R2B-P2-204-03-P-CRG-KAR701-5-5-01091 - B - Overall Schedule

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 2

SAMSUNG

ENGINEERING CO., LTD

Received
DOCUMENT TITLE : Overall Schedule 11 Jan 2022

PTI-ID V/P NO : R2B-P2-204-03-P-CRG-KAR701-5-5-01091


SECL V/P NO : SO6627-KAR701-5-5-01- K0SCH001-001
REQUISITION NO : KAR701-5-5
PURCHASE ORDER NO : 5000071282-0
ITEM DESCRIPTION : Analyzer

□ APPROVED □ WITH COMMENT


□ REVIEWED □ RESUBMIT

This approval or review does not relieve the vendor /


subcontractor of his responsibilities to meet all
requirements of the purchase order

ORIGINAL CHECKED APPD(PRJ)

SIGN

DATE
SAMSUNG ENGINEERING CO., LTD

B 10-JAN-2022 FOR APPROVAL Jenny Zhou Felix Deng Felix Deng


A 12-NOV-2021 FOR APPROVAL Jenny Zhou Felix Deng Felix Deng
REV DATE DESCRIPTION PREPARED CHECKED APPROVED

Dos Bocas New Refinery Project

PTI-Infraestructura de Desarrollo, S.A. de C.V. (PTI-ID)

SAMSUNG Ingeniería Manzanillo, S.A. de C.V.

ABB Engineering (Shanghai) LTD


AUS-4498-00239 Dos Bocas New Refinery Project
Master Schedule
ID % Task Duration Start Finish Predecessors Qtr 4, 2021 Qtr 1, 2022 Qtr 2, 2022 Qtr 3, 2022 Qtr 4, 2022
Complete Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct
1 1% AUS-4498-00239 Doc Bocas New Refinery Project 273.5 days Tue 9/14/21 Mon 10/10/22
2 100% Project Initiation 34 days Tue 9/14/21 Fri 10/29/21
3 100% Purchase Order Award 1 day Tue 9/14/21 Tue 9/14/21
4 100% Kick-off Meeting 3 days Wed 10/13/21 Fri 10/15/21 3FS+4 wks
5 100% Datasheet Freeze 0 days Fri 10/29/21 Fri 10/29/21 4FS+2 wks 10/29
6 1% Project Execution 249.5 days Mon 10/18/21 Mon 10/10/22
7 7% Engineering Design and Vendor Prints 249.5 days Mon 10/18/21 Mon 10/10/22
8 15% Preliminary Engineering Design 16 wks Mon 10/18/21 Mon 2/14/22 4
9 0% Detailed Engineering Design 10 wks Tue 2/15/22 Mon 4/25/22 8
10 0% Final Documentation 8 wks Mon 8/15/22 Mon 10/10/22 72
11 0% Material Sub-order 140 days Fri 11/12/21 Mon 6/6/22
12 0% Analyzer 140 days Fri 11/12/21 Mon 6/6/22
13 0% ABB AO2020 Analyzers 100 days Fri 12/10/21 Mon 5/9/22
17 0% ABB AWT210&TB264 Conductivity Analyzer 60 days Fri 12/24/21 Mon 3/28/22
21 0% AAI OMA-300 100 days Fri 12/10/21 Mon 5/9/22
25 0% Ametek WDG VC 140 days Fri 11/12/21 Mon 6/6/22
29 0% Emerson GDM 100 days Fri 12/10/21 Mon 5/9/22
33 0% Emerson OXT4C 100 days Fri 12/10/21 Mon 5/9/22
37 0% GE Panametrics Moisture.IQ 100 days Fri 12/10/21 Mon 5/9/22
41 0% Hobre C-Quand 110 days Fri 12/10/21 Mon 5/23/22
45 0% Michell QMA 601 100 days Fri 12/24/21 Mon 5/23/22
49 0% Thermo Fisher SOLA.iQ 110 days Fri 12/10/21 Mon 5/23/22
53 0% Electrical & Instrumentation 14 wks Tue 2/15/22 Mon 5/23/22 8
54 0% SCS Components 14 wks Tue 2/15/22 Mon 5/23/22 8
55 0% Consumables 8 wks Tue 3/1/22 Mon 4/25/22 8FS+2 wks
56 0% Pre-Inspection Meeting 11 days Mon 2/14/22 Tue 3/1/22
57 0% Inspection Notfication 0 days Mon 2/14/22 Mon 2/14/22 8 2/14
58 0% Pre-Inspection Meeting 1 day Tue 3/1/22 Tue 3/1/22 57FS+2 wks
59 0% System Integration 76.5 days Wed 3/2/22 Thu 6/16/22
60 0% Raw Material Preparation 2 wks Wed 3/2/22 Tue 3/15/22 58
61 0% Pre-fabrication 4 wks Wed 3/16/22 Tue 4/12/22 60
62 0% Painting and Jointing 3 wks Wed 4/13/22 Tue 5/3/22 61
63 0% Mounting Unistructs and Trays 2 wks Wed 5/4/22 Tue 5/17/22 62,55
64 0% Sample Conditioning Systems Integration 8 days Tue 5/24/22 Thu 6/2/22
65 0% Components Lay-out (Enclousure, EPS Tubing, Flowmeter, Ball Valve, etc.) 1 wk Tue 5/24/22 Mon 5/30/22 54
66 0% Components Fixation 3 days Tue 5/31/22 Thu 6/2/22 65
67 0% Mounting SCS Enclosures to Containers 2 days Fri 6/3/22 Mon 6/6/22 64
68 0% Mounting E&I Components 1.5 wks Tue 5/24/22 Thu 6/2/22 53
69 0% Cable Distribution 2 wks Wed 5/18/22 Tue 5/31/22 63
70 0% Tubing Connections 1.5 wks Tue 6/7/22 Thu 6/16/22 67
71 0% Cable & Wiring Connections 2 wks Wed 6/1/22 Tue 6/14/22 69
72 0% Inspection and final delivery 42 days Thu 6/16/22 Mon 8/15/22
73 0% Internal FAT and Punch Clerance 4 wks Thu 6/16/22 Thu 7/14/22 59
74 0% Factory Acceptance Test 2 wks Thu 7/14/22 Thu 7/28/22 73
75 0% FAT Punch Clerance 2 wks Thu 7/28/22 Thu 8/11/22 74
76 0% Packing, marking and submission of shipping documents 2 days Thu 8/11/22 Mon 8/15/22
77 0% Packing in Shanghai Workshop 2 days Thu 8/11/22 Mon 8/15/22 75
78 0% Inspection/Shipping Release 0 days Mon 8/15/22 Mon 8/15/22 77 8/15

Project: DBNR PJT Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline
Milestone Inactive Task Manual Task Manual Summary External Tasks Progress

Page 1