Professional Documents
Culture Documents
GC Reports
GC Reports
GC Reports
SUBMITTED BY
SALMAN ARIF
2017-GCUF-73017
12941
Training Period
24-10-20 to 19-01-21
DEPARTMENT
SAHIWAL CAMPUS
2021
SUPERVISED INDUSTRIAL TRAINING REPORT
TECHNO TIME CONSTRUCTION (PVT) LTD
CANAL BANK ROAD, NEW CAMPUS LAHORE
I hereby certify that I have completed the Ten Weeks Training in partial fulfilment of the
requirement for the award of BSc Civil Engineering Technology. I did my Training in
Techno time construction (Pvt) Ltd. From 24-10-2020 to 19-01-2021
The matter presented in this Report has been submitted by me only for the completion of my
degree.
Signature of Student
Examined by:
INCHARGED/HOD
All praise and glory to Almighty Allah, the most compassionate and merciful, who enabled us
with a power and means to contribute a drop to existing ocean of knowledge. For what I have
received, may the Lord make me truly thankful. And more truly for what I have not received.
All studies, planning, development and execution of the field training report were carried out
under the able supervision and guidance of our honored teacher. We acknowledge this help,
guidance and valuable advice at all stages of study and express our great debt of gratitude to
our most esteemed advisor Engr. Sami Ullah lecturer of Department of Civil Engineering
and Technology without his able guidance, encouragement, interest and generous
contribution from his own experience, this study might not have been accomplished.
We would like to express our sincere thanks to head of Department of Civil Engineering
Technology Dr. Muhammad Ashraf all academic staff of Department of Civil Engineering
Technology and Management for their support throughout our stay in this institution. The
authors are also abundantly obliged to staff of Techno Time Construction (PVT) Ltd for
their cooperation during internship. Last but not the least: we must acknowledge our beloved
parents, brother and sisters whom prayers have always been matter of encouragement
throughout our lives and especially during our academic career.
In the end, we must thank once again to all those who helped us in our internship period. We
shall pray and recall with pleasure and gratitude those never fading pleasant memories of
golden years spent.
Signature of Student
i
Salman Arif (12941)
ii
TABLE OF CONTENTS
Acknowledgement ⅰ
Table of Contents ii
List of Figures ⅱ
List of Tables ⅲ
List of Abbreviations ⅳ
TABLE OF CONTENTS
CHAPTER 1: INTRODUCTION..........................................................................................1
1.3 Address..............................................................................................................................3
1.5 Purpose..............................................................................................................................3
1.6 Vision................................................................................................................................3
1.21 Surveyor..........................................................................................................................6
1.22 QA\QC............................................................................................................................6
1.24 Accountant......................................................................................................................6
ii
1.26 Office Management.........................................................................................................6
1.27 Cashier.............................................................................................................................7
1.28 Advertisement.................................................................................................................7
2.2.2 Shapes.........................................................................................................................8
2.3.4 SHAPES.....................................................................................................................9
2.7 Overlap............................................................................................................................11
2.9 Chairs..............................................................................................................................11
2.12 Purpose..........................................................................................................................12
2.13 Dowels...........................................................................................................................13
2.19 Curing............................................................................................................................14
2.20 Pier................................................................................................................................15
2.25 Material:........................................................................................................................17
2.28 Tripod............................................................................................................................18
2.30 Excavator.......................................................................................................................19
2.34 Loader............................................................................................................................21
2.43 Apparatus......................................................................................................................26
iv
2.44 The test includes following steps..................................................................................27
3.9 Decision-making.............................................................................................................33
4.1 Feedback..........................................................................................................................34
4.2 Conclusion.......................................................................................................................34
4.3 Recommendations...........................................................................................................35
REFERENCES........................................................................................................................37
v
LIST OF FIGURES
vi
2.28 Blocks................................................................................................................................28
2.29 Universal test Machine.................. ...................................................................................29
2.30 Concrete block..................................................................................................................30
vii
LIST OF TABLES
2.1 Material......................................................................................................................18
viii
ABBREVIATIONS
TC tower crane
PM Project manager
CM Construction manager
ix
Chapter 1: INTRODUCTION
The project located and name is Flyover at Railway Crossing on Jhall Road Sahiwal.
Flyover is ongoing construction on LBDC canal railway line crossing. It has a single road
capacity for 24 hours in all-weather condition.
The cost is estimated to be Rs. 600 Million including cost of Service Road on both side
from Mazdoor puli to view hotel NH- 5, resettlement and other pre-construction activities. The
total length of flyover is 2079 feet that consist of 28 spans. The total length of the road on both
sides will be approximately 3.9 km.
Projects in the city of Sahiwal under PHA. Implementation of these projects would
provide all- weather connectivity from central city to the view hotel national highway 5. It will
also reduce journey time due traffic jam on railway crossing during train passing. It will
provide fast rout of Sahiwal people to reach main highway road.
This commitment with sustainability underpins the entire project, extending also to the
project design that achieves reduced traffic jam and regulate the traffic flow. With a carefully
crafted massing solution to stand out from the surroundings, the design aims to provide a very
strong image and presence that inspires confidence and innovation, embracing users (both
visitors and staff) at their approach.
The main objective of the project is connected central city to view hotel national
highway Another objective is also a bridge is exiting on LBDC canal Jhall road through
railway crossing but there is high traffic congestion in term train passing by or traffic on the
road that causes of traffic jam and disturbance in traffic flow.
1
This project has 28 spans and 27 piers and 2 abutments of bridges are going to be
constructed. There is also two side approach to connect flyover. At the top-level flyover with
the surroundings is creating a distinctive effect, clearly visible desirable bird eye view of
Sahiwal city for approaching visitors which acts also as a way finding method.
Incorporating the latest international requirements and standards, the flyover internal
planning and design ensures clear flow segregation and operational safety standards, be it at
the level of circulations (with staff and visitors’ segregation); at the level of goods logistics, or
at the level of materials storage.
The project was started on mid-September 2019 to June 2021 complete the project.
After the completion of the project the NHA has to maintain and control it after completion.
2
1.2 Company Introduction
i. Techno Time Construction (PVT) LTD stands for a Contracting Company capable of
undertaking mega multi pharaohs Construction Projects especially Residential,
Commercial and Industrial Buildings, HVAC, Elevators, Escalators, Roads and Bridges.
ii. Construction Company established in the year 1987 and is continuously striving for setting
standard pace ahead and is moving ahead in construction industry. It has developed
Qualitative Measurement System for implementation of Projects at all corporate levels as
well as at the field activity.
iii. TTC is rendering high quality & expert engineering services in this field. TTC stands for
performance, integrity and quality services because of total commitment to excellence by
the Staff and the Management.
iv. A large number of sizeable achievements have been made and the company is continuously
maintaining these with the help of its trained & experienced work force. TTC has got very
rich experience in Project Planning Implementation and timely execution. TTC possesses
ample resources and facilities which can enable the Company to complete every project
within the stipulate period and within allocated budget.
During last 23 years the company has achieved a high profile and completed most of
the projects ahead of time. TTC is continuously beating the clock.
1.3 Address
1.5 Purpose
To bring prosperity and well-being to our clients and society at large by adding value
through Engineering, Construction, Management and Technology.
1.6 Vision
To become a world class Engineering and construction company operating
internationally.
4
Figure: 1.2 Associates charts
5
the progress, mutual interaction and tasks of various parties in such a way that reduces the risk
of overall failure, maximizes benefits, and minimizes costs.
6
1.16 Civil supervisor
Civil Supervisors monitor civil construction projects. They oversee activities such as
building bridges, repairing highways and doing construction on airports.
1.21 Surveyor
Surveyors update boundary lines and prepare sites for construction so that legal
disputes are prevented. Surveyors make precise measurements to determine property
boundaries. They provide data relevant to the shape and contour of the Earth's surface for
engineering, mapmaking, and construction projects.
7
1.22 QA/QC
QA/QC is the combination of quality assurance, the process or set of processes used to
measure and assure the quality of a product, and quality control, the process of ensuring
products and services meet consumer expectations.
1.24 Accountant
Accountants and auditors ensure that companies or organizations are efficiently
operating. They do this by accessing financial records of their clients. Duties include analyzing
data, finance reports, budgets, tax returns, and accounting records.
1.27 Cashier
i. Receive payment by cash, check, credit cards, vouchers, or automatic debits.
ii. Issue receipts, refunds, credits, or change due to customers.
iii. Count money in cash drawers at the beginning of shifts to ensure that amounts are
correct and that there is adequate change.
1.28 Advertisement
Paid, non-personal, public communication about causes, goods and services, ideas,
organizations, people, and places, through means such as direct mail, telephone, print, radio,
8
television, and internet.
9
Chapter 2: Training Work
Pile is necessary when the bearing capacity of soil below the structure is insufficient for
a spread footing. It transfers the load to deeper, firmer strata. Piles used where the soil
particularly affects by seasonal changes, to transfer the load below the level of such influence
The load support exceeds the bearing capacity of a single pile, a group of piles uses.The group
capped by a spread footing or a cap to distribute load to all piles in the group. Where there are
a large number of closely space piles, provide individual caps. It is more economical to provide
just one large cap, forming a piled raft.
10
2.2.2 Shapes
The shape and plan dimensions of the pile cap depend on two factors.
11
Structure consists of major three categories:
i. Steel work
ii. Form work
iii. Concrete work
iv. Pile Cap
v. Pile cap Necessity
vi. Shapes
vii. Structural works
12
Figure: 2.5 Form work
13
2.7 Overlap
Overlap is a joint in steel fixing when length or width is greater than the length of a
steel bar. In this culvert lap was taken as 50D of the bar (main & distribution bars).
2.9 Chairs
Chair rods are nothing but just enabling rods that help to maintain the proper space
between the bottom and top reinforcements of a slab, beams and shear wall.
14
2.10 Concrete work
Concrete is a construction material composed of cement, fine aggregates (sand) and
coarse aggregates mixed with water which hardens with time. In a Flyover construction,
concrete is used for the construction of lean concretes, file cap and other load bearing
elements.
2.12 Purpose
During construction of reinforced concrete works as well as their maintenance, we need
to support the structure as long as it is in its premature state or plastic state as it could not even
bear its own load. After the suitable duration of time, i.e. when concrete sets enough to take its
own load, these temporary supports are removed systematically.
15
Figure: 2.10 Shuttering and Scaffolding
2.13 Dowels
Dowel bars are short steel rods placed at the transverse joints of a concrete pavement
to provide a connection between pile cap or pier. The dowel bars act to spread the load across
both slabs when traffic is moving off the edge of one slab to the next. I observed that size of
dowels at site for beam was T-20, T-10. T-25 for beams compression or tension bars. T-10 was
used for ring purposes. T-12 was used for roof slabs.
16
Figure: 2.11 Class-B concrete
2.19 Curing
Once all the placement and finishing are complete, the concrete can rest and begin to
cure. The curing process lasts 28 days, with the first 48 hours being the most critical. It is
recommended that a liquid chemical curing and sealing compound be applied to the concrete as
soon as the finishing process is complete. The curing compound helps the concrete cure slowly
and evenly, which helps reduce cracks, curling, and surface discolorations.
17
The colder the temperature, the longer it will take concrete to cure. You can start to use
your concrete for light foot traffic 3 to 4 days after placement.
2.20 Pier
Pier in fly over construction, vertical load bearing member such as an intermediate
support for adjacent ends of two bridge spans. In foundations for large buildings, piers are
usually cylindrical concrete shafts, cast in prepared holes, while in bridges they take the form
of caissons, which are sunk into position.
Figure: 2.12
18
2.23 Precast Structure
Precast concrete is a construction product produced by casting concrete in a reusable
mold or "form" which is then cured in a controlled environment, transported to the
construction site and lifted into place. Precast girders are used in flyover.
Water = 239.2Kgs
W/C = 0.57Kgs
Slump = 80mm
Grade M-35/45
Water = 227Kgs
W/C = 0.14Kgs
Slump = 50mm
20
Description of Equipment
21
2.28 Tripod
A tripod is a portable three-legged frame or stand, used as a platform for supporting
the weight and maintaining the stability of some other object. A tripod provides stability
against downward forces and horizontal forces and movements about horizontal axes. The
positioning of the three legs away from the vertical center allows the tripod better leverage for
resisting lateral forces.
22
Figure: 2.15 Tripod
23
Figure: 2.16
2.30 Excavator
Excavators are important and widely used equipment in construction industry. Their
general purpose is to excavation but other than that they are also used for many purposes like
heavy lifting, demolition, river dredging, cutting of trees etc. Excavators contains a long arm
and a cabinet. At the end of long arm digging bucket is provided and cabinet is the place
provided for machine operator. This whole cabin arrangement can be rotatable up to 360o
which eases the operation. Excavators are available in both wheeled and tracked forms of
vehicles.
25
Figure: 2.19 Tower Cranes
2.34 Loader
Loader are used in construction site to load the material onto dumpers, trucks etc. The
materials may be excavated soil, demolition waste, raw materials, etc. A loader contains large
sized bucket at its front with shorter moving arm. Loader may be either tracked or wheeled.
Wheeled loader are widely used in sites while tracked or crawled loader are used in sites where
wheeled vehicles cannot reach.
26
Figure: 2.21 Loader
27
Figure: 2.26 Steel Bending
Air entrainment in concrete was one of the concepts developed by cold countries in
order to prevent damages due to freezing and thawing. Later on, as experimentation’s proved
multidimensional benefits of air entrainment along with improved the workability of concrete
at lower water/cement ratio.
As the achievement of the desired workability at lower water content helped one to
achieve concrete with the greater compressive strength which in turn, leads to light concrete
with greater compressive strength.
We are all very aware of how excess water can be harmful to the strength of concrete.
Cement being the major binding material in concrete needs water for hydration process, but
that is only limited to about (0.20 to 0.25) % of cement content. The excess water turns out to
be beneficial in contributing to workability and finishing of concrete.
The very aspect where excess water is considered harmful because as the water in the
concrete matrix dries, it leaves large interstitial spaces among aggregate and cement grains.
This interstitial space becomes primary cracks during compressive strength testing of concrete.
2.42 Apparatus
As per IS: 516-1959 Compressive testing machine (2000Kn),15cm×15cm×15cm steel
cube molds or Cylinder having Dia 15cm and length 30cm are used.
29
Figure 2.27 Mould
Machine mixing: The ingredient must not be rotated for more than 2 minutes and the
following pattern must be followed
Dry mixing of fine aggregates and cement>addition of coarse aggregate with the even
distribution>addition of calculated water in batch till consistency is achieved.
The casting molds are chosen to be made of cast iron and must be rubbed with grease
on inner side for easy removal of cubes. The specimen must be cast in 3 layers (5cm each) and
properly compacted in order that honeycombing formation does not take place.
iv. Compaction
In compacting through tamping bar, 35 strokes must be done in all parts of a cube for
proper compacting. This tamping bar has the dimension of diameter 16mm and length of 0.6m.
30
v. Age of test
The cube test for Compressive strength can be done on 1,3, 7, 14 and 28 days. In some
cases, the strength of greater ages is required which is performed from 13 to 52 weeks.
vi Number of specimens
It is mandatory to have at least 3 specimens for testing from different batches. The
mean of compressive strength achieved by this specimen is used to determine actual strength of
the batch.
i. Place the prepared concrete mix in the steel cube mould for casting.
ii. Once it sets, after 24 hours remove the concrete cube from the mould.
iii. Keep the test specimens submerged underwater for stipulated time.
iv. As mentioned, the specimen must be kept in water for 7 or 14 or 28 days and for every 7
days the water is changed.
v. Ensure that concrete specimen must be well dried before placing it on the UTM.
vi. Weight of samples is noted in order to proceed with testing and it must not be less than
8.1Kg.
vii. Testing specimens are placed in the space between bearing surfaces.
viii. Care must be taken to prevent the existence of any loose material or grit on the metal
plates of machine or specimen block.
31
Figure: 2.29 Universal test machine
32
Chapter 3: Skill Attained
In today’s highly competitive, global world, civil engineers who possess the proper
training, education, and experience often find they have multiple career opportunities and
options available to them. These highly skilled engineers use their wide range of knowledge to
grow and successful careers in the public and private sectors. For those civil engineers who are
early on in their career, or for those who are looking to further their career success, it’s
important to have a solid grasp of the essential skills that are necessary for civil engineers
today.
33
3.4 Leadership skills
The responsibility for the outcomes of projects falls on the civil engineers who manage
them. Therefore, it is important that managers have significant leadership skills when
overseeing planners, technicians, technologists, surveyors, and contractors. This involves being
able to plan and prioritize, manage time effectively, delegate duties when necessary, make
decisions with confidence and authority, and motivate members of the team.
3.7 Decision-making
While working as a leader and manager of a project, a civil engineer will need to
consider the available information, conflicting goals from different parties involved,
professional ethics, financial responsibilities, and safety concerns when making decisions.
They need to have confidence in themselves and in their team for providing accurate and
useful information in order to make decisions that are clear and effective. Also, when mistakes
are made, they should take responsibility, learn what went wrong, and guide the project on a
new path.
34
Chapter 4: Feedback & Recommendations
4.1 FEEDBACK
During my internship period, I have been able to meet and network with so many people that I
am sure will be able to help me with opportunities in the future.
I conclude that internship is a bridge between the theoretical knowledge and the practical or the
reality work at the field of construction or civil engineering work.
One main thing that I have learned through this internship is time management skills as well as
self-motivation. When I first started, I did not think that I was going to be able to make myself
to be at site almost. Once I realized what I had to do I organized my day and work so that I
was not wasting my hours. I learned that I needed to be organized and have questions ready
for when it was the correct time to get feedback. From this internship and time management I
had to learn how to motivate myself through being in the site for so many hours. I came up
with various proposals and ideas that the company is still looking into using.
Overall, the internship laid sound foundation for us to start our career. We are proud to be able
to contribute towards nation building the country’s extremely critical period of the history. It
will be definitely sensible to scale this practice up and to replicate in other disciplines as well..
4.2 CONCLUSION
An initial geotechnical assessment of a group of board piles in a chalk has been
presented in this paper discussing the stages implemented to ensure that safe working loads are
applied during the bearing replacement of the bridge pier and no excessive deflection or
rotation will result from the new temporary distribution. To establish the ground condition and
determine the engineering parameters of the strata the existing geotechnical was collected from
as built records and then evaluated against a historical static load test using CBR.
The bearing capacity of single pile was calculated considering two different methods in
obtaining the ultimate skin friction where the larger value based on the effective over burden
pressure has been found to be in agreement with result of pile load test analysis.
The elastic response of the pile group was analyzed using PIGLET software which has
predicated a significant increase in the vertical loads on the edge piles at the North side (where
the bridge maintenance work will occur.) However, this proved to be an over estimation
compared with the result obtain from REPUTE software where a prefect plastic behavior of the
chalk was considered.
35
4.3 RECOMMENDATIONS
When it comes to design and construction projects, the conventional design process is
relatively straightforward: The client hires the firm, the client shares expectations and
requirements for the project, the firm develops and refines the design, and the design is
constructed. Client expectations are confined to satisfaction with the final constructed state as
it relates to functionality and aesthetics.
The rules change when the facility is already built and operating and cannot be shut down for
the sake of the project. While the objective of the project remains the same as in a conventional
construction project—a functional, code-compliant design—the path to achieving a complete
design and getting the project constructed under budget is far more complicated. This is
especially so in large facilities that contain multiple exhaust streams and scores of gas, water,
and chemical distribution systems—particularly when these processes and systems have an
array of “owners.”
From the perspective of designers and engineers, the difference between designing and
constructing a brand-new facility versus designing and constructing for “live factory” projects
is very important and can greatly impact the success of your project.
Successful design and construction firms recognize the unique challenges inherent in taking on
a significant project within an existing space. This article offers insights into these challenges
and provides ten great tips that can serve as a checklist of sorts to evaluate whether you and
your A/E supplier are employing best practices on your new design project.
Site/factory engineer(s) usually interface most frequently with the A/E firm. These engineers
generally identify the need for a project in the first place and provide to the A/E firm a general
concept of what the project design will entail.
i. Always be mindful that the A/E firm is a consultant accountable only to the PM. As the
design is developed and the A/E interacts with stakeholders, new requirements and
scope will be discovered, some more justified than the rest. The PM must decipher
which of these elements should be incorporated into the project and determine the value
of added design and construction costs.
ii. Do not underestimate project impacts to pipelines, electrical panels or equipment.
Necessary work around may require engineered designs, bypass piping, or ductwork.
Temporary facilities or HVAC and/or a plan for partial plant or equipment shutdowns
may also need to be provided.
36
REFERENCES
i. https://en.wikipedia.org/wiki/Pile_cap(10:02 am 02:08:20)
ii. https://alliedmaterials.com.pk/transit-concrete-mixer-karachi/
iii. https://en.wikipedia.org/wiki/Crane_(machine)
iv. https://www.civilsimplified.com/resources/what-is-total-station
v. http://www.cement.pk/types-of-cement/
vi. https://civiltoday.com/civil-engineering-materials/sand/233-sand-composition-types
vii. https://www.meadmetals.com/blog/steel-grades
viii. https://www.engineersupply.com/total-stations.aspx
37