Flood Damages Proforma 29.07.2023

You might also like

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 14

District No.

of Habs affected Restored Bal Habs

Nalgonda 193 193 0


Mulugu 154 137 17
Mulugu 57 57 0
Mulugu 19 0 19
Jayasankar 7 7 0
Bhupalapally
Jayasankar 14 14 0
Bhupalapally
Jayasankar 16 0 16
Bhupalapally
Jayasankar 15 15 0
Bhupalapally
Jayasankar 3 3 0
Bhupalapally
Jayasankar 127 127 0
Bhupalapally
Nizamabad 2 2 0
Sircilla 14 7 7
Jagitial 14 1 13
Jagitial 5 2 3
Jagitial 1 1
Karimnagar 35 35
Adilabad 11 11 0
Adilabad 13 9 4
Adilabad 12 12
Adilabad 2 2 0
Adilabad 10 9 1
Adilabad 1 1 0
Adilabad 4 1 3
Adilabad 1 1 0
Adilabad 3 3 0
Adilabad 1 1 0
Adilabad 2 2
Adilabad 1 1 0
Adilabad 11 10 1
Adilabad 9 9 0
Nirmal 4 0 4
Adilabad 487 180 307
Asifabad 488 360 128
Asifabad 650 394 256
Mancherial 265 196 69
Mancherial 258 221 37
Mancherial 41 41 0
Mancherial 73 73
Nirmal 204 103 101
Khammam 4 0 4
Bhadradri 188 42 146
Bhadradri 1182 1115 67
Khammam 186 186 0
Mahabubabad 174 174 0
Heavy rains and Floods- Status
Flood Damages
SNo District Segment No.of Mandal wise Damage details Restore Bal Present Status of Restoration
Habs d Habs
affected
1 Nalgonda Augmentation 193 Addagudur-19 500mm DI Pumping main near 70 123 Restoration work in
Motkur-25 Anneswaraswamy Gutta was disturbed and progress. 70 habs restored
S.Gowraram-45 dislodged due to land slide affecting 106 through alternative line
Nakrekal-37 habs in Nakrekal Constituency and 87 Habs
Kethepally-33 in Tungaturthy constituency.
Kattangur-34

2 Mulugu Godavari 154 Venkatapuram-17 Pumping main in Pusuru damaged due to 130 24 Restoration in progress
Wazedu-43 floods

3 Mulugu Godavari 57 Mangapet-57 Power supply poles breakdown near 0 57 After restoration of power
Mangapet ramnagar intakewell in Godavari flood supply, Intake will be put to
(Mulugu Constituency-57) operation
4 Jayasankar Manthani 7 Kataram-6 Damage of 110 dia HDPE in korlakunta vagu 7 0 Restored
Bhupalapally Bhupalapally Mahamuttaram-1 (Manthani Constituency)
5 Jayasankar Manthani 14 Kataram-4 Damage of HDPE 225 dia in Gundrathpally 14 0 Restored
Bhupalapally Bhupalapally Mahadevpur-10 vagu (Manthani Consy)
6 Jayasankar Manthani 16 Palimela-15 Damage of DI-300 dia in Peddampet vagu 0 16 Restoration in progress
Bhupalapally Bhupalapally Mahadevpur-1 (Manthani Constituency)

7 Jayasankar Manthani 15 Malharrao-15 Damage of HDPE - 250 dia in Mallaram vagu 15 0 Restored
Bhupalapally Bhupalapally (Manthani Constituency)
SNo District Segment No.of Mandal wise Damage details Restore Bal Present Status of Restoration
Habs d Habs
affected
8 Jayasankar Manthani 3 Malharrao-3 Damage of HDPE-110 dia in koyyur vagu 3 0 Restored
Bhupalapally Bhupalapally (Manthani Constituency)
9 Jayasankar Manthani 127 M.Mutharam-46 Damage of 300 dia scour on 600 Dia DI at 127 0 Restored
Bhupalapally Bhupalapally Kataram-45 Mahamutharam vagu (Manthani
Mahadevpur-15 Constituency)
Malharrao-21
10 Nizamabad SRSP 2 Jakranpally-2 HDPE 90 mm dia pipeline damaged due to 2 0 Restored
Balkonda floods( Nizamabad rural constituency)
11 Sircilla SVC 14 Veernapally-4 Damage of HDPE Pipeline in 6 stretches 5 14 Work will be restored after
Vemulawada-1 (Sircilla Constituency, Vemulawada receding flood
Gangadhara-6 Constituency, Choppadandi Constituency)
Mallial Mandal-3
12 Jagitial KJD 14 Raikal-6 Damage of DI Pipeline in 4 stretches 14 R&B road dams damaged
Sarangapur-7 (Jagitial Constituency, Dharmapuri due to Heavy floods.
Pegadapalli-1 Constituency) Restoration will be done
after getting access
5 Ibrahimpatnam-1 Damage of HDPE Pipeline in 3 stretches 2 5
Metpally-1 (Jagitial and Korutla Constituency)
Beerpur-3
1 Gollapalli-1 80mm MS Pipeline damaged due to Heavy 1
Floods Pipeline (Dharmapuri Constituency)
13 Karimnagar LMD-MHH 35 Veenavanka-31 MS 450 leakages in the stream (Huzurabad 35 Restoration work will be
Jammikunta-2 Constituency-33 and Manakonduru started after receding the
Shankarapatnam-2 Constituency-2) flood water
14 Adilabad SRSP 11 Tamsi-5 100mm MS pipeline dislocated at 11 0 For Bal habs, Restoration
Adilabad Bheempur-6 Vamannagar to Ambugaon (Boath Consy) work progress
13 Adilabad-13 Damage of HDPE Pipelines at 6 stretches 9 4
(Adilabad Constituency)
12 Adilabad-12 Damage of 100 mm MS Pipeline near 12
Sevadasnagar Jn and Harijanaguda Jns
(Adilabad Constituency)
SNo District Segment No.of Mandal wise Damage details Restore Bal Present Status of Restoration
Habs d Habs
affected
2 Bazarhathnoor-2 Damage of Compound wall due to flood 1 1
water at 150KL sump at Bhuthai k & 75 mm
HDPE near Gulabthanda OHSR Jn (Boath
Constituency)
10 Bela-10 Damage of HDPE Pipeline in 6 stretches 9 1
(Adilabad Constituency)
1 Bheempur-1 Damage of 75 mm dia HDPE Pipeline near 1 0
Neemguda Jn (Boath Constituency)
4 Boath-4 Damage of 80 mm GI Pipeline near Tanya 1 3
thanda & 90 mm HDPE Pipeline near
Kanugutta jn (Boath Constituency)
4 Basar-4 Damage of 250K9 DI Pumping main from 0 4
Owni Jn to Basar Jn

1 Gudihathnor-1 Damage of 65mm dia GI pipeline near 1


Tosham thanda x rd (Boath Constituency)
3 Ichoda-3 Damage of HDPE & GI pipeline near 3 0
Mankuguda jn and Gandhinagar jn (Boath
Constituency)
1 Jainath-1 Damage of 100 mm MS Pipeline near 1 0
Laxmipur Jn(Adilabad Constituency)
2 Sirikonda Damage of 65mm Dia GI Pipeline near 2
Narayanpur jn(Boath Constituency)
1 Tallamadugu-1 Damage of 75mm Dia HDPE Pipeline from 1 0
Kappardevi X road Junction
11 Neradigonda-20 Damage of HDPE Pipelines in 7 reaches of 10 1
Neradigonda mdl(Boath Constituency)
9 Neradigonda-20 Damage of DI Pipelines in 2 reaches of 9 0
Neradigonda mandal(Boath Constituency)
SNo District Segment No.of Mandal wise Damage details Restore Bal Present Status of Restoration
Habs d Habs
affected
15 Adilabad Komrambhee 487 Indervelly - 116 At Dhanora intake well , the turbidity of raw 120 367 Flood receded, Resoration
m segment Sirikonda - 32 water increased heavily to a whopping 8400 under progress.
Utnoor - 187 NTU due to which the Dhanora WTPs could
Gadiduda - 89 not be operated (Asifabad constituency-152
Narnoor - 63 & Khanapur Constituency-335)

16 Asifabad 488 Lingapur - 58 At Dhanora intake well , the turbidity of raw 210 278
Sirpur U - 89 water increased heavily to a whopping 8400
Tiryani - 138 NTU due to which the Dhanora WTPs could
Jainoor - 91 not be operated ( Asifabad constituency-488)
Kerameri - 112

17 Asifabad Komaram 650 Asifabad-128 Due to very high turbidity, the Ada (Manik 294 356 Receding flood. Ada WTP
bheem Bejjur-51 guda)WTP was shutdown (Asifabad put to operation
Asifabad C.Manepally-35 constituency-294,Sirpur consy-367-
Dahegoan-49 Bellampally consy-254)
Kagaznagar-106
Kowtala-45
Penchikalpet-25
Rebbena-61
Sirpur T-45
Wankidi-105

18 Mancherial 265 Bellampalli-35 196 69


Bheemini-24
Kannepally-39
Kasipet-57
Nennal-34
Tandoor-48
Vemanpalle-28
SNo District Segment No.of Mandal wise Damage details Restore Bal Present Status of Restoration
Habs d Habs
affected
19 Mancherial Yellampally 258 Bheemaram-18 Due to very high turbidity, the Gudipet WTP 205 53 Receding flood. WTP put to
Mancherial Chennur-54 was shutdown (Chennur consy-153, operation
Dandepally-68 Mancherial-105)
Hazipur-35
Jaipur-31
Kotapally-33
Mandamarri-17
Luxettipet-2

20 Mancherial Yellampally 41 Kotapally-11 Due to very high turbidity, the Itikyal WTP 41 0 Restored
Mancherial Luxettipet-30 was shutdown (Mancherial constituency-
30,Chennur Consy-11)
21 Mancherial Kadem 73 Jannaram - 73 Kadem Project Water surrounded 73 Power restored, WTP
Transformer yard near intake well and hence under trail run
22 Nirmal 204 Dasthurabad - 23 no power (Khanapur Constituency-277) 101 103
Kaddam - 75
Khanapur - 54
Pembi - 52
23 Khammam Wyra 4 Penubally-4 125 mm HDPE pipe damaged along KM 0 4 Restoration work will be
Banjara to LS Banjara on katleru vaagu started after receding the
(Sathupally Constituency) flood

24 Bhadradri Godavari 188 Cherla-87 Parnasala substation flooded with Godavari 0 188 After receding of flood &
Dummugudem-101 Water & power supply stopped and hence restoration of power, Intake
WTP at Parnasala could not be operated & Parnasala WTP will be
(Bhadrachalam consty-188) put to operation
Bhadradri
SNo District Segment No.of Mandal wise Damage details Restore Bal Present Status of Restoration
Habs d Habs
affected
25 Godavari 1182 Allapalli-38 Due to Heavy Flood around intakewell cum 1109 73 Restored 1109 habs in
Annapureddipalli-31 Substation premises near Kummarigida Bhadradri,186 in
Aswapuram-71 thereby Dummugudem WTP could not be Khammam & 174 in
Aswaraopeta-84 operated. (Aswaraopet Constituency-347, Mahabubabad. 250mm dia
Burgampahad-35 Kothagudem Constituency-223,Pinapaka MS pipeline & HDPE lines
Chandrugonda-38 Constituency-343,Sathupalli Constituency- in Vagu portions damaged
Chunchupally-31 30,Wyra-104,Yellandu Constituency-492 ) due to heavy floods in
Dammapeta-91 Kinnerasani river near
Gundala-61 Allapalli (73 habs)

Karakagudem-42
Laxmidevipally-77
Manuguru-36
Mulakalapally-103
Palvancha-63
Pinapaka-60
Sujathanagar-52
Tekulapalle-137
Yellandu-129

26 Khammam 186 Kamepalle-52 186 0


Sathupalli-30
Singareni-104
27 Mahabubabad 174 Bayyaram-88 174 0
Garla-86

Total 4942 3067 1882


Damages due to Heavy rains and Floods- MB Supply
No.of Habs
Date of Restored Bal Present Status of Reasons for delay in Anticipated target date for Remarks Reson
Sno District Segment Mandal name affected in Damage details
Damage habs (No) Habs Restoration restoration balance restoration
the mandal

Pipeline has been


80 mm dia GI Pipe Joints dislocated
damaged once Restoration work will begin once Road Damge Not
1 Adilabad SRSP-Adilabad Adilabad Rural 1 20/07/2023 ( Salaiguda OHSR Jn to Shivaguda 0 1 30/07/23 Not Complited
again.Restoration not the impact of the flood subsides పాసిబుల్
OHSR)
yet started

Due to flooding in Satnala River down


Restoration not yet Restoration work will begin once
2 Adilabad SRSP-Adilabad Jainath 34 19/07/2023 stream area ,500 mm dia ,DI K-9 0 34 31/07/23 Not Complited
started the impact of the flood subsides
Pipejoints dislocated

90 mm dia HDPE Pipeline washed away


Restoration not yet Restoration work will begin once wadaddi gates open
4 Adilabad SRSP-Adilabad Tamsi 1 24/07/2023 in floods (Waddadi OHSR Jn to Waddadi 0 1 30/07/23 Not Complited
started the impact of the flood subsides not passible
OHSR)

100 mm dia MS Pipe Joints


28.07.2023this Date Leakage
9 Adilabad SRSP-Adilabad Adilabad Rural 29 27/07/2023 dislocated(Daheguda sump to Moulal 29 0 Restored - - Complited Sir
rectification complited
gutta OHBR)

100 mm dia MS Pipe Joints dislocated


Restoration not yet Restoration work will begin once No road Lohara Dhegara Road
10 Adilabad SRSP-Adilabad Adilabad Rural 1 27/07/2023 (Boringuda OHSR Jn to Maregom X 0 1 30/07/23 Not Complited
started the impact of the flood subsides curt aendhi
Road)

100 mm dia MS Pipe Joints


Restoration not yet Restoration work will begin once
11 Adilabad SRSP-Adilabad Talamadugu 2 27/07/2023 dislocated(Ruyyadi OHSR Jn to 0 2 30/07/23 Not Complited
started the impact of the flood subsides
Ramachandrapuram OHSR Jn)

Damage of 75 mm dia HDPE Pipeline Restoration not yet Restoration work will begin once
12 Adilabad SRSP-Adilabad Talamadugu 1 27/07/2023 0 1 30/07/23 Today rectification complited
from Regulguda jn to Regulguda OHSR started the impact of the flood subsides

150 mm dia MS Pipe joints


Restoration not yet Restoration work will begin once
13 Adilabad SRSP-Adilabad Talamadugu 3 27/07/2023 disloacted(Narsapur ST Jn to Palli k X 0 3 30/07/23 Complited 29.07.2023
started the impact of the flood subsides
Road)

Damage of 75 mm dia HDPE Pipeline Restoration not yet Restoration work will begin once Tata ace పోదు Road ఫుల్ డామేజ్
14 Adilabad SRSP-Adilabad Talamadugu 1 27/07/2023 0 1 30/07/23
from Palli k OHSR Jn to Palli B OHSR started the impact of the flood subsides బురద unnadhi

Damage of 90 mm dia HDPE Pipeline


15 Adilabad SRSP-Adilabad Adilabad Rural 2 27/07/2023 2 0 Restored - - complited
from Lingudua X road to Lingudua OHSR
Heavy rains and Floods- Status of MB Supply
Flood Damages
SNo District Segment No.of Mandal wise Damage details Restore Bal Present Status of Restoration
Habs d Habs
affected
1 Nalgonda Augmentation 193 Addagudur-19 500mm DI Pumping main near 70 123 Restoration work in
Motkur-25 Anneswaraswamy Gutta was disturbed and progress. 70 habs restored
S.Gowraram-45 dislodged due to land slide affecting 106 through alternative line
Nakrekal-37 habs in Nakrekal Constituency and 87 Habs
Kethepally-33 in Tungaturthy constituency.
Kattangur-34

2 Mulugu Godavari 154 Venkatapuram-17 Pumping main in Pusuru damaged due to 80 74 Restoration in progress
Wazedu-43 floods
3 Mulugu Godavari 57 Mangapet-57 Power supply poles breakdown near 57 After restoration of power
Mangapet ramnagar intakewell in Godavari flood supply, Intake will be put to
(Mulugu Constituency-57) operation
4 Jayasankar Manthani 7 Kataram-6 Damage of 110 dia HDPE in korlakunta vagu 7 0 Restored
Bhupalapally Bhupalapally Mahamuttaram-1 (Manthani Constituency)
5 Jayasankar Manthani 14 Kataram-4 Damage of HDPE 225 dia in Gundrathpally 14 0 Restored
Bhupalapally Bhupalapally Mahadevpur-10 vagu (Manthani Consy)
6 Jayasankar Manthani 16 Palimela-15 Damage of DI-300 dia in Peddampet vagu 0 16 Restoration in progress
Bhupalapally Bhupalapally Mahadevpur-1 (Manthani Constituency)
7 Jayasankar Manthani 15 Malharrao-15 Damage of HDPE - 250 dia in Mallaram vagu 15 0 Restored
Bhupalapally Bhupalapally (Manthani Constituency)
8 Jayasankar Manthani 3 Malharrao-3 Damage of HDPE-110 dia in koyyur vagu 3 0 Restored
Bhupalapally Bhupalapally (Manthani Constituency)
9 Jayasankar Manthani 127 M.Mutharam-46 Damage of 300 dia scour on 600 Dia DI at 127 0 Restoration work will be
Bhupalapally Bhupalapally Kataram-45 Mahamutharam vagu (Manthani started after receding the
Mahadevpur-15 Constituency) flood water
Malharrao-21
10 Nizamabad SRSP 2 Jakranpally-2 HDPE 90 mm dia pipeline damaged due to 2 0 Restored
Balkonda floods( Nizamabad rural constituency)
SNo District Segment No.of Mandal wise Damage details Restore Bal Present Status of Restoration
Habs d Habs
affected
11 Adilabad SRSP 11 Tamsi-5 100mm MS pipeline dislocated at 11 0 Restoration work progress
Adilabad Bheempur-6 Vamannagar to Ambugaon (Boath Consy) in some habs and the
balance will be started after
12 Adilabad-12 Damage of HDPE Pipelines at 6 stretches 9 3
receding flood water
(Adilabad Constituency)
12 Adilabad-12 Damage of 100 mm MS Pipeline from near 12
Sevadasnagar Jn and Harijanaguda Jns
(Adilabad Constituency)
2 Bazarhathnoor-2 Damage of Compound wall due to flood 2 0
water at 150KL sump at Bhuthai k & 75 mm
HDPE near Gulabthanda OHSR Jn (Boath
Constituency)
10 Bela-10 Damage of HDPE Pipeline in 6 stretches 4 6
(Adilabad Constituency)
1 Bheempur-1 Damage of 75 mm dia HDPE Pipeline near 1 0
Neemguda Jn (Boath Constituency)
4 Boath-4 Damage of 80 mm GI Pipeline near Tanya 1 3
thanda & 90 mm HDPE Pipeline near
Kanugutta jn (Boath Constituency)
1 Gudihathnor-1 Damage of 65mm dia GI pipeline near 1
Tosham thanda x rd (Boath Constituency)
3 Ichoda-3 Damage of HDPE & GI pipeline near 1 2
Mankuguda jn and 125mm GI pipeline near
Gandhinagar jn (Boath Constituency)
1 Jainath-1 Damage of 100 mm MS Pipeline near 1 0
Laxmipur Jn(Adilabad Constituency)
2 Sirikonda Damage of 65mm Dia GI Pipeline near 2
Narayanpur jn(Boath Constituency)
1 Tallamadugu-1 Damage of 75mm Dia HDPE Pipeline from 1 0
Kappardevi X road Junction
11 Neradigonda-20 Damage of HDPE Pipelines in 7 reaches of 8 3
Neradigonda mandal(Boath Constituency)
SNo District Segment No.of Mandal wise Damage details Restore Bal Present Status of Restoration
Habs d Habs
affected
9 Neradigonda-20 Damage of DI Pipelines in 2 reaches of 9 0
Neradigonda mandal(Boath Constituency)
12 Sircilla SVC 14 Veernapally-4 Damage of HDPE Pipeline in 6 stretches 14 Incoming Flood is heavy
Vemulawada-1 (Sircilla Constituency, Vemulawada and work will be restored
Gangadhara-6 Constituency, Choppadandi Constituency) after receding
Mallial Mandal-3
13 Jagitial KJD 14 Rikal-6 Damage of DI Pipeline in 4 stretches 14 R&B road damaged due to
Sarangapur-7 (Jagitial Constituency, Dharmapuri Heavy floods. Restoration
Pegadapalli-1 Constituency) will be done after getting
access
5 Ibrahimpatnam-1 Damage of HDPE Pipeline in 3 stretches 5
Metpally-1 (Jagitial and Korutla Constituency)
Beerpur-3
1 Gollapalli-1 80mm MS Pipeline damaged due to Heavy 1
Floods Pipeline (Dharmapuri Constituency)
14 Karimnagar LMD-MHH 35 Veenavanka-31 MS 450 leakages in the stream (Huzurabad 35 Restoration work will be
Jammikunta-2 Constituency-33 and Manakonduru started after receding the
Shankarapatnam-2 Constituency-2) flood water
15 Adilabad Komrambhee 487 Indervelly - 116 At Dhanora intake well , the turbidity of raw 487 Flood receded, Resoration
m segment Sirikonda - 32 water increased heavily to a whopping 8400 under progress.
Utnoor - 187 NTU due to which the Dhanora WTPs could
Gadiduda - 89 not be operated (Asifabad constituency-152
Narnoor - 63 & Khanapur Constituency-335)

16 Asifabad 488 Lingapur - 58 At Dhanora intake well , the turbidity of raw 210 278
Sirpur U - 89 water increased heavily to a whopping 8400
Tiryani - 138 NTU due to which the Dhanora WTPs could
Jainoor - 91 not be operated ( Asifabad constituency-488)
Kerameri - 112
SNo District Segment No.of Mandal wise Damage details Restore Bal Present Status of Restoration
Habs d Habs
affected
17 Asifabad Komaram 650 Asifabad-128 Due to very high turbidity, the Ada (Manik 294 356 Receding flood. Ada WTP
bheem Bejjur-51 guda)WTP was shutdown (Asifabad put to operation
Asifabad C.Manepally-35 constituency-294,Sirpur consy-367-
Dahegoan-49 Bellampally consy-254)
Kagaznagar-106
Kowtala-45
Penchikalpet-25
Rebbena-61
Sirpur T-45
Wankidi-105

18 Mancherial 265 Bellampalli-35 196 69


Bheemini-24
Kannepally-39
Kasipet-57
Nennal-34
Tandoor-48
Vemanpalle-28

19 Mancherial Yellampally 258 Bheemaram-18 Due to very high turbidity, the Gudipet WTP 205 53 Receding flood. Ada WTP
Mancherial Chennur-54 was shutdown (Chennur consy-153, put to operation
Dandepally-68 Mancherial-105)
Hazipur-35
Jaipur-31
Kotapally-33
Mandamarri-17
Luxettipet-2

20 Mancherial Yellampally 41 Kotapally-11 Due to very high turbidity, the Itikyal WTP 41 0 Restored
Mancherial Luxettipet-30 was shutdown (Mancherial constituency-
30,Chennur Consy-11)

21 Mancherial Kadem 73 Jannaram - 73 Kadem Project Water surrounded 73 Power restored, WTP
Transformer yard near intake well and hence under trail run
no power (Khanapur Constituency-277)
SNo District Segment No.of Mandal wise Damage details Restore Bal Present Status of Restoration
Kadem Habs Kadem Project Water surrounded d Habs Power restored, WTP
affected
Transformer yard near intake well and hence under trail run
22 Nirmal 204 Dasthurabad - 23 no power (Khanapur Constituency-277) 204
Kaddam - 75
Khanapur - 54
Pembi - 52
23 Bhadradri Godavari 188 Cherla-87 Parnasala substation flooded with Godavari 188 After receding of flood &
Dummugudem-101 Water & power supply stopped and hence restoration of power, Intake
WTP at Parnasala could not be operated & Parnasala WTP will be
(Bhadrachalam consty-188) put to operation
24 Godavari 1182 Allapalli-38 Due to Heavy Flood around intakewell cum 1182 After receding flood and
Annapureddipalli-31 Substation premises near Kummarigida restoration of power supply,
Aswapuram-71 thereby Dummugudem WTP could not be Intake & Dummugudem
Aswaraopeta-84 operated. (Aswaraopet Constituency-347, WTP will be put to
Burgampahad-35 Kothagudem Constituency-223,Pinapaka operation
Chandrugonda-38 Constituency-343,Sathupalli Constituency-
Chunchupally-31 30,Wyra-104,Yellandu Constituency-492 )
Dammapeta-91
Gundala-61

Karakagudem-42
Laxmidevipally-77
Manuguru-36
Mulakalapally-103
Palvancha-63
Pinapaka-60
Sujathanagar-52
Tekulapalle-137
Yellandu-129

25 Khammam 186 Kamepalle-52 186


Sathupalli-30
Singareni-104
SNo District Segment No.of Mandal wise Damage details Restore Bal Present Status of Restoration
Habs d Habs
affected
26 Mahabubabad 174 Bayyaram-88 174
Garla-86

27 Khammam Wyra 4 Penubally-4 125 mm HDPE pipe damaged along KM 4 Restoration work will be
Banjara to LS Banjara on katleru vaagu started after receding the
(Sathupally Constituency) flood
Total 4937 1312 3625