QUALITY CONTROL OBSERVATIONS

Report No. 15 20/06/2023


S.No. Observations Photographs
1. Academic
block - Crack
on the wall of
stairs ground
floor near
library

Report No. 15 Page 1 of 41


2. Academic
block -
dampness on
the wall of
staircase
ground floor
near library

Report No. 15 Page 2 of 41


3. Academic
block -
Above library
washroom,
grits visible on
the mortar
placed on the
wall

Report No. 15 Page 3 of 41


4. Academic
block -

Slanting stone
finishing at
washroom
entrance 1st
floor above
library

Report No. 15 Page 4 of 41


5. Academic
block -

Corridor 1st
floor granite
edge finishing
required all
over

Report No. 15 Page 5 of 41


6. Academic
block -

1st floor
washroom near
library, water
logging issue

Report No. 15 Page 6 of 41


7. Academic
block -

1st floor
washroom near
library,
Improper
concreting
above the lintel

Report No. 15 Page 7 of 41


8. Academic
block -

1st floor
washroom near
library,

Brick wall
having faded
bricks and
severe patches
at the entrance
of washroom

Report No. 15 Page 8 of 41


9. Academic
block -

Slanting edge
of the pillar at
the staircase 1st
floor, near
reception (part
5)

Report No. 15 Page 9 of 41


10. Academic
Block-

Ground floor
washroom near
part 1, tiles not
fixed properly

Report No. 15 Page 10 of 41


11. Academic
Block-

No anti skid
tiles at the
drinking water
area ground
floor near
library as per
NIT

Report No. 15 Page 11 of 41


12. Water filled in
the cable
trench of ESS
1, in which 11
kV cable is
also going, it is
a very serious
issue from the
security point
of view need
to be rectified
on priority.

Report No. 15 Page 12 of 41


13. Water filled in
the cable
trench of ESS
1, in which 11
kV cable is
also going, it is
a very serious
issue from the
security point
of view need
to be rectified
on priority.

Report No. 15 Page 13 of 41


14. Academic
Block-

Shuttering still
left on the
ceiling of part
7, 1st floor

Report No. 15 Page 14 of 41


15. Academic
Block-

Uneven
thickness of
the alum frame
near part 5, 1st
floor lift lobby

Report No. 15 Page 15 of 41


16. Academic
Block-

1 floor part 5,
different
skirting height
and improper
finishing

Report No. 15 Page 16 of 41


17. Academic
Block-

1st floor part 6,


the deeper
beam creating
obstruction in
path of vent
pipes located
at sides

Report No. 15 Page 17 of 41


18. Academic
Block-

1st floor
AHU room
above
auditorium-
door packing
not properly
done

Report No. 15 Page 18 of 41


19. Academic
Block-

White patched
brick wall, 1st
floor
washroom part
4 near
classroom

Report No. 15 Page 19 of 41


20. Academic
Block-

Improper
plaster work,
1st floor
washroom part
4 near
classroom

Report No. 15 Page 20 of 41


21. Academic
Block-

No anti skid
tiles at the
drinking water
area first floor
above
auditorium as
per NIT

Report No. 15 Page 21 of 41


22. Outside
Academic
Block-

Outside part 3,
column is bent

Report No. 15 Page 22 of 41


23. Outside
Academic
Block-

Shuttering still
not removed
below the
column

Report No. 15 Page 23 of 41


24. Outside
Academic
Block-

Shuttering still
not removed
below the
column/beam

Report No. 15 Page 24 of 41


25. Outside
Academic
Block-

Poor shuttering
work, damaged
shuttering

Report No. 15 Page 25 of 41


26. Outside
Academic
Block-

Outside part 7,
sagging
shuttering.

Report No. 15 Page 26 of 41


27. Outside
Academic
Block-

Outside part 7-
The plinth
protection wall
collapsing,
needs
rectification on
priority.

Report No. 15 Page 27 of 41


28. Outside
Academic
Block-

Outside part 7-
The plinth
protection wall
collapsing,
needs
rectification on
priority

Report No. 15 Page 28 of 41


29. Outside
Academic
Block-

Outside part 7-

The wooden
shuttering is
still present
below the
column

Report No. 15 Page 29 of 41


30. Outside
Academic
Block-

Wooden
shuttering still
present below
the base wall
near cafeteria
staircase

Report No. 15 Page 30 of 41


31. Assistant
Professor
Residence 2-

Ground floor,
near staircase-

Shuttering not
removed from
the ceiling and
wall

Report No. 15 Page 31 of 41


32. Assistant
Professor
Residence 2-

Ground floor-

Shuttering not
removed from
the ceiling

Report No. 15 Page 32 of 41


33. Assistant
Professor
Residence 2-

Ground floor-

Shuttering not
removed from
the ceiling

Report No. 15 Page 33 of 41


34. Assistant
Professor
Residence 2-

Ground floor-

The brick wall


made
improperly,
showing sag
and the mortar
is improperly
filled.

Report No. 15 Page 34 of 41


35. Assistant
Professor
Residence 2-

Ground floor-

Dampness on
the ceiling and
wall joint

Report No. 15 Page 35 of 41


36. Assistant
Professor
Residence 2-

Ground floor-

Dampness on
the ceiling and
wall joint

Report No. 15 Page 36 of 41


37. Assistant
Professor
Residence 2-

Ground floor-

Shuttering not
removed from
the ceiling

Report No. 15 Page 37 of 41


38. Medical
centre-

No cupboard
seen upto the
ceiling height
as per the NIT

Report No. 15 Page 38 of 41


39. Shopping
Block-

Dampness on
the wall of
shopping
room, second
picture shows
the already
reported issue
of water
logging on the
roof of the
shopping
block, needs to
be rectified

Report No. 15 Page 39 of 41


40. Hostel Block-

None of the
cupboard is
upto the
ceiling height
as per the NIT.

Report No. 15 Page 40 of 41


Thank You.

Report No. 15 Page 41 of 41