DAILY ENGINEERING OPERATION REPORT (July 29, 2023)

EMD:

Wheat Intake/Storage and Substation


Replace and install busted 100w flood light at center of mealy bin. (2hrs)

Screens room and Pollard packing


Rechecking of Mill 1A 20kg load cell from bin #3 dirty wheat. (1.5hrs) Elect.
Installation of 50kg load cell for Mill 1A. Zeroing and calibration. Okay. (2hrs) Elect.
Interchange service switch for Bin #3 and Bin #4 tube screw of PMF. Tested and observed.
(2hrs) Elect.

Mill Proper
No Activities in this area.

Flour Silo, Flour Packing and warehousing


Dismantle wiring of motor for LPF from APF system (Packing), Pull out purging control & level
sensors then test. Recover 1 unit of sensor. (6hrs) Elect.
Trouble at carousel #2 bag checker, found out that controller is defective. Pull out & repaired at
shop. Installed back, Tested & monitored. (3hrs) Elect.
Trouble at cake flour recycling system not starting, found out that interlocking is affected by
pulling out of unused wires. (1hr) Elect.

Machining / Fabrication Shop.


No Activities in this area.

Activities in other area


Replace defective extension cable for LAN cabinet at miller’s office. (1hr) Elect.

Job Request
0 JR received yesterday.

Note: Engineering personnel utilized yesterday: 4 Elect. regular