0-Landscape Construction Schedule 20171231
0-Landscape Construction Schedule 20171231
0-Landscape Construction Schedule 20171231
December
Total Total January Total finished
Sr. Activity
quantity Finished per- plan percentage
Plan Finished
centage
1 Soil replacement for palm trees in LRR&LDR (Nos.) 4527 2191 252 253 100% 142 48%
2 Mass excavation and backfill in LRR&LDR (M2) 78500 48396 2854 3640 128% 2724 62%
5 Car parking mid island remaining area casting (Nos.) 50 32 7 5 71% 5 64%
64.67(+794M
8 Paver Type1 installtion(M2) 225229 0 546 - 2658 0%
2 SUBBASE)
152.4(+1294
9 Paver Type2 installtion(M2) 76654 28 359 - 1294 0.04%
SUBBASE)
Average 103%