Professional Documents
Culture Documents
FLN-MNE-WMS-CV-001 - Perimeter Fence - Reva
FLN-MNE-WMS-CV-001 - Perimeter Fence - Reva
FLN-MNE-WMS-CV-001 - Perimeter Fence - Reva
Mexico, Pampanga
Fluence Energy
DOCUMENT NO:
FLN-MNE-WMS-001
DOCUMENT TITLE:
Project Monitoring Department Effectivity Date: July 15, 2022 Page No. Page 1 of 13
TABLE OF CONTENTS
3. REFERENCES ………………………………………………………………………………………………………..….4
Project Monitoring Department Effectivity Date: July 15, 2022 Page No. Page 2 of 13
Project Monitoring Department Effectivity Date: July 15, 2022 Page No. Page 3 of 13
The QA/QC Inspector shall monitor all QA/QC activities for all
disciplines needed in the project. Set-up the Quality Systems onsite and ensure
Quality Assurance Plans and Procedures are implemented as per Standard
Specification and International Standard requirements. Supervises a multidisciplinary
team of QC inspectors on site and perform quality audits.
2.5 Foreman
Project Monitoring Department Effectivity Date: July 15, 2022 Page No. Page 4 of 13
Project Monitoring Department Effectivity Date: July 15, 2022 Page No. Page 5 of 13
Document
Work Method Statement FLN-MNE-WMS-001
No.:
Document Title: Work Method Statement for Perimeter
Rev. No. A
Fence
Project Monitoring Department Effectivity Date: July 15, 2022 Page No. Page 6 of 13
Document
Work Method Statement FLN-MNE-WMS-001
No.:
Document Title: Work Method Statement for Perimeter
Rev. No. A
Fence
Project Monitoring Department Effectivity Date: July 15, 2022 Page No. Page 7 of 13
Document
Work Method Statement FLN-MNE-WMS-001
No.:
Document Title: Work Method Statement for Perimeter
Rev. No. A
Fence
Project Monitoring Department Effectivity Date: July 15, 2022 Page No. Page 8 of 13
Document
Work Method Statement FLN-MNE-WMS-001
No.:
Document Title: Work Method Statement for Perimeter
Rev. No. A
Fence
Project Monitoring Department Effectivity Date: July 15, 2022 Page No. Page 9 of 13
4.2 Excavation
4.2.1 The first and primary step involved in the excavation is to find out the
extent of soil and clearing of construction site of unwanted bushes, weeds, and
plants.
4.2.2 Setting out or ground tracing is the process of laying down the excavation
lines and center lines etc. on the ground before the excavation is started.
4.2.3 Maximum of 4 and minimum of 2 benchmarks are marked in the corner
for the measurement of level. These benchmarks are marked on permanent
structures like, plinth, road, or tree.
4.2.4 The tracing is marked by lime powder.
4.2.5 With the reference of drawing and benchmarks the depth of the excavation
is fixed.
4.2.6 Excavation is done by manual using shovel and Digging Bar.
4.2.7 The excavated soil is to either removed out the site or stocked around the
excavation pit. 0Minimum of 1 in distance must be maintained between the
stocking of excess soil and pit, so that due to rain or other forces the soil
should not sweep into the pits.
4.2.8 Dressing of excavated pits is to be done as specified in the drawings.
4.2.9 Dewatering of excavated area is to provide if needed.
4.2.10 All the sides of the building must be sealed for the safety propose.
Project Monitoring Department Effectivity Date: July 15, 2022 Page No. Page 10 of 13
Project Monitoring Department Effectivity Date: July 15, 2022 Page No. Page 11 of 13
appear. Insert rebar into the bars fixed on the table. Insert the pipe on the rebar.
Hold the pipe and bend it at the point where you want the bending to appear.
Project Monitoring Department Effectivity Date: July 15, 2022 Page No. Page 12 of 13
4.8.2 After cleaning, the cleaning holes of column formworks are to be tightly
closed since the maximum pressure of the concrete mix is occurring at the
foot of the formwork where the cleaning holes are always to be put against
the thrust-board and against framework bearers. If necessary, additional
formwork is to be thoroughly wetted with water because thereby less water
will be extracted from the concrete mix and later stripping will be
facilitated. When placing the concrete, it is to be made sure that no changes
take place with the formwork.
4.8.3 The design mix and materials for the grade of concrete specified will be
prepared by the ready-mix concrete supplier’s laboratory and will be
approved by clients.
6. SAFETY SECTION