 Method Statement for Kerb Casting
Method Statement for Form work/ Reinforcement/
17
Concrete
18 Method Statement for Pipe Culvert
19 Method Statement for Box Culvert/Underpass
Revision No Page No
1
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I
Revision No Page No
2
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I
Revision
Date WMS No: Prepared By Reviewed By Approved By
No:
ARTL/QAP/WMS/
18.01.20
R0 01
22
Revision No Page No
3
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I
1.0 Purpose
The purpose of the procedure is to describe and define the methods adopted
in setting out for road works.
2.0 Scope
This procedure applies for setting out data of Center line to grades as per
contract drawings for survey of road works undertaken by the company.
3.0 Definition
LS : Longitudinal Section.
CS : Cross Section.
The Engineering method of transferring the plan & elevation from drawings to
the field with a firm control of alignment.
Reference point of known elevation established between the GTS bench marks
at closer intervals.
Revision No Page No
4
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I
3.6 Grades
3.7 Gridlines
Imaginary lines running Horizontal & Vertical with each line having a
designated northing and easting.
4.0 Responsibility
The Senior Surveyor shall be the Key Personnel, responsible for the Setting out
work.
5.0 Procedure
5.1 Preparation
5.1.1 The setting out works shall be carried out as per the approved drawing.
5.1.3 The working or Temporary Bench Mark (TBM) will be established at every
250 mtr interval and also at or near all drainage structures and
underpasses. The working benchmark / levels will be approved by the
Engineer. Checks will be made on these benchmarks as and when
required and adjusted if any, got approved with the Engineer and
recorded. An up-to-date record of all TBMs including approved
adjustment, if any, will be maintained and a copy will be submitted to the
Engineer.
Revision No Page No
5
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I
Instruments appropriate for the intended setting out task and according to the
accuracy requirements will be used. The instruments will be calibrated
periodically and will be kept in good working condition. The following
instruments will be used for setting out survey works.
Tripods
5.3.1 With reference to the known BM (as at Clause-5.1.3) values, the centerline
of the proposed road will be located and marked at feasible locations
along the highway using a total station.
5.3.2 All the HIP’s & VIP’s for Horizontal & vertical curves along the alignment
will be located and nailed at site in a similar manner (as at Clause: 5.3.1).
As per the drawing coordinates, the traversing will be closed at BM and
error, if any will be linearly distributed.
5.3.3 Pegging will be done at toe lines at every 27.50 mtr longitudinal intervals
of the embankment and in cases of no embankment, 2mtr away from the
edge of the proposed road.
5.3.4 The alignment as pegged will be checked jointly with respect to the
drawing and shall be approved by the Engineer.
5.4.1 The existing ground levels will be recorded jointly on a level book along
the horizontal sectioning at 10mtr interval for straight as well as curve
portions and along the cross section as per the requirements depending
upon the profile of the terrains with reference to the known BM
elevation. (As at Clause: 5.1.2 & 5.1.3)
Revision No Page No
6
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I
5.4.2 Upon approval of the alignment (as at Clause: 5.3.4) and existing ground
level by the Engineer, road works will commence for construction of
pavement layers.
Revision No Page No
7
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I
Revision
Date WMS No: Prepared By Reviewed By Approved By
No:
ARTL/QAP/WMS/
18.01.20
R0 2
22
Revision No Page No
8
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I
1.0 Purpose
This Method Statement provides detail of procedure adopted for the clearing
and grubbing operation.
2.0 Scope
This work will consist of cutting, removing and disposing of all materials such
as trees, bushes, shrubs, stumps, roots, grasses, woods, top organic soil not
exceeding 150mm in thickness, rubbish etc, which in the opinion of the
Engineer are unsuitable. Clearing and grubbing will be performed in advance of
earthwork operation and in accordance with the requirements of the
specification.
3.0 Responsibility
Section In charge will be responsible for quality control of the section for the C
& G operation. He will liaise with the Engineer. Further he will be assisted by
field Engineers, Surveyors, Supervisors and Lab Technicians.
4.0 Equipment
Tipper
Wheel loader
Excavator
Grader
5.0 Procedure
Revision No Page No
9
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I
recorded jointly with Engineer before starting the clearing and grubbing
operation.
All trees, stumps etc. falling within excavation and fill line, will be cut to
such depth below ground level that, in no case these fall within 500 mm of the
sub grade.
All branches of tree, extending above the road way will be trimmed as
directed by the Engineer.
All excavation below the general ground level arising out of the removal
of trees, stumps etc will be filled with suitable material and compacted
thoroughly.
Revision No Page No
10
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I
Revision No Page No
11
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I
Revision
Date WMS No: Prepared By Reviewed By Approved By
No:
ARTL/QAP/WMS/
18.01.20
R0 03
22
Revision No Page No
12
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I
1.0 Purpose
2.0 Scope
3.0 Equipment
Dumper / trucks
Grader
Vibratory Roller
Water tanker
Revision No Page No
13
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I
4.0 Procedure
4.1.1 Material
The materials used in the works shall be soil, moorum, gravel, a mixture of
these or any other material approved by the Engineer as per requirements of
Clause 305.2.1 of MORTH Specifications (Fifth revision).
The Borrow Materials shall be sourced from nearby areas. The details shall be
submitted to the Engineer for approval. Samples shall be collected from these
Borrow areas and tested jointly to check suitability. The embankment material
shall be incorporated in the works only after approval is obtained from the
Engineer.
All excavations will be carried out in conformity with the directions laid and in
a manner approved by the Engineer. The suitable materials obtained from
excavation will be satisfactorily utilized.
The Centerline of the road will be set out by means of Total Station. The
reference points for this will be as per the project drawings.
The working Bench Marks will be established from the approved Reference
Bench Marks at the rate of four per Km and also at or near all drainage
structures and got approved from the Engineer.
The reference points will be so located that these will not be disturbed during
construction.
Reference pegs, marking the limits of embankment shall be fixed on both sides
of the slopes. These pegs are meant as guides and will be about 2.0m away
from the toe of the embankment.
Atterberg limits, MDD, OMC, and in-situ dry density (FDD) of the material at
ground level will be determined. Any unsuitable material will be removed and
replaced with suitable material. Suitable / approved earth will be laid in layers
Revision No Page No
14
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I
Once the compaction of Original Ground Level is completed after Clearing and
Grubbing operation, joint level with the Engineer will be recorded for the
purpose of measurement and preparation of Cross Section and Longitudinal
Section.
Revision No Page No
15
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I
than 75mm that the same will not present any difficulty as regards the
placement of fill material and its compaction to the requirements of these
Specifications. The maximum particle size in such cases, however, shall not be
more than two-thirds of the compacted layer thickness.
f) The natural moisture content of soil will be found out and the balance
amount of water to be added to the soil will calculated as OMC minus NMC, so
as to maintain moisture content from 2 % below to 1% above the OMC at the
time of compaction.
Quality control tests shall be done as per Sl. no. 1 of Quality Control Tests and
Acceptance Criteria
5.3 The size of the coarse material in the mixture of earth shall ordinarily
not exceed 50mm. However, the Engineer may at his discretion permit the use
of material coarser than 50mm that the same will not present any difficulty as
regards the placement of fill material and its compaction to the requirements
Revision No Page No
16
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I
5.4 If the degree of compaction does not conform to the requirement, the
area will be re-compacted at OMC until the required density is achieved.
6.1 Approved material for Shoulder Constructions will be laid as per the
drawing and specification prior or along with the laying of adjacent layer. The
construction sequence, Quality Control etc. will essentially be the same as for
Sub grade Construction. The same will be watered, leveled, graded and
compacted to the required density as per the drawing and specification.
Quality control tests shall be done as per Sl. no. 1 of Quality Control Tests and
Acceptance Criteria
Revision No Page No
17
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I
Revision
Date WMS No: Prepared By Reviewed By Approved By
No:
ARTL/QAP/WMS/
18.01.20
R0 04
22
Revision No Page No
18
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I
1.0 Purpose
2.0 Scope
3.0 Equipment
Dumper / trucks
Grader
Vibratory Roller
Water tanker
Plate Compactor
4.0 Responsibility
Section in Charge will be responsible for execution and quality control of the
section for the construction of Embankment with fly ash. Further he will be
assisted by Field Engineers, Surveyors, Supervisors and Lab Technicians.
5.0 Procedure
After the site has been cleared to Clause 201, the limits of embankment should
be set out true to lines, curves, slopes, grades and sections as shown in
approved drawing and Clause 301.3.1of MORTH Specification (Fifth revision).
The limits of toe line will be marked by means of lime powder or pegs to
facilitate the construction activity.
Revision No Page No
19
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I
5.3 Where ever possible the original ground after excavation should be
scarified, mixed with water to achieve OMC, leveled and compacted by 8 – 10
T capacity vibratory earth compactor. Ground supporting the embankment will
be prepared and compacted to specified density of minimum 97 % of Lab MDD
to meet the requirement of IRC SP:58-2001, Clause 4.5.1.
The fly ash will be dozed, graded; water will be sprinkled ± 2% of the OMC on
the entire area uniformly. Then it will be compacted by means of 8-10-ton
vibratory roller with adequate passes of the roller so as to achieve 95%
compaction as per MORTH Specification (Fifth revision) clause 305 & Table
300-1 & 300-2 as well as Cl. 4.7.5 of IRC SP 58-2001.
Quality control tests shall be done as per Sl. no. 1 of Quality Control Tests and
Acceptance Criteria
Revision No Page No
20
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I
Revision
Date WMS No: Prepared By Reviewed By Approved By
No:
ARTL/QAP/WMS/
18.01.20
R0 05
22
Revision No Page No
21
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I
Method Statement for Sub grade Construction with Fly ash + Sand
1.0 Purpose
The purpose of this Method Statement for Construction of Sub-grade with fly
ash modified soil is to provide details of Construction Method Statement.
2.0 Scope
3.0 Equipment
Dumper / trucks
Grader
Vibratory Roller
Water tanker.
Plate Compactor
4.0 Responsibility
5.0 Procedure
Revision No Page No
22
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I
After the Site has been cleared as per MORTH Clause 201, the limits of
excavations shall be set out true to lines, curves, slopes, grades and sections as
shown on the drawings or as directed by the Engineer and as per established
Bench Marks / Co-ordinates.
Quality control tests shall be done as per Sl. no. 1 of Quality Control Tests and
Acceptance Criteria
Revision No Page No
23
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I
Revision
Date WMS No: Prepared By Reviewed By Approved By
No:
ARTL/QAP/WMS/
18.01.20
R0 06
22
Revision No Page No
24
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I
1.0 Purpose
2.0 Scope
This work will consist of backfilling behind abutment of bridges and around
structures like foundations, underpass, box culvert and other similar structures
in accordance with the requirements of these specifications (MORTH clause
no. 305.4.4)and lines & dimensions shown in the drawing or as indicated by
the Engineer.
3.0 Material
4.0 Responsibility
Section In charge will be responsible for quality control of the section for the
backfilling work. He will liaise with Concessionaire Engineer In Charge. Further
he will be assisted by field Engineers, Surveyors, Supervisors and lab
technicians.
5.0 Equipment
Dumper / trucks
Grader
Water tanker
Plate Compactor
Revision No Page No
25
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I
6.0 Procedure
Filling behind abutments and wing walls for all structures without weep-hole,
will be done with approved filling material. The fill material will be deposited in
loose thickness and compacted after necessary watering up to a thickness of
250mm, until the required compaction of 95% & 97% of MDD at OMC achieved,
for embankment & sub grade respectively. Filling will be carried out in equal
layers on each side of the structures to avoid displacement and unequal
pressure.
Where provision of any filter media is specified behind abutment (where weep-
hole exists), filter media as designed will be laid and compacted after
necessary watering up to a compacted thickness of 250mm until 95% & 97% of
MDD at OMC achieved, for embankment & sub grade respectively. The material
used for filter media will conform to the requirement for filter medium spelt
out in clause 2504.2 / 309.3.2.
Revision No Page No
26
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I
Quality control tests shall be done as per Sl. no. 1 of Quality Control Tests and
Acceptance Criteria
Revision No Page No
27
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I
Revision
Date WMS No: Prepared By Reviewed By Approved By
No:
ARTL/QAP/WMS/
18.01.20
R0 07
22
Revision No Page No
28
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I
1.0 Purpose
This section provides details of Method Statement adopted for the granular
sub-base construction activity.
2.0 Scope
3.0 Responsibility
Section In charge will be responsible for quality control of the section for the
construction of Sub-base. He will liaise with the Engineer In charge.
Further he will be assisted by the field engineers, surveyors, supervisors and
lab technicians.
4.0 Procedure
Before laying of sub-base over already finished sub-grade all the vegetation
shall be removed, if any. Light sprinkling of water shall be done as required and
rolled with two passes of 8 to 10 ton vibratory roller.The materials of GSB layer
shall be Grading V & VI as per Table 400-1 of MORTH. The material shall be
brought at site first and dumped in heap in such a way that after spreading
and compaction the required thickness is obtained.
The spreading shall be done with the help of motor grader of required
capacity. Rolling shall start immediately after spreading with the help of
vibratory roller of 8 to 10 ton static weight. Rolling shall commence at the
lower edge and proceed towards the upper edge longitudinally for portions
having unidirectional cross fall. Each pass of roller shall uniformly overlap not
less than one third of track made in the preceding pass. The grade and cross
fall shall be checked and any high spots or depressions, which become
apparent will be corrected by removing or adding fresh material. The speed of
roller shall not exceed 5km/hr. Rolling shall be continued until the density
achieved is at least 98% of the maximum dry density.
Revision No Page No
29
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I
Quality control tests shall be done as per Sl. no. 3 of Quality Control Tests and
Acceptance Criteria
Revision No Page No
30
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I
Revision
Date WMS No: Prepared By Reviewed By Approved By
No:
ARTL/QAP/WMS/
18.01.20
R0 08
22
Revision No Page No
31
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I
1.0 Purpose
2.0 Scope
This work shall consist of mixing, laying and compacting of aggregates mixed
with cement or cement-fly ash in a mixing plant as a sub-base/base course on
prepared sub grade/sub-base in accordance with the requirements of the
Specifications and in conformity with the lines, grades and cross-sections
shown on the drawings or as directed by the Engineer.
3.0 Equipment
Mixing Plant
Dumpers/Tippers
Water Tanker
Paver
Roller
4.0 Responsibility
Section In charge will be responsible for quality control of the section for the
construction CTSB/CTB. He will liaise with the Concessionaire Engineer In
charge. Further he will be assisted by field engineers, surveyors, supervisors
and lab technicians
5.0 Procedure
Material for the CTSB/CTB shall be prepared as per mix design in mixing plant.
Moisture shall be maintained within tolerance range as determined by Mix
Revision No Page No
32
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I
Design. The mix shall be spread by a paver finisher in full width of pavement as
per approved drawing. In exceptional cases where it is not possible for the
paver to be utilized, mechanical means like motor grader may be used with the
prior approval of the Engineer. Maximum care shall be taken to spread the
material uniformly. The compaction shall be carried out as per clause 403.3.5
with the help of vibratory roller of 8T to 10 T static weight. Rolling shall be
continued until the density achieved is at least 98 percent of maximum dry
density.
Quality control tests shall be done as per Sl. no. 4 of Quality Control Tests and
Acceptance Criteria
Revision No Page No
33
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I
Revision
Date WMS No: Prepared By Reviewed By Approved By
No:
ARTL/QAP/WMS/
18.01.20
R0 09
22
Revision No Page No
34
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I
1.0 Purpose
This provides details of Method Statement adopted for the Wet Mix Macadam
laying and compaction.
2.0 Scope
3.0 Responsibility
Section In charge will be responsible for quality control of the section for the
construction of WMM. He will liaise with the Concessionaire Engineer In
charge. Further he will be assisted by field engineers, surveyors, supervisors
and lab technicians.
4.0 Procedure
Construction operation shall be as per Clause 406.3. Before laying Wet Mix
Macadam (WMM) on already prepared GSB/CTB, the shoulder shall be
constructed first in order to provide confinement. Material for the wet mix
macadam shall be prepared as per mix design in the wet mix plant. Moisture
shall be maintained within tolerance range as determined by Mix Design. The
mix shall be spread by a paver finisher in full width of a pavement including
hard shoulder as per Clause 406.3.4.In exceptional cases where it is not
possible for the paver to be utilized, mechanical means like motor grader may
be used with the prior approval of the Engineer. Maximum care shall be taken
to spread the material uniformly. The compaction shall be carried out as per
clause 406.3.5 with the help of vibratory roller of 8T to10 T static weight.
Rolling shall be continued until the density achieved is at least 98 percent of
maximum dry density for material.
Quality control tests shall be done as per Sl. no. 5 of Quality Control Tests and
Acceptance Criteria
Revision No Page No
35
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I
Revision No Page No
36
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I
Revision
Date WMS No: Prepared By Reviewed By Approved By
No:
ARTL/QAP/WMS/
18.01.20
R0 10
22
Revision No Page No
37
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I
1.0 Purpose
The Method Statement provides detail of the procedure adopted for the
application of Tack Coat and Prime Coat. A prime coat is an application of low
viscosity bituminous binder to an absorbent non-bituminous surface. A tack
coat is a light application of bituminous binder to a bituminous or concrete
surface.
2.0 Scope
Preparation of surface
3.0 Responsibility
4.0 Equipment
The following construction machinery will be used for the execution of the
work.
Revision No Page No
38
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I
The full-scale application trials will be carried out on previously prepared base
surface using the plant and methods proposed.
The trials will be carried out with the agreement, and under supervision of the
Engineer.
Works associated with Prime coat/Tack coat will not commence until trial
sections have been approved. No variation in the spray or spread rates or type,
size, source or supply of materials will be made without the prior agreement of
the Engineer who shall have the authority to instruct further trial sections if
such variations should become necessary.
The trials will be carried out to demonstrate the suitability of the plant,
Equipment and work procedures and to confirm that the other specified
requirements of the Prime coat/Tack coat can be achieved.
The trial area shall be at least 50m long, and to the full construction width. It
may form part of the permanent works. The trial of Prime coat/Tack coat shall
be undertaken ahead of the proposed work to commence full-scale work.
The temperature of the Prime coat/Tack coat materials at the time of spraying.
The site trial shall be deemed to be successful if all specified sets of results
meet the specified requirements for the material. The above data as recorded
in the site trial shall become the agreed basis on which the particular material
shall be provided and processed to achieve the specified requirements.
6.0 Procedure
Revision No Page No
39
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I
6.1.1 Immediately before spraying, all loose material and foreign matter will
be removed by thorough brushing with mechanical brooms and/or washing or
other accepTable methods. All hardened mud or other foreign matter will be
loosened by scraping before sweeping. The debris shall be deposited well
clear of the surface to be sprayed. It shall be shaped to the specified grades
and section.
6.2.1 As soon as the surface preparation as specified in section 6.1.1 has been
carried out to the approval of the Engineer, the primer or tack coat will be
sprayed at the specified rate. The quantity of binder used shall give complete
coverage of the surface with a light trace of run-off in places. The edge of the
area to be sprayed will be marked out with a line of string or wire pegged down
at intervals not exceeding 15m on straights or 7.5 m on curves.
Revision No Page No
40
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I
7.2 All loose material on the sprayed surface, including any blinding
material, will be removed before any further bituminous binder is sprayed.
8.1 The work will not be carried out in adverse weather conditions or when
prescribed by the Engineer.
Quality control tests shall be done as per Sl. no. 6.0 of Quality Control Tests
and Acceptance Criteria
Revision No Page No
41
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I
Revision
Date WMS No: Prepared By Reviewed By Approved By
No:
ARTL/QAP/WMS/
18.01.20
R0 11
22
Revision No Page No
42
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I
1.0 Purpose
This work shall consist of laying and compacting well graded material on
prepared wet mix macadam in accordance with the requirements of these
specifications. The material shall be laid in single layer/double layer as shown
in cross section drawing or as directed by the Engineer.
2.0 Scope
The Scope of this Method Statement shall cover the following activities:
(iii) Laying of Dense Bituminous Macadam with sensor paver, compacting and
testing as per Technical Specifications and approved Inspection and Test
Plans.
3.0 Responsibility
Section In charge will be responsible for execution and Material Engineer for
overall quality of materials for the section. Both will liaise with Engineer and
Employer related to their job. Further, Site Engineer, Surveyors and Supervisors
Lab Technicians will assist.
4.0 Equipment
The construction machinery used for the execution of the work is as follows:
Sensor Paver
Revision No Page No
43
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I
Pneumatic Blower
Water tanker
(a) The initial or breakdown rolling shall be done with 8-10 tons smooth
wheeled tandem Rollers.
(b) The intermediate rolling shall be done with 8-10 ton dead weight
vibratory roller or with a Pneumatic tyre roller of 12-15 ton weight, with tyre
Pressure of at least 5.6 kg/cm2.
(c) Finishing rolling shall be done with smooth wheeled tandem Rollers.
The coarse aggregates to be used in DBM shall be crushed rock, or other hard
material retained on the 2.36mm sieve. Use of RAP shall be in accordance with
MORTH section 519. The material should be hard, sound, durable and un
weathered. It shall contain no deleterious constituents such as organic matter
clay and decomposed rock. The Fine aggregate shall be crushed or naturally
occurring mineral material, or a combination of the two, passing the 2.36mm
sieve and retained on 75micron sieve. It shall be free from dust organic or
other deleterious matter. The bitumen/final binder shall be paving bitumen of
VG40/VG30 grade conforming to IS:73. The Filler shall be finely divided mineral
matter such as rock dust, hydrated lime or cement as approved by the
Engineer and conform to Table 500-9 of MORTH specifications. The grading
shall confirm to grading-2 given in Table 500-10.
The material to be used in the Dense Graded Bituminous material shall meet
the other physical requirements as per MORTH Cl: 505.3.1.
Revision No Page No
44
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I
Laying trials shall be carried out at a trial stretch to demonstrate the laying
and compaction of the proposed mix in accordance with clause 501.
7.0 Procedure
A Prime coat shall be applied in accordance with the provisions of Clause 502,
if DBM is to be laid on other than a bitumen bound layer.
The material to be used for DBM shall be as per approved Job mix formula,
conforming to MORTH Table 500-10. The material shall be prepared in a Hot
Mix Plant of adequate capacity. Appropriate mixing temperature shall be
maintained as per Table 500-2 of MORTH specifications. The bituminous
material shall be transported in clean and covered tippers to the place of
laying.
The surface finish of DBM Layer shall be checked and all the high and low
spots remedied by removing or adding DBM Material as may be required. The
surface finish shall conform to the requirements of Clause 902.
Revision No Page No
45
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I
7.5 Compaction
Bituminous materials shall be laid and compacted in layers, which enable the
specified thickness, surface level, regularity requirements and compaction to
be achieved.
In portions with super-elevated and uni-directional camber, after the edge has
been rolled, the roller shall progress from the lower to the upper edge. Rollers
should move at a speed of not more than 5 km per hour. The roller shall not be
permitted to stand on pavement, which has not been fully compacted, and
necessary precautions shall be taken to prevent dropping of oil, grease, petrol
Revision No Page No
46
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I
or other foreign matter on the pavement either when the rollers are operating
or standing. The wheels of rollers shall be kept moist with water, and the spray
system provided with the machine shall be in good working order, to prevent
the mixture from adhering to the wheels. Only sufficient moisture to prevent
adhesion between the wheels of rollers and the mixture should be used.
Surplus water shall not be allowed to stand on the partially compacted
pavement. Rolling pattern as determined from trials will be adopted for the full
works.
The work will not be carried out in adverse weather conditions or when
prescribed by the Engineer. Bituminous material will not be applied to wet or
frozen surfaces or when weather conditions otherwise prevent the proper
handling and finishing of the mixture. The bituminous material will be placed
when both the ambient temperatures and road surface temperatures are
greater than 10°C with rising trend.
The newly laid surface shall not be open to traffic for at least 24 hrs after
laying and completion of compaction, without the express approval of
Engineer in writing.
Quality control tests shall be done as per Sl. No 7 of Quality Control Tests and
Acceptance Criteria
Revision No Page No
47
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I
Revision
Date WMS No: Prepared By Reviewed By Approved By
No:
ARTL/QAP/WMS/
18.01.20
R0 12
22
Revision No Page No
48
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I
1.0 Purpose
2.0 Scope
The Scope of the Method Statement covers the laying and compacting well-
graded BC material on prepared DBM/existing road surface as per the
approved drawings. It involves the following:
(iii) Site trial will be performed as per MORTH Section 900 before laying of
Bituminous Concrete at site with sensor paver, compacting and testing as per
Technical Specifications and approved QAP.
3.0 Responsibility
4.0 Equipment
The construction machinery used for the execution of the work is as follows:
Revision No Page No
49
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I
Sensor Paver,
Pneumatic Blower
Water tanker
The material to be used in the Bituminous Concrete material shall meet the
other physical requirements as per MORTH Cl:.507.2
6.0 Procedure
The full-scale laying and compaction trials are carried out on BC materials for
the permanent works using the plant and methods proposed. The trials are
Revision No Page No
50
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I
carried out under supervision of the Engineer. The trials are carried out to
demonstrate the suitability of the plant, Equipment and work procedures to
provide and compact the material to the specified proportions, density and
voids content and to confirm that the other specified requirements of the
completed asphalt pavement can be achieved. The trial of pavement layer is
undertaken ahead of the proposed work to commence full-scale work. The
data retrieved from the trials i.e., composition, grading, bitumen content,
Marshall Parameters, rolling pattern and other test results which will be
submitted separately.
The mixing plant will be of the batch-mix type and shall be capable of
regulating the composition of the mixture to within the tolerances specified by
Clause 507.3.4, Table 500-18 of MORTH.
Revision No Page No
51
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I
Immediately after receiving the transported materials from hot mix plant to the
site it will be spread on prepared and approved surface, the mixture will be
spread to line and level by the Sensor paver without segregation or dragging.
The temperature of mix at the time of lying will be as per Table 500-2 of
MORTH. The mixture will be placed in full width of the pavement. The
compacted thickness of any layer shall be as per specification. The paver shall
be capable of operating at forward speeds consistent with uniform and
continuous laying of the mixture.
Paver shall be equipped with accurate screed controls for maintaining the
screed at the specified longitudinal grade and transverse slope. The controls
shall be capable of maintaining the screed at the specified transverse slope.
Automatic controls in the paver shall be backed by manual controls that can
be optionally activated.
Revision No Page No
52
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I
Initial static rolling with a steel tandem roller as per MORTH Specification,
Section-500, Clause 501.6. The rollers shall be operated with uniform speed
not exceeding 5 km/hr.
Rolling shall normally commence from the outer edge and proceed
longitudinally parallel to the centerline, each pass overlapping the previous
pass by one half of the roller width. On super elevated curves, rolling shall
begin at the low side and progress to the high side. Where laying is carried out
care shall be taken to prevent the entrapment of water.
Intermediate vibratory rolling with steel tandem roller shall follow immediately
upon initial rolling.
Intermediate rolling will be done with pneumatic tyre roller having 0.56 MPA
tyre pressure. In case of failure of pneumatic tyre roller at site during operation
any one type of roller shall substitute the other for the day’s work to obtain the
specified requirement. Final static rolling with a steel wheel roller shall be used
to eliminate marks from previous rolling.
The roller wheels and drums shall be kept lightly moistened with water to
prevent adhesion of the mixture to the rollers.
All rolling operations shall be completed in all respects before the temperature
of the mix falls below 100°C.
Rolling pattern as determined from trials is adopted for the full works
Any mixture that becomes loose or broken, mixed with dirt or foreign matter,
or defective will be removed, and it will be replaced with fresh hot mixture and
compacted.
Revision No Page No
53
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I
The edges of the course will be rolled concurrently with or immediately after
the finishing. In rolling the edges, roller wheels will extend 50 mm to 100 mm
beyond the edge.
Any fresh mixture on the existing work shall be removed carefully sweeping it
back on to un-compacted work, so as to avoid formation of irregularities at the
previous face.
The work will not be carried out in adverse weather conditions or when
prescribed by the Engineer.
Quality control tests shall be done as per Sl. No 7 of Quality Control Tests and
Acceptance Criteria
Revision No Page No
54
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I
Revision
Date WMS No: Prepared By Reviewed By Approved By
No:
ARTL/QAP/WMS/
18.01.20
R0 13
22
Revision No Page No
55
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I
1.0 Purpose
This work shall consist of constructing a single layer of mastic asphalt wearing
course for road pavements or as water proofing layer for bridge decks under
the wearing course.
2.0 Material
2.1 Bitumen :Subject to the approval of the Engineer, the binder shall be a
paving/ Industrial grade bitumen meeting the requirements given in Table 500-
39 of MORTH
2.3 Fine aggregate : The fine aggregates shall be the fraction passing
the 2.36 mm and retained on 0.075 mm sieve consisting of crusher run
screening, natural sand or a mixture of both
2.4 Filler: Lime stone powder passing through 75 micron I.S. sieve having
minimum Calcium Carbonate (CaCo3) content 80% by weight.
3.0 Responsibility
4.0 Procedure
4.1 Weather limitation: Minimum air and surface temperature shall be 100C.
Laying will be suspended during rain, foggy weather or adverse situations.
4.2 Preparation of the Base: In case of a cement concrete base, the surface
shall be thoroughly swept and scraped clean and free of dust and other
deleterious matter. Under no circumstances bitumen mastic shall be spread on
a base containing a binder which will soften under high application
temperatures. If any such spots or area are there, the same shall be cut out
and repaired before the bitumen mastic is laid.
Revision No Page No
56
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I
4.3 Tack Coat: A tack coat as per MORTH Specification Clause 503 shall be
applied on the base or as directed by the Engineer.
4.6 Joints: It shall be ensured that all construction joints are properly and
truly made. These joints shall be made by warming existing mastic asphalt by
the application of an excess quantity of the hot mastic asphalt mix which
afterwards shall be trimmed off to make it flush with surfaces on either side.
Quality control tests shall be done as per Sl. No 8 of Quality Control Tests and
Acceptance Criteria
Revision No Page No
57
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I
Revision
Date WMS No: Prepared By Reviewed By Approved By
No:
ARTL/QAP/WMS/
18.01.20
R0 14
22
Revision No Page No
58
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I
1.0 Purpose
2.0 Materials
These shall consist of Ordinary Portland Cement from approved source The
minimum cement content shall be 150 kg/cu.m of concrete. In case flyash is
blended at site as part replacement of cement, the quantity of flyash shall not
be more than 20 percent by weight of cementitious material and the content
of OPC shall not be less than 120 kg/cu.m.
These shall be in conformation with IS 383. The coarse aggregate shall be dry,
clean, hard, and durable of crushed stone. The maximum size of the coarse
aggregate shall be 26.5 mm, and aggregate gradation shall comply with Table
600-1.
The fine aggregates shall consist of clean natural sand or crushed stone sand
or a combination of the two and shall conform to IS 383.
The blended aggregate of coarse and fine aggregate shall confirm to the
following gradation as per Table 600-1 of MORTH
Revision No Page No
59
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I
2.36 17-42
0.600 8-22
0.300 7-17
0.150 2-12
0.075 0-10
2.4 Water
Water used for mixing and curing of concrete shall meet the requirements of
IS 456.
3.0 Procedure
3.1 Mix
The mix shall be proportioned with a maximum aggregate cement ratio of 15:1
and with minimum cement content of 150kG/cum. However, the proportions of
aggregate to cement can be increased based on the trial mix and performance
during the trail stretch. Trial mixes with moisture contents of 5.0, 5.5, 6.0, 6.5
and 7.0 %shall be made using the above stated cement and blended
aggregates. Optimum moisture and density shall be obtained by making cubes.
These cubes shall be made in three layers, each layer being compacted with
electronic/pneumatic vibratory hammer of 300-400N downward force. After
the determination of moisture a set of 6 cubes shall be cast for determination
of compressive strength on 3 and 7 days. The average compressive strength of
each consecutive group of 5 cubes shall not be less than 10 MPa at 7 days. In
addition, the minimum compressive strength of any individual cube shall not
be less than 7.5 MPa at 7 days. If the required compressive strength is not
achieved, increasing the cement shall make trials and the above stated
procedure shall be repeated to achieve the required strength. Before
production of concrete, natural moisture in the aggregate shall be determined
and adjusted on day-to-day basis.
3.2 Mixing
Revision No Page No
60
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I
A trial stretch shall be made to the required width. The in-situ density of the
freshly laid concrete shall be determined by sand replacement method by
making 3 density holes at equal distances that diagonally bisects the trial
length, these shall not be made in the strip of 500mm from the edges. The
average of these shall be considered as 100%, and with this the field density of
the regular work shall be compared. The hardened concrete may be cut for 3m
width in the trial length and reversed to check the bottom surface for any
segregation or honey-combing, if found necessary adjustments shall be made
in the mix design.
3.5 Compaction
The compaction shall commence as soon as the concrete laid and leveled to
the full width till there is no further movement under the roller and the surface
is closed. In addition to the number of passes required for compaction, there
shall be a pass without vibration as preliminary pass and another at the end as
final pass. The minimum dry density obtained shall be 97% of that achieved in
trial length, and at a distance of 500mm from edge it shall be 95% of that
achieved in the trial length. The final surface shall be inspected immediately,
and all loose, segregated or defective areas shall be corrected by using fresh
lean concrete. Honeycombed areas, any level/ thickness deficiency and surface
irregularities shall be corrected by concrete with 10mm and down aggregates.
Special care and attention shall be exercised during compaction near joints,
kerb, channels, side forms, around gullies and manholes.
Revision No Page No
61
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I
vertical face where correct thickness of compacted layer has obtained. Curing
shall be done by covering the surface with gunny bags/ hessian cloth, which
shall be kept continuously moist for 7days by sprinkling water.
Quality control tests shall be done as per Sl. No 9 of Quality Control Tests and
Acceptance Criteria
Revision No Page No
62
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I
Revision
Date WMS No: Prepared By Reviewed By Approved By
No:
ARTL/QAP/WMS/
18.01.20
R0 15
22
Revision No Page No
63
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I
1.0 Purpose
2.0 Materials
When Ordinary Portland Cement (OPC) is used the quantity of cement shall not
be less than 360 kg/cu.m. In case fly ash grade I (as per IS:3812) is blended at
site as part replacement of cement, the quantity of fly ash shall be upto 20
percent by weight of cementitious material and the quantity of OPC in such a
blend shall not be less than 310 kg/cu.m. The minimum of OPC content, in case
ground granulated blast furnace slag cement blended, shall also not be less
than 310 kg/m3.
2.2 Admixture: The admixtures shall confirm to IS 6925 and IS 9103 shall
improve the workability of concrete or extension of time and will not have any
effect on the properties of concrete. The performance of these admixtures will
be proved both on laboratory trials and in trial paving works.
2.4 Water : Water used for mixing and curing of concrete shall be free from
oil, salt, acid and other substances, which are harmful to concrete.
2.5 Dowel and tie bars : Dowel bars shall confirm to IS:432 of Grade I. High
yield Strength Deformed bars conforming to IS:1786 and grade of Fe 500 or
plain bars conforming to IS:432 of Grade I
Revision No Page No
64
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I
2.6 Pre-Molded joint filler: This shall be used for expansion joints abutting
structures like bridges, culverts and at end of the day’s work. These shall be of
20-25mm thickness or as shown in drawings. It shall be 25mm less in depth
than the thickness of slab provided in suitable lengths, which shall not be less
than lane width. Holes shall be made to accommodate dowel bars.
2.7 Joint sealing compound: The joint sealing compound shall be of hot
poured, elastomeric type or cold polysulphide/polyurethene/silicone type
having flexibility, resistance to age hardening and durability as per IRC:57.
3.0 Procedure
3.1 Mix :The mix shall be designed as per IRC:44 or IS 10262. And the
design shall be based on the flexural strength of concrete. The water content
shall be minimum required to provide workability for full compaction of the
concrete to the required density. The mix shall be proportioned to give an
average strength at 28 days exceeding the specified strength (4.5Mpa) by 1.65
times the standard deviation calculated from the flexural strength of the first
30 beams. The workability requirements at the batching plant and at site shall
be established by slump tests while doing trial length. A slump value of
2515mm is reasonable for slip form paving and 50±15mm for fixed form
paving.
3.3 Joints dowel and tie bars : The location and type of joint shall be as
shown in the drawings.
Revision No Page No
65
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I
The dowel bars shall mild steel with details and dimensions as indicated in the
drawings. Unless otherwise shown in the drawings the dowel bars shall be
positioned at the mid depths of the slab with suitable tools/means within +/-
20mm tolerances. The dowel bars shall be covered with plastic sheath for at
least 2/3rd from one end for contraction joint, and ½ length +50mm for
expansion joint. For expansion joints, a closely fitting cap of 100mm long shall
be provided at the sheath end. To block the entry of cement slurry between
dowels and cap a compressible sponge may be used.
The longitudinal joints shall be saw cut as shown in the drawings. A groove of
1/3rd the depth of the slab may be cut after the final set of the concrete. The
tie bars shall be deformed steel bars of 415 Mpa/500 Mpa complying to IS
1786. Tie bars shall be painted with bituminous paint for 75mm at the both
ends and positioned with suitable tools/means. Tie bars shall be placed within
the middle third of the slab depth.
Tie bars in the longitudinal joints shall be made up into rigid assemblies with
adequate supports to remain firmly in position during the construction of slab.
Revision No Page No
66
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I
Using sealants, not before 14days after construction of slab shall seal all
transverse and longitudinal joints, but prior to allowing the traffic ply on the
new construction.
The trial panel shall be constructed which is proposed for the main work.
This shall consist of straight side forms made of steel or other suitable
material. These shall have a depth equal to the prescribed thickness of the
pavement. These forms shall be straight and free from bends and warps. Side
forms shall be of sufficient rigidity in the form and in the interlocking
connection with adjoining form such that springing will not occur under the
weight of the sub grade and paving Equipment or from pressure of concrete.
The vibrators for concreting shall be either surface pan type or internal type
with immersed tube or multiple spuds.
After the final regulation of the slab and before the start of curing, the surface
of the concrete shall be brush-textured as per MORTH Cl. 602.9.11 at right
angles to the longitudinal axis. The surface and sides shall be cured by
application of curing compound or wet hessian bags. The curing compound
shall have a water retention efficiency of 90%. If water curing is done, the
pavement shall be covered with moist Hessian cloth or pond with water for at
least a period of 14 days.
Revision No Page No
67
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I
When saw cuts joints are adopted in construction, they are not made to
provide the minimum width specified in the drawings, they shall be widened
subsequently by sawing before sealing, and the width and depth are controlled
by gauges. When sealants are applied, an appropriate primer shall also be used,
if recommended by the manufacturer and it shall be applied in accordance
with their requirements. The sealant shall be applied within the minimum and
maximum drying time of the primer recommended by the manufacturer. Before
sealing, the temporary seal provided for blocking the ingress of dirt, soil, etc.
should be removed. A highly compressible heat resistant paper-backed de-
bonding strip as shown in drawing shall be inserted in the groove to serve the
purpose of breaking the bond between sealant and the bottom of the groove
and to plug the joint groove, so that the sealant may not leak through the
cracks.
The road may be opened for regular traffic after completion of curing period
and after sealing of joints.
The surface to be tested shall be dried; any extraneous mortar and loose
material shall be removed and swept clean, using a wire brush at right angles
and parallel to the carriageway. A cylindrical container of 25ml capacity shall
be filled with sand passing 300microns sieve and retained on 150microns
sieve, compacted by tapping the base and excess sand stroked off to level with
the top of cylinder. Then the sand shall be poured on the surface to be tested
into a heap and spread with the help of flat wooden disc of 64mm diameter of
1.5mm thick, with its face kept flat, in a circular motion, so that the sand is
spread into a circular patch, with the surface depressions filled with sand to
the level of peaks.
The diameter of the patch shall be measured to the nearest 5mm. The texture
depth of concrete shall be calculated as follows:
Five such texture depth tests shall be taken along the diagonal line across the
lane width at least 2m apart, between 50m points along the road. No
measurement shall be taken within the 300mm of longitudinal edges of the
slab constructed in one pass.
Revision No Page No
68
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I
Revision No Page No
69
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I
Revision
Date WMS No: Prepared By Reviewed By Approved By
No:
ARTL/QAP/WMS/
18.01.20
R0 16
22
Revision No Page No
70
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I
1.0 Purpose
This Method Statement provides detail procedure for the laying of concrete
Kerb as per the approved drawing.
2.0 Scope
This work consists of constructing cement concrete kerb in the central median
and /or along the footpaths in conformity with the lines, levels and dimensions
as specified in the drawings.
3.0 Responsibility
Section In charge will be responsible for quality control of the section for the
construction of Kerb. Further field engineers, surveyors, supervisors and lab
technicians will assist him.
4.0 Equipment
5.0 Procedure
a. Lines and levels will be marked and the sensor of the kerb-casting
machine will be adjusted accordingly. Pegs will be put at every 10 meters
interval indicating the levels. These pegs will be joined with a metal wire.
b. The concrete of Grade M20 to be used for kerb will be produced at the
batching plant as per the approved mix formula.
c. The concrete will be loaded on to the transit mixer directly from the
batching plant and transported to the kerb location.
Revision No Page No
71
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I
e. Before laying the foundation with lean concrete, the base will be leveled
and lightly watered to make it damp.
g. In the median portions in the straight reaches, the kerb will be cast in
continuous lengths. In the portions where footpaths are provided and /or the
slope of the carriageway is towards median gap/recess will be provided in the
kerb by cutting to facilitate drainage openings.
h. After laying the kerb and just prior to 6 to 8 hours after laying of the
concrete, saw cut grooves will be provided at 5m intervals or as specified by
the engineer.
j. Vertical and horizontal tolerances with respect to true line and level will
be + 6mm.
Quality control tests shall be done as per Sl. No 10 of Quality Control Tests and
Acceptance Criteria
Revision No Page No
72
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I
Revision
Date WMS No: Prepared By Reviewed By Approved By
No:
ARTL/QAP/WMS/
18.01.20
R0 17
22
Revision No Page No
73
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I
1.0 Scope
This item of work shall be dealt in compliance to Section 1500, 1600, and 1700
of Technical specifications.
2.0 Materials
2.1 Formwork
This work shall consists of providing and fixing of form work (shuttering) of
approved quality for cast- in- situ/ precast / pre-stressed plain or reinforced
concrete with necessary props, staging, centering, scaffolding and any
temporary construction required for their support.
2.2 Reinforcement
This work shall consist of providing and placing of high yield strength
deformed bars of the shape and dimensions as shown in approved drawings.
2.3 Concrete
This work shall consist of providing and placing of plain or reinforced concrete
of all grades with 20mm graded aggregates as defined in Technical
specifications, machine mixed and mechanically vibrated to the required level,
slope, etc. as per approved drawings.
The source of materials (for cement, coarse aggregate, fine aggregate, water,
admixture, reinforcement steel. Etc.) shall be identified and the sources will
confirm to the specifications mentioned on the drawings and the requirements
laid down in the section 1000 of MORTH or to the requirements specified by
the Engineer.
Revision No Page No
74
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I
Cement to be used shall be any of the following types with the prior approval
of the Engineer.
Fly ash when used, shall neither be less than 20 percent nor shall be greater
than 35 percent of the total by mass of ordinary Portland cement and fly ash
and shall conform to grade-1 of IS:3812.
Ground granulated blast furnace (GGBS) slag when used, shall neither be less
than 50 percent nor greater than 70 percent of the total mass of ordinary
Portland cement and GGBS and shall conform to IS: 12089.
2.3.2 Water
The water to be used shall be free from oils, acids, alkalis, salts, sugar, organic
materials or other substances that may be deleterious to concrete and steel.
Potable water generally considered satisfactory. The water to be used shall
satisfy the requirements as per clause 1010 of technical specifications.
Coarse aggregate shall consist of clean, hard, strong, dense, non-porous and
durable pieces of crushed stone. All coarse aggregates shall conform to clause
1107 of technical specifications and IS 383, when tested in accordance to IS
2386 parts 1 to 8.
Revision No Page No
75
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I
Fine aggregate shall consist of clean, hard, strong, dense, and durable pieces
of crushed stone or natural sand or a combination of both. All fine aggregates
shall confirm to IS 383, when tested in accordance to IS 2386 parts 1 to 8. The
fineness modulus of fine aggregate shall not be less than 2.0 or greater than
3.5. The grading shall confirm to Table 1000-2 of MOSRT&H specification.
2.3.5 Admixtures
2.3.6 Reinforcement
3.0 Procedure
3.1 Formwork
Revision No Page No
76
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I
d) Releasing agents such as diesel mixed with grease, shuttering oil, etc.
shall be applied before fixing formwork, and shall not allowed to come into
contact with any reinforcement or pre-stressing tendons and anchorages.
e) The formwork shall be cleaned carefully, dried and releasing agents shall
be applied before re-use.
h) Before any erection is taken up the design & drawing of complete farm
work (i.e. the farm as well as their supports) as per specification clause 1503 &
1507, has to be approved by the Engineer.
Revision No Page No
77
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I
3.3 Concrete
3.3.1 Mixing
b) The concrete shall be placed gently in position and shall not have a free
fall of 1.5m as per specification clause 1709.
Revision No Page No
78
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I
d) All formwork and reinforcement shall be cleaned and made free from
standing water, dust, etc., immediately before placing concrete.
3.3.3 Compaction
b) When vibrators are used, vibration shall be done continuously during the
placing of each batch of concrete until expulsion air has practically ceased
and in a manner does not promote segregation. Where immersion vibrators are
used contact with reinforcement and all inserts shall be avoided. Standby
vibrators in serviceable conditions shall be kept at site so that they can be
used in the event of breakdowns.
5.0 Curing
Revision No Page No
79
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I
after acceptance of surface finish, and the second coat shall be after first
coat has set, on the saturated surface before the surface water film
disappears.
6.0 Finishing
Quality control tests shall be done as per Sl. No 10 of Quality Control Tests and
Acceptance Criteria
Revision No Page No
80
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I
Revision
Date WMS No: Prepared By Reviewed By Approved By
No:
ARTL/QAP/WMS/
18.01.20
R0 18
22
Revision No Page No
81
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I
1.0 Purpose
This work shall consist of furnishing and installing reinforced cement concrete
pipes, of the type, diameter and length as per design and details and at
locations shown on the drawings
2.0 Scope
Excavation
Laying of pipes
Jointing
Back Filling
3.0 Equipment
Backhoe loader/excavator
Formwork
Transit Mixer
Vibrator
Batching plant
Dewatering Pump, if required
Dumpers
4.0 Materials
All materials used in the construction of pipe culverts shall conform to the
requirements of Section 1000 of MORTH.
Revision No Page No
82
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I
5.0 Responsibility
Section In-charge will be responsible for quality control of the section for the
construction of Kerb. Further field engineers, surveyors, supervisors and lab
technicians will assist him.
6.0 Procedure
6.1 Excavation
The foundation bed for pipe culverts & Head wall shall be excavated true to
the lines and grades shown on the drawings
PCC of specified grade and thickness shall be laid to the specified dimension
and level for leveling course below head walls as per approved drawing
The layout of the Head wall shall be made on the PCC as per approved drawing
The formwork shall be fixed to true line, levels, plumb, etc., rigid, adequately
braced both horizontally and vertically. Form joints shall be as much as
minimized shall be tight and shall not permit any leakage of slurry from
concrete.
Second stage concreting shall be carried out. After placing and aligning
all the pipes
The bedding shall be sand / granular material passing 5.6mm sieve. Specified
thickness of granular material bedding shall be provided below the pipes as per
the approved drawing. The bed shall be compacted/rammed with adequate
water.
In case of high embankments where the height of fill is more than three times
the external diameter of the pipe, the embankment shall be built first to an
Revision No Page No
83
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I
elevation above the top of the pipe equal to the external diameter of the pipe,
and to width on each side of the pipe not less than five times the diameter of
pipe, after which the trench for pipe bedding shall be excavated
The arrangement for lowering the pipes in the bed shall be done
carefully so as not to cause damage or undue strain to the pipes, preferably it
shall be done by means of tripod, manual labour or by cranes for loading,
unloading & setting the pipes.
The gap between two rows of pipes shall be at least 450mm or half the
diameter of the pipe, whichever is maximum for new culvert and existing gap
shall be maintained for widening of the existing culverts.
The laying of NP4 pipes shall start from the outlet end & shall be
completed at the inlet end to specified lines & grades as specified in the
approved drawing.
6.5 Jointing
The pipes shall be joined by flush joint. The ends of the pipes especially
shaped to form self-centering joint with a jointing space 13mm wide. The
jointing space shall be filled with cement mortar 1:2 sufficiently dry to remain
in position. The jointing shall be made with care so that the interior surface is
smooth & consistent with the interior surface of the pipe. The joints shall be
kept damp for at least four days till the joints are sufficiently hardened.
The existing head walls shall be dismantled to the required level and
dimension as per the approved drawing. New pipe shall be jointed with the
existing pipe as shown in the approved drawing.
Pipe encasing if any, shall be carried out as per the approved drawings in
accordance with the method statement detailed in ARARL/NH16/MS/18.
Revision No Page No
84
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I
Trenches shall be backfilled after the completion of jointing and encasing. The
backfill soil shall be clean, free from boulders, large roots, excessive amounts
of sods or other vegetable matter, and lumps and shall be approved by the
Engineer. Backfilling up to 300 mm above the top of the pipe shall be carefully
done and the soil thoroughly rammed, tamped or vibrated in layers not
exceeding 150 mm, particular care being taken to thoroughly consolidate the
materials under the haunches of the pipe. Approved pneumatic or light
mechanical tamping Equipment can be used.
Filling of the trench shall be carried out simultaneously on both sides of the
pipe in such a manner that unequal pressures do not occur.
In case of high embankment, after filling the trench up to the top of the pipe in
the above said manner, a loose fill of a depth equal to external diameter of the
pipe shall be placed over the pipe before further layers are added and
compacted
Quality control tests shall be done as per Sl. No 10 & 14 of Quality Control
Tests and Acceptance Criteria
Revision No Page No
85
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I
Revision
Date WMS No: Prepared By Reviewed By Approved By
No:
ARTL/QAP/WMS/
18.01.20
R0 19
22
Revision No Page No
86
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I
1. Purpose
This work shall consist of Method Statement adopted for the construction of
Box culvert and Under Pass.
2. Scope
3. Equipment
4. Responsibility
5. Procedure
5.1 Excavation
After the site has been cleaned according to clause 201. The limits of
excavation shall be set out true to lines, curves and slopes to clause 301.3.1.
The excavation shall be carried out as per MORTH clauses 304.3.2 & 2903. The
depth to which excavation shall be as shown on the drawings, where water is
met with in excavation due to stream flow, seepage, springs etc., adequate
measure shall be taken to pump out water to keep foundation trenches dry.
Revision No Page No
87
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I
5.3 Reinforcement
5.4 Formwork
Shuttering plates made of suitable material shall be used for inside and
outside wall shuttering. Vertical props and cross bracings of sufficient
strength shall be used to protect any bulkage / deformation of concrete. All
the joints shall be properly sealed. PVC joint, sealing tapes, foam, and rubber
will be used in order to prevent leakage of slurry.
5.5 Concreting
Revision No Page No
88
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I
Second phase of shuttering and formwork shall be erected for the top slab
and remaining portion of wall. Tying of slab reinforcement shall be done as
per drawing. Then concrete shall be poured and compacted. Concrete shall
not be freely dropped in to place from a height exceeding 1.5m. Curing shall
be done for 14 days by keeping surface moist.
Quality control tests shall be done as per Sl. No 10 of Quality Control Tests and
Acceptance Criteria
Revision No Page No
89
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I
Revision
Date WMS No: Prepared By Reviewed By Approved By
No:
ARTL/QAP/WMS/
18.01.20
R0 20
22
Revision No Page No
90
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I
1.0 Purpose
This work shall consist of Method Statement adopted for the construction of
Retaining wall
2.0 Scope
3.0 Equipment
4.0 Responsibility
5.0 Procedure
The plan dimensions of the foundation shall be set out at the bottom of
foundation trench and checked with respect to original reference line and axis
5.2 Excavation
a) Excavation will be done to the size of the foundation plus safe working area
including necessary slopes as per site condition.
b) At some locations if the surface is below sub soil water level requires de
watering, and then the same will be done by installing adequate capacity
pumps. Necessary cofferdams and cribs shall be constructed and shall be
Revision No Page No
91
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I
Any one of the procedures will be adapted to suit the site conditions.
d) Excavation will be carried out to the required depth as per the foundation
details given in the drawings and if there are any obstructions /hindrances are
there in the course of the work then they will be immediately brought to the
notice of the engineer for their necessary instruction/action.
e) If Excavation done more than required depth, the extra depth of exaction
should be filled with sand or by soil compacted in layers till it reaches the
desired level of PCC.
5.3 PCC
Marking will be given as per the drawing on dressed surface. Side shuttering
shall be provided of the required thickness and size of the footing plus offset
for PCC
PCC of required thickness and grade will be laid on the dressed surface.
Revision No Page No
92
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I
Reinforcement will be tied over the PCC for footing and substructure as per
the drawings and proper formwork will be fixed to suit the requirement and as
per drawings.
Quality control tests shall be done as per Sl. No 10 of Quality Control Tests and
Acceptance Criteria
Revision No Page No
93
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I
Revision
Date WMS No: Prepared By Reviewed By Approved By
No:
ARTL/QAP/WMS/
18.01.20
R0 21
22
Revision No Page No
94
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I
1.0 Purpose
2.0 Scope
Concreting
a. Rotary hydraulic Rig: adequate nos. of piling rigs shall be used for
installation of bored cast-in-situ Piles.
Or
b. Piling Rig with Winch: adequate nos. of conventional piling rigs with
driving winches (Electrically motor driven) shall be used for installation of
bored cast-in-situ Piles.
Revision No Page No
95
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I
g. Transit Mixer: Adequate nos. of standard transit mixer shall be used for
transporting concrete from batching plant to pile pour location.
4.0 Responsibility
5.0 Procedure
Pile installation procedure has been described for Bored Cast-in-situ Pile in the
following steps:
a. Pile points shall be marked at exact pile locations as per relevant bridge
structural drawings with Total Station and reference grid pillars established.
Reference points shall be marked/fixed at a suitable distance from pile points
to cross check the center of pile during drilling operation.
b. The working level /ground level should be minimum 1.5 M above the
water Table/high tide level.
g. The bore hole will then be filled with Bentonite slurry. Bentonite
circulation channel shall be made from bore hole to Bentonite tank and fresh
Revision No Page No
96
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I
Bentonite slurry shall be pumped to drilling chisel via. Extension rods and
flexible tubes installed. Bentonite powder is to be mixed in the fresh water
tank at least 24 hours prior to start of Pile boring to ensure that Bentonite is
completely dispersed in the water and attains required density to stabilize the
sides of bore hole during drilling.
l. Depth of Pile shall be checked with sounding chain and exact depth
shall be recorded in the Pile report.
m. After flushing is over, the Chisel and connected DMC rods shall be
removed for further cage lowering and pile concreting operations.
The following steps shall describe the cage fabrication and lowering:
Revision No Page No
97
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I
f. After necessary inspection is over, the cage shall be lowed inside the
bore hole true vertically and it will be ensured that the cover blocks are not
damaged during lowering operation.
g. If two or more cages are to be lowered, all those cages shall be lapped
with minimum lap length as per relevant drawings/specifications; spirals shall
be placed round the lapped length and tack-welded to main bars. Also cover
blocks of required nos. shall be provided for lap length portion.
c. The length of tremie pipe (total individual joined pipes) shall be more
than the length of the pile and base of tremie pipe should be lowered to
bottom of the borehole, allowing water or drilling mud to rise inside it before
pouring concrete.
Revision No Page No
98
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I
d. The top of the tremie pipe shall be fitted with a large diameter funnel to
receive the concrete with steel sealing plate arrangement at bottom of the
funnel.
e. Before start of Concreting operation, the bore hole shall be flushed with
fresh Bentonite slurry to flush out all loose particles, deleterious materials, if
any, present in the bore.
k. The tremie shall be gently lowered on to the old concrete with very little
penetration initially. A vermiculate plug should be introduced in the tremie.
Fresh concrete of slump between 150mm - 200 mm should be filled in the
tremie which will push the plug forward and will emerge out of the tremie
displacing the laitance/scum in its way. When tremie is buried by about 60 to
100 cm, concreting may be resumed.
Revision No Page No
99
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I
n. After concreting up to the required level is done, the casing pipe will be
withdrawn.
o. Pile concreting data shall be entered in the relevant formats for future
reference.
Revision No Page No
100
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I
Revision
Date WMS No: Prepared By Reviewed By Approved By
No:
ARTL/QAP/WMS/
18.01.20
R0 22
22
Revision No Page No
101
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I
1.0 Purpose
This work shall consist of Method Statement adopted for the construction of
pile cap in accordance with the approved drawings
2.0 Scope
3.0 Equipment
4.0 Responsibility
5.0 Procedure
5.1 Excavation
Once all the piles in a pile-group are completed, marking for the pile cap shall
be done.
The final dressing to reach the desired depth shall be done manually.
Revision No Page No
102
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I
The Chipping of the pile up to the cut off level shall be commenced after the
excavation is completed.
The projected portion of the piles shall be broken using chisel and hammers or
breakers up to cutoff levels as shown in the drawings. Projected reinforcement
from the piles shall be straightened and given ‘L’ bend as per drawings.
The bottom of the pile cap will be properly rammed using hand rammers. All
the levels will be checked and the center of the pile cap will be marked
properly.
For PCC, required grade of concrete will be poured and compacted to achieve
the desired levels as per drawing. PCC will be done as per dimensions given in
the drawings
5.4 Reinforcement
The bars, crossing one another shall be tied together at every intersection with
binding wire, to make the skeleton of reinforcement rigid such that it does not
get displaced during placing of concrete or any other operation.
Adequate cover shall be maintained on all sides except on the top surface to
achieve proper cover as per the drawing.
The rebar for the pier shall be placed after properly marking location in
accordance with the approved drawings.
Revision No Page No
103
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I
5.5 Formwork
Required formwork shall be made out of plywood/ steel shutters to suit the
site conditions.
The formwork shall be erected in true to line, levels, plumb, etc., rigid,
adequately braced both horizontally and vertically.
Form joints shall be as much as minimized, shall be tight and shall not permit
any leakage of slurry from concrete.
If concrete pump is used, concrete pumps and pump lines shall be primed
before commencement of concrete pumping operations.
No layer of concrete shall be laid until previous layer in the same lift has been
consolidated thoroughly.
Revision No Page No
104
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I
Curing of concrete shall be carried out for 14 days from the date of casting
Quality control tests shall be done as per Sl. No 10 of Quality Control Tests and
Acceptance Criteria
Revision No Page No
105
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I
Revision
Date WMS No: Prepared By Reviewed By Approved By
No:
ARTL/QAP/WMS/
18.01.20
R0 23
22
Revision No Page No
106
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I
1.0 Purpose
2.0 Scope
3.0 Equipment
Transit Mixer
Vibrator
Batching plant
4.0 Responsibility
5.0 Procedure
The vertical bars shall be tied to ledger pipes as per spacing which in turn is
supported to staging tower to keep the vertical bars in correct position.
Starter formwork shall be made out of plywood/ steel shutters to suit the site
conditions.
Revision No Page No
107
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I
5.2 Staging
5.3 Reinforcement
The bars, crossing one another shall be tied together at every intersection with
binding wire, to make the skeleton of reinforcement rigid such that it does not
get displaced during placing of concrete or any other operation.
Cover blocks of thickness equal to the specified cover shall be placed between
formwork and bars made of concrete of specified grade of concrete.
5.4 Shuttering
Required formwork shall be made out of plywood/ steel shutters to suit the
site conditions.
Revision No Page No
108
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I
The formwork shall be erected in true to line, levels, plumb, etc., rigid,
adequately braced both horizontally and vertically.
Form joints shall be as much as minimized, shall be tight and shall not permit
any leakage of slurry from concrete.
The placement of concrete for Pier shall be done with Boom placer /Crane-
bucket with funnel chute so as to restrict the height of fall of concrete not
more than 1.50m
Curing of concrete shall be carried out for 14 days from the date of casting.
Subsequent lifts shall be laid only after the previous lift approval.
Revision No Page No
109
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I
Quality control tests shall be done as per Sl. No 10 of Quality Control Tests and
Acceptance Criteria
Revision No Page No
110
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I
Revision
Date WMS No: Prepared By Reviewed By Approved By
No:
ARTL/QAP/WMS/
18.01.20
R0 24
22
Revision No Page No
111
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I
1.0 Purpose
2.0 Scope
3.0 Equipment
4.0 Responsibility
5.0 Procedure
5.1 Staging
5.2 Shuttering
Required formwork shall be made out of plywood/ steel shutters to suit the
site conditions.
Revision No Page No
112
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I
The formwork shall be erected in true to line, levels, plumb, etc., rigid,
adequately braced both horizontally and vertically.
Form joints shall be as much as minimized, shall be tight and shall not permit
any leakage of slurry from concrete.
5.3 Reinforcement
Once the rebar cage is ready and the soffit shuttering of pier cap is
ready to receive the cage, the rebar cage shall be placed symmetrically over
pier with the help of crane.
In case the pier/abutment cap location is not accessible for the crane
movement, the tying for the pier cap shall be taken up at location itself.
The rebar for the bearing pedestals shall be placed after properly
marking location in accordance with the approved drawings
Revision No Page No
113
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I
Staging and soffit de shuttering shall be carried out after the specified
period based on the span whereas the other shuttering can be removed after
24 hours.
Curing of concrete shall be carried out for 14 days from the date of
casting
Quality control tests shall be done as per Sl. No 10 of Quality Control Tests and
Acceptance Criteria
Revision No Page No
114
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I
Revision
Date WMS No: Prepared By Reviewed By Approved By
No:
ARTL/QAP/WMS/
18.01.20
R0 25
22
Revision No Page No
115
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I
1.0 Purpose
2.0 Scope
3.0 Equipment
4.0 Responsibility
5.0 Procedure
Form vibrator location shall be welded with base plate for fixing the vibrator
during concreting.
Pre-fabricated bottom shutter shall be placed over the casting bed.
Bottom shutter shall be aligned to the required line and level and welded
to the base channel.
Revision No Page No
116
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I
Foam sheet shall be fixed with glue at all the joints (vertical &
horizontal) of steel shutters to avoid slurry leakage during concrete.
The form work shall be cleaned by using Buffing wheel. Shuttering oil
shall be applied and erected in sequence as specified in the detailed shutter
drawing.
The walk way for girder to be fixed for concreting works and shall be
free from obstructions.
5.2 Reinforcement
The reinforcement shall be cut and bent as per approved drawings and
BBS
If the girder is of pre stressed, anchor heads on both ends of the girder with
burst reinforcement, sheathing duct for stressing cables as per the profile and
grout vents shall be placed as shown in the drawings
5.3 Concreting
Revision No Page No
117
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I
The top surface shall be finished and remove the top laitance by using
wire brush to make construction joint.
Moist curing shall be commenced to the girder top surface after initial
set.
The side shutter shall be removed after 12 hrs from the time of casting.
After removal of side shutter hessian cloth shall be fixed over the
concrete surface and water curing shall be commenced.
Quality control tests shall be done as per Sl. No 10 & 15 of Quality Control
Tests and Acceptance Criteria
Revision No Page No
118
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I
Revision
Date WMS No: Prepared By Reviewed By Approved By
No:
ARTL/QAP/WMS/
18.01.20
R0 26
22
Revision No Page No
119
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I
1.0 Purpose
The work shall consist of constructing surface drains in accordance with the
requirements of these Specifications and to the lines, grades, dimensions and
other particulars shown on the drawings
2.0 Scope
3.0 Equipment
Excavator
Dumpers
Batching plant
Transit Mixers
Vibrators
4.0 Responsibility
5.0 Procedure
5.2 Excavation
Excavation will be done conforming to the lines, grades, slopes and levels as
shown on the approved working drawings, as per the specification clause 301
Revision No Page No
120
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I
5.3 Concreting
5.3.1 Leveling Course: PCC of the drain with approved design mix concrete
will be done conforming to the lines, grades, slopes and levels as shown on the
approved working drawings.
5.3.3 Walls: The shuttering is erected to the exact dimension and the walls
are cast above the raft to bottom level of slab. The procedure adopted will be
same as raft.
5.3.4 Weep Holes: Weep Holes will be provided at required spacing as shown
in the drawing.
5.3.5 Slab: The shuttering is made to support the top slab of drain and
necessary care is taken to seal the joints to avoid slurry loss from concrete
through joints. The steel is positioned and concreted.
The necessary back filling will be done after completion of curing works.
Quality control tests shall be done as per Sl. No 10 of Quality Control Tests and
Acceptance Criteria
Revision No Page No
121
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I
Revision
Date WMS No: Prepared By Reviewed By Approved By
No:
ARTL/QAP/WMS/
18.01.20
R0 27
22
Revision No Page No
122
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I
1.0 Purpose
The work shall consist of covering the river side slopes of guide bunds and
road embankments with stone boulders over a layer of granular material which
will act as a filter.
2.0 Materials
2.1 Pitching Stone The size and weight of stone shall conform to Clause
5.3.5.1 of IRC: 89. No stone, shall weigh less than 40 kg. The size of spalls shall
be a minimum of 25 mm and shall be suitable to fill the voids in the pitching
The material for the filter shall consist of sand, gravel, crusher dust or GSB to
act as a filter medium, shall be provided underneath the pitching, to prevent
loss of the embankment material and build-up of uplift head on the pitching
The gradation of the filter material shall satisfy the following requirements of
MORTH Cl 2504.2.2
3.0 Procedure
Before laying the pitching and construction of toe wall the sides of banks shall
be trimmed to the required slope and profiles put up by means of line and pegs
at intervals of 3m to ensure regular straight work and a uniform slope
throughout. Depressions shall be filled and thoroughly compacted.
The filter granular material shall be laid over the prepared base and suitably
compacted to the thickness specified on the drawings.
The lowest course of pitching shall be started from the toe wall built-up in
courses upwards
The toe wall shall be in dry rubble masonry (uncoursed) conforming to Clause
1405.3, of these Specifications in case of dry rubble pitching. It shall be in
nominal mix cement concrete (M 15) conforming to Clause 1704 of MORTH in
case of cement concrete block pitching.
Revision No Page No
123
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I
The stone pitching shall commence in a trench over the toe of the slope. Stone
shall be placed by hand to the required length, thickness and depth
conforming to the drawings. Stones shall be set normal to the slope and
placed so that the largest dimension is perpendicular to the face of the slope,
unless each dimension is greater than the specified thickness of pitching.
The largest stones shall be placed in the bottom courses and for use as
headers for subsequent courses.
The stone of flat stratified nature shall be placed with the principle bedding
plane normal to the slope. The pattern of laying shall be such that the joints
are broken and voids are minimum by packing with spalls of the proper size
and wedged in with hammers to ensure tight packing.
When two or more layers of stones must be laid to obtain the design thickness
of pitching, dry masonry shall be used and shall be well bonded.
Revision No Page No
124
R0