TỔNG CÔNG TY ĐẦU TƯ PHÁT TRIỂN ĐƯỜNG CAO TỐC VIỆT NAM - VIET NAM EXPRESSWAY CORP.
BQLDA ĐƯỜNG CAO TỐC HỒ CHÍ MINH - LONG THÀNH - DẦU GIÂY
HỒ CHÍ MINH - LONG THÀNH - DẦU GIÂY EXPRESSWAY PROJECT MANAGEMENT UNIT
Project: NORTH - SOUTH EXPRESSWAY CONSTRUCTION PROJECT Package (Gói thầu): 1a
(HO CHI MINH CITY - DAU GIAY SECTION) Station: km 4+000 - km 7+500
(Tên dự án: Dự án đường cao tốc Bắc - Nam đoạn TP HCM - Dầu Giây) (Lý trình: km 4+100 - km 7+500)
Consultants (TV): CONSORTIUM OF NIPPON KOEI AND TEDIS Contractor (Nhà thầu): CHINA ROAD & BRIDGE CORP.
Comment
No. Check List Signed Date
(Nhaän
(Soá) (Danh muïc) (Kyù teân) (Ngaøy)
xeùt)
01 List of Acceptance Minutes for Pier Column construction (Danh muïc nghieäm thu thi coâng Thaân Truï)
02 Inspection for Steel Bar (Bieân baûn nghieäm thu coát theùp) OK
03 Inspection for Rebar and Formwork (Bieân baûn nghieäm thu coát theùp vaø vaùn khuoân) OK
04 Inspection for Position, Elevation of Formwork (B/baûn k/tra vò trí, cao ñoä vaùn khuoân) OK
05 Inspection of Construction Preparation Work (B/baûn k/tra cg taùc chuaån bò thi coâng) OK
06 Inspection for Sampling of placed Concrete (Bieân baûn kieåm tra laáy maãu beâ toâng) OK
07 Inspection for Concreting of Pier Column (Bieân baûn kieåm tra ñoå beâ toâng Thaân Truï) OK
08 Inspection for Pier Column completed (B/baûn k/tra h/hoïc Thaân Truï hoaøn thaønh) OK
Concrete Compressive Strength Test result (Keát quaû thí nghieäm neùn kieåm tra cöôøng ñoä beâ toâng) OK
FOR CONTRACTOR
CONTRACTOR FOR CONSULTANT
CONSULTANT
NHÀ THẦU TƯ VẤN
QC Manager Project Manager Structural Engineer Resident Engineer
CONSTRUCTION TEAM Q.C OFFICE PROJECT MANAGER ENGINEER IN CHARGE APPROVED BY
Date: ĐỘI XÂY DỰNG Date:
QUẢN LÝ CHẤT LƯỢNG Date:
GIÁM ĐỐC DỰ ÁN Date:
KỸ SƯ PHỤ TRÁCH CHẤPTHUẬN BỞI
MINISTRY OF TRANSPORT Central Mekong Delta Region Connectivity Project (CMDCP) -
Dự án Kết nối Khu vực Trung tâm Đồng bằng Mê-kông
(CMDRCP)
Number
Dia -meter (mm) Length (mm)
Rebar No Đường kính (mm) Chiều dài (mm) Remark
Số lượng
Cốt thép số Design Actual Design Actual Design Actual Ghi nhận
Thiết kế Thực tế Thiết kế Thực tế Thiết kế Thực tế
Acceptance (Sự chấp thuận): Accepted (chấp thuận): Not accepted (không chấp thuận):
4. Construction Joint between Pile Cap & Column (Moái noái thi coâng giöõa Beä moùng & Thaân truï)
Removal and cleaning of loose concrete Ö
Removal and cleaning of harmful material Ö
Overall Judgement Accepted (Chaáp thuaän) Not accepted (Khoâng chaáp thuaän)
Ö
Remark:
(Nhaän xeùt):
Consultants (TV): CONSORTIUM OF NIPPON KOEI AND TEDIS Contractor (Nhà thầu): CHINA ROAD & BRIDGE CORP.
Checking point 5T 6T 7T 8T
Coordinate &
X (North) Y (East) Z (Lev) X (North) Y (East) Z (Lev) X (North) Y (East) Z (Lev) X (North) Y (East) Z (Lev)
Level
Design (m)
Actual (m)
Difference (mm)
Hor. Dev. (mm)
Tolerance (mm)
Conclusion OK OK OK OK OK OK OK OK
Note: Horizontal Deviation (Hor. Dev. - A): DX: Difference in X direction
A = (DX2+DY2)0.5 DY: Difference in Y direction
DZ: Difference in Z direction (Level)
Remark:
(Nhaän xeùt)
FOR CONTRACTOR
CONTRACT0R FOR CONSULTANT
CONSULTANT
NHÀ THẦU TƯ VẤN
Const. Team Surveyor Const. Manager Surveyor
CONSTRUCTION TEAM SITE ENGINEER CONSTRUCTION MANAGER INSPECTOR
ĐỘI XÂY DỰNG GIÁM SAT HIỆN TRƯỜNG GIÁM ĐỐC THI CÔNG GIÁM SÁT VIÊN
Br-IS-PCO-05 rev.02
TỔNG CÔNG TY ĐẦU TƯ PHÁT TRIỂN ĐƯỜNG CAO TỐC VIỆT NAM - VIET NAM EXPRESSWAY CORP.
BQLDA ĐƯỜNG CAO TỐC HỒ CHÍ MINH - LONG THÀNH - DẦU GIÂY
HỒ CHÍ MINH - LONG THÀNH - DẦU GIÂY EXPRESSWAY PROJECT MANAGEMENT UNIT
Project: NORTH - SOUTH EXPRESSWAY CONSTRUCTION PROJECT Package (Gói thầu): 1a
(HO CHI MINH CITY - DAU GIAY SECTION) Station: km 4+000 - km 7+500
(Tên dự án: Dự án đường cao tốc Bắc - Nam đoạn TP HCM - Dầu Giây) (Lý trình: km 4+100 - km 7+500)
Consultants (TV): CONSORTIUM OF NIPPON KOEI AND TEDIS Contractor (Nhà thầu): CHINA ROAD & BRIDGE CORP.
Date(dd/mm/yy-ngaøy/thaùng/naêm):
Work Item (Haïng muïc): Preparation for concreting of Pier Column (Chuaån bò ñoå beâ toâng Thaân Truï)
Abutment/Pier (Moá/Truï): Abutment/Pier …………… (Mố/Trụ ………………..)
Remark:
(Nhaän xeùt)
FOR CONTRACTOR
CONTRACT0R FOR CONSULTANT
CONSULTANT
NHÀ THẦU TƯ VẤN
Const. Team Site Engineer Const. Manager Inspector
CONSTRUCTION TEAM SITE ENGINEER CONSTRUCTION MANAGER INSPECTOR
ĐỘI XÂY DỰNG GIÁM SAT HIỆN TRƯỜNG GIÁM ĐỐC THI CÔNG GIÁM SÁT VIÊN
Br-IS-PCO-06 rev.02
TỔNG CÔNG TY ĐẦU TƯ PHÁT TRIỂN ĐƯỜNG CAO TỐC VIỆT NAM - VIET NAM EXPRESSWAY CORP.
BQLDA ĐƯỜNG CAO TỐC HỒ CHÍ MINH - LONG THÀNH - DẦU GIÂY
HỒ CHÍ MINH - LONG THÀNH - DẦU GIÂY EXPRESSWAY PROJECT MANAGEMENT UNIT
Project: NORTH - SOUTH EXPRESSWAY CONSTRUCTION PROJECT Package (Gói thầu): 1a
(HO CHI MINH CITY - DAU GIAY SECTION) Station: km 4+000 - km 7+500
(Tên dự án: Dự án đường cao tốc Bắc - Nam đoạn TP HCM - Dầu Giây) (Lý trình: km 4+100 - km 7+500)
Consultants (TV): CONSORTIUM OF NIPPON KOEI AND TEDIS Contractor (Nhà thầu): CHINA ROAD & BRIDGE CORP.
Date (dd/mm/yy-ng/th/năm):
Work Item (Hạng mục): Concreting of Pier Column (Đổ bê tông Thân Trụ)
Location (Vị trí) : Abutment/Pier …………… (Mố/Trụ ………………..)
Temperatu
Number Air
Volume Name of Slump re of
No. Time Vehicle No. of temperatur Weather Remark
(m3) Sample (cm) concrete
Samples e
< 32º
Khối
Biển số xe Số lượng Độ sụt Nhiệt độ BT Nhiệt độ
Số Thời gian lượng Tên mẫu Thời tiết Ghi nhận
mẫu thử (cm) < 32º không khí
(m3)
1
2
3
4
5
6
7
8
9
10
11
12
Acceptance (Nghiệm thu): Accepted (Chấp thuận) Ö Not accepted (Không chấp thuận)
FOR CONTRACT0R
CONTRACTOR FORCONSULTANT
CONSULTANT
NHÀ THẦU TƯ VẤN
Const. Team
CONSTRUCTION TEAM
Site Engineer Const. Manager
CONSTRUCTION MANAGER
Inspector
SITE ENGINEER INSPECTOR
ĐỘI XÂY DỰNG GIÁM SAT HIỆN TRƯỜNG GIÁM ĐỐC THI CÔNG GIÁM SÁT VIÊN
Br-IS-PCO-07 rev.02
TỔNG CÔNG TY ĐẦU TƯ PHÁT TRIỂN ĐƯỜNG CAO TỐC VIỆT NAM - VIET NAM EXPRESSWAY CORP.
BQLDA ĐƯỜNG CAO TỐC HỒ CHÍ MINH - LONG THÀNH - DẦU GIÂY
HỒ CHÍ MINH - LONG THÀNH - DẦU GIÂY EXPRESSWAY PROJECT MANAGEMENT UNIT
Project: NORTH - SOUTH EXPRESSWAY CONSTRUCTION PROJECT Package (Gói thầu): 1a
(HO CHI MINH CITY - DAU GIAY SECTION) Station: km 4+000 - km 7+500
(Tên dự án: Dự án đường cao tốc Bắc - Nam đoạn TP HCM - Dầu Giây(Lý trình: km 4+100 - km 7+500)
Consultants (TV): CONSORTIUM OF NIPPON KOEI AND TEDIS Contractor (Nhà thầu): CHINA ROAD & BRIDGE CORP.
Date (dd/mm/yy-ng/th/naêm):
Work Item (Haïng muïc): Concreting of Pier Column (Ñoå beâ toâng Thaân Truï)
Location (Vò trí) : Abutment/Pier …………… (Mố/Trụ ………………..)
General Information (Thoâng tin chung)
Concrete Class (Caáp beâ toâng) C30-(Design Mix Name - Teân caáp phoái)
Design Conc. Vol. (Khoái löôïng beâ toâng thieát keá) 0.00 m3 ; Actual Conc. Vol. (Kh/lg BT thöïc teá): 0.00 m3
Curing method (Phöông phaùp baûo döôõng) Bags + water (Bao boá + töôùi nöôùc)
Protection from raining (Baûo veä khi möa) Cover with plastic sheet (Che phuû baèng baït nhöïa)
Pouring method (Phöông phaùp ñoå) Pumping car (Xe bôm beâ toâng)
Total 0 0
Remark:
(Nhaän xeùt)
FOR CONTRACT0R
CONTRACTOR FORCONSULTANT
CONSULTANT
NHÀ THẦU TƯ VẤN
Const. Team Site Engineer Const. Manager Inspector
CONSTRUCTION TEAM SITE ENGINEER CONSTRUCTION MANAGER INSPECTOR
ĐỘI XÂY DỰNG GIÁM SAT HIỆN TRƯỜNG GIÁM ĐỐC THI CÔNG GIÁM SÁT VIÊN
Br-IS-PCO-07 rev.02
TỔNG CÔNG TY ĐẦU TƯ PHÁT TRIỂN ĐƯỜNG CAO TỐC VIỆT NAM - VIET NAM EXPRESSWAY CORP.
BQLDA ĐƯỜNG CAO TỐC HỒ CHÍ MINH - LONG THÀNH - DẦU GIÂY
HỒ CHÍ MINH - LONG THÀNH - DẦU GIÂY EXPRESSWAY PROJECT MANAGEMENT UNIT
Project: NORTH - SOUTH EXPRESSWAY CONSTRUCTION PROJECT Package (Gói thầu): 1a
(HO CHI MINH CITY - DAU GIAY SECTION) Station: km 4+000 - km 7+500
(Tên dự án: Dự án đường cao tốc Bắc - Nam đoạn TP HCM - Dầu Giây(Lý trình: km 4+100 - km 7+500)
Consultants (TV): CONSORTIUM OF NIPPON KOEI AND TEDIS Contractor (Nhà thầu): CHINA ROAD & BRIDGE CORP.
Date (dd/mm/yy-ng/th/naêm):
Work Item (Haïng muïc): Concreting of Pier Column (Ñoå beâ toâng Thaân Truï)
Location (Vò trí) : Abutment/Pier …………… (Mố/Trụ ………………..)
General Information (Thoâng tin chung)
Concrete Class (Caáp beâ toâng) C30-(Design Mix Name - Teân caáp phoái)
Design Conc. Vol. (Khoái löôïng beâ toâng thieát keá) 0.00 m3 ; Actual Conc. Vol. (Kh/lg BT thöïc teá): 0.00 m3
Curing method (Phöông phaùp baûo döôõng) Bags + water (Bao boá + töôùi nöôùc)
Protection from raining (Baûo veä khi möa) Cover with plastic sheet (Che phuû baèng baït nhöïa)
Pouring method (Phöông phaùp ñoå) Pumping car (Xe bôm beâ toâng)
Consultants (TV): CONSORTIUM OF NIPPON KOEI AND TEDIS Contractor (Nhà thầu): CHINA ROAD & BRIDGE CORP.