QUALITY ASSURANCE

Development of Six Lane Badakumari – Karki Section PLAN


of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I

Summary Sheet for Work Method Statement

Method
Description of Activity
Statement No
01 Method Statement For Survey & Setting works
02 Method Statement for Clearing and Grubbing
Construction of Embankment, Sub grade and Shoulder
03
with soil
04 Construction of Embankment with Fly ash
Method Statement for Sub grade Construction with Fly
05
ash + Sand
Method Statement For Backfilling Behind Abutment &
06
Around Structures
Method Statement for the Construction of Granular Sub
07
Base
Method Statement for the Construction of Cement
08
Treated Sub-Base/Base
Method Statement for the Construction of Wet Mix
09
Macadam
10 Method Statement for Prime Coat/Tack Coat
Method Statement for the Construction of Dense
11
Bituminous Macadam
Method Statement for the Construction of Bituminous
12
Concrete
13 Method Statement for Mastic Asphalt Construction
Method Statement For Construction of Dry Lean
14
Concrete
Method Statement for Construction of Pavement
15
Quality Concrete
16 Method Statement for Kerb Casting
Method Statement for Form work/ Reinforcement/
17
Concrete
18 Method Statement for Pipe Culvert
19 Method Statement for Box Culvert/Underpass

Revision No Page No
1
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I

20 Method Statement for Open Foundation


21 Method Statement for Pile Foundation
22 Method Statement for Pile Cap
23 Method Statement for Pier/Abutment Construction
24 Method Statement for Pier/Abutment Cap Construction
25 Method Statement for Pre-Cast Girder Casting
26 Method Statement For construction of Drain
27 Method Statement for Stone Pitching on slopes
28 Method Statement for Stone Pitching on slopes
Method Statement for the following works shall be submitted during
execution of works
Method Statement for Vertical Load Test on Piles
Method Statement for Lateral Load Test on Piles
Method statement for RE wall construction
Method statement for Precast Girder erection, Deck slab concreting for
bridges, Flyover & Interchange.
Method statement for bearing pedestal casting & installation of bearings
Method statement for Prestressing

Revision No Page No
2
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I

Method Statement for Survey and Setting Out

Revision
Date WMS No: Prepared By Reviewed By Approved By
No:

ARTL/QAP/WMS/
18.01.20
R0 01
22

Revision No Page No
3
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I

Method Statement for Survey and Setting Out

1.0 Purpose

The purpose of the procedure is to describe and define the methods adopted
in setting out for road works.

2.0 Scope

This procedure applies for setting out data of Center line to grades as per
contract drawings for survey of road works undertaken by the company.

3.0 Definition

HIP : Horizontal Intersection Point

VIP : Vertical Intersection Point

LS : Longitudinal Section.

CS : Cross Section.

3.1 Setting Out

The Engineering method of transferring the plan & elevation from drawings to
the field with a firm control of alignment.

3.2 GTS Bench Mark

Reference point established by Great Trigonometrical Survey of India


development. These have been set up at interval all over the country with very
high precision.

3.3 Permanent / Reference Bench Mark

Reference point of known elevation established between the GTS bench marks
at closer intervals.

3.4 Bench Mark

It is a fixed reference point of known elevation.

3.5 Temporary or Works Bench Mark (TBM)

Revision No Page No
4
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I

Reference points established from permanent BM at convenient location for


setting out the pavement structure.

3.6 Grades

Elevation of any point with reference to a specified datum.

3.7 Gridlines

Imaginary lines running Horizontal & Vertical with each line having a
designated northing and easting.

4.0 Responsibility

The Senior Surveyor shall be the Key Personnel, responsible for the Setting out
work.

5.0 Procedure

5.1 Preparation

5.1.1 The setting out works shall be carried out as per the approved drawing.

5.1.2 The values of the co-ordinates & elevation of reference or permanent


bench mark (BM) will be obtained from the contract drawing / GTS. The
correctness of these values will be checked physically at site for line and.
TBM values as verified will be compared with values in the contract
drawing. Discrepancies, if any, will be brought to the notice of the
Engineer. Written approval of the values of BM as checked shall be
obtained from the Engineer prior to commencement of the work.

5.1.3 The working or Temporary Bench Mark (TBM) will be established at every
250 mtr interval and also at or near all drainage structures and
underpasses. The working benchmark / levels will be approved by the
Engineer. Checks will be made on these benchmarks as and when
required and adjusted if any, got approved with the Engineer and
recorded. An up-to-date record of all TBMs including approved
adjustment, if any, will be maintained and a copy will be submitted to the
Engineer.

5.2 Instrument for Setting out

Revision No Page No
5
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I

Instruments appropriate for the intended setting out task and according to the
accuracy requirements will be used. The instruments will be calibrated
periodically and will be kept in good working condition. The following
instruments will be used for setting out survey works.

 Precision Automatic level instrument.

 Total station. (least count 0.5 seconds.)

 Tripods

 Staff (least count 5mm)

 30 mtr/ 50 mtr steel or Fiber measuring tape.

5.3 Setting Out Works:

5.3.1 With reference to the known BM (as at Clause-5.1.3) values, the centerline
of the proposed road will be located and marked at feasible locations
along the highway using a total station.

5.3.2 All the HIP’s & VIP’s for Horizontal & vertical curves along the alignment
will be located and nailed at site in a similar manner (as at Clause: 5.3.1).
As per the drawing coordinates, the traversing will be closed at BM and
error, if any will be linearly distributed.

5.3.3 Pegging will be done at toe lines at every 27.50 mtr longitudinal intervals
of the embankment and in cases of no embankment, 2mtr away from the
edge of the proposed road.

5.3.4 The alignment as pegged will be checked jointly with respect to the
drawing and shall be approved by the Engineer.

5.4 Level along & across the alignment

5.4.1 The existing ground levels will be recorded jointly on a level book along
the horizontal sectioning at 10mtr interval for straight as well as curve
portions and along the cross section as per the requirements depending
upon the profile of the terrains with reference to the known BM
elevation. (As at Clause: 5.1.2 & 5.1.3)

Revision No Page No
6
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I

5.4.2 Upon approval of the alignment (as at Clause: 5.3.4) and existing ground
level by the Engineer, road works will commence for construction of
pavement layers.

Revision No Page No
7
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I

Method Statement for Clearing and Grubbing

Revision
Date WMS No: Prepared By Reviewed By Approved By
No:

ARTL/QAP/WMS/
18.01.20
R0 2
22

Revision No Page No
8
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I

Method Statement for Clearing and Grubbing

1.0 Purpose

This Method Statement provides detail of procedure adopted for the clearing
and grubbing operation.

2.0 Scope

This work will consist of cutting, removing and disposing of all materials such
as trees, bushes, shrubs, stumps, roots, grasses, woods, top organic soil not
exceeding 150mm in thickness, rubbish etc, which in the opinion of the
Engineer are unsuitable. Clearing and grubbing will be performed in advance of
earthwork operation and in accordance with the requirements of the
specification.

3.0 Responsibility

Section In charge will be responsible for quality control of the section for the C
& G operation. He will liaise with the Engineer. Further he will be assisted by
field Engineers, Surveyors, Supervisors and Lab Technicians.

4.0 Equipment

The following construction machineries will be deployed for C & G work.

Tipper

Wheel loader

Dozer with ripper

Excavator

Grader

5.0 Procedure

5.1 Clearing & Grubbing

 Once the center line is established, level at every 10 mts intervals in


longitudinal direction as well as at suitable grid in transverse direction shall be

Revision No Page No
9
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I

recorded jointly with Engineer before starting the clearing and grubbing
operation.

 All trees, stumps etc. falling within excavation and fill line, will be cut to
such depth below ground level that, in no case these fall within 500 mm of the
sub grade.

 Site will be cleared from all vegetation such as roots, undergrowth,


grasses and other deleterious materials prior to start of the embankment
works.

 On areas beyond the limit, trees and stumps required to be removed as


directed by the Engineer, will be cut down to 1mtr below ground level so that
these do not present an unsightly appearance.

 All branches of tree, extending above the road way will be trimmed as
directed by the Engineer.

 All excavation below the general ground level arising out of the removal
of trees, stumps etc will be filled with suitable material and compacted
thoroughly.

5.2 Topsoil, unsuitable/deleterious materials & dismantled structure


removals.

 Topsoil suitable for plant growth existing over the embankment


foundation areas or borrow pits will be stripped and stored at the site located
by Engineer for covering embankment slopes, cut slopes or other disturbed
areas where re-vegetation is desired in due course of time.

 Topsoil cleared from ground and/or slopes to be stockpiled and


preserved for possible future use as directed by Engineer.

 Site to be cleared from all debris, deleterious materials prior to start of


embankment works.

 Unserviceable materials collected from the dismantling of structures will


be disposed at the site located by Engineer.

 Serviceable materials collected from the dismantling of structures will


be stockpiled at the site located by Engineer.

Revision No Page No
10
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I

 Unsuitable material will be determined by laboratory testing, physical


and visual examination or combination thereof. Depth of removal of such
materials will be as per the direction of the Engineer.

6.0 Safety & Environment

While working Safety & Environment Procedure shall be followed as per


approved EHS Manual

Revision No Page No
11
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I

Method Statement for Construction of


Embankment, Subgrade and Shoulder with soil

Revision
Date WMS No: Prepared By Reviewed By Approved By
No:

ARTL/QAP/WMS/
18.01.20
R0 03
22

Revision No Page No
12
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I

Method Statement for Construction of Embankment, Subgrade and Shoulder


with soil

1.0 Purpose

The purpose of this Method Statement for Construction of Embankment /


Subgrade/ Shoulder with soil is to provide details of the Construction Method
Statement, Quality Control System, Procedures and Safety & Environment.

2.0 Scope

The Scope of this Method Statement covers the following activities:

a) Excavation necessary for construction of roadway complete as per


MORTH Specifications Clause 301 & Loosening and re compaction of the
original ground /sub grade up to the required depths as directed by the
Engineer and as per MORTH Clause 305.

b) Construction of Embankment with approved borrow material or suitable


excavated soil from roadway complete as per MORTH Clause 305 and
amendments therein including all leads and lifts.

c) Construction of sub grade with approved borrow material or suitable


excavated soil from roadway complete as per MORTH. Clause 305 including all
leads and lifts.

d) Construction of shoulder with approved material and complete as per


MORTH. Clause 305 with all leads and lifts.

3.0 Equipment

The following construction machineries will be deployed.

Dumper / trucks

Grader

Vibratory Roller

Water tanker

Revision No Page No
13
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I

4.0 Procedure

4.1 Embankment Construction using Borrow Soil

4.1.1 Material

The materials used in the works shall be soil, moorum, gravel, a mixture of
these or any other material approved by the Engineer as per requirements of
Clause 305.2.1 of MORTH Specifications (Fifth revision).

The Borrow Materials shall be sourced from nearby areas. The details shall be
submitted to the Engineer for approval. Samples shall be collected from these
Borrow areas and tested jointly to check suitability. The embankment material
shall be incorporated in the works only after approval is obtained from the
Engineer.

All excavations will be carried out in conformity with the directions laid and in
a manner approved by the Engineer. The suitable materials obtained from
excavation will be satisfactorily utilized.

4.1.2 Setting out Works:

The Centerline of the road will be set out by means of Total Station. The
reference points for this will be as per the project drawings.

The working Bench Marks will be established from the approved Reference
Bench Marks at the rate of four per Km and also at or near all drainage
structures and got approved from the Engineer.

The reference points will be so located that these will not be disturbed during
construction.

Reference pegs, marking the limits of embankment shall be fixed on both sides
of the slopes. These pegs are meant as guides and will be about 2.0m away
from the toe of the embankment.

4.1.3 Preparation of Original/Natural ground for Embankment Construction

Atterberg limits, MDD, OMC, and in-situ dry density (FDD) of the material at
ground level will be determined. Any unsuitable material will be removed and
replaced with suitable material. Suitable / approved earth will be laid in layers

Revision No Page No
14
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I

not exceeding 250 mm compacted thickness and compacted to specifications


or as directed by the Engineer.

The natural ground, supporting embankment shall be leveled, scarified, mixed


with water and compacted to achieve 95% of lab density by 8-10 T vibratory
roller with an approved pattern of rolling.

Once the compaction of Original Ground Level is completed after Clearing and
Grubbing operation, joint level with the Engineer will be recorded for the
purpose of measurement and preparation of Cross Section and Longitudinal
Section.

4.1.4 Embankment Construction Operation

Embankment shall be constructed as per the MORTH Specifications, Clause –


305.

a) The limits of Embankment will be marked by fixing batter pegs at regular


intervals on both sides of the Embankment layer and working line with white
lime.

b) The Embankment will be built sufficiently wider than the designed


dimensions so that after proper compaction is achieved up to the toe of the
embankment and surplus materials shall be removed / trimmed to get the
proper compacted slopes of embankment.

c) The Ground supporting embankment /sub grade shall be compacted as


per guidelines given in amended clause 305.3.4. When existing embankment is
to be widened and its slopes are steeper than 1 vertical on 4 horizontal,
continuous horizontal benches each at least 300mm wide shall be cut into the
old slope for ensuring adequate bond with the fresh embankment to be added.

d) Soil from approved borrow areas shall be excavated with Excavators/


JCB and loaded onto tippers/tractor trailer with hydraulic attachment for
transportation to the approved stretch ready to receive Embankment Material.

e) The Embankment material shall be spread in layer of uniform thickness


not exceeding 250 mm compacted thickness over the entire width of
embankment by mechanical means, finished by motor grader. The size of the
coarse material in the mixture of earth shall ordinarily not exceed 75mm.
However, the Engineer may at his discretion permit the use of material coarser

Revision No Page No
15
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I

than 75mm that the same will not present any difficulty as regards the
placement of fill material and its compaction to the requirements of these
Specifications. The maximum particle size in such cases, however, shall not be
more than two-thirds of the compacted layer thickness.

f) The natural moisture content of soil will be found out and the balance
amount of water to be added to the soil will calculated as OMC minus NMC, so
as to maintain moisture content from 2 % below to 1% above the OMC at the
time of compaction.

g) The amount of water required for construction will be sprinkled from a


water tanker uniformly. After proper mixing and leveling with grader, the
leveled layer of fill will be compacted by vibratory road roller of 8-10 T capacity
to achieve required density as 95% of Modified Proctor Density. The numbers
of passes and rolling pattern will be established by joint trial at site to ensure
the achievement of required degree of compaction.

4.1.5 Quality Control and Testing

Quality control tests shall be done as per Sl. no. 1 of Quality Control Tests and
Acceptance Criteria

5.0 Sub grade Construction

5.1 The construction of sub grade Method Statement will be same as


mentioned for embankment with the following variations.

5.2 The Samples of existing shoulder material to be collected jointly for


conducting laboratory tests for their suitability to use as sub grade material as
mentioned in the drawing. If the existing shoulder material or the original
ground material do not conform the requirements as per the drawing and
specification the same shall be removed and replaced by suitable approved
material. If the original ground material or the existing sub grade material as
the case may be found conforming the specification and drawing other than
compaction the same will be loosened and re-compacted at OMC to 97% of
MDD as per I.S. 2720 (Part-8) and tested at specified frequency.

5.3 The size of the coarse material in the mixture of earth shall ordinarily
not exceed 50mm. However, the Engineer may at his discretion permit the use
of material coarser than 50mm that the same will not present any difficulty as
regards the placement of fill material and its compaction to the requirements

Revision No Page No
16
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I

of these Specifications. The maximum particle size in such cases, however,


shall not be more than two-thirds of the compacted layer thickness.

5.4 If the degree of compaction does not conform to the requirement, the
area will be re-compacted at OMC until the required density is achieved.

5.5 Quality Control and Testing:

a) Quality control tests shall be done as per Sl. No. 1 of QAP

b) The control of alignment, level and surface regularity to be followed as


per MORTH. clause 902.2 and Table 900-1.

6.0 Shoulder Construction

6.1 Approved material for Shoulder Constructions will be laid as per the
drawing and specification prior or along with the laying of adjacent layer. The
construction sequence, Quality Control etc. will essentially be the same as for
Sub grade Construction. The same will be watered, leveled, graded and
compacted to the required density as per the drawing and specification.

6.2 Quality Control and Testing

Quality control tests shall be done as per Sl. no. 1 of Quality Control Tests and
Acceptance Criteria

7.0 Safety & Environment

While working Safety & Environment Procedure shall be followed as per


approved EHS Manual.

Revision No Page No
17
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I

Method Statement for Construction of


Embankment with Fly ash

Revision
Date WMS No: Prepared By Reviewed By Approved By
No:

ARTL/QAP/WMS/
18.01.20
R0 04
22

Revision No Page No
18
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I

Method Statement for Construction of Embankment with Fly ash

1.0 Purpose

This Method Statement shall be adopted for the construction of embankment


with Fly Ash.

2.0 Scope

Setting out, compacting the ground supporting Embankment, Blanketing,


Leveling and Compaction

3.0 Equipment

The following construction machineries will be deployed.

Dumper / trucks

Grader

Vibratory Roller

Water tanker

Plate Compactor

4.0 Responsibility

Section in Charge will be responsible for execution and quality control of the
section for the construction of Embankment with fly ash. Further he will be
assisted by Field Engineers, Surveyors, Supervisors and Lab Technicians.

5.0 Procedure

5.1 Setting out

After the site has been cleared to Clause 201, the limits of embankment should
be set out true to lines, curves, slopes, grades and sections as shown in
approved drawing and Clause 301.3.1of MORTH Specification (Fifth revision).

The limits of toe line will be marked by means of lime powder or pegs to
facilitate the construction activity.

Revision No Page No
19
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I

5.2 Compacting the ground supporting Embankment

5.3 Where ever possible the original ground after excavation should be
scarified, mixed with water to achieve OMC, leveled and compacted by 8 – 10
T capacity vibratory earth compactor. Ground supporting the embankment will
be prepared and compacted to specified density of minimum 97 % of Lab MDD
to meet the requirement of IRC SP:58-2001, Clause 4.5.1.

5.4 Leveling and Compaction

The fly ash will be dozed, graded; water will be sprinkled ± 2% of the OMC on
the entire area uniformly. Then it will be compacted by means of 8-10-ton
vibratory roller with adequate passes of the roller so as to achieve 95%
compaction as per MORTH Specification (Fifth revision) clause 305 & Table
300-1 & 300-2 as well as Cl. 4.7.5 of IRC SP 58-2001.

6.0 Quality Control and Testing

Quality control tests shall be done as per Sl. no. 1 of Quality Control Tests and
Acceptance Criteria

7.0 Safety & Environment

While working Safety & Environment Procedure shall be followed as per


approved EHS Manual.

Revision No Page No
20
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I

Method Statement for Sub grade Construction with


Fly ash + Sand

Revision
Date WMS No: Prepared By Reviewed By Approved By
No:

ARTL/QAP/WMS/
18.01.20
R0 05
22

Revision No Page No
21
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I

Method Statement for Sub grade Construction with Fly ash + Sand

1.0 Purpose

The purpose of this Method Statement for Construction of Sub-grade with fly
ash modified soil is to provide details of Construction Method Statement.

2.0 Scope

The Scope of this Method Statement covers the construction of Sub-grade


with fly ash modified soil with the requirement of the Technical Specification

3.0 Equipment

The following construction machineries will be deployed.

Dumper / trucks

Grader

Vibratory Roller

Water tanker.

Plate Compactor

4.0 Responsibility

Section In charge will be responsible for execution as well as for quality


control of the section for construction of embankment. He will be assisted by
Field Engineers as well as quality control Engineers. Further, Surveyors and
Supervisors will assist Field Engineer whereas Lab Technicians will assist
Quality Control Engineer.

5.0 Procedure

5.1 Site Clearance Works

Site Clearance, Grubbing, Dismantling of existing structures and disposal of


unserviceable materials at designated areas and stacking of t materials for use
in Embankment Construction works etc. shall be carried out as per MORTH
Technical Specification, Section – 200 and also as per modifications to

Revision No Page No
22
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I

MORTH Clauses, 201.1,201.4,201.5,202.4 and 202.5 furnished in Additional


Technical Specifications of the Project.

5.2 Survey and Setting Out Works

After the Site has been cleared as per MORTH Clause 201, the limits of
excavations shall be set out true to lines, curves, slopes, grades and sections as
shown on the drawings or as directed by the Engineer and as per established
Bench Marks / Co-ordinates.

5.3 Construction Operation

a) The sub grade will be constructed in two layers of 250 mm thickness.

b) The material of sub grade should fulfill the technical specification


requirement and designed effective CBR of minimum 12%.

c) Gravel will be dumped and dozed to form a uniform un-compacted thickness


of approx. 250 to 300 mm as per the requirement of the mix.

d) The Gravel will be leveled by Motor Grader to form a un-compacted layer


which will meet the requirements.

e) The Gravel will be dozed, graded; water will be sprinkled at  2% of OMC on


the entire area uniformly. The area will be compacted by means of 8 - 10 T
vibratory roller with adequate no. of passes of the roller so as to achieve
97% of MDD with a compacted thickness of 250mm. (Compaction as per
MORTH clause-305.3.4 and Table-300.1).

f) Sub grade layers will be supported by earthen confinement in extreme end


to restrict erosion.

6.0 Quality Control and Testing

Quality control tests shall be done as per Sl. no. 1 of Quality Control Tests and
Acceptance Criteria

Revision No Page No
23
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I

Method Statement For Backfilling Behind Abutment


& Around Structures

Revision
Date WMS No: Prepared By Reviewed By Approved By
No:

ARTL/QAP/WMS/
18.01.20
R0 06
22

Revision No Page No
24
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I

Method Statement For Backfilling Behind Abutment & Around Structures

1.0 Purpose

This Method Statement provides detail of procedure adopted for the


construction of backfilling behind structures and abutment.

2.0 Scope

This work will consist of backfilling behind abutment of bridges and around
structures like foundations, underpass, box culvert and other similar structures
in accordance with the requirements of these specifications (MORTH clause
no. 305.4.4)and lines & dimensions shown in the drawing or as indicated by
the Engineer.

3.0 Material

Approved material will be used as a backfill material from approved sources.


Fill material shall be free from logs, stumps, roots, rubbish or any other
ingredients likely to deteriorate or affect the structure.

4.0 Responsibility

Section In charge will be responsible for quality control of the section for the
backfilling work. He will liaise with Concessionaire Engineer In Charge. Further
he will be assisted by field Engineers, Surveyors, Supervisors and lab
technicians.

5.0 Equipment

The following construction machineries will be deployed for backfilling work.

Dumper / trucks

Grader

Small Vibratory Roller

Water tanker

Plate Compactor

Revision No Page No
25
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I

6.0 Procedure

6.1 Backfilling around structures

Backfilling will be done with approved material after concrete or masonry is


fully set and carried out in such a way as not to cause undue thrust on any
part of the structure. All spaces between foundation, masonry or concrete and
sites of excavation will be backfilled. Fill material will be spread in layers
manually or by grader in layers of uniform thickness not exceeding 250mm
compacted thickness over the entire width of the structure. Each layer of
approved materials will be thoroughly compacted after necessary watering by
means of small vibratory rollers/plate compactor or thoroughly rammed in
small areas where mechanical means cannot be deployed. Successive layers
will not be placed until the layers under construction have been thoroughly
compacted to the specified requirement of Table 300-2, i: e; 95% and 97% of
MDD at OMC for embankment and sub grade respectively.

6.2 Backfilling Behind abutment and Wing wall

Filling behind abutments and wing walls for all structures without weep-hole,
will be done with approved filling material. The fill material will be deposited in
loose thickness and compacted after necessary watering up to a thickness of
250mm, until the required compaction of 95% & 97% of MDD at OMC achieved,
for embankment & sub grade respectively. Filling will be carried out in equal
layers on each side of the structures to avoid displacement and unequal
pressure.

Where provision of any filter media is specified behind abutment (where weep-
hole exists), filter media as designed will be laid and compacted after
necessary watering up to a compacted thickness of 250mm until 95% & 97% of
MDD at OMC achieved, for embankment & sub grade respectively. The material
used for filter media will conform to the requirement for filter medium spelt
out in clause 2504.2 / 309.3.2.

If impracticable to use conventional rollers, the compaction will be carried out


by mechanical means like small vibratory roller/plate compactor. Care will be
taken to see that, the compaction Equipment does not hit or come too close to
any structural member, so as to cause any damage to them or excessive
pressure against the structure.

7.0 Quality Control and Testing

Revision No Page No
26
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I

Quality control tests shall be done as per Sl. no. 1 of Quality Control Tests and
Acceptance Criteria

8.0 Safety & Environment

While working Safety & Environment Procedure shall be followed as per


approved EHS Manual.

Revision No Page No
27
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I

Method Statement for the Construction of Granular


Sub Base

Revision
Date WMS No: Prepared By Reviewed By Approved By
No:

ARTL/QAP/WMS/
18.01.20
R0 07
22

Revision No Page No
28
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I

Method Statement for the Construction of Granular Sub Base

1.0 Purpose

This section provides details of Method Statement adopted for the granular
sub-base construction activity.

2.0 Scope

The Scope of plan covers laying and compacting well-graded material on


prepared sub-grade.

3.0 Responsibility

Section In charge will be responsible for quality control of the section for the
construction of Sub-base. He will liaise with the Engineer In charge.
Further he will be assisted by the field engineers, surveyors, supervisors and
lab technicians.

4.0 Procedure

Before laying of sub-base over already finished sub-grade all the vegetation
shall be removed, if any. Light sprinkling of water shall be done as required and
rolled with two passes of 8 to 10 ton vibratory roller.The materials of GSB layer
shall be Grading V & VI as per Table 400-1 of MORTH. The material shall be
brought at site first and dumped in heap in such a way that after spreading
and compaction the required thickness is obtained.

The spreading shall be done with the help of motor grader of required
capacity. Rolling shall start immediately after spreading with the help of
vibratory roller of 8 to 10 ton static weight. Rolling shall commence at the
lower edge and proceed towards the upper edge longitudinally for portions
having unidirectional cross fall. Each pass of roller shall uniformly overlap not
less than one third of track made in the preceding pass. The grade and cross
fall shall be checked and any high spots or depressions, which become
apparent will be corrected by removing or adding fresh material. The speed of
roller shall not exceed 5km/hr. Rolling shall be continued until the density
achieved is at least 98% of the maximum dry density.

5.0 Quality Control and Testing

Revision No Page No
29
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I

Quality control tests shall be done as per Sl. no. 3 of Quality Control Tests and
Acceptance Criteria

6.0 Safety & Environment

While working Safety & Environment Procedure shall be followed as per


approved EHS Manual.

Revision No Page No
30
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I

Method Statement for the Construction of Cement


Treated Sub-Base/Base

Revision
Date WMS No: Prepared By Reviewed By Approved By
No:

ARTL/QAP/WMS/
18.01.20
R0 08
22

Revision No Page No
31
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I

Method Statement for the Construction of Cement Treated Sub-Base/Base

1.0 Purpose

This provides details of Method Statement to be adopted for CTSB/CTB laying


and compaction.

2.0 Scope

This work shall consist of mixing, laying and compacting of aggregates mixed
with cement or cement-fly ash in a mixing plant as a sub-base/base course on
prepared sub grade/sub-base in accordance with the requirements of the
Specifications and in conformity with the lines, grades and cross-sections
shown on the drawings or as directed by the Engineer.

3.0 Equipment

Mixing Plant

Dumpers/Tippers

Water Tanker

Paver

Roller

4.0 Responsibility

Section In charge will be responsible for quality control of the section for the
construction CTSB/CTB. He will liaise with the Concessionaire Engineer In
charge. Further he will be assisted by field engineers, surveyors, supervisors
and lab technicians

5.0 Procedure

Construction operation shall be as per Clause 403.3 of MORTH or Chapter 5 of


IRC SP 89. Before laying CTSB/CTB on already prepared sub base, the shoulder
shall be constructed first in order to provide confinement.

Material for the CTSB/CTB shall be prepared as per mix design in mixing plant.
Moisture shall be maintained within tolerance range as determined by Mix

Revision No Page No
32
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I

Design. The mix shall be spread by a paver finisher in full width of pavement as
per approved drawing. In exceptional cases where it is not possible for the
paver to be utilized, mechanical means like motor grader may be used with the
prior approval of the Engineer. Maximum care shall be taken to spread the
material uniformly. The compaction shall be carried out as per clause 403.3.5
with the help of vibratory roller of 8T to 10 T static weight. Rolling shall be
continued until the density achieved is at least 98 percent of maximum dry
density.

The sub-base/base course shall be suitable cured for 7 days. Subsequent


pavement course shall be laid soon after to prevent the surface from drying
out and becoming friable. No traffic of any kind shall ply over the completed
sub-base/base unless permitted by the Engineer.

6.0 Quality Control and Testing

Quality control tests shall be done as per Sl. no. 4 of Quality Control Tests and
Acceptance Criteria

7.0 Safety & Environment

While working Safety & Environment Procedure shall be followed as per


approved EHS Manual.

Revision No Page No
33
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I

Method Statement for the Construction of Wet Mix


Macadam

Revision
Date WMS No: Prepared By Reviewed By Approved By
No:

ARTL/QAP/WMS/
18.01.20
R0 09
22

Revision No Page No
34
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I

Method Statement for the Construction of Wet Mix Macadam

1.0 Purpose

This provides details of Method Statement adopted for the Wet Mix Macadam
laying and compaction.

2.0 Scope

The Scope of plan covers following activities:

Laying and compacting clean, crushed, graded aggregate, RAP + graded


aggregate, pre mixed with necessary moisture, to a dense mass on a prepared
sub base in accordance with the requirement of the specifications.

3.0 Responsibility

Section In charge will be responsible for quality control of the section for the
construction of WMM. He will liaise with the Concessionaire Engineer In
charge. Further he will be assisted by field engineers, surveyors, supervisors
and lab technicians.

4.0 Procedure

Construction operation shall be as per Clause 406.3. Before laying Wet Mix
Macadam (WMM) on already prepared GSB/CTB, the shoulder shall be
constructed first in order to provide confinement. Material for the wet mix
macadam shall be prepared as per mix design in the wet mix plant. Moisture
shall be maintained within tolerance range as determined by Mix Design. The
mix shall be spread by a paver finisher in full width of a pavement including
hard shoulder as per Clause 406.3.4.In exceptional cases where it is not
possible for the paver to be utilized, mechanical means like motor grader may
be used with the prior approval of the Engineer. Maximum care shall be taken
to spread the material uniformly. The compaction shall be carried out as per
clause 406.3.5 with the help of vibratory roller of 8T to10 T static weight.
Rolling shall be continued until the density achieved is at least 98 percent of
maximum dry density for material.

5.0 Quality Control Testing and Acceptance

Quality control tests shall be done as per Sl. no. 5 of Quality Control Tests and
Acceptance Criteria

Revision No Page No
35
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I

6.0 Safety & Environment

While working Safety & Environment Procedure shall be followed as per


approved EHS Manual.

Revision No Page No
36
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I

Method Statement for Prime Coat/Tack Coat

Revision
Date WMS No: Prepared By Reviewed By Approved By
No:

ARTL/QAP/WMS/
18.01.20
R0 10
22

Revision No Page No
37
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I

Method Statement for the Prime Coat/Tack Coat

1.0 Purpose

The Method Statement provides detail of the procedure adopted for the
application of Tack Coat and Prime Coat. A prime coat is an application of low
viscosity bituminous binder to an absorbent non-bituminous surface. A tack
coat is a light application of bituminous binder to a bituminous or concrete
surface.

2.0 Scope

The Scope of the Plan covers the following activities:

 Preparation of surface

 Application of Prime coat/Tack coat over the prepared base as per


MORTH.

 The primer shall be cationic bitumen emulsion SS1 grade conforming to


IS:8887 or medium curing cutback bitumen conforming to IS:217.

 Tack coat shall be RS-1.

3.0 Responsibility

Section In charge will be responsible for execution and Quality Control


Manager for overall quality of materials for the section where the application
of Prime coat/Tack coat will be done. Both will liaise with the Concessionaire
Engineer In charge. Further, Surveyors and Supervisors will assist Field
Engineer whereas Lab Technicians will assist Quality Control Engineer

4.0 Equipment

The following construction machinery will be used for the execution of the
work.

Broomer, Compressor, Bitumen distributor.

5.0 Site Trials

Revision No Page No
38
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I

The full-scale application trials will be carried out on previously prepared base
surface using the plant and methods proposed.

The trials will be carried out with the agreement, and under supervision of the
Engineer.

Works associated with Prime coat/Tack coat will not commence until trial
sections have been approved. No variation in the spray or spread rates or type,
size, source or supply of materials will be made without the prior agreement of
the Engineer who shall have the authority to instruct further trial sections if
such variations should become necessary.

The trials will be carried out to demonstrate the suitability of the plant,
Equipment and work procedures and to confirm that the other specified
requirements of the Prime coat/Tack coat can be achieved.

The trial area shall be at least 50m long, and to the full construction width. It
may form part of the permanent works. The trial of Prime coat/Tack coat shall
be undertaken ahead of the proposed work to commence full-scale work.

The following data at each Site trial will be recorded:

The composition of the material cationic emulsion or cutback with the


bitumen content and type and grade of bitumen used,

The temperature of the Prime coat/Tack coat materials at the time of spraying.

The speed of vehicle and applied pressure at the time of spray.

The rate of application achieved at different speed of vehicle, spray


temperature of materials and pressure applied during spray.

The site trial shall be deemed to be successful if all specified sets of results
meet the specified requirements for the material. The above data as recorded
in the site trial shall become the agreed basis on which the particular material
shall be provided and processed to achieve the specified requirements.

6.0 Procedure

6.1 Preparation of Surface

Revision No Page No
39
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I

6.1.1 Immediately before spraying, all loose material and foreign matter will
be removed by thorough brushing with mechanical brooms and/or washing or
other accepTable methods. All hardened mud or other foreign matter will be
loosened by scraping before sweeping. The debris shall be deposited well
clear of the surface to be sprayed. It shall be shaped to the specified grades
and section.

6.1.2 Immediately prior to the commencement of all bituminous spraying on


surface, Engineer's approval will be taken. Any defect of the surface shall be
made good as instructed by the Engineer.

6.2 Application of Prime Coat and Tack Coat

6.2.1 As soon as the surface preparation as specified in section 6.1.1 has been
carried out to the approval of the Engineer, the primer or tack coat will be
sprayed at the specified rate. The quantity of binder used shall give complete
coverage of the surface with a light trace of run-off in places. The edge of the
area to be sprayed will be marked out with a line of string or wire pegged down
at intervals not exceeding 15m on straights or 7.5 m on curves.

6.2.2 Emulsion will be sprayed from a constant pressure distributor of


minimum capacity 4KL complying with the requirements of the Specification.
Hand spraying, only at the discretion of the Engineer will be applied in small
areas or to make good defective areas such as those caused by a blocked
nozzle. Nozzles will be arranged to give a uniform spray and shall be tested
prior to spraying by plate test. If during spraying, a nozzle becomes blocked or
develops a defect, the nozzle shall be cleaned/ replaced and spraying shall be
continued. Any area incompletely sprayed shall be made good with a hand-
spray. The machine shall be repaired before further spraying is commenced.

6.2.3 Temperatures of Application:

The range of temperature at the time of application will be between 20 to


70C for bituminous emulsion.

The range of temperature at the time of application will be between 50 to


800C for cutback.

7.0 Curing and Blinding of Prime Coat

Revision No Page No
40
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I

7.1 Following the application of bituminous material, the surface will be


allowed to cure for at least 24 hours or for any other period so as to allow
penetration into the base course and oxidation. If it is not absorbed within 24
hours after application, sand will be sprayed over the surface to blot the
excess prime or tack coat materials. Care will be taken to prevent over priming;
any pools of excess primer left on any part of the surface will be swept out
over the adjacent surface before spreading sand.

7.2 All loose material on the sprayed surface, including any blinding
material, will be removed before any further bituminous binder is sprayed.

8.0 Limitations to Construction

8.1 The work will not be carried out in adverse weather conditions or when
prescribed by the Engineer.

8.2 Bituminous material will not be applied to wet or frozen surfaces or


when weather conditions otherwise prevent the proper handling and finishing
of the mixture. The bituminous material will be placed when both the ambient
0
temperatures and road surface temperatures are greater than 10 C with rising
trend and the wind velocity is less than 50 km/hr. The materials will be laid
when the prevailing conditions in the field allow the specified requirement to
be fulfilled.

9.0 Quality Control Testing and Acceptance

Quality control tests shall be done as per Sl. no. 6.0 of Quality Control Tests
and Acceptance Criteria

10.0 Safety & Environment

While working Safety & Environment Procedure shall be followed as per


approved EHS Manual.

Revision No Page No
41
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I

Method Statement for the Construction of Dense


Bituminous Macadam

Revision
Date WMS No: Prepared By Reviewed By Approved By
No:

ARTL/QAP/WMS/
18.01.20
R0 11
22

Revision No Page No
42
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I

Method Statement for the Construction of Dense Bituminous Macadam

1.0 Purpose

This work shall consist of laying and compacting well graded material on
prepared wet mix macadam in accordance with the requirements of these
specifications. The material shall be laid in single layer/double layer as shown
in cross section drawing or as directed by the Engineer.

2.0 Scope

The Scope of this Method Statement shall cover the following activities:

(i) Identification of Sources, Bitumen & aggregates for DBM, materials


Selection, Testing and Approval of all Materials and finalization of mixing
proportions, trials etc.

(ii) Survey and Setting out Works.

(iii) Laying of Dense Bituminous Macadam with sensor paver, compacting and
testing as per Technical Specifications and approved Inspection and Test
Plans.

3.0 Responsibility

Section In charge will be responsible for execution and Material Engineer for
overall quality of materials for the section. Both will liaise with Engineer and
Employer related to their job. Further, Site Engineer, Surveyors and Supervisors
Lab Technicians will assist.

4.0 Equipment

The construction machinery used for the execution of the work is as follows:

 Hot mix Plant

 Vibratory tandem roller

 Pneumatic Tyre roller,

 Sensor Paver

Revision No Page No
43
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I

 Pneumatic Blower

 Water tanker

 Tippers and Dumpers.

Rollers : Refer Cl .501.6-MORT& H

(a) The initial or breakdown rolling shall be done with 8-10 tons smooth
wheeled tandem Rollers.

(b) The intermediate rolling shall be done with 8-10 ton dead weight
vibratory roller or with a Pneumatic tyre roller of 12-15 ton weight, with tyre
Pressure of at least 5.6 kg/cm2.

(c) Finishing rolling shall be done with smooth wheeled tandem Rollers.

5.0 Material Requirement for Dense Graded Bituminous layer

5.1 Physical Requirement

The coarse aggregates to be used in DBM shall be crushed rock, or other hard
material retained on the 2.36mm sieve. Use of RAP shall be in accordance with
MORTH section 519. The material should be hard, sound, durable and un
weathered. It shall contain no deleterious constituents such as organic matter
clay and decomposed rock. The Fine aggregate shall be crushed or naturally
occurring mineral material, or a combination of the two, passing the 2.36mm
sieve and retained on 75micron sieve. It shall be free from dust organic or
other deleterious matter. The bitumen/final binder shall be paving bitumen of
VG40/VG30 grade conforming to IS:73. The Filler shall be finely divided mineral
matter such as rock dust, hydrated lime or cement as approved by the
Engineer and conform to Table 500-9 of MORTH specifications. The grading
shall confirm to grading-2 given in Table 500-10.

5.2 General Requirement

The material to be used in the Dense Graded Bituminous material shall meet
the other physical requirements as per MORTH Cl: 505.3.1.

6.0 Construction of trial stretch

Revision No Page No
44
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I

Laying trials shall be carried out at a trial stretch to demonstrate the laying
and compaction of the proposed mix in accordance with clause 501.

7.0 Procedure

7.1 Preparation of base

Before laying of Dense Graded Bituminous Macadam, the base on which it is to


be laid shall be prepared in accordance with Clause 501 and 902 as
appropriate or as directed by the Engineer. The surface shall be thoroughly
swept clean by a mechanical broom and the dust removed by compressed air.

7.2 Prime Coat

A Prime coat shall be applied in accordance with the provisions of Clause 502,
if DBM is to be laid on other than a bitumen bound layer.

7.3 Mixing and Transportation of the Mixture

The material to be used for DBM shall be as per approved Job mix formula,
conforming to MORTH Table 500-10. The material shall be prepared in a Hot
Mix Plant of adequate capacity. Appropriate mixing temperature shall be
maintained as per Table 500-2 of MORTH specifications. The bituminous
material shall be transported in clean and covered tippers to the place of
laying.

7.4 Spreading of material

DBM material shall be laid in layers of uniform thickness as given in the


approved drawings over the Wet mix macadam/Profile corrective layer in
accordance with clause 501.5. It shall be spread, leveled and tamped by an
approved self propelled paving machine. In areas where mechanical paver
cannot be used, the material shall be spread, raked and leveled with suitable
hand tools and compacted.

The surface finish of DBM Layer shall be checked and all the high and low
spots remedied by removing or adding DBM Material as may be required. The
surface finish shall conform to the requirements of Clause 902.

Revision No Page No
45
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I

7.5 Compaction

Bituminous materials shall be laid and compacted in layers, which enable the
specified thickness, surface level, regularity requirements and compaction to
be achieved.

Compaction of bituminous materials shall commence as soon as possible after


laying. Compaction shall be substantially completed before the temperature
falls below the minimum rolling temperatures stated in the relevant part of
these Specifications. Rolling of the longitudinal joints shall be done
immediately behind the paving operation. After this, rolling shall commence at
the edges and progress towards the centre longitudinally except that on super
elevated and unidirectional cambered portions, it shall progress from the lower
to the upper edge parallel to the centre line of the pavement. Rolling shall
continue until all roller marks have been removed from the surface. All
deficiencies in the surface after laying shall be made good by the attendants
behind the paver, before initial rolling is commenced. The initial or breakdown
rolling shall be done with 8-10 ton dead weight smooth-wheeled rollers. The
intermediate rolling shall be done with 8-10 ton dead weight or vibratory roller
or with a pneumatic tyre roller of 12 to 15 ton weight with a tyre pressure of at
least 5.6 kg/sqcm. The finish rolling shall be done with smooth wheeled
tandem rollers/PTR.

Where compaction is to be determined by density of cores the requirements to


prove the performance of rollers shall apply in order to demonstrate that the
specified density can he achieved. In such cases the Contractor shall nominate
the plant, and the method by which he intends to achieve the specified level of
compaction and finish at temperatures above the minimum specified rolling
temperature. Laying trials shall then demonstrate the acceptability of the
plant and method used. Bituminous materials shall be rolled in a longitudinal
direction, with the driven rolls nearest the paver. The roller shall first compact
material adjacent to joints and then work from the lower to the upper side of
the layer, overlapping on successive passes byat least one-third of the width of
the rear roll or, in the case of a pneumatic tyre roller, at least the nominal
width of 300mm.

In portions with super-elevated and uni-directional camber, after the edge has
been rolled, the roller shall progress from the lower to the upper edge. Rollers
should move at a speed of not more than 5 km per hour. The roller shall not be
permitted to stand on pavement, which has not been fully compacted, and
necessary precautions shall be taken to prevent dropping of oil, grease, petrol

Revision No Page No
46
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I

or other foreign matter on the pavement either when the rollers are operating
or standing. The wheels of rollers shall be kept moist with water, and the spray
system provided with the machine shall be in good working order, to prevent
the mixture from adhering to the wheels. Only sufficient moisture to prevent
adhesion between the wheels of rollers and the mixture should be used.
Surplus water shall not be allowed to stand on the partially compacted
pavement. Rolling pattern as determined from trials will be adopted for the full
works.

7.6 Limitations to laying DBM

The work will not be carried out in adverse weather conditions or when
prescribed by the Engineer. Bituminous material will not be applied to wet or
frozen surfaces or when weather conditions otherwise prevent the proper
handling and finishing of the mixture. The bituminous material will be placed
when both the ambient temperatures and road surface temperatures are
greater than 10°C with rising trend.

7.7 Opening to Traffic

The newly laid surface shall not be open to traffic for at least 24 hrs after
laying and completion of compaction, without the express approval of
Engineer in writing.

8.0 Surface Finish

The surface finish of construction shall be conformed to the requirements of


Clause 902

9.0 Quality Control Testing and Acceptance

Quality control tests shall be done as per Sl. No 7 of Quality Control Tests and
Acceptance Criteria

10.0 Safety & Environment

While working Safety & Environment Procedure shall be followed as per


approved EHS Manual

Revision No Page No
47
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I

Method Statement for the Construction of


Bituminous Concrete

Revision
Date WMS No: Prepared By Reviewed By Approved By
No:

ARTL/QAP/WMS/
18.01.20
R0 12
22

Revision No Page No
48
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I

Method Statement for the Construction of Bituminous Concrete

1.0 Purpose

The Method Statement provides the method to be adopted for construction of


Bituminous Concrete works, a thoroughly controlled, hot-mixed, hot-laid, plant
mix of well-graded dried aggregates, filler and bitumen that, when compacted,
forms a dense layer. This work consists of constructing in a single layer
Bituminous Concrete of thickness as mentioned in the drawing on previously
prepared Bituminous Course to the specified requirements.

2.0 Scope

The Scope of the Method Statement covers the laying and compacting well-
graded BC material on prepared DBM/existing road surface as per the
approved drawings. It involves the following:

(i) Identification of sources of bitumen & aggregates for BC, proper


selection of material, it’s testing and approval of the mix after trials.

(ii) Survey and Setting out of works.

(iii) Site trial will be performed as per MORTH Section 900 before laying of
Bituminous Concrete at site with sensor paver, compacting and testing as per
Technical Specifications and approved QAP.

3.0 Responsibility

Section In charge will be responsible for the execution as well as quality


control of the section for construction of BC. He shall liaise with the
Independent Engineer. He will be assisted by field engineers and quality
control engineer. Further, field engineer will be assisted by surveyors and
supervisors whereas quality control engineer will be assisted by lab technician.

4.0 Equipment

The construction machinery used for the execution of the work is as follows:

 Hot mix Plant

 Vibratory tandem roller

Revision No Page No
49
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I

 Pneumatic tyre roller,

 Sensor Paver,

 Pneumatic Blower

 Water tanker

 Tippers and Dumpers.

5.0 Material Requirement for Bituminous Concrete

5.1 Physical Requirement

The materials used for preparation of BC will satisfy the specified


requirements as stated below:

 Bitumen shall be VG30/VG40 as per IS 73 from approved source.

 Coarse aggregate consist of crushed stone of specified sizes, Reclaimed


asphalt pavement (RAP) as per MORTH clause 519 will be used. Coarse
aggregate shall be clean, strong, durable of fairly cubical shape and free from
disintegrated pieces, organic or other deleterious matter and adherent
coating. Coarse aggregate obtained from approved source.

 Fine aggregate fraction of 4.75mm passing and filler passing 75micron


sieve consists crushed dust from approved source.

 Gradation of aggregates for Bituminous Concrete will be as per


requirements specified in Table 500-17 of MORTH specifications.

5.2 General Requirement

The material to be used in the Bituminous Concrete material shall meet the
other physical requirements as per MORTH Cl:.507.2

6.0 Procedure

6.1 Site Trials

The full-scale laying and compaction trials are carried out on BC materials for
the permanent works using the plant and methods proposed. The trials are

Revision No Page No
50
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I

carried out under supervision of the Engineer. The trials are carried out to
demonstrate the suitability of the plant, Equipment and work procedures to
provide and compact the material to the specified proportions, density and
voids content and to confirm that the other specified requirements of the
completed asphalt pavement can be achieved. The trial of pavement layer is
undertaken ahead of the proposed work to commence full-scale work. The
data retrieved from the trials i.e., composition, grading, bitumen content,
Marshall Parameters, rolling pattern and other test results which will be
submitted separately.

6.2 Preparation of Base

The base on which BC is to be laid will be prepared, shaped and conditioned to


the specified lines, grade and cross sections in accordance with Clause 501 or
as directed by the Engineer. The surface shall be thoroughly swept clean free
from foreign matter; loose materials and dust removed by thorough brushing
with mechanical brooms and/or blown off by compressed air or other
acceptable methods. Any defect of the surface will be made good as
instructed by the Engineer. A tack coat as needed will be applied in
accordance with Clause 503 or as directed by the Engineer in accordance with
the Method Statement.

6.3 Preparation of Mix

The BC mix will be prepared in a mixing plant.

The mixing plant will be of the batch-mix type and shall be capable of
regulating the composition of the mixture to within the tolerances specified by
Clause 507.3.4, Table 500-18 of MORTH.

The bitumen tank is capable of maintaining its contents at the specified


temperature and a fixed thermometer easily read from outside the tank. The
dryer is of the rotating drum type capable of heating the aggregates to the
temperatures as per MORTH Table 500-2. Bitumen will be heated to the
specified temperature in tanks and delivered to the mixing plant via insulated
pipes such that heat losses are minimized. The minimum mixing period will be
adopted to get the suitable mix. Plants shall have automatic controls that co-
ordinate the proportioning, timing, and discharge of the mixer.

Revision No Page No
51
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I

The mixing will be thorough to ensure that a homogeneous mixture is obtained


in which all particles of the aggregates are coated uniformly, and the
discharge temperature of mix shall be as per Table 500-2 of MORTH.

Bituminous mixes will be kept free of contamination and segregation during


transportation. Trucks used for hauling asphalt mixture will be adequately free
of petroleum oils, solvents or other materials that adversely affect asphalt
mixture.

6.4 Laying of Bituminous Mix

The BC mix will be laid by a self-propelled spreader finisher equipped with a


hopper, delivery augers and capable of spreading, tamping and finishing the
mix to specified grade, lines and cross-section. It shall be capable of laying
bituminous materials with no segregation, dragging, burning or other defects
and within the specified level and surface regularity tolerances and shall meet
the Specification as per Clause 507.4.

Immediately after receiving the transported materials from hot mix plant to the
site it will be spread on prepared and approved surface, the mixture will be
spread to line and level by the Sensor paver without segregation or dragging.
The temperature of mix at the time of lying will be as per Table 500-2 of
MORTH. The mixture will be placed in full width of the pavement. The
compacted thickness of any layer shall be as per specification. The paver shall
be capable of operating at forward speeds consistent with uniform and
continuous laying of the mixture.

Paver shall be equipped with accurate screed controls for maintaining the
screed at the specified longitudinal grade and transverse slope. The controls
shall be capable of maintaining the screed at the specified transverse slope.
Automatic controls in the paver shall be backed by manual controls that can
be optionally activated.

If the automatic controls fail or malfunction, the Equipment will be operated


manually for the remaining period of the normal working day, provided that the
specified requirements are met.

6.5 Compaction of The Laid Mix

Revision No Page No
52
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I

Sufficient rollers will be provided of appropriate types sizes and weights to


achieve the specified compaction. Rollers shall be self-propelled and of steel
wheel, pneumatic tyre and vibratory types, including combinations thereof,
capable of reversing without shoving or tearing the mixture.

Immediately after spreading the bituminous mixture, the mix will be


compacted thoroughly and uniformly by rolling in compliance with the general
procedures outlined below. Rolling shall continue until the layer under
compaction has attained the specified requirements.

Initial static rolling with a steel tandem roller as per MORTH Specification,
Section-500, Clause 501.6. The rollers shall be operated with uniform speed
not exceeding 5 km/hr.

Rolling shall normally commence from the outer edge and proceed
longitudinally parallel to the centerline, each pass overlapping the previous
pass by one half of the roller width. On super elevated curves, rolling shall
begin at the low side and progress to the high side. Where laying is carried out
care shall be taken to prevent the entrapment of water.

Intermediate vibratory rolling with steel tandem roller shall follow immediately
upon initial rolling.

Intermediate rolling will be done with pneumatic tyre roller having 0.56 MPA
tyre pressure. In case of failure of pneumatic tyre roller at site during operation
any one type of roller shall substitute the other for the day’s work to obtain the
specified requirement. Final static rolling with a steel wheel roller shall be used
to eliminate marks from previous rolling.

The roller wheels and drums shall be kept lightly moistened with water to
prevent adhesion of the mixture to the rollers.

All rolling operations shall be completed in all respects before the temperature
of the mix falls below 100°C.

Rolling pattern as determined from trials is adopted for the full works

6.6 Finishing of Edges

Any mixture that becomes loose or broken, mixed with dirt or foreign matter,
or defective will be removed, and it will be replaced with fresh hot mixture and
compacted.

Revision No Page No
53
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I

The edges of the course will be rolled concurrently with or immediately after
the finishing. In rolling the edges, roller wheels will extend 50 mm to 100 mm
beyond the edge.

Any fresh mixture on the existing work shall be removed carefully sweeping it
back on to un-compacted work, so as to avoid formation of irregularities at the
previous face.

6.7 Surface Finish

The surface finish of construction shall be conformed to the requirements of


Clause 902.

6.8 Limitations to Construction

The work will not be carried out in adverse weather conditions or when
prescribed by the Engineer.

Bituminous material will not be applied to wet or frozen surfaces or when


weather conditions otherwise prevent the proper handling and finishing of the
mixture. The bituminous material will be placed when both the ambient
temperatures and road surface temperatures are greater than 10°C with rising
trend.

7.0 Quality Control Testing and Acceptance

Quality control tests shall be done as per Sl. No 7 of Quality Control Tests and
Acceptance Criteria

8.0 Safety & Environment

While working Safety & Environment Procedure shall be followed as per


approved EHS Manual

Revision No Page No
54
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I

Method Statement for Mastic Asphalt Construction

Revision
Date WMS No: Prepared By Reviewed By Approved By
No:

ARTL/QAP/WMS/
18.01.20
R0 13
22

Revision No Page No
55
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I

Method Statement for Mastic Asphalt Construction

1.0 Purpose

This work shall consist of constructing a single layer of mastic asphalt wearing
course for road pavements or as water proofing layer for bridge decks under
the wearing course.

2.0 Material

2.1 Bitumen :Subject to the approval of the Engineer, the binder shall be a
paving/ Industrial grade bitumen meeting the requirements given in Table 500-
39 of MORTH

2.2 Coarse aggregate: The coarse aggregates shall consist of crushed


stone, crushed gravel/shingle or other stones.

2.3 Fine aggregate : The fine aggregates shall be the fraction passing
the 2.36 mm and retained on 0.075 mm sieve consisting of crusher run
screening, natural sand or a mixture of both

2.4 Filler: Lime stone powder passing through 75 micron I.S. sieve having
minimum Calcium Carbonate (CaCo3) content 80% by weight.

3.0 Responsibility

Section In charge will be responsible for the execution as well as quality


control of the. He will be assisted by field engineers and quality control
engineer. Further, field engineer will be assisted by surveyors and supervisors
whereas quality control engineer will be assisted by lab technician.

4.0 Procedure

4.1 Weather limitation: Minimum air and surface temperature shall be 100C.
Laying will be suspended during rain, foggy weather or adverse situations.

4.2 Preparation of the Base: In case of a cement concrete base, the surface
shall be thoroughly swept and scraped clean and free of dust and other
deleterious matter. Under no circumstances bitumen mastic shall be spread on
a base containing a binder which will soften under high application
temperatures. If any such spots or area are there, the same shall be cut out
and repaired before the bitumen mastic is laid.

Revision No Page No
56
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I

4.3 Tack Coat: A tack coat as per MORTH Specification Clause 503 shall be
applied on the base or as directed by the Engineer.

4.4 Preparation of Mastic Asphalt: Preparation of bitumen mastic consists


of two stages the first stage shall be mixing of filler and fine aggregates and
then heating the mixture to a temperature of 1700C to 2000C. Required
quantity of bitumen shall be heated to 1700C to 1800C and added to the
heated aggregate. They shall be mixed and cooked in an approved type of
mechanically agitated mastic cooker for some time till the materials are
thoroughly mixed. Initially the filler alone is to be heated in the cooker for an
hour and then half the quantity of binder is added. After heating and mixing
for some time, the fine aggregates and the balance of binder are to be added
and further cooked for about one hour. The second stage is incorporation of
coarse aggregates and cooking the mixture for a total period of 3 hours.
During cooking and mixing, care shall be taken to ensure that the contents in
the cooker are at no time heated to a temperature exceeding 2000C.

4.5 Spreading: The bitumen mastic shall be deposited directly on the


prepared base and it is spread uniformly by means of wooden floats to the
required thickness. The mix shall be laid to the required width and thickness.
The temperature of the mix at the time of laying shall be around 1700C. In case
blowing takes place while laying the bitumen mastic, the bubbles shall be
punctured while it is hot and the surface treated well. Grafting shall be done.

4.6 Joints: It shall be ensured that all construction joints are properly and
truly made. These joints shall be made by warming existing mastic asphalt by
the application of an excess quantity of the hot mastic asphalt mix which
afterwards shall be trimmed off to make it flush with surfaces on either side.

5.0 Quality Control Testing and Acceptance

Quality control tests shall be done as per Sl. No 8 of Quality Control Tests and
Acceptance Criteria

6.0 Safety & Environment

While working Safety & Environment Procedure shall be followed as per


approved EHS Manual.

Revision No Page No
57
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I

Method Statement for the Construction of Dry


Lean Concrete (DLC)

Revision
Date WMS No: Prepared By Reviewed By Approved By
No:

ARTL/QAP/WMS/
18.01.20
R0 14
22

Revision No Page No
58
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I

1.0 Purpose

This Method Statement shall be applicable for construction of dry lean


concrete sub-base with approved materials and mix, to the lines, grades,
camber and thickness as shown in the drawing for general roads. For taxiway /
roadway / Toll plaza the work shall be executed as per the special technical
specifications for pavements.

2.0 Materials

2.1 Cementitious materials

These shall consist of Ordinary Portland Cement from approved source The
minimum cement content shall be 150 kg/cu.m of concrete. In case flyash is
blended at site as part replacement of cement, the quantity of flyash shall not
be more than 20 percent by weight of cementitious material and the content
of OPC shall not be less than 120 kg/cu.m.

2.2 Coarse aggregate

These shall be in conformation with IS 383. The coarse aggregate shall be dry,
clean, hard, and durable of crushed stone. The maximum size of the coarse
aggregate shall be 26.5 mm, and aggregate gradation shall comply with Table
600-1.

2.3 Fine aggregate

The fine aggregates shall consist of clean natural sand or crushed stone sand
or a combination of the two and shall conform to IS 383.

The blended aggregate of coarse and fine aggregate shall confirm to the
following gradation as per Table 600-1 of MORTH

IS Sieve (mm) % of passing


26.5 100
19 75-95
9.5 50-70
4.75 30-55

Revision No Page No
59
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I

2.36 17-42
0.600 8-22
0.300 7-17
0.150 2-12
0.075 0-10

2.4 Water

Water used for mixing and curing of concrete shall meet the requirements of
IS 456.

3.0 Procedure

3.1 Mix

The mix shall be proportioned with a maximum aggregate cement ratio of 15:1
and with minimum cement content of 150kG/cum. However, the proportions of
aggregate to cement can be increased based on the trial mix and performance
during the trail stretch. Trial mixes with moisture contents of 5.0, 5.5, 6.0, 6.5
and 7.0 %shall be made using the above stated cement and blended
aggregates. Optimum moisture and density shall be obtained by making cubes.
These cubes shall be made in three layers, each layer being compacted with
electronic/pneumatic vibratory hammer of 300-400N downward force. After
the determination of moisture a set of 6 cubes shall be cast for determination
of compressive strength on 3 and 7 days. The average compressive strength of
each consecutive group of 5 cubes shall not be less than 10 MPa at 7 days. In
addition, the minimum compressive strength of any individual cube shall not
be less than 7.5 MPa at 7 days. If the required compressive strength is not
achieved, increasing the cement shall make trials and the above stated
procedure shall be repeated to achieve the required strength. Before
production of concrete, natural moisture in the aggregate shall be determined
and adjusted on day-to-day basis.

3.2 Mixing

The materials shall be mixed in a mechanized batching plant, with weighing


balances calibrated. While mixing, moisture content shall be kept optimum +
2%, to avoid the evaporation losses.

Revision No Page No
60
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I

3.3 Trial Stretch

A trial stretch shall be made to the required width. The in-situ density of the
freshly laid concrete shall be determined by sand replacement method by
making 3 density holes at equal distances that diagonally bisects the trial
length, these shall not be made in the strip of 500mm from the edges. The
average of these shall be considered as 100%, and with this the field density of
the regular work shall be compared. The hardened concrete may be cut for 3m
width in the trial length and reversed to check the bottom surface for any
segregation or honey-combing, if found necessary adjustments shall be made
in the mix design.

3.4 Transportation and placing

The plant mix concrete shall be transported by sufficient number of trucks to


ensure continuous, uniform supply of concrete to feed the laying Equipment.
The mix shall be protected from the weather, by covering the tippers/dumpers
with tarpaulin during the transit. The lean concrete shall be laid to the
required widths, grades, camber and thickness with self-propelled, electronic
sensor/mechanical paver. The Equipment shall be capable of laying the
materials in an even manner without segregation, to the specified thickness
after the compaction. The paving machine shall have high amplitude tamping
bars to give good initial compaction.

3.5 Compaction

The compaction shall commence as soon as the concrete laid and leveled to
the full width till there is no further movement under the roller and the surface
is closed. In addition to the number of passes required for compaction, there
shall be a pass without vibration as preliminary pass and another at the end as
final pass. The minimum dry density obtained shall be 97% of that achieved in
trial length, and at a distance of 500mm from edge it shall be 95% of that
achieved in the trial length. The final surface shall be inspected immediately,
and all loose, segregated or defective areas shall be corrected by using fresh
lean concrete. Honeycombed areas, any level/ thickness deficiency and surface
irregularities shall be corrected by concrete with 10mm and down aggregates.
Special care and attention shall be exercised during compaction near joints,
kerb, channels, side forms, around gullies and manholes.

Longitudinal and transverse joints shall be provided as shown in drawings. At


these joints unless vertical forms are used, the edge shall be cut back to a

Revision No Page No
61
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I

vertical face where correct thickness of compacted layer has obtained. Curing
shall be done by covering the surface with gunny bags/ hessian cloth, which
shall be kept continuously moist for 7days by sprinkling water.

4.0 Quality Control Testing and Acceptance

Quality control tests shall be done as per Sl. No 9 of Quality Control Tests and
Acceptance Criteria

5.0 Safety & Environment

While working Safety & Environment Procedure shall be followed as per


approved EHS Manual.

Revision No Page No
62
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I

Method Statement for the Construction of


Pavement Quality Concrete (PQC)

Revision
Date WMS No: Prepared By Reviewed By Approved By
No:

ARTL/QAP/WMS/
18.01.20
R0 15
22

Revision No Page No
63
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I

Method Statement for the Construction of Pavement Quality Concrete

1.0 Purpose

This Method Statement shall be applicable for construction of dowel jointed or


plain cement concrete pavement in accordance with the lines, grades, camber
and thickness as shown in the drawings using fixed forms.

2.0 Materials

2.1 Cement : Cement shall be OPC/PPC/PSC

Fly-ash upto 20 percent by weight of cementitious material may be used in


Ordinary Portland.

When Ordinary Portland Cement (OPC) is used the quantity of cement shall not
be less than 360 kg/cu.m. In case fly ash grade I (as per IS:3812) is blended at
site as part replacement of cement, the quantity of fly ash shall be upto 20
percent by weight of cementitious material and the quantity of OPC in such a
blend shall not be less than 310 kg/cu.m. The minimum of OPC content, in case
ground granulated blast furnace slag cement blended, shall also not be less
than 310 kg/m3.

2.2 Admixture: The admixtures shall confirm to IS 6925 and IS 9103 shall
improve the workability of concrete or extension of time and will not have any
effect on the properties of concrete. The performance of these admixtures will
be proved both on laboratory trials and in trial paving works.

2.3 Aggregates: The aggregates shall be of crushed stone or naturally


available confirming to IS 383, MORTH cl. 602.2.6.2 & 602.2.6.3. The coarse
aggregate shall be clean, hard, strong, dense and durable of crushed stone the
fine aggregate shall be of clean natural sand or crushed stone sand or
combination of both. These shall be free from clay, shale, loam, mica and other
organic matter. The combined gradation of fine and coarse aggregates shall be
as per Table 600-3 of MORTH.

2.4 Water : Water used for mixing and curing of concrete shall be free from
oil, salt, acid and other substances, which are harmful to concrete.

2.5 Dowel and tie bars : Dowel bars shall confirm to IS:432 of Grade I. High
yield Strength Deformed bars conforming to IS:1786 and grade of Fe 500 or
plain bars conforming to IS:432 of Grade I

Revision No Page No
64
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I

2.6 Pre-Molded joint filler: This shall be used for expansion joints abutting
structures like bridges, culverts and at end of the day’s work. These shall be of
20-25mm thickness or as shown in drawings. It shall be 25mm less in depth
than the thickness of slab provided in suitable lengths, which shall not be less
than lane width. Holes shall be made to accommodate dowel bars.

2.7 Joint sealing compound: The joint sealing compound shall be of hot
poured, elastomeric type or cold polysulphide/polyurethene/silicone type
having flexibility, resistance to age hardening and durability as per IRC:57.

2.8 Separation membrane: A separation membrane of impermeable plastic


sheeting 125 microns thick shall lay between the concrete slab and sub-base
by nailing with concrete nails to the lower layer. Where overlap is necessary
the same shall be laid by at least 300mm.

3.0 Procedure

3.1 Mix :The mix shall be designed as per IRC:44 or IS 10262. And the
design shall be based on the flexural strength of concrete. The water content
shall be minimum required to provide workability for full compaction of the
concrete to the required density. The mix shall be proportioned to give an
average strength at 28 days exceeding the specified strength (4.5Mpa) by 1.65
times the standard deviation calculated from the flexural strength of the first
30 beams. The workability requirements at the batching plant and at site shall
be established by slump tests while doing trial length. A slump value of
2515mm is reasonable for slip form paving and 50±15mm for fixed form
paving.

The ratio of 7 days strength to 28 days strength shall be maintained, by testing


pairs of beams and cubes batch wise for at least six batches of trial mix.

3.2 Mixing :The materials shall be mixed in a mechanized batching plant


consisting of weigh hoppers, separate scales for cement, fine and coarse
aggregate with weighing balances calibrated, aggregates being proportioned
by automatic weighing devices using load cells. The concrete ingredients shall
be mixed thoroughly by a mixer to get a homogenous mix without being
segregated while discharge.

3.3 Joints dowel and tie bars : The location and type of joint shall be as
shown in the drawings.

Revision No Page No
65
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I

3.4 Contraction Joints

Transverse joints shall be contraction and expansion joints, cut with


mechanical saw, could start as early as 6-8 hours, i.e. initial hardening of
concrete, after paving. The contraction joints shall consist of mechanical sawn
joint groove, 3 to 5mm wide and 1/4 to 1/3 depth of the slab. The expansion
joints shall consist of a joint filler board positioned vertically with the
prefabricated assemblies along the line of joint.

The dowel bars shall mild steel with details and dimensions as indicated in the
drawings. Unless otherwise shown in the drawings the dowel bars shall be
positioned at the mid depths of the slab with suitable tools/means within +/-
20mm tolerances. The dowel bars shall be covered with plastic sheath for at
least 2/3rd from one end for contraction joint, and ½ length +50mm for
expansion joint. For expansion joints, a closely fitting cap of 100mm long shall
be provided at the sheath end. To block the entry of cement slurry between
dowels and cap a compressible sponge may be used.

The dowel bars shall be supported on cradles / chairs in pre-fabricated joint


assemblies positioned prior to the construction of slab or mechanically
inserted with vibration into the plastic concrete by a method which ensures
correct placement of the bars besides full re-compaction of the concrete
around the dowel bars.

3.5 Longitudinal Joints

The longitudinal joints shall be saw cut as shown in the drawings. A groove of
1/3rd the depth of the slab may be cut after the final set of the concrete. The
tie bars shall be deformed steel bars of 415 Mpa/500 Mpa complying to IS
1786. Tie bars shall be painted with bituminous paint for 75mm at the both
ends and positioned with suitable tools/means. Tie bars shall be placed within
the middle third of the slab depth.

Tie bars in the longitudinal joints shall be made up into rigid assemblies with
adequate supports to remain firmly in position during the construction of slab.

3.6 Construction Joints

Transverse construction joints shall be place whenever concreting is


completed for the day’s work on is suspended for more than 30 minutes. These

Revision No Page No
66
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I

shall be provided at regular location of contraction joints using dowel bars as


stated above.

Using sealants, not before 14days after construction of slab shall seal all
transverse and longitudinal joints, but prior to allowing the traffic ply on the
new construction.

3.7 Separation membrane

A separation membrane of impermeable plastic sheeting 125 microns thick


shall lay between the concrete slab and the sub base by nailing with concrete
nails to the lower layer. Wherever overlap is necessary, the same shall be laid
by at least 300mm. Before placing the separation membrane, the sub-base
shall be swept clean of all extraneous materials using high pressure water
jetting or compressed air.

4.0 Trial length

The trial panel shall be constructed which is proposed for the main work.

5.0 Construction by fixed form

This shall consist of straight side forms made of steel or other suitable
material. These shall have a depth equal to the prescribed thickness of the
pavement. These forms shall be straight and free from bends and warps. Side
forms shall be of sufficient rigidity in the form and in the interlocking
connection with adjoining form such that springing will not occur under the
weight of the sub grade and paving Equipment or from pressure of concrete.

The vibrators for concreting shall be either surface pan type or internal type
with immersed tube or multiple spuds.

After the final regulation of the slab and before the start of curing, the surface
of the concrete shall be brush-textured as per MORTH Cl. 602.9.11 at right
angles to the longitudinal axis. The surface and sides shall be cured by
application of curing compound or wet hessian bags. The curing compound
shall have a water retention efficiency of 90%. If water curing is done, the
pavement shall be covered with moist Hessian cloth or pond with water for at
least a period of 14 days.

6.0 Joints sealing

Revision No Page No
67
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I

When saw cuts joints are adopted in construction, they are not made to
provide the minimum width specified in the drawings, they shall be widened
subsequently by sawing before sealing, and the width and depth are controlled
by gauges. When sealants are applied, an appropriate primer shall also be used,
if recommended by the manufacturer and it shall be applied in accordance
with their requirements. The sealant shall be applied within the minimum and
maximum drying time of the primer recommended by the manufacturer. Before
sealing, the temporary seal provided for blocking the ingress of dirt, soil, etc.
should be removed. A highly compressible heat resistant paper-backed de-
bonding strip as shown in drawing shall be inserted in the groove to serve the
purpose of breaking the bond between sealant and the bottom of the groove
and to plug the joint groove, so that the sealant may not leak through the
cracks.

The road may be opened for regular traffic after completion of curing period
and after sealing of joints.

7.0 Sand Patch Test (for measuring the texture depth)

The surface to be tested shall be dried; any extraneous mortar and loose
material shall be removed and swept clean, using a wire brush at right angles
and parallel to the carriageway. A cylindrical container of 25ml capacity shall
be filled with sand passing 300microns sieve and retained on 150microns
sieve, compacted by tapping the base and excess sand stroked off to level with
the top of cylinder. Then the sand shall be poured on the surface to be tested
into a heap and spread with the help of flat wooden disc of 64mm diameter of
1.5mm thick, with its face kept flat, in a circular motion, so that the sand is
spread into a circular patch, with the surface depressions filled with sand to
the level of peaks.

The diameter of the patch shall be measured to the nearest 5mm. The texture
depth of concrete shall be calculated as follows:

Texture depth in mm = 31000/D2

Where D is the mean diameter of the patch.

Five such texture depth tests shall be taken along the diagonal line across the
lane width at least 2m apart, between 50m points along the road. No
measurement shall be taken within the 300mm of longitudinal edges of the
slab constructed in one pass.

Revision No Page No
68
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I

The requirements of texture depth as per MORTH Table 600-2 are as


follows:

Required texture depth


No. of (mm)
Time of test
measurements Specified
Tolerances
value
Between 24hrs. and
7days after the Average of
1.00 0.25
construction of the slab 5 measurements

Not later than 6 weeks,


Average of +0.25
before the road is 1.00
5 measurements -0.35
opened to traffic

8.0 Quality Control Testing and Acceptance


Quality control tests shall be done as per Sl. No 9 of Quality Control Tests and
Acceptance Criteria

9.0 Safety & Environment

While working Safety & Environment Procedure shall be followed as per


approved EHS Manual.

Revision No Page No
69
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I

Method Statement for the Construction of Kerb

Revision
Date WMS No: Prepared By Reviewed By Approved By
No:

ARTL/QAP/WMS/
18.01.20
R0 16
22

Revision No Page No
70
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I

Method Statement for Kerb Casting

1.0 Purpose

This Method Statement provides detail procedure for the laying of concrete
Kerb as per the approved drawing.

2.0 Scope

This work consists of constructing cement concrete kerb in the central median
and /or along the footpaths in conformity with the lines, levels and dimensions
as specified in the drawings.

3.0 Responsibility

Section In charge will be responsible for quality control of the section for the
construction of Kerb. Further field engineers, surveyors, supervisors and lab
technicians will assist him.

4.0 Equipment

A continuous kerb casting equipment will be deployed capable of laying the


kerb in required cross-sections and producing a well-compacted mass of
concrete.

Where continuous casting with Equipment is not practicable, manual


construction with suitable shutter will be done with the approval of the
Engineer.

5.0 Procedure

a. Lines and levels will be marked and the sensor of the kerb-casting
machine will be adjusted accordingly. Pegs will be put at every 10 meters
interval indicating the levels. These pegs will be joined with a metal wire.

b. The concrete of Grade M20 to be used for kerb will be produced at the
batching plant as per the approved mix formula.

c. The concrete will be loaded on to the transit mixer directly from the
batching plant and transported to the kerb location.

Revision No Page No
71
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I

d. Kerb casting will be laid on firm foundation of minimum 150 mm


thickness of cement concrete of M20 grade cast-in-situ and extending 50mm
beyond the kerb stone or over WMM surface as per site condition.

e. Before laying the foundation with lean concrete, the base will be leveled
and lightly watered to make it damp.

f. The cast - in - situ kerb will be constructed in all situations except at


location where continuous casting with Equipment is not practicable, manual
construction with suitable shutter with the approval of the Engineer.

g. In the median portions in the straight reaches, the kerb will be cast in
continuous lengths. In the portions where footpaths are provided and /or the
slope of the carriageway is towards median gap/recess will be provided in the
kerb by cutting to facilitate drainage openings.

h. After laying the kerb and just prior to 6 to 8 hours after laying of the
concrete, saw cut grooves will be provided at 5m intervals or as specified by
the engineer.

i. Curing of kerb will be done by applying curing compound / or any other


suitable method

j. Vertical and horizontal tolerances with respect to true line and level will
be + 6mm.

k. Saw joint groove mechanically cut to 3mm to 5mm wide.

6.0 Quality Control Testing and Acceptance

Quality control tests shall be done as per Sl. No 10 of Quality Control Tests and
Acceptance Criteria

7.0 Safety & Environment

While working Safety & Environment Procedure shall be followed as per


approved EHS Manual

Revision No Page No
72
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I

Method Statement Method Statement for Form


work/ Reinforcement/ Concrete

Revision
Date WMS No: Prepared By Reviewed By Approved By
No:

ARTL/QAP/WMS/
18.01.20
R0 17
22

Revision No Page No
73
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I

Method Statement for Form work/ Reinforcement/ Concrete

1.0 Scope

This item of work deals with formwork, reinforcement and placement of


concrete for all structures with approved materials as per the terms of
contract agreement

This item of work shall be dealt in compliance to Section 1500, 1600, and 1700
of Technical specifications.

2.0 Materials

The materials shall confirm to section 1000 of technical specifications.

2.1 Formwork

This work shall consists of providing and fixing of form work (shuttering) of
approved quality for cast- in- situ/ precast / pre-stressed plain or reinforced
concrete with necessary props, staging, centering, scaffolding and any
temporary construction required for their support.

2.2 Reinforcement

This work shall consist of providing and placing of high yield strength
deformed bars of the shape and dimensions as shown in approved drawings.

2.3 Concrete

This work shall consist of providing and placing of plain or reinforced concrete
of all grades with 20mm graded aggregates as defined in Technical
specifications, machine mixed and mechanically vibrated to the required level,
slope, etc. as per approved drawings.

The source of materials (for cement, coarse aggregate, fine aggregate, water,
admixture, reinforcement steel. Etc.) shall be identified and the sources will
confirm to the specifications mentioned on the drawings and the requirements
laid down in the section 1000 of MORTH or to the requirements specified by
the Engineer.

All the materials will be stored as per Specification clause 1014.

Revision No Page No
74
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I

2.3.1 Cement, Fly Ash & GGBS

Cement to be used shall be any of the following types with the prior approval
of the Engineer.

a. Ordinary Portland cement, to IS:269.

b. Sulphate resisting Portland cement, conforming to IS:12330.

c. Portland Pozzolana cement (fly ash based) conforming to IS:1489


(Part 1)

d. Portland slag cement conforming to IS :455

e. Rapid Hardening Portland cement, conforming to IS:8041

f. Low heat Portland cement conforming to IS :12600

Fly ash when used, shall neither be less than 20 percent nor shall be greater
than 35 percent of the total by mass of ordinary Portland cement and fly ash
and shall conform to grade-1 of IS:3812.

Ground granulated blast furnace (GGBS) slag when used, shall neither be less
than 50 percent nor greater than 70 percent of the total mass of ordinary
Portland cement and GGBS and shall conform to IS: 12089.

2.3.2 Water

The water to be used shall be free from oils, acids, alkalis, salts, sugar, organic
materials or other substances that may be deleterious to concrete and steel.
Potable water generally considered satisfactory. The water to be used shall
satisfy the requirements as per clause 1010 of technical specifications.

2.3.3 Coarse aggregate

Coarse aggregate shall consist of clean, hard, strong, dense, non-porous and
durable pieces of crushed stone. All coarse aggregates shall conform to clause
1107 of technical specifications and IS 383, when tested in accordance to IS
2386 parts 1 to 8.

2.3.4 Fine aggregate

Revision No Page No
75
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I

Fine aggregate shall consist of clean, hard, strong, dense, and durable pieces
of crushed stone or natural sand or a combination of both. All fine aggregates
shall confirm to IS 383, when tested in accordance to IS 2386 parts 1 to 8. The
fineness modulus of fine aggregate shall not be less than 2.0 or greater than
3.5. The grading shall confirm to Table 1000-2 of MOSRT&H specification.

2.3.5 Admixtures

Admixtures shall confirm to the requirements of IS 9103. The manufacturer


test certificate shall be furnished for each consignment. As Per Quality
Assurance plan, Admixture should be tested by the third party for checking the
properties of Admixture

2.3.6 Reinforcement

For plain or reinforced cement concrete or pre-stressed concrete the


reinforcement shall be of grade Fe 500/500D or any other higher grade
confirming to IS 1786 HYSD bars. The steel supplied shall be assembled in
accordance with approved drawings and shall ensure storing to avoid
deterioration and corrosion. As per Quality Assurance Plan, Reinforcement
should be tested by the third party for checking the properties of
Reinforcement Quality

3.0 Procedure

3.1 Formwork

a) The formwork shall provide a smooth finish of uniform texture and


appearance. This material shall leave no stains on the concrete and so fixed to
its backing as not to impart any blemishes.

b) Ensuring necessary care will be taken, the formwork in true to line,


levels, plumb, etc., rigid, adequately braced both horizontally and vertically.
Form joints shall be as much as minimized and foam should be provided at
every joint to avoid the leakage of slurry from concrete.

c) Required formwork shall be made out of plywood/ steel shutters to suit


the site conditions. Formwork materials shall be rigid, even surface, and
sufficiently strong to prevent deformation during concrete.

Revision No Page No
76
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I

d) Releasing agents such as diesel mixed with grease, shuttering oil, etc.
shall be applied before fixing formwork, and shall not allowed to come into
contact with any reinforcement or pre-stressing tendons and anchorages.

e) The formwork shall be cleaned carefully, dried and releasing agents shall
be applied before re-use.

f) The formwork shall be so removed as not to cause any damage to the


concrete. Centering shall be gradually and uniformly lowered so as the
concrete to take stresses due to its own weight uniformly and gradually to
avoid any shock or vibration.

g) Before re-use all components of formwork shall be examined for damage


and damage pieces shall be rectified. Before re-use all components shall be
cleaned of deposits of soils, concrete or other unwanted materials. Threaded
parts shall be oiled after cleaning.

h) Before any erection is taken up the design & drawing of complete farm
work (i.e. the farm as well as their supports) as per specification clause 1503 &
1507, has to be approved by the Engineer.

i) The removal of formwork shall be done as per specification clause 1508


and the used formwork will be reused is required as per specification clause
1509

3.2 Reinforcement Steel

a) Bar bending schedule shall be strictly as per approved drawings, and


reinforcement steel shall be cut and bend as per approved bar bending
schedule. Bars shall be bent cold to the specified shape and dimensions, using
a proper bar bender, operated by hand or power to obtain correct radii of
bends and shape.

b) Reinforcement bars shall be placed accurately in position as shown in


the drawings. The bars, crossing one another shall be tied together at every
intersection with binding wire (dia. of binding wire shall not be less than 1mm),
to make the skeleton of reinforcement rigid such that it does not get displaced
during placing of concrete or any other operation.

Revision No Page No
77
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I

c) Spacer bars at approx. 1m intervals shall separate layers of


reinforcement. The minimum dia. of spacer bar shall be 12mm to a maximum of
main reinforcement or maximum size of aggregate, whichever is greater. Cover
blocks of thickness equal to the specified cover shall be placed between
formwork and bars made of concrete/ cement mortar of specified grade of
concrete/ strength as those of the member.

d) Necessary stays, blocks, chairs, spacers, hangers, etc. or other subsidiary


reinforcement shall be provided and approved by engineer, to fix the
reinforcement firmly in its correct position. Laps shall be staggered.

3.3 Concrete

The grades of concrete shall be as specified in the drawings/ contract.


Necessary mix designs shall be carried out well in advance as per clause 1700
of MORTH specifications.

3.3.1 Mixing

a) The mixing of concrete shall be done in batch type concrete mixer or by


concrete batching and mixing plant. All measuring devices shall be maintained
in a clean and serviceable condition. Its accuracy shall be checked periodically.

b) Mixing of concrete shall be continued till the individual particle of


coarse aggregate shows complete coating of mortar containing its
proportionate amount of cement. Corrections in water and aggregate with
respect to moisture present in the aggregates shall be done on day-to-day
basis.

3.3.2 Transportation and placing

a) Concrete shall be transported and placed as near as practicable to its


final position, so that no contamination, segregation or loss of its constituent
materials takes place. Concrete from batching plants shall be transported by
scoop tippers or transit mixers.

b) The concrete shall be placed gently in position and shall not have a free
fall of 1.5m as per specification clause 1709.

c) Concrete shall be placed in horizontal layers to a compacted layer not


exceeding 450mm. Concrete when deposited shall have a temperature not
less than 50C and not more than 400C.

Revision No Page No
78
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I

d) All formwork and reinforcement shall be cleaned and made free from
standing water, dust, etc., immediately before placing concrete.

3.3.3 Compaction

a) Concrete shall be thoroughly compacted with vibrators or other means


during placing and worked around reinforcement, tendons, and embedded
figures and into corners of formwork to produce a dense homogeneous void-
free mass having a required surface finish.

b) When vibrators are used, vibration shall be done continuously during the
placing of each batch of concrete until expulsion air has practically ceased
and in a manner does not promote segregation. Where immersion vibrators are
used contact with reinforcement and all inserts shall be avoided. Standby
vibrators in serviceable conditions shall be kept at site so that they can be
used in the event of breakdowns.

4.0 Construction joints

a) Construction joints shall be avoided as far as possible, when unavoidable


shall be provided in a direction perpendicular to the axis of the member. The
old surface shall be thoroughly cleaned and soaked with water. Standing water
shall be removed and surface shall be wetted with neat cement slurry shortly
before placing of fresh concrete and shall be thoroughly compacted.
Concreting shall be carried out continuously up to the construction joints.

b) For a vertical construction joint, a supporting board shall be fixed


previously at predetermined position and shall be properly stayed to prevent
displacement or bulging when concrete is compacted against it. Concreting
shall be continued right up to the board.

5.0 Curing

a) Exposed surfaces of concrete shall be kept continuously in a damp or


wet condition by ponding or by covering with a layer of sacks, canvas, hessian
or by similar materials and shall be kept constantly wet at least for a period of
14 days.

b) Curing compounds shall be used upon the approval by the Engineer.


Curing compounds shall be continuously agitated before use. All concrete
cured by this method shall receive two applications; the first coat immediately

Revision No Page No
79
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I

after acceptance of surface finish, and the second coat shall be after first
coat has set, on the saturated surface before the surface water film
disappears.

6.0 Finishing

Immediately after removal of forms, exposed bars or bolts, if any, as far as


possible shall be removed, or if necessary, shall be cut inside the concrete
member to a depth at least 50mm below surface of concrete and the resulting
hole shall be filled by fresh cement mortar. All fins caused by form joints, all
cavities produced by removal of form ties all other holes and depressions,
honeycomb spots, broken edges or corners, and other defects, shall be
thoroughly cleaned, saturated with water, and carefully pointed and rendered
true with mortar of cement and fine aggregate mixed in the proportions used
in the grade of concrete. A surface, which has been thus rendered, shall be
kept moist for a period of 24hours.

10.0 Quality Control Testing and Acceptance

Quality control tests shall be done as per Sl. No 10 of Quality Control Tests and
Acceptance Criteria

11.0 Safety & Environment

While working Safety & Environment Procedure shall be followed as per


approved EHS Manual

Revision No Page No
80
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I

Method Statement Method Statement for


construction of Pipe Culvert

Revision
Date WMS No: Prepared By Reviewed By Approved By
No:

ARTL/QAP/WMS/
18.01.20
R0 18
22

Revision No Page No
81
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I

Method Statement for Pipe Culvert

1.0 Purpose

This work shall consist of furnishing and installing reinforced cement concrete
pipes, of the type, diameter and length as per design and details and at
locations shown on the drawings

2.0 Scope

The scope of work includes the following

Excavation

Head Wall construction

Bedding for Pipe

Laying of pipes

Jointing

Back Filling

3.0 Equipment

Backhoe loader/excavator
Formwork
Transit Mixer
Vibrator
Batching plant
Dewatering Pump, if required
Dumpers

4.0 Materials

All materials used in the construction of pipe culverts shall conform to the
requirements of Section 1000 of MORTH.

Each consignment of cement concrete pipes shall be inspected, tested before


incorporation in the work and should conform to IS 458.

Revision No Page No
82
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I

5.0 Responsibility

Section In-charge will be responsible for quality control of the section for the
construction of Kerb. Further field engineers, surveyors, supervisors and lab
technicians will assist him.

6.0 Procedure

6.1 Excavation

The foundation bed for pipe culverts & Head wall shall be excavated true to
the lines and grades shown on the drawings

6.2 Head Wall

PCC of specified grade and thickness shall be laid to the specified dimension
and level for leveling course below head walls as per approved drawing

The layout of the Head wall shall be made on the PCC as per approved drawing

The formwork shall be fixed to true line, levels, plumb, etc., rigid, adequately
braced both horizontally and vertically. Form joints shall be as much as
minimized shall be tight and shall not permit any leakage of slurry from
concrete.

 Concreting of head wall shall be carried out in two stages according to


site conditions.

 First stage shall be done up to bottom of Hume pipe.

 Second stage concreting shall be carried out. After placing and aligning
all the pipes

6.3 Bedding for Pipe

The bedding shall be sand / granular material passing 5.6mm sieve. Specified
thickness of granular material bedding shall be provided below the pipes as per
the approved drawing. The bed shall be compacted/rammed with adequate
water.

In case of high embankments where the height of fill is more than three times
the external diameter of the pipe, the embankment shall be built first to an

Revision No Page No
83
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I

elevation above the top of the pipe equal to the external diameter of the pipe,
and to width on each side of the pipe not less than five times the diameter of
pipe, after which the trench for pipe bedding shall be excavated

6.4 Laying of Pipes

 The arrangement for lowering the pipes in the bed shall be done
carefully so as not to cause damage or undue strain to the pipes, preferably it
shall be done by means of tripod, manual labour or by cranes for loading,
unloading & setting the pipes.

 The gap between two rows of pipes shall be at least 450mm or half the
diameter of the pipe, whichever is maximum for new culvert and existing gap
shall be maintained for widening of the existing culverts.

 The laying of NP4 pipes shall start from the outlet end & shall be
completed at the inlet end to specified lines & grades as specified in the
approved drawing.

6.5 Jointing

 The pipes shall be joined by flush joint. The ends of the pipes especially
shaped to form self-centering joint with a jointing space 13mm wide. The
jointing space shall be filled with cement mortar 1:2 sufficiently dry to remain
in position. The jointing shall be made with care so that the interior surface is
smooth & consistent with the interior surface of the pipe. The joints shall be
kept damp for at least four days till the joints are sufficiently hardened.

 The existing head walls shall be dismantled to the required level and
dimension as per the approved drawing. New pipe shall be jointed with the
existing pipe as shown in the approved drawing.

6.6 Pipe Encasing

Pipe encasing if any, shall be carried out as per the approved drawings in
accordance with the method statement detailed in ARARL/NH16/MS/18.

6.7 Back Filling

Revision No Page No
84
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I

Trenches shall be backfilled after the completion of jointing and encasing. The
backfill soil shall be clean, free from boulders, large roots, excessive amounts
of sods or other vegetable matter, and lumps and shall be approved by the
Engineer. Backfilling up to 300 mm above the top of the pipe shall be carefully
done and the soil thoroughly rammed, tamped or vibrated in layers not
exceeding 150 mm, particular care being taken to thoroughly consolidate the
materials under the haunches of the pipe. Approved pneumatic or light
mechanical tamping Equipment can be used.

Filling of the trench shall be carried out simultaneously on both sides of the
pipe in such a manner that unequal pressures do not occur.

In case of high embankment, after filling the trench up to the top of the pipe in
the above said manner, a loose fill of a depth equal to external diameter of the
pipe shall be placed over the pipe before further layers are added and
compacted

7.0 Quality Control Testing and Acceptance

Quality control tests shall be done as per Sl. No 10 & 14 of Quality Control
Tests and Acceptance Criteria

8.0 Safety & Environment

While working Safety & Environment Procedure shall be followed as per


approved EHS Manual

Revision No Page No
85
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I

Method Statement Method Statement for


construction of Box Culvert/Underpass

Revision
Date WMS No: Prepared By Reviewed By Approved By
No:

ARTL/QAP/WMS/
18.01.20
R0 19
22

Revision No Page No
86
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I

Method Statement for Box Culvert/Underpass

1. Purpose

This work shall consist of Method Statement adopted for the construction of
Box culvert and Under Pass.

2. Scope

The Scope of the plan covers the following activity.

 Site Clearance including removal of trees, Bushes, stumps etc.

 Excavation necessary for the construction of box culvert as per


technical specification and most specification

 Construction of Box culvert as per technical specification and MORTH


Specification.

3. Equipment

Backhoe loader/excavator, Formwork, Transit Mixer, Vibrator, Batching plant,


Dewatering Pump, if required

4. Responsibility

Section In charge will be responsible for the execution as well as quality


control. He will be assisted by field engineer. Further, field engineer will be
assisted by surveyors and supervisors whereas quality control engineer will be
assisted by lab technician

5. Procedure

5.1 Excavation

After the site has been cleaned according to clause 201. The limits of
excavation shall be set out true to lines, curves and slopes to clause 301.3.1.
The excavation shall be carried out as per MORTH clauses 304.3.2 & 2903. The
depth to which excavation shall be as shown on the drawings, where water is
met with in excavation due to stream flow, seepage, springs etc., adequate
measure shall be taken to pump out water to keep foundation trenches dry.

Revision No Page No
87
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I

5.2 Base Preparation

The bottom of foundation shall be leveled both longitudinally and transversely


and compacted by suitable compactor. Granular sand shall be filled by making
confined box and saturated by using water to achieve compaction.

Over compacted Granular sand fill a leveling course of concrete of required


thickness and grade as specified in drawing shall be laid.

5.3 Reinforcement

Reinforcement of Grade Fe 500/Fe 500D or higher grade confirming to IS


specification 1786 shall be used. The reinforcement steel shall be procured
from approved source. Bar bending schedule shall be prepared and got
approved from Independent Engineer. Bars shall be cut and bent cold to the
specified shape and dimension. Reinforcement bars shall be placed
accurately in position as shown on drawings. The bars crossing one another
shall be tied together at every intersection with binding wire conforming to
IS 280. Necessary stays, a blocks metal chair spacer etc. shall be provided to
fix the reinforcement in its correct position. Placing and fixing of
reinforcement shall be inspected and approved by engineer before placing
of concrete.

5.4 Formwork

Shuttering plates made of suitable material shall be used for inside and
outside wall shuttering. Vertical props and cross bracings of sufficient
strength shall be used to protect any bulkage / deformation of concrete. All
the joints shall be properly sealed. PVC joint, sealing tapes, foam, and rubber
will be used in order to prevent leakage of slurry.

Weep holes shall be provided as per drawing and specification.

5.5 Concreting

Revision No Page No
88
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I

Concrete of required grade and specification and as per approved mix


design shall be mixed at batching plant and transported to site by using
Transit Mixers. Concrete of grade as specified in drawings will be laid in the
bottom raft portion including haunch portion. Then sidewall will be
constructed in one lift depending on the height mentioned in drawing.
Concrete will be poured in the erected formwork by using Chutes/pump and
compacted by using needle vibrators.

Second phase of shuttering and formwork shall be erected for the top slab
and remaining portion of wall. Tying of slab reinforcement shall be done as
per drawing. Then concrete shall be poured and compacted. Concrete shall
not be freely dropped in to place from a height exceeding 1.5m. Curing shall
be done for 14 days by keeping surface moist.

6. Quality Control Testing and Acceptance

Quality control tests shall be done as per Sl. No 10 of Quality Control Tests and
Acceptance Criteria

7. Safety & Environment

While working Safety & Environment Procedure shall be followed as per


approved EHS Manual

Revision No Page No
89
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I

Method Statement Method Statement for


construction of Open Foundation

Revision
Date WMS No: Prepared By Reviewed By Approved By
No:

ARTL/QAP/WMS/
18.01.20
R0 20
22

Revision No Page No
90
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I

Method Statement for Open Foundation

1.0 Purpose

This work shall consist of Method Statement adopted for the construction of
Retaining wall

2.0 Scope

The Scope of the plan covers the following activity.

Setting out, Excavation, PCC laying, Reinforcement tying, Formwork erection,


Concerting & curing

3.0 Equipment

Backhoe loader/excavator, Transit Mixer, Concrete pump/boom placer,


Vibrator, Batching plant, Dumpers, Dewatering Pump, if required

4.0 Responsibility

Section In charge will be responsible for the execution as well as quality


control. He will be assisted by field engineer. Further, field engineer will be
assisted by surveyors and supervisors whereas quality control engineer will be
assisted by lab technician

5.0 Procedure

5.1 Setting out at Site

The plan dimensions of the foundation shall be set out at the bottom of
foundation trench and checked with respect to original reference line and axis

5.2 Excavation

a) Excavation will be done to the size of the foundation plus safe working area
including necessary slopes as per site condition.

b) At some locations if the surface is below sub soil water level requires de
watering, and then the same will be done by installing adequate capacity
pumps. Necessary cofferdams and cribs shall be constructed and shall be

Revision No Page No
91
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I

removed after completion. All necessary sheeting, shoring, bracing if required


shall be provided.

c) If hard rock is encountered while excavation, suitable procedures will be


adapted like

1. Pneumatic breaking using compressor and pavement breakers

2. Wedge and hammer method i.e. drilling and splitting of rock

3. Control blasting and de mucking

Any one of the procedures will be adapted to suit the site conditions.

d) Excavation will be carried out to the required depth as per the foundation
details given in the drawings and if there are any obstructions /hindrances are
there in the course of the work then they will be immediately brought to the
notice of the engineer for their necessary instruction/action.

Surface dressing will be done before doing the PCC.

e) If Excavation done more than required depth, the extra depth of exaction
should be filled with sand or by soil compacted in layers till it reaches the
desired level of PCC.

5.3 PCC

Marking will be given as per the drawing on dressed surface. Side shuttering
shall be provided of the required thickness and size of the footing plus offset
for PCC

PCC of required thickness and grade will be laid on the dressed surface.

5.4 Reinforcement & Form Work:

Marking will be given as per the drawing over PCC

Bar Bending schedule shall be prepared as per Drawing and Fabrication of


Reinforcement should be done as per the approved B.B.S.

Revision No Page No
92
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I

Reinforcement will be tied over the PCC for footing and substructure as per
the drawings and proper formwork will be fixed to suit the requirement and as
per drawings.

5.5 Concreting& Curing

Concreting shall be done either by crane/bucket or by a concrete pump or


manually as detailed in Method statement ARARL/NH16/MS/18

Grade of concrete shall be maintained as per drawings.

Curing shall be done for 14 days by keeping surface moist.

6.0 Quality Control Testing and Acceptance

Quality control tests shall be done as per Sl. No 10 of Quality Control Tests and
Acceptance Criteria

7.0 Safety & Environment

While working Safety & Environment Procedure shall be followed as per


approved EHS Manual

Revision No Page No
93
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I

Method Statement Method Statement for


construction of Pile Foundation

Revision
Date WMS No: Prepared By Reviewed By Approved By
No:

ARTL/QAP/WMS/
18.01.20
R0 21
22

Revision No Page No
94
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I

Method Statement for Pile Foundation

1.0 Purpose

Installation of Cast-in-situ Bored Piles by Hydraulic rig/Piling Rig with Winch


and Direct Mud Circulation Method (DMC) and to provide details of the
Construction Method Statement & Resources deployment.

2.0 Scope

 Survey and Setting out works marking pile points/locations etc.

 Boring for pile

 Fabrication and Lowering of Reinforcement Cage

 Concreting

3.0 Equipment for Piling Operation:

The following Plant/Equipment shall be used for Installation of Bored cast-in-


situ piles:

a. Rotary hydraulic Rig: adequate nos. of piling rigs shall be used for
installation of bored cast-in-situ Piles.

Or

b. Piling Rig with Winch: adequate nos. of conventional piling rigs with
driving winches (Electrically motor driven) shall be used for installation of
bored cast-in-situ Piles.

c. DMC Rods: Direct Mud Circulation Pipes of required diameter shall be


used for drilling of bore hole.

d. Chisel : Chisel of required diameter shall be used for drilling

e. Miscellaneous Accessories: other miscellaneous piling accessories i.e.,


hose pipes, mud pump, channels etc. shall be used in piling operation.

f. Batching Plant: A batching plant shall be used to produce the concrete.

Revision No Page No
95
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I

g. Transit Mixer: Adequate nos. of standard transit mixer shall be used for
transporting concrete from batching plant to pile pour location.

4.0 Responsibility

Section In charge will be responsible for the execution as well as quality


control. He will be assisted by field engineer. Further, field engineer will be
assisted by surveyors and supervisors whereas quality control engineer will be
assisted by lab technician.

5.0 Procedure

Pile installation procedure has been described for Bored Cast-in-situ Pile in the
following steps:

5.1 Boring of Pile

a. Pile points shall be marked at exact pile locations as per relevant bridge
structural drawings with Total Station and reference grid pillars established.
Reference points shall be marked/fixed at a suitable distance from pile points
to cross check the center of pile during drilling operation.

b. The working level /ground level should be minimum 1.5 M above the
water Table/high tide level.

c. Initial boring of about 1.5/2.0 meters shall be done using bailer.

d. The permanent liner of thickness specified in the drawing up to


maximum scour level in length with inner diameter equivalent to nominal
diameter of the Pile, will be driven.

e. Position/center line of the liner/guide Casing pipe with reference to pile


reference points already fixed around the pile locations shall be checked to
shift/adjust the liner/casing pipe to ensure that drilling will be proceeded at
exact pile locations without any deviations.

f. The diameter of cutting tool/chisel will be 70 mm to 80 mm less than


outside diameter of casing/guide pipe for free movement of the chisel in the
casing pipe during drilling operation.

g. The bore hole will then be filled with Bentonite slurry. Bentonite
circulation channel shall be made from bore hole to Bentonite tank and fresh

Revision No Page No
96
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I

Bentonite slurry shall be pumped to drilling chisel via. Extension rods and
flexible tubes installed. Bentonite powder is to be mixed in the fresh water
tank at least 24 hours prior to start of Pile boring to ensure that Bentonite is
completely dispersed in the water and attains required density to stabilize the
sides of bore hole during drilling.

h. Bentonite used to stabilize the sides of bore hole should be conforming


to requirements. Density of Bentonite solution should be checked during
boring operation to ensure that the density is about 1.05 g/cc.

i. Bentonite slurry is pumped by high-pressure reciprocating


pumps/vertical pump into the bore hole through the cutting chisel and the
same is allowed to overflow the bore hole. The overflow slurry with bored
mud/soil etc. that comes out along with Bentonite slurry is passed through
channels and is collected in sediment tanks where sediments settle and
Bentonite can be re-used. If necessary, the Bentonite may be passed through
the de-sander tank to remove sand particles before it is re-used.

j. Boring will be done up to the founding strata as per drawings/


specifications etc.

k. After the founding stratum is reached, the bore will be flushed by


Bentonite slurry with direct mud circulation chisel/tremie pipe. The pumping
for the flushing will be done by use of mud circulation pump. During flushing,
the chisel will be kept resting on the founding strata to remove all the loose
sediments which might have accumulated on the founding strata. Further, the
flushing operation shall be continued till the consistency of inflowing and out-
flowing slurry is similar.

l. Depth of Pile shall be checked with sounding chain and exact depth
shall be recorded in the Pile report.

m. After flushing is over, the Chisel and connected DMC rods shall be
removed for further cage lowering and pile concreting operations.

5.2 Fabrication and Lowering of Reinforcement Cage:

The following steps shall describe the cage fabrication and lowering:

a. Reinforcement cage as per relevant Pile drawings shall be fabricated at


steel yard and transported to pile locations.

Revision No Page No
97
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I

b. Bar Bending schedule shall be prepared for different types of Piles.

c. Cover blocks of required diameter as per spec. /drawings shall be


provided at suitable locations. (Cover blocks are of same grade of concrete).

d. Lapping /Staggering etc. as per drawing/specifications shall be provided.


Spiral rings shall be tack-welded to main bars of pile to ensure rigidity /stability
during cage lowering.

e. Before lowering of the cage thorough inspection shall be made along


with the Engineer.

f. After necessary inspection is over, the cage shall be lowed inside the
bore hole true vertically and it will be ensured that the cover blocks are not
damaged during lowering operation.

g. If two or more cages are to be lowered, all those cages shall be lapped
with minimum lap length as per relevant drawings/specifications; spirals shall
be placed round the lapped length and tack-welded to main bars. Also cover
blocks of required nos. shall be provided for lap length portion.

5.3 Pile Concreting

The following steps shall describe the Pile Concreting:

a. After lowering of Reinforcement cage the next activity is lowering of


tremie pipes of required diameter usually of 200 mm diameter

b. The tremie pipes shall be clean, watertight and of adequate diameter to


allow the free flow of Concrete. Before lowering, all the tremie pipes shall be
thoroughly checked and form oil to be applied inside the pipes for free flow of
concrete inside the tremie.

c. The length of tremie pipe (total individual joined pipes) shall be more
than the length of the pile and base of tremie pipe should be lowered to
bottom of the borehole, allowing water or drilling mud to rise inside it before
pouring concrete.

Revision No Page No
98
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I

d. The top of the tremie pipe shall be fitted with a large diameter funnel to
receive the concrete with steel sealing plate arrangement at bottom of the
funnel.

e. Before start of Concreting operation, the bore hole shall be flushed with
fresh Bentonite slurry to flush out all loose particles, deleterious materials, if
any, present in the bore.

f. Before pouring the concrete through tremie, the bottom of the


concreting funnel should be closed with steel plate fitted with the funnel.
After the funnel is filled with concrete, the plate will be removed and concrete
discharged. Thereafter, Concreting will be done in a continuous manner up to
the required level.

g. It should always be ensured that the bottom of the tremie pipe is


minimum 2.0 meters within Concrete to avoid mixing of fresh concrete with
Bentonite slurry.

h. Slump of concrete shall be checked for each batch and recorded in


Concrete Pour report. (Slump of concrete shall be checked at Batching Plant
as well as at pouring location.)

i. Concreting of the pile should be uninterrupted. In the exceptional case


of interruption of concreting; but which can be resumed within 1 or 2 hours,
the tremie shall not be taken out of the concrete. Instead it shall be raised and
lowered slowly, from time to time to prevent the concrete around the tremie
from setting. Concreting should be resumed by introducing a little richer
concrete with a slump of about 200 mm for easy displacement of the partly
set concrete.

j. In case of withdrawal of tremie out of the concrete, either accidentally


or to remove a choke in the tremie, the tremie may be re-introduced in the
following manner to prevent impregnation of laitance or scum lying on the top
of the concrete already deposited in the bore.

k. The tremie shall be gently lowered on to the old concrete with very little
penetration initially. A vermiculate plug should be introduced in the tremie.
Fresh concrete of slump between 150mm - 200 mm should be filled in the
tremie which will push the plug forward and will emerge out of the tremie
displacing the laitance/scum in its way. When tremie is buried by about 60 to
100 cm, concreting may be resumed.

Revision No Page No
99
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I

l. Theoretical and Actual Concrete built-up depth shall be checked with


sounding chains in between the Pile concreting operation and recorded.

m. Concrete in the pile is to be filled approximately 0.6 m (as per site


conditions) above the cutoff level to permit removal of all laitance and weak
concrete before capping and to ensure good concrete at the cut-off level for
proper embedment into the pile cap.

n. After concreting up to the required level is done, the casing pipe will be
withdrawn.

o. Pile concreting data shall be entered in the relevant formats for future
reference.

6.0 Quality Control Testing and Acceptance


Quality control tests shall be done as per Sl. No 10 & 13 of Quality Control
Tests and Acceptance Criteria
7.0 Safety & Environment
While working Safety & Environment Procedure shall be followed as per
approved EHS Manual

Revision No Page No
100
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I

Method Statement Method Statement for


construction of Pile Cap

Revision
Date WMS No: Prepared By Reviewed By Approved By
No:

ARTL/QAP/WMS/
18.01.20
R0 22
22

Revision No Page No
101
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I

Method Statement for Pile Cap

1.0 Purpose

This work shall consist of Method Statement adopted for the construction of
pile cap in accordance with the approved drawings

2.0 Scope

Scope of pile cap constructions shall consist of the following activities

Excavation, Chipping of piles, laying of levelling course, Reinforcement tying,


Formwork erection and Concreting

3.0 Equipment

Backhoe loader/excavator, Dumpers, Transit Mixer, Vibrator, Batching plant,


Dewatering Pump, if required

4.0 Responsibility

Section In charge will be responsible for the execution as well as quality


control. He will be assisted by field engineer. Further, field engineer will be
assisted by surveyors and supervisors whereas quality control engineer will be
assisted by lab technician.

5.0 Procedure

5.1 Excavation

Once all the piles in a pile-group are completed, marking for the pile cap shall
be done.

The excavation for the pile-cap shall be taken up by excavator.

The final dressing to reach the desired depth shall be done manually.

While taking up excavation, care shall be taken to provide adequate slope so


that the excavated side slopes are stable.

Revision No Page No
102
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I

5.2 Chipping & development of piles

The Chipping of the pile up to the cut off level shall be commenced after the
excavation is completed.

The projected portion of the piles shall be broken using chisel and hammers or
breakers up to cutoff levels as shown in the drawings. Projected reinforcement
from the piles shall be straightened and given ‘L’ bend as per drawings.

The bottom of the pile cap will be properly rammed using hand rammers. All
the levels will be checked and the center of the pile cap will be marked
properly.

5.3 Levelling course

For PCC, required grade of concrete will be poured and compacted to achieve
the desired levels as per drawing. PCC will be done as per dimensions given in
the drawings

5.4 Reinforcement

Pile cap dimension shall be marked over the PCC.

Bar bending schedule shall be prepared as per approved drawings, and


reinforcement steel shall be cut and bend as per approved bar bending
schedule.

Reinforcement bars shall be placed accurately in position as shown in the


drawings.

The bars, crossing one another shall be tied together at every intersection with
binding wire, to make the skeleton of reinforcement rigid such that it does not
get displaced during placing of concrete or any other operation.

Spacer bars at approximately 1m intervals shall separate layers of


reinforcement, if required.

Adequate cover shall be maintained on all sides except on the top surface to
achieve proper cover as per the drawing.

The rebar for the pier shall be placed after properly marking location in
accordance with the approved drawings.

Revision No Page No
103
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I

5.5 Formwork

Required formwork shall be made out of plywood/ steel shutters to suit the
site conditions.

Releasing agent shall be applied before fixing the form work

The formwork shall be erected in true to line, levels, plumb, etc., rigid,
adequately braced both horizontally and vertically.

Form joints shall be as much as minimized, shall be tight and shall not permit
any leakage of slurry from concrete.

Formwork materials shall be rigid, even surface, and sufficiently strong to


prevent deformation during concrete.

5.6 Placement of Concrete

Concrete shall be placed carefully at designated position.

Concrete shall be placed by chute or manually as per the specified grade of


concrete and vibrated properly using needle vibrator. The concrete shall be
supplied by batching plant and transported through transit mixers.

Free fall of concrete shall not exceed 1.5 m.

Construction joints shall be avoided as far as possible, when unavoidable shall


be provided in a direction perpendicular to the axis of the member.

If concrete pump is used, concrete pumps and pump lines shall be primed
before commencement of concrete pumping operations.

Concrete shall be thoroughly compacted with immersion type vibrators and


worked around reinforcement and embedded figures and into corners of
formwork to produce a dense homogeneous void-free mass having a required
surface finish.

No layer of concrete shall be laid until previous layer in the same lift has been
consolidated thoroughly.

De-shuttering shall be done after 12 Hrs. from the time of casting

Revision No Page No
104
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I

Curing of concrete shall be carried out for 14 days from the date of casting

8.0 Quality Control Testing and Acceptance

Quality control tests shall be done as per Sl. No 10 of Quality Control Tests and
Acceptance Criteria

9.0 Safety & Environment

While working Safety & Environment Procedure shall be followed as per


approved EHS Manual

Revision No Page No
105
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I

Method Statement Method Statement for


construction of Pier/Abutment

Revision
Date WMS No: Prepared By Reviewed By Approved By
No:

ARTL/QAP/WMS/
18.01.20
R0 23
22

Revision No Page No
106
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I

Method Statement for Pier/Abutment Construction

1.0 Purpose

This item of work deals with construction of substructure of Bridges, Flyovers


& Interchanges with approved materials and drawings.

2.0 Scope

Starter concreting, Staging erection, Reinforcement tying, shuttering erection


and Placement of Concrete

3.0 Equipment

Crane-Bucket/Boom placer/Concrete Pump

Transit Mixer

Vibrator

Batching plant

4.0 Responsibility

Section In charge will be responsible for the execution as well as quality


control. He will be assisted by field engineer. Further, field engineer will be
assisted by surveyors and supervisors whereas quality control engineer will be
assisted by lab technician

5.0 Procedure

5.1 Starter Concreting

Starter concreting shall be 150mm thickness to enable pier shutter fixing.

The vertical bars shall be tied to ledger pipes as per spacing which in turn is
supported to staging tower to keep the vertical bars in correct position.

Starter formwork shall be made out of plywood/ steel shutters to suit the site
conditions.

Revision No Page No
107
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I

Formwork materials shall be rigid, and sufficiently strong to prevent


deformation during concrete.

The concrete shall be supplied by batching plant and transported through


transit mixers.

Concrete shall be thoroughly compacted with immersion type vibrators and


worked around reinforcement and into corners of formwork to produce a
dense homogeneous void-free mass having a required surface finish.

De-shuttering shall be done after 12 Hrs. from the time of casting.

5.2 Staging

Staging shall be erected to facilitate the workmen for reinforcement tying in


position, erection of formwork and placement of Pier concrete.

5.3 Reinforcement

Bar bending schedule shall be prepared as per approved drawings, and


reinforcement steel shall be cut and bend as per approved bar bending
schedule.

Reinforcement bars shall be placed accurately in position as shown in the


drawings.

The bars, crossing one another shall be tied together at every intersection with
binding wire, to make the skeleton of reinforcement rigid such that it does not
get displaced during placing of concrete or any other operation.

Spacer bars at approximately 1m intervals shall separate layers of


reinforcement, if required.

Cover blocks of thickness equal to the specified cover shall be placed between
formwork and bars made of concrete of specified grade of concrete.

5.4 Shuttering

Required formwork shall be made out of plywood/ steel shutters to suit the
site conditions.

Releasing agent shall be applied before fixing the form work

Revision No Page No
108
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I

The formwork shall be erected in true to line, levels, plumb, etc., rigid,
adequately braced both horizontally and vertically.

Form joints shall be as much as minimized, shall be tight and shall not permit
any leakage of slurry from concrete.

Formwork materials shall be rigid, even surface, and sufficiently strong to


prevent deformation during concrete.

Fixtures such as insert plates shall be provided in Pier for fixing/welding of


Safety railing which is required during concreting of Pier/Abutment cap

5.5 Placement of Concrete

The preparation of surface and concreting of construction joint shall be in


accordance with Appendix 1700/I of MORTH specifications.

Concrete shall be placed carefully at designated position.

Concreting of Pier/Abutment shall be done in lifts depending upon the site


condition.

The concrete shall be supplied by batching plant and transported through


transit mixers.

The placement of concrete for Pier shall be done with Boom placer /Crane-
bucket with funnel chute so as to restrict the height of fall of concrete not
more than 1.50m

Concrete shall be thoroughly compacted with immersion type vibrators and


worked around reinforcement and into corners of formwork to produce a
dense homogeneous void-free mass having a required surface finish.

Shuttering shall be removed after 24 hours.

Curing of concrete shall be carried out for 14 days from the date of casting.

Subsequent lifts shall be laid only after the previous lift approval.

6.0 Quality Control Testing and Acceptance

Revision No Page No
109
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I

Quality control tests shall be done as per Sl. No 10 of Quality Control Tests and
Acceptance Criteria

7.0 Safety & Environment

While working Safety & Environment Procedure shall be followed as per


approved EHS Manual

Revision No Page No
110
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I

Method Statement Method Statement for


construction of Pier/Abutment Cap

Revision
Date WMS No: Prepared By Reviewed By Approved By
No:

ARTL/QAP/WMS/
18.01.20
R0 24
22

Revision No Page No
111
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I

Method Statement for Pier/Abutment Cap Construction

1.0 Purpose

This item of work deals with construction of Pier/Abutment cap of Bridges,


Flyovers & Interchanges with the approved materials, drawings.

2.0 Scope

Erection of Staging, Reinforcement tying, Shuttering and Placement of


Concrete

3.0 Equipment

Crane-Bucket/Boom placer/Concrete Pump


Transit Mixer
Vibrator
Batching plant

4.0 Responsibility

Section In charge will be responsible for the execution as well as quality


control. He will be assisted by field engineer. Further, field engineer will be
assisted by surveyors and supervisors whereas quality control engineer will be
assisted by lab technician

5.0 Procedure

5.1 Staging

Staging shall be erected to facilitate the workmen for reinforcement tying in


position, erection of formwork and placement of Pier concrete.

5.2 Shuttering

Required formwork shall be made out of plywood/ steel shutters to suit the
site conditions.

Releasing agent shall be applied before fixing the form work.

Revision No Page No
112
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I

The formwork shall be erected in true to line, levels, plumb, etc., rigid,
adequately braced both horizontally and vertically.

Form joints shall be as much as minimized, shall be tight and shall not permit
any leakage of slurry from concrete.

Formwork materials shall be rigid, even surface, and sufficiently strong to


prevent deformation during concrete.

5.3 Reinforcement

 Bar bending schedule shall be prepared as per approved drawings, and


reinforcement steel shall be cut and bend as per approved bar bending
schedule.

 The pier/abutment cap rebar cage shall be fabricated

 Once the rebar cage is ready and the soffit shuttering of pier cap is
ready to receive the cage, the rebar cage shall be placed symmetrically over
pier with the help of crane.

 In case the pier/abutment cap location is not accessible for the crane
movement, the tying for the pier cap shall be taken up at location itself.

 Reinforcement bars shall be placed accurately in position as shown in


the drawings.

 The bars, crossing one another shall be tied together at every


intersection with binding wire, to make the skeleton of reinforcement rigid
such that it does not get displaced during placing of concrete or any other
operation.

 Spacer bars at approximately 1m intervals shall separate layers of


reinforcement, if required.

 Adequate cover shall be maintained on all sides except on the top


surface to achieve proper cover as per the drawing.

 The rebar for the bearing pedestals shall be placed after properly
marking location in accordance with the approved drawings

5.4 Placement of Concrete

Revision No Page No
113
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I

 The preparation of surface and concreting of construction joint shall be


done in accordance with Appendix 1700/I of MORTH specifications.

 The concrete shall be supplied by batching plant and transported


through transit mixers.

 Concrete shall be placed carefully at designated position.

 Concrete shall be placed by concrete pump/ crane with bucket


arrangement as per the specified grade of concrete and vibrated properly
using needle vibrator.

 Concrete shall be thoroughly compacted with immersion type vibrators


and worked around reinforcement and into corners of formwork to produce a
dense homogeneous void-free mass having a required surface finish.

 The surface on which the bearings are to be placed shall be finished to a


perfect level plane.

 Staging and soffit de shuttering shall be carried out after the specified
period based on the span whereas the other shuttering can be removed after
24 hours.

 Curing of concrete shall be carried out for 14 days from the date of
casting

6.0 Quality Control Testing and Acceptance

Quality control tests shall be done as per Sl. No 10 of Quality Control Tests and
Acceptance Criteria

7.0 Safety & Environment

While working Safety & Environment Procedure shall be followed as per


approved EHS Manual

Revision No Page No
114
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I

Method Statement Method Statement for


construction of Pre-Cast Girder

Revision
Date WMS No: Prepared By Reviewed By Approved By
No:

ARTL/QAP/WMS/
18.01.20
R0 25
22

Revision No Page No
115
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I

Method Statement for Pre Cast Girder Casting

1.0 Purpose

This item of work deals with construction of Pier/Abutment cap of Bridges,


Flyovers & interchanges with the approved materials, drawings.

2.0 Scope

Shutter fabrication, fixing, cutting, bending and tying of reinforcement,


Concreting of Girders

3.0 Equipment

Crane-Bucket/Boom placer/Concrete Pump


Transit Mixer
Vibrator
Batching plant

4.0 Responsibility

Section In charge will be responsible for the execution as well as quality


control. He will be assisted by field engineer. Further, field engineer will be
assisted by surveyors and supervisors where as quality control engineer will be
assisted by lab technician

5.0 Procedure

5.1 Shutter Fabrication & Fixing

Shuttering fabrication shall be done as per the approved drawings

Necessary hooks shall be provided as specified in the drawing for handling.

Form vibrator location shall be welded with base plate for fixing the vibrator
during concreting.
 Pre-fabricated bottom shutter shall be placed over the casting bed.

 The bottom shutter shall be fixed within the tolerance limits

 Bottom shutter shall be aligned to the required line and level and welded
to the base channel.

Revision No Page No
116
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I

 Shutter joints shall be filled with masking tape.

 Foam sheet shall be fixed with glue at all the joints (vertical &
horizontal) of steel shutters to avoid slurry leakage during concrete.

 The form work shall be cleaned by using Buffing wheel. Shuttering oil
shall be applied and erected in sequence as specified in the detailed shutter
drawing.

 Supports shall be fixed as specified in the drawing and align it to the


line and level.

 Wooden blocks shall be fixed as mentioned in the drawing.

 Complete the shutter fixing after placing the reinforcement, duct in


place as detailed in 5.3 and ensure the line and level of the girder shutter.

 Final dimensions of the shutters shall be checked.

 The walk way for girder to be fixed for concreting works and shall be
free from obstructions.

5.2 Reinforcement

 The reinforcement shall be cut and bent as per approved drawings and
BBS

 Reinforcement tying shall be started on the prepared base plate. The


position of reinforcement shall be ensured.

 Lap length and spacing of spacer blocks shall be checked

If the girder is of pre stressed, anchor heads on both ends of the girder with
burst reinforcement, sheathing duct for stressing cables as per the profile and
grout vents shall be placed as shown in the drawings

5.3 Concreting

 Concrete of required grade from batching plant shall be placed either


with concrete bucket arrangement or concrete pump/Boom placer.

 Height of fall of concrete not more than 1.5 m shall be ensured.

Revision No Page No
117
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I

 The concrete shall be poured in layers. During concreting, vibration shall


be done properly by using mould vibrator and needle vibrator to ensure proper
compaction.

 40 mm/ 60 mm needle in the cover portion shall be followed after


compacting with mould vibrator and poker vibrator to eliminate air bubbles.

 The top surface shall be finished and remove the top laitance by using
wire brush to make construction joint.

 Moist curing shall be commenced to the girder top surface after initial
set.

 The side shutter shall be removed after 12 hrs from the time of casting.

 After removal of side shutter hessian cloth shall be fixed over the
concrete surface and water curing shall be commenced.

 Curing shall be continued at casting bed, till required strength is


attained for lifting

 Date of casting and span shall be marked by the side of girder.

6.0 Quality Control Testing and Acceptance

Quality control tests shall be done as per Sl. No 10 & 15 of Quality Control
Tests and Acceptance Criteria

7.0 Safety & Environment

While working Safety & Environment Procedure shall be followed as per


approved EHS Manual

Revision No Page No
118
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I

Method Statement Method Statement for


construction of Drain

Revision
Date WMS No: Prepared By Reviewed By Approved By
No:

ARTL/QAP/WMS/
18.01.20
R0 26
22

Revision No Page No
119
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I

Method Statement for Construction of Drain

1.0 Purpose

The work shall consist of constructing surface drains in accordance with the
requirements of these Specifications and to the lines, grades, dimensions and
other particulars shown on the drawings

2.0 Scope

Setting out, Excavation, Leveling course laying, Raft Construction, Wall


Construction and Slab Construction

3.0 Equipment

Excavator

Dumpers

Batching plant

Transit Mixers

Vibrators

4.0 Responsibility

Section In charge will be responsible for the execution as well as quality


control. He will be assisted by field engineer. Further, field engineer will be
assisted by surveyors and supervisors whereas quality control engineer will be
assisted by lab technician

5.0 Procedure

5.1 Setting Out

Layout marking will be done as per approved working drawing

5.2 Excavation

Excavation will be done conforming to the lines, grades, slopes and levels as
shown on the approved working drawings, as per the specification clause 301

Revision No Page No
120
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I

If required dewatering will be done

All the excavated materials will be disposed

5.3 Concreting

5.3.1 Leveling Course: PCC of the drain with approved design mix concrete
will be done conforming to the lines, grades, slopes and levels as shown on the
approved working drawings.

5.3.2 Raft: The reinforcement shall be placed in position and shuttering is


erected to exact dimensions of raft and after due checks, raft is concreted to
the required thickness as detailed in drawing.

5.3.3 Walls: The shuttering is erected to the exact dimension and the walls
are cast above the raft to bottom level of slab. The procedure adopted will be
same as raft.

5.3.4 Weep Holes: Weep Holes will be provided at required spacing as shown
in the drawing.

5.3.5 Slab: The shuttering is made to support the top slab of drain and
necessary care is taken to seal the joints to avoid slurry loss from concrete
through joints. The steel is positioned and concreted.

The formwork is removed after due time as per norms.

The curing of concrete will be start immediately after completion of the


concrete.

The necessary back filling will be done after completion of curing works.

6.0 Quality Control Testing and Acceptance

Quality control tests shall be done as per Sl. No 10 of Quality Control Tests and
Acceptance Criteria

7.0 Safety & Environment

While working Safety & Environment Procedure shall be followed as per


approved EHS Manual

Revision No Page No
121
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I

Method Statement Method Statement for


construction of Stone Pitching on Slopes

Revision
Date WMS No: Prepared By Reviewed By Approved By
No:

ARTL/QAP/WMS/
18.01.20
R0 27
22

Revision No Page No
122
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I

Method Statement for Stone Pitching on slopes

1.0 Purpose

The work shall consist of covering the river side slopes of guide bunds and
road embankments with stone boulders over a layer of granular material which
will act as a filter.

2.0 Materials

2.1 Pitching Stone The size and weight of stone shall conform to Clause
5.3.5.1 of IRC: 89. No stone, shall weigh less than 40 kg. The size of spalls shall
be a minimum of 25 mm and shall be suitable to fill the voids in the pitching

2.2 Filter Medium

The material for the filter shall consist of sand, gravel, crusher dust or GSB to
act as a filter medium, shall be provided underneath the pitching, to prevent
loss of the embankment material and build-up of uplift head on the pitching

The gradation of the filter material shall satisfy the following requirements of
MORTH Cl 2504.2.2

3.0 Procedure

Before laying the pitching and construction of toe wall the sides of banks shall
be trimmed to the required slope and profiles put up by means of line and pegs
at intervals of 3m to ensure regular straight work and a uniform slope
throughout. Depressions shall be filled and thoroughly compacted.

The filter granular material shall be laid over the prepared base and suitably
compacted to the thickness specified on the drawings.

The lowest course of pitching shall be started from the toe wall built-up in
courses upwards

The toe wall shall be in dry rubble masonry (uncoursed) conforming to Clause
1405.3, of these Specifications in case of dry rubble pitching. It shall be in
nominal mix cement concrete (M 15) conforming to Clause 1704 of MORTH in
case of cement concrete block pitching.

Revision No Page No
123
R0
QUALITY ASSURANCE
Development of Six Lane Badakumari – Karki Section PLAN
of NH-130-CD Road from km 179+000 to km
226+500 under Raipur-Visakhapatnam Economics WORK METHOD STATEMENT
Corridor in the state of Odisha on Hybrid Annuity
Mode (Package – OD-3) (Length 47.500 km) ANNEXURE - I

The stone pitching shall commence in a trench over the toe of the slope. Stone
shall be placed by hand to the required length, thickness and depth
conforming to the drawings. Stones shall be set normal to the slope and
placed so that the largest dimension is perpendicular to the face of the slope,
unless each dimension is greater than the specified thickness of pitching.

The largest stones shall be placed in the bottom courses and for use as
headers for subsequent courses.

The stone of flat stratified nature shall be placed with the principle bedding
plane normal to the slope. The pattern of laying shall be such that the joints
are broken and voids are minimum by packing with spalls of the proper size
and wedged in with hammers to ensure tight packing.

When two or more layers of stones must be laid to obtain the design thickness
of pitching, dry masonry shall be used and shall be well bonded.

4.0 Safety & Environment

While working Safety & Environment Procedure shall be followed as per


approved EHS Manual