The daily engineering operation report summarizes maintenance activities from July 29, 2023. Technicians replaced a flood light in the wheat storage area and checked load cells in the screens room. In the flour silo area, wiring was dismantled for a motor and a carousel bag checker controller was repaired. The only other task was replacing an extension cable at the miller's office. Four electricians were utilized for these maintenance jobs.
The daily engineering operation report summarizes maintenance activities from July 29, 2023. Technicians replaced a flood light in the wheat storage area and checked load cells in the screens room. In the flour silo area, wiring was dismantled for a motor and a carousel bag checker controller was repaired. The only other task was replacing an extension cable at the miller's office. Four electricians were utilized for these maintenance jobs.
The daily engineering operation report summarizes maintenance activities from July 29, 2023. Technicians replaced a flood light in the wheat storage area and checked load cells in the screens room. In the flour silo area, wiring was dismantled for a motor and a carousel bag checker controller was repaired. The only other task was replacing an extension cable at the miller's office. Four electricians were utilized for these maintenance jobs.
Replace and install busted 100w flood light at center of mealy bin. (2hrs)
Screens room and Pollard packing
Rechecking of Mill 1A 20kg load cell from bin #3 dirty wheat. (1.5hrs) Elect. Installation of 50kg load cell for Mill 1A. Zeroing and calibration. Okay. (2hrs) Elect. Interchange service switch for Bin #3 and Bin #4 tube screw of PMF. Tested and observed. (2hrs) Elect.
Mill Proper No Activities in this area.
Flour Silo, Flour Packing and warehousing
Dismantle wiring of motor for LPF from APF system (Packing), Pull out purging control & level sensors then test. Recover 1 unit of sensor. (6hrs) Elect. Trouble at carousel #2 bag checker, found out that controller is defective. Pull out & repaired at shop. Installed back, Tested & monitored. (3hrs) Elect. Trouble at cake flour recycling system not starting, found out that interlocking is affected by pulling out of unused wires. (1hr) Elect.
Machining / Fabrication Shop.
No Activities in this area.
Activities in other area
Replace defective extension cable for LAN cabinet at miller’s office. (1hr) Elect.