Field Operations
Version 3.11 – 16 April 2010
SAPETRO
BR
Summary
Daily Evening Maintenance Meeting 28
Daily Evening Production Meeting 29
Presentation of the entity
Marine Operations Meeting 30
Organisation Chart 4 Permit to Work Validation Meeting 31
List and Agenda of Meetings 5 Daily Evening Site Meeting 32
Weekly Calendar 6
FOMS
Weekly Meetings
7
Weekly HSE Site Meeting 34
Daily Meetings Weekly Site Planning Meeting 35
CPO Handover 9 Weekly Site Performance Meeting 36
CCR Operator / CCR Leader Hand-over 10 Weekly Maintenance Evaluation 37
Shift Team Leader Hand-over 11 Weekly Inspection Meeting 38
Start of Shift Tool Box Talk 12 5 weeks Planning & Coordination Meeting 39
Daily Performance Production Meeting 13 Weekly Well Performance 40
Start of Job Tool Box Talk 14
Daily Morning Site Meeting Weekly M & I Meeting 41
15 Weekly Production Meeting
Daily Logistics (Cargo) Meeting 16 42
Daily Turbo Gen / Compressor Meeting 17 Weekly Treatment & Chemicals Meeting 43
Daily Production Phone Call 18 SMR Meeting 44
Daily Inspection Phone Call 19 Weekly Maintenance Planning Meeting 45
Daily Maintenance & Inspection Phone Call 20
Daily Chemicals Phone Call 21 Monthly Meetings
Daily Morning Site-Base Phone Call 22 MTMC Monthly Site Performance Meeting 47
Daily Maintenance Review - Telecom 23 COSITE HSE 48
Daily Maintenance Review - Mechanical 24
Daily Maintenance Review -Electrical Organisation
25
Daily Maintenance Review – Management Operating System 50
Instrument/ICCS 26
Permit To Work Risk Assessment 27 Meeting Evaluation Matrix 51
OFFSHORE PLANNING
MEDIC.
& SIMOPS COORD.
HEAD OFFSHORE HEAD OFFSHORE HEAD OFFSHORE MANAGER OFFSHORE HEAD OFFSHORE
TECHNICAL SUPPORT PRODUCTION TUPNI MAINTENANCE AND MARINE OPERATIONS HSE DW TUPNI
INSPECTION
Topside Maint.
Leader Laboratory
Engineer
Leader Production
IS/IT Engineer
shift Team 1
Leader Production
shift Team 2
Objectives Agenda
Agenda
Transmission of key information from the previous shift Information on the problems observed during the shift (2’)
To make an effective handover between the two chief production Information on the new downgraded situations (1’)
operator Information on the work permits in progress, current status and
potential issues (4’)
Key points from the Walk The Floor (2’)
Hand-over of CPO Log Book (1’)
Objectives Agenda
Agenda
To have an effective transfer of key information from one shift to Information on the problems observed during the shift (1’)
the next Check the Short Interval control of production (PI) (1’)
To review in detail events from the content of the log book Check the register of inhibitions (2’)
To launch daily activities, according to the last events of the night Information on the work permits in progress (3’)
To review production performance Hand-over of CCR log book (1’)
To confirm the priorities for the day Verification of temporary guideline (2’)
Objectives Agenda
Agenda
To have an effective transfer of key information from one shift to Events of the previous shift (3’)
the next Situation of the production compare to objective (1’)
To review in detail events from the previous shift Review Production / injections target (1’)
To launch daily activities, according to the last events of the Review of Log Book (1’)
previous shift Review the inhibitions (2’)
To review production performance Follow up of Work Permits (status and potential issues) (3’)
To confirm the priorities for the day Review degraded situations (1’)
Review the activities of the operators from the Operations
Whiteboard for preparation of assignment (3’)
Objectives Agenda
Agenda
To emphasise the HSE aspects of the jobs coming HSE Review (anomalies, incidents…) (2’)
To launch daily activities, according to the last events of the night Review of last night and Day – 1 Key facts (2’)
To review production performance Production Operations Task List - Priorities for Day D (2’)
To confirm the priorities for the day Validation of planning for Day D and assignment (2’)
Reminder on HSE critical aspects for Day D activities (2’)
Objectives Agenda
Agenda
Review production, injection and export figures for Day D-1 Review of Day D-1 Highlights (2’)
Identify and make first analysis of main Production and Injection Review of Well Testing results and changes vs previous test (1’)
Shortfalls Analysis of BSW and HC in Water ratio (1’)
Initiate corrective actions if necessary Analysis of Production and Injection Shortfalls for Day D-1 and
Control the quality of data reported in PDMS and sent to Lagos allocations (6’)
Review and update of action plan (2’)
Preparation of synthesis for OIM (3’)
Objectives Agenda
Agenda
Clear understanding of the job by all personnel involved Outline of the job (2‘)
Identification of all critical safety factors and correct method of Critical safety factors (2‘)
work Equipment to be used (3’)
Effective and efficient plan for how to carry out the job How to approach the job (3’)
Objectives Agenda
Agenda
Review of Health & Safety events of the night Highlights HSE and operations review (last night) (3’)
Review of Environmental events of the night Review of D-1 Performance for each function HSE, Prod, M&I …
Review and first analysis of Performance Results of Day D-1 using Dashboard KPI as frame and highlights as explanations (15’)
Identification of main Production and Injection Shortfalls Planning day D
Review of highlights (operations, logistics, …) of the night and D Review of Production SIC of Day D (2’)
Take corrective actions if necessary Review of Key Actions (4’)
Update day D events and tasks according to previous day D-1 Review and update of action plan (4’)
events Review of AKPO FPSO meeting planning of the day (2’)
Highlighting pending support expecting from the Base
Objectives Agenda
Agenda
Organise the day for lifting and handling according to the HSE Review (anomalies, incidents…) (1’)
requirement Priorities and guidelines for Day D activities (7’)
Ensure availability of utilities (crane, forklift, pallet truck) empty Planning for Day D and D+1 (7’)
baskets and containers for the Day D, D+1, D+2
Review logistics priorities according operation planning
To kick-off the day, reinforce team work and improve marine
operations performance
Objectives Agenda
Agenda
Review of previous day’s actions Review of previous day’s actions and major events day D-1 (4’)
Review priorities for the Day D Site key concerns and needs for support (4’)
Confirm support needs of onshore support Overview of daily forecasted operations (4’)
Update Action Plan Review of priorities for the Day D (3’)
Progress on affairs’ preparation (2’)
Review & Update of Action plan (3’)
Objectives Agenda
Agenda
Highlight shortfalls and launch specific corrective actions Review of major events day D-1 (3’)
Review key facts & results of day D-1 Site key concerns and needs for support (3’)
Review priorities for the Day D Overview of daily forecasted operations (3’)
Review updates on affairs and specific projects Review of priorities for the Day D (1’)
Confirm support needs of onshore support Progress on affairs’ preparation (2’)
Update Action Plan Review & Update of Action plan (3’)
Objectives Agenda
Agenda
To provide to site the best operational support from maintenance Review of major events day D-1 (3’)
teams at base Site key concerns and needs for support (3’)
Review key facts & results of day D-1 Overview of daily forecasted operations (3’)
Review priorities for the Day D Review of priorities for the Day D (1’)
Review updates on affairs and specific project Progress on affairs’ preparation (2’)
Confirm support needs of onshore support Review & Update of Action plan (3’)
Update Action Plan
Objectives Agenda
Agenda
To provide to site the best operational support from maintenance Review of major events day D-1 (3’)
teams at base Site key concerns and needs for support (5’)
Review key facts & results of day D-1 Overview of daily forecasted operations (3’)
Review of vital functions and machine availability Review of priorities for the Day D (3’)
Review priorities for the Day D Progress on affairs’ preparation (3’)
Confirm support needs of onshore support Review & Update of Action plan (3’)
Clarify vendor requirements
Review updates on affairs and specific project
Update Action Plan
Identify key issues for specific discussion (outwith this meeting)
Objectives Agenda
Agenda
To provide to site the best operational support from maintenance Review of major events day D-1 (3’)
teams at base Site key concerns and needs for support (3’)
Review key facts & results of day D-1 Overview of daily forecasted operations (3’)
Review priorities for the Day D Review of priorities for the Day D (1’)
Review updates on affairs and specific project Progress on affairs’ preparation (2’)
Confirm support needs of onshore support Review & Update of Action plan (3’)
Update Action Plan
Objectives Agenda
Agenda
Review of Health & Safety events of the night + day D-1 HSE Highlights (3’)
Review of Environmental events of the night + day D-1 General Information (2’)
Communication of general information Review of D-1 Performance for each function HSE, Prod, M&I …
Review and first analysis of Performance Results of Day D-1 using Dashboard KPI (HSE, production shortfalls, vital functions
Identification of main Production and Injection Shortfalls status) as frame and highlights as explanations (10’)
Review of highlights (operations, logistics, …) of the night and D-1 Review of daily forecasted operations (5’)
Take corrective actions if necessary Review of Key Actions and blocking issues (5’)
Review of main program for Day D and D+1 Review and update of action plan (5’)
Highlighting pending support expecting from the Base
Update Action Plan
Objectives Agenda
Agenda
To provide to site the best operational support from maintenance Review of major events day D-1 (3’)
teams at base Site key concerns and needs for support (3’)
Review key facts & results of day D-1 Overview of daily forecasted operations (3’)
Review of vital functions and systems availability Review of priorities for the Day D (3’)
Review priorities for the Day D Review & Update of Action plan (3’)
Confirm support needs of onshore support
Update Action Plan
Objectives Agenda
Agenda
To provide to site the best operational support from maintenance Review of major events day D-1 (3’)
teams at base Site key concerns and needs for support (3’)
Review key facts & results of day D-1 Overview of daily forecasted operations (3’)
Review of vital functions and machine availability Review of priorities for the Day D (3’)
Review priorities for the Day D Review & Update of Action plan (3’)
Confirm support needs of onshore support
Confirm urgent spare parts needs
Clarify vendor needs and timings
Update Action Plan
Objectives Agenda
Agenda
To provide to site the best operational support from maintenance Review of major events day D-1 (3’)
teams at base Site key concerns and needs for support (3’)
Review key facts & results of day D-1 Overview of daily forecasted operations (3’)
Review of vital functions and machine availability Review of priorities for the Day D (3’)
Review priorities for the Day D Review & Update of Action plan (3’)
Confirm support needs of onshore support
Confirm urgent spare parts needs
Clarify vendor needs and timings
Update Action Plan
Objectives Agenda
Agenda
To provide to site the best operational support from maintenance Review of major events day D-1 (3’)
teams at base Site key concerns and needs for support (3’)
Review key facts & results of day D-1 Overview of daily forecasted operations (3’)
Review of vital functions and machine availability Review of priorities for the Day D (3’)
Review priorities for the Day D Review & Update of Action plan (3’)
Confirm support needs of onshore support
Confirm urgent spare parts needs
Clarify vendor needs and timings
Confirm urgent spare parts needs
Clarify vendor needs and timings
Update Action Plan
Objectives Agenda
Agenda
To prepare work pack of day D+1 to be validated by RSES during the Check the last reviewed planning for the day D+1, D+2 (5’)
day For each PTW request : (2’ per PTW)
Evaluate that Performing Authority has taken into account the risks of Check & challenge risk analysis & correct if necessary
the job Check & challenge risk mitigations & correct if necessary
Review final analysis of potential interferences between operations Check the additional documents (sketches, work procedure,
that could increase the risk level task-pack, process, mechanical and electrical isolations,
Challenging risk and validate inhibitions, FPSO map …)
Validate previous day notifications to transform in Work Order Check the respect of Risk Assessment Meeting outputs and
needs for a specific Kick-off Meeting
Select PTW to be reconsidered (5’)
Analyse notifications raised during previous day and validate the
ones which should convert into work orders
Objectives Agenda
Agenda
Review of Key facts of Day D, blocking issues, status of planned Review of Maintenance key HSE facts for Day D (1’)
operations of Day D and potential continuations during the night Review of key facts and blocking issues of Day D for each trade (15’)
Revise progress of work, team work and improve maintenance Review of progress of work and continuations during the night (5’)
efficiency Priorities and guidelines for Day D+1 activities (5’)
Review of planning and priorities for Day D+1 Identify interference with other operations for Day D+1
Anticipation of potential interferences with other operations for Validation of planning D+1 (10’)
day D+1 and D+2 Review of Action Plan (2’)
Take corrective actions if necessary Transfer of information on Plant status (2’)
Objectives Agenda
Agenda
Review of Key facts of Day D, blocking issues, status of planned Key HSE Events of the day (1’)
operations of Day D and potential continuations during the night Production status vs Objective at 18pm (1’)
Revise progress of work, team work and improve production Review of key facts and blocking issues of Day D for process,
performance, taking corrective actions utilities and subsea (12’)
Review of Short Interval Control and trend of Production/Injection First review of the Shortfalls causes & allocation in the Excel file
since 0h00 (2’)
Review of planning and priorities for Day D+1 Review of progress of work and continuations during the night (5’)
Anticipation of potential interferences with other operations for Priorities and guidelines for Day D+1 activities (5’)
day D+1 and D+2 Transfer of information on Plant status (4’)
Review of inhibitions
Objectives Agenda
Agenda
To review the day, reinforce team work and improve marine HSE Review (anomalies, incidents…) (2’)
operations performance Review of Key facts Day D and D – 1 (night) (5’)
Ensure availability of utilities for the Day D+1, D+2 Deck operations
Review logistics priorities according operation planning Field activities
Tank activities
Planning for Day D+1 and D+2 (3’)
Priorities and guidelines for Day D activities (5’)
Objectives Agenda
Agenda
Approval of opening WP Select & validate appropriate PTWs to be opened (15’)
Check any interferences
Objectives Agenda
Agenda
Review of Health & Safety events of the day Review of Site key HSE facts for Day D (3’)
Review of Environmental events of the day Review of Site key facts and blocking issues for Day D
Review of Key facts of Day D, blocking issues, status of planned (Production, Maintenance, Construction (15’)
operations of Day D and potential continuations during the night Review continuing operations overnight & PTW extensions (if req)(3’)
Review of planning and priorities for Day D+1 Review and validation of planning and priorities for tomorrow
Anticipation of potential interferences between operations for day activities (D+1), anticipation of potential interference between
D+1 and D+2 operations and coordination (10’)
Review of the PoB Review of special operations (treatment, tests, etc…) and SIMPOS (5’)
Take corrective actions if necessary Validation of logistics and Marine operations (offloading, liftings) (4’)
Confirmation of meetings for next day Review and update of action plan (7’)
Validation POB & visitors for the next day D+1 (1’)
Any other business priorities and meeting agenda for day D+1 (1’)
Summary of plan priorities (1’)
Objectives Agenda
Agenda
To improve HSE performance during operations by reviewing and Review of HSE issues and KPI for last week (accidents, incidents,
analysing HSE events of the past week spills,…) (5’)
To exchange information with the contractors to facilitate Review of Inhibitions and Downgraded Situations status (5’)
management of HSE issues Explanation of new cases (5’)
Review Site status on Inhibitions, Downgraded Situations, including Feedback on Work Permits audits (5’)
adequacy of temporary measures Feedback on Operators Walk-the-Floor and Site Audits (5’)
To take improvement or corrective actions Review on potential issues regarding accommodation & catering (5’)
To review the efficiency of HSE corrective actions previously Open discussion around the table (10’)
implemented Review and update of action plan (5’)
To give feedback from REX and validate Weekly theme of HSE Talk Presentation of Weekly theme of HSE Talk support and REX (10’)
Review on anomalies (5’)
Includes operators 1 week in 2 New anomalies this week
Most critical open anomalies blocked
Objectives Agenda
Agenda
To review last week realisation of planned operation Review of previous week plan attainment (KPI) (4’)
To review any conflicts of works and ensure efficient work start Review of continuation and progress of works (4’)
To set a relevant Maintenance/Production/Works schedule for the Presentation and review of the proposed schedule for the coming
coming week (W+1), so as to enforce plan attainment week (W+1) with consequential need of equipment (20’)
To set priorities according to safety and production objectives Agreement on the schedule of equipments availability for
To review specific plans (e.g. shutdown, major intervention, maintenance (4’)
campaigns, etc.) and Field Ops ¾ months integrated planning Review of Integrated Field Ops Planning (10’)
To ensure that preparatory work for execution is under way and Validation POB - logistics & visitors (8’)
completed, and needed Pre-Job and Kick-Off meetings planned Meeting schedule for the week (2’)
To ensure specific resources are requested and available Re-cap of Works priority (3’)
Validate POB Review and update of action plan (5’)
Objectives Agenda
Agenda
Review and inform personnel on site weekly performance on : General Information (3’)
HSE and ISO 14001 Review of weekly KPIs for HSE, production & maintenance (7’)
Production & Injection Review of operations performance and operation status (5’)
Planning and operations Review of Vital Functions availability and related action plan (5’)
Review of major production events, Shutdowns and Shortfalls Ensure that all shortfall related problems are clearly identified
Improve site performances and initiate corrective actions and understood (identify actions required to achieve this) (10’)
Identify needs for onshore assistance Ensure that all shutdown related problems are clearly identified
Get feed back from previous “Root Cause Analysis” and “Problem and understood (identify actions required to achieve this) (15’)
Solving Group” Identify causes of planning slippage (real vs plan) (5’)
Review and update of action plan (5’)
Review of TOP TEN Subjects progress vs plan (5’)
Objectives Agenda
Agenda
Review last week maintenance events and any behaviour or Review of weekly maintenance highlights :
performance that would impact maintenance weekly/ monthly KPI HSE (5’)
Vital Functions and Equipment status (5’)
Review of shutdowns and / or shortfalls due to maintenance (5’)
Identification of good performance related to an outstanding
efficient of maintenance teams (5’)
Review of inappropriate /or efficient behaviour of maintenance
teams (5’)
Objectives Agenda
Agenda
HSE review and general information (2’)
Communication of general information
Feedback of Field Operations meetings (3’)
Review of the last week’s events :
Encountered issues on on-going interventions (10’)
Dysfonctionings, issues
Site’s request for support (5’)
Impact on production / injection
Progress on affairs’ preparation (5’)
Blocking point and gaps with planning
Analyse feedback on audits and related action plan (5’)
Improve site Field Ops performance by initiating corrective actions
Review of Crane activities (5’)
Prioritisation of actions to be done the coming week
Blocking point regarding on-going supplies (5’)
Task allocation for the coming week
Key points and priorities for the coming week (5’)
Anticipate planning’s modifications
Modification of the interventions’ planning (5’)
Review updates on affairs and specific project
Review and update of action plan (10’)
Analyse feedback on audits
Objectives Agenda
Agenda
To comment on and complete drafts 4 months schedules Review progress of main activities up to 5 weeks(5’)
To validate site activities for the 5 weeks to come Comment draft of the 5 weeks schedule by trade(5’)
To validate the feasibility of validated Week S+1 activities Identify any further potential for simultaneous execution of jobs
To ensure that preparatory work for execution is under way and and anticipate any blocking issues for Week M+1 – M+4 (5’)
completed Review of the draft 4W Field Ops planning per Trade / Project (35’)
To plan Pre-Job and Kick-Off meetings and Management venue Ensure all conditions (resources, site status…) are available to
according to POB achieve scheduled activities:
To ensure specific resources are requested and available POB forecasted
To coordinate activities and logistics to reduce shortfalls and Brief scan weekly schedule of next week (W+1)
shutdowns Validation of the week W+2 (100%)
Validation of weeks W+3 and W+4 (60%)
Clarification of Works priority (5’)
Review and update of action plan (5’)
Objectives Agenda
Agenda
Review safety issues – well integrity Review of the safety of wells open and closed(10’)
Identify the non-conformities and delays on safety actions Review of the delayed well safety actions, oil and gas tightness down
Analyse weekly well performance hole and surface, test eruptivity, valve greasing, increase in annular
Review Gas and Water Injection space pressure.(10’)
Validate the actions for the week on safety/ integrity, productivity List the well to be worked on the following week W+1 (10’)
and on injection Review sand and H2S measurement and treatment(5’)
Review well performance of the week W+1(10’)
Documentation de support Review actions for well productivity for the week W+1; well test
priorities, well optimisation (injection products, choke settings,
Database «Well Integrity»/General view of wells (APS)
Dashboard from the database « Well integrity » (APS) follow-up of wells (sampling and recording of parameters) (10’)
Reports and notable well safety events of the week; test for leaks Review injection of water and gas (5’)
surface and downhole, test eruptivity, greasing well valves, raised
annular pressures(APS)
Record of sand Document
measurement to and
support
H2S andthe meeting
follow up and treatment
Livrables deoflathe
Deliverables réunion
meeting
(LAB/PFS). Notable well productivity events of the week; production The reporting of tests and their results
test priorities; well optimisation (chemical injection, choke settings,
Agreement and recording of actions
parameter modification and parameter follow up FCW)
Review of Well Tests « Verification Test » (APS) Action plan updated (PFS)
List of priority wells to test sent by e des puits à tester WP & RES The planning of well activities for the following week W+1 (PFS)
Meeting notes – Weekly Well Monitoring
Review of the wells (APS)
Objectives Agenda
Agenda
Communication of general information HSE review and general information (2’)
Review of the last week’s events : Feedback of Field Operations meetings (3’)
Dysfonctionings, issues Encountered issues on on-going interventions (10’)
Impact on production / injection Monitoring of Vital Function & Machine unavailability and related
action plan (5’)
Blocking point and gaps with planning
Backlog status Ensure that production related problems are clearly identified (10’)
Improve site Field Ops performance by initiating corrective actions POB and vendor visits (4’)
Prioritization of actions to be done the coming week Site’s request for support (4’)
Task allocation for the coming week Progress on affairs’ preparation (4’)
Anticipate planning’s modifications Blocking point regarding on-going supplies (4’)
Key points and priorities for the coming week (4’)
Modification of the interventions’ planning (5’)
Review and update of action plan (5’)
Objectives Agenda
Agenda
To communicate general information General Information and review of agenda for Week W (5’)
Review and inform personnel Field Ops weekly performance for Review of weekly KPIs and highlights for HSE (5’)
Week W-1 , prepare Weeks W and W+1 on : Review of production performance with weekly dashboard
HSE and ISO 14001 (production, injection, shortfalls, shutdowns…) (10’)
Production & Injection Explain operations performance and status using weekly KPIs and
Planning and operations highlights (20’)
Review of major production events, Shutdowns and Shortfalls Review of Vital Functions availability and related action plan (5’)
Improve site performances and initiate corrective actions on Ensure that all shortfall/ shutdown related problems are identified
critical issues and understood (identify actions needed to achieve this) (15’)
Review onshore needs for assistance and initiate actions Identify causes of planning slippage (real vs plan) (5’)
Define priorities for next week W and W+1 Review and update of action plan (10’)
Review of TOP TEN Subjects (Integrity) progress vs plan (10’)
Open discussion around the table (5’)
Objectives Agenda
Agenda
To check chemical injection Review of chemical injections (5’)
To optimise chemical injection Analysis of the gap between instructions and injections (10’)
To review impact of chemical injection on production performance Review of treatment efficiency (10’)
To anticipate any procurement issue on chemicals Review of chemical stocks & procurement (10’)
Review of Lab performance (5’)
Review and update of action plan (5’)
Objectives Agenda
Agenda
To review the SMR portfolio management (budget; Gates; Class 2 SMR: review every week
planning; …) Class 1 SMR: review every two weeks
Analysis of new SMR request Review of the performance Dashboard for the SMR (2nd /month)
Agreement on the technical solution to be implemented Presentation of new SMR (every two weeks)
Follow the progress of the SMR linked to HSE issues Validate technical proposal to be implemented
Re-assess the priority for the SMR Progress review of SMR linked to HSE
Analyze the blocking points
Review the SMR Priority and update the SMR planning in the TUPNI
Integrated Planning
Objectives Agenda
Agenda
To review last week realisation of planned operation Review of previous week plan attainment (KPI) (5’)
To review any conflicts of works and ensure efficient work start Review of works in backlog – rescheduling and priorisation (15’)
To set a relevant Maintenance schedule for the coming week Review of continuation and progress of works (15’)
(W+1), so as to enforce plan attainment Presentation and review of the proposed schedule for the coming
To set priorities according to safety and production objectives week (W+1) with consequential need of equipment (45’)
To review specific plans (e.g. shutdown, major intervention, Agreement on the schedule of equipment availability for
campaigns, etc.) and Field Ops ¾ months integrated planning maintenance (10’)
To ensure that preparatory work for execution is under way and Re-cap of Works priority (10’)
completed, and needed Pre-Job and Kick-Off meetings planned Review and update of action plan (10’)
To ensure specific resources are requested and available
Validate POB associated with planned jobs
Objectives Agenda
Agenda
Have an evaluation of the month regarding: HSE review
Events, anomalies and incidents Review of the month Key events and their impact in the
Blocking points, gaps with the planning operational performance of AKPO
Review the KPI’s for the month Status of the ongoing actions and review of all the blocking points
Review of the medium term maintenance planning
Definition of the corrective actions to improve the maintenance
performances
Validation of the performance score for the month
Objectives Agenda
Agenda
Review and analysis off the Hygiene-Safety & environment events, Analysis of the HSE results and KPI (10’)
for the month and ISO 14001 improvement actions
Review of the integrity level of the installation: (20’)
Review of the Downgraded Situation and long term inhibitions
Review DS and LT Inhibitions
Validation of the new environmental objectives
Status of the inspection of the safety equipments
Review Training needs
Status on the Preventive Program maintenance
Review Audit’s results if any
Review and analysis of the monthly HSE Key Events (10’)
Rex on the monthly safety exercises
Status of HSE actions in Action Plan and SYNERGI(5’)
Communication with the contractors on the key HSE points
Team awareness on the major theme recorded in the anomalies REX on safety exercises and Safety Inspection Tour (5’)
Communicate the key HSE objectives validated at TUPNI level REX from headquarter accident feedbacks on other affiliates (5’)
Open discussion (5’)
Update of HSE actions in Action Plan (5’)
1 note by line :
- 0 : non conforming
- 1 : partially
conforming
- 2 : conforming
Coefficient
associated with
the question