7. Introduction SiteFracturing
Hydraulic Supervisors

Module – 13
Work Over Operations

Section – 7
Introduction to
Hydraulic Fracturing

C. Alvarez
7. Introduction to Hydraulic Fracturing

Introduction to Hydraulic Fracturing

C. Alvarez Quartz School. Module 13: Work Over Operations / Section 7: Introduction to Hydraulic Fracturing
7. Introduction to Hydraulic Fracturing

Low Permeability Reservoir


Increase well productivity by creating a highly conductive path compared to
the reservoir permeability.

Damage

XL = Fracture half length XL

The fracture will extend through the damaged near wellbore area.
The fracture size is limited to two criteria :
„ Drainage Radius
„ Cost
Fracturing is : Pumping fluid into the formation above fracture pressure.
3 PA
04/25/2006

C. Alvarez Quartz School. Module 13: Work Over Operations / Section 7: Introduction to Hydraulic Fracturing
7. Introduction to Hydraulic Fracturing

Applications for Hydraulic Fracturing

„ If wells natural permeability is low ( Ke < 10 md )

„ Natural production is below economic potential

„ Skin By-Pass “ HyperSTIM “ or higher permeability and soft formations.

„ Modify flow regime deep within the formation (tens to hundreds of feet)

The injected fluid is pumped at a rate above the fracture pressure


of the reservoir to create cracks or fractures within the rock itself.
4 PA
04/25/2006

C. Alvarez Quartz School. Module 13: Work Over Operations / Section 7: Introduction to Hydraulic Fracturing
7. Introduction to Hydraulic Fracturing

Hydraulic Fracturing Treatment

Primary Purpose :
„ To increase the effective wellbore area by creating a fracture of length XL
whose conductivity is greater than that of the formation.

Dimensionless Conductivity ( Fcd ) = Kf Wf / Ke Xf

Two Methods :
„ Sand Frac
„ Acid Frac

5 PA
04/25/2006

C. Alvarez Quartz School. Module 13: Work Over Operations / Section 7: Introduction to Hydraulic Fracturing
7. Introduction to Hydraulic Fracturing

Dimensionless Fracture Conductivity

kfw
CfD = k xf
rw' / xf

where: kf = Fracture Permeability (mD)

w = Average fracture width (ft)


xf = Fracture Half-Length (ft)
k = Formation Permeability (mD)

6 PA
04/25/2006 CfD
C. Alvarez
7. Introduction to Hydraulic Fracturing

Hydraulic Fracture
Modification of reservoir flow

Linear Flow: Early times and


for infinite conductivity fractures

Bi-linear Flow: Finite conductivity


fractures

Psuedo-radial Flow: Long time


7 PA
04/25/2006

C. Alvarez
7. Introduction to Hydraulic Fracturing
Hydraulic Fracture
Acid and Propped Fracturing

open fracture fracture tends to close


during pumping once the pressure has
0.5" been
released

PROPPED FRACTURE ACID FRACTURE

Acid etches fracture


Sand/proppant used to surface
prop Formation integrity
the fracture open prevents
collapse
8 PA
04/25/2006

C. Alvarez
7. Introduction to Hydraulic Fracturing

Advantages of Hydraulic Fracturing

• Connect discontinuous hydrocarbon bearing formations


- Production from lenticular formations

• Connect naturally fissured system

• Assure production from laminated intervals

• Distribute pressure drop along the fracture length


- Hydraulic fracturing for sand control

9 PA
04/25/2006

C. Alvarez
7. Introduction to Hydraulic Fracturing
Advantages of Hydraulic Fracturing
Connecting Lenticular Reservoirs Naturally Fissured Systems

Sub - Parallel Fissures

Orthogonal Fissures

Connecting Laminated Formations


Distribution of Wellbore Drawdown

Pay stimulated by
a fracture treatment Pressure

Reduction in formation
sand production

Distance
10 PA Pay stimulated by
04/25/2006
an acid treatment
C. Alvarez
7. Introduction to Hydraulic Fracturing

Hydraulic Fracturing
Harsh Fracturing Environments
• Very high permeability ( 1-2 Darcy )
- Exceptionally high poroelastic effects

• Weak barriers to fracture height growth

• Very high pore pressure (i.e. over pressurized reservoirs)

• Formations with a high degree of natural fissures

• Proximity to oil-water contact

• Lenticular formations bounded by higher stressed formations


11 PA
04/25/2006

C. Alvarez Quartz School. Module 13: Work Over Operations / Section 7: Introduction to Hydraulic Fracturing
7. Introduction to Hydraulic Fracturing

Hydraulic Fracturing
Typical Formations

• Very tight formations => mD permeability

• Wells with significant damage

• Good producing wells (high permeability formations)

• Fracture for Sand Control

Every well should be considered for hydraulic fracturing


12 PA
04/25/2006

C. Alvarez Quartz School. Module 13: Work Over Operations / Section 7: Introduction to Hydraulic Fracturing
7. Introduction to Hydraulic Fracturing

Fractures in High Permeability Formations

1.00
• Low Permeability
xf
r'w =
Low Permeability
xf limited
2

r w' / x f
0.10

High Permeability
• High Permeability kf w limited

kf w
r' w = 0.28 0.01

k 0.1 1 10
FCD
100 1000

13 PA
04/25/2006

C. Alvarez Quartz School. Module 13: Work Over Operations / Section 7: Introduction to Hydraulic Fracturing
7. Introduction to Hydraulic Fracturing

Fractures in High Permeability Formations

kf w
r 'w = 0.28
k

• Increase in r’w => large fracture conductivity


– Increased fracture width
– Increased fracture permeability

• Fracture length not important


– Short fractures bypassing near wellbore
damage
14 PA
04/25/2006

C. Alvarez Quartz School. Module 13: Work Over Operations / Section 7: Introduction to Hydraulic Fracturing
7. Introduction to Hydraulic Fracturing

Importance of Fracture Width

• Overcome detrimental effects of propping embedment

• Reduce skin effects due to non-darcy hydrocarbon flow in


fracture (significant in gas wells)

• Reduce convergent flow skin, particularly for deviated


wellbores.

15 PA
04/25/2006

C. Alvarez Quartz School. Module 13: Work Over Operations / Section 7: Introduction to Hydraulic Fracturing
7. Introduction to Hydraulic Fracturing

Propping Embedment in High Perm

• Reduced propped width and


conductivity
– 40% reduction in width
– 1.5 - 2.0 lb/ft2 prop. conc.
loss

• Damage to proppant pack


from subsequent fines
migration

• Higher in soft formations, larger proppant sizes and increased


fluid leakoff

16 PA
04/25/2006

C. Alvarez Quartz School. Module 13: Work Over Operations / Section 7: Introduction to Hydraulic Fracturing
7. Introduction to Hydraulic Fracturing

Propping Embedment
4.00
)

3.00
2
Embedment (lb/ft

2.00

1.00
Embedment
2
at 7 lb/ft
0.00
0 300,000 600,000 900,000 1,200,000

Modulus (psi)
17 PA
04/25/2006

C. Alvarez Quartz School. Module 13: Work Over Operations / Section 7: Introduction to Hydraulic Fracturing
7. Introduction to Hydraulic Fracturing

Productivity Increase
High Permeability Low Permeability
Formations Formations
Folds of Increase, (J/Jo)

14 100%
90%
12
80%
70%
10 60% Xf
8 50% re
40%
6 30%
20%
4 10%
2

2 3 4 5 6
10 10 10 10 10
kf w 40
Relative Conductivity,
k A
18 PA
04/25/2006

C. Alvarez
7. Introduction to Hydraulic Fracturing

19 PA
04/25/2006

C. Alvarez
7. Introduction to Hydraulic Fracturing

Fracture Length
Propped Length
Effective Length

Hydraulic Length
20 PA
04/25/2006

C. Alvarez
7. Introduction to Hydraulic Fracturing
Propped Fracture Optimization

Optimize the reservoir deliverability by balancing fracture


characteristics and reservoir properties
Analyze the effect of production systems :
„ Nodal Analysis
Determine the pumping parameters :
„ Minifrac (DataFRAC*)
Tailor the fracturing fluid and proppant to the reservoir
Determine treatment size (Fluid & proppant amount)
„ Calculate XLand FCD
Calculate the benefit of the treatment => $
21 „ FracNPV
PA
04/25/2006

C. Alvarez Quartz School. Module 13: Work Over Operations / Section 7: Introduction to Hydraulic Fracturing
7. Introduction to Hydraulic Fracturing

Acid Fracture

„ Bottom hole pressure above fracturing pressure

„ Acid reacts with the formation

„ Fracture is etched

„ Formation must retain integrity without fracture collapse

22 PA
04/25/2006

C. Alvarez Quartz School. Module 13: Work Over Operations / Section 7: Introduction to Hydraulic Fracturing
7. Introduction to Hydraulic Fracturing

Hydraulic Fracturing Accomplishes:

Creates Deep Penetrating Fractures to :

„ Improve productivity
„ Interconnect formation permeability
„ Improve ultimate recovery
„ Aid in secondary recovery
„ Increase ease of injectivity

A hydraulic Fracture has to be cost effective to the operator.


23 PA
04/25/2006

C. Alvarez Quartz School. Module 13: Work Over Operations / Section 7: Introduction to Hydraulic Fracturing
7. Introduction to Hydraulic Fracturing

Fracture Penetration is influenced by:


FORMATION CHARACTERISTICS :
„ Type
„ Hardness
„ Permeability
„ Zone Height “ Presence of Barriers “
„ Drainage Radius
FRAC FLUID CHARACTERISTICS :
„ Base Fluid
„ Viscosity
„ Volume
„ Pump Rate

24 PA
„ Fluid Loss
04/25/2006

C. Alvarez Quartz School. Module 13: Work Over Operations / Section 7: Introduction to Hydraulic Fracturing
7. Introduction to Hydraulic Fracturing
Orientation of The Fracture

The fracture will extend perpendicular to the axis of the least stress.
„ X - Y - Z Coordinate :
Overburden Pressure

Favored Fracture Direction

Least Principal Stress

(i.e. Vertical Fracture)


25 PA
04/25/2006

C. Alvarez Quartz School. Module 13: Work Over Operations / Section 7: Introduction to Hydraulic Fracturing
7. Introduction to Hydraulic Fracturing
Hydraulic Fracture Fracture Orientation
Overburden Pressure

Vertical fracture plane is


perpendicular to earth’s
surface due to overburden
stress being too great to
overcome
Least Principal
Stress

Maximum Rule of Thumb


Principal Stress Overburden Pressure/Least FG < 0.8 psi/ft = Vertical Fracture
Principal Stress FG > 1.0 psi/ft = Horizontal Fracture

Intermediate
Principal Stress Horizontal fracture with a
pancake like geometry.
Usually associated with
shallow wells of less than
3,000 ft. depth
26 PA
04/25/2006

C. Alvarez
Maximum Principal Stress
7. Introduction to Hydraulic Fracturing

Decision Tree For Stimulation


Start

Production Test

K, S

Analyze
Skin
Mech Pseudo
Skin
Wellbore Zero
Skin Recommendation
Location K<20
Wellbore No
Clean Up
No Candidate Yes
Matrix for high K HCI Yes
Treatment Frac Soluble
No Acid
Be Happy
Prop Frac
Frac

Predict
Production
Do Don’t
$
27 PA
04/25/2006 End

C. Alvarez Quartz School. Module 13: Work Over Operations / Section 7: Introduction to Hydraulic Fracturing
7. Introduction to Hydraulic Fracturing

Hydraulic Fracturing Equipment

C. Alvarez
7. Introduction to Hydraulic Fracturing

Example of a “massive” (High Volume) Frac Job

29 PA
04/25/2006

C. Alvarez Quartz School. Module 13: Work Over Operations / Section 7: Introduction to Hydraulic Fracturing
7. Introduction to Hydraulic Fracturing

Example of a “massive” (High Volume) Frac Job

30 PA
04/25/2006

C. Alvarez Quartz School. Module 13: Work Over Operations / Section 7: Introduction to Hydraulic Fracturing
7. Introduction to Hydraulic Fracturing

Frac Pump

31 PA
04/25/2006

C. Alvarez Quartz School. Module 13: Work Over Operations / Section 7: Introduction to Hydraulic Fracturing
7. Introduction to Hydraulic Fracturing

Precision Continuos Mixer - PCM

Built to reduce time on location Ramp gel loadings


Reduces cost to client No disposal problems
32 PA
04/25/2006

C. Alvarez
7. Introduction to Hydraulic Fracturing

POD Phase II Blender - SBT-612

33 PA
04/25/2006

C. Alvarez Quartz School. Module 13: Work Over Operations / Section 7: Introduction to Hydraulic Fracturing
7. Introduction to Hydraulic Fracturing

High-Rate Sand Feeder - SSS-351

34 PA
04/25/2006

C. Alvarez Quartz School. Module 13: Work Over Operations / Section 7: Introduction to Hydraulic Fracturing
7. Introduction to Hydraulic Fracturing

SUS-701 Blender Sand-Hopper

35 PA
04/25/2006

C. Alvarez Quartz School. Module 13: Work Over Operations / Section 7: Introduction to Hydraulic Fracturing
7. Introduction to Hydraulic Fracturing

Monitoring and Control


JMU : SMT 502R FracCAT MV: SMT 503

FracCAT MV:
SMT 504
36 PA
04/25/2006

C. Alvarez
7. Introduction to Hydraulic Fracturing
General Field View

37 PA
04/25/2006

C. Alvarez
7. Introduction to Hydraulic Fracturing

Wellhead

Tree Saver
Remote Controlled Master Valve on
the tree
Ground Master Valve
Bleed Lines
Check Valves
Pressure Sensors
Flow Meter
Density Meter

38 PA
04/25/2006

C. Alvarez
7. Introduction to Hydraulic Fracturing

Central Manifold : Missile


High Pressure and Low Pressure
2 ea 3” High Pressure Lines, 15,000
psi WP
40 BPM
Up to 10 Pumps
4” Low Pressure, 70 psi

39 PA
04/25/2006

C. Alvarez Quartz School. Module 13: Work Over Operations / Section 7: Introduction to Hydraulic Fracturing
7. Introduction to Hydraulic Fracturing

Annulus Control

Main Valves
Bleed Lines
Pressure Sensors
Check Valves
Pop-Off Valves

Annulus 1 Annulus 2
9-5/8” Casing 7” Casing

40 PA
04/25/2006

C. Alvarez
7. Introduction to Hydraulic Fracturing
HP Pumps
fluid end 2000 hhp engine

4” LP suction

3’ HP discharge

Catfrac Main line SPF 942 “saharian’

HP line max 15000psi


LP line 70psi

Catfrac SPF 942


F-head inline fluid end
triplex 3.5’ x 8’ triplex 4.5’ x 11’
41 PA
04/25/2006

C. Alvarez Quartz School. Module 13: Work Over Operations / Section 7: Introduction to Hydraulic Fracturing
7. Introduction to Hydraulic Fracturing
POD Blender
Control
Cabin

Liquid
additive
Dry add
EB Clean
PCM
8” +4”

Discharge
manifold

Vortex

42 PA
04/25/2006

C. Alvarez Quartz School. Module 13: Work Over Operations / Section 7: Introduction to Hydraulic Fracturing
7. Introduction to Hydraulic Fracturing
Precision Control Mixer - PCM

control cabin
4 liquid add
slurry gel

KCl pump

Discharge 8”+4”

hydrostatic tank 5 mixing compartment


50 bbl residence tank
suction 2x8” 200 bbl
43 PA
04/25/2006

C. Alvarez Quartz School. Module 13: Work Over Operations / Section 7: Introduction to Hydraulic Fracturing
7. Introduction to Hydraulic Fracturing

“SandChief”, Frac Tanks, Blender


Storage

Conveyor belt

Mixing Gate
4” return
circulation
batch mixing
8 “ suction
tank manifold

4x4” to blender
44 PA
04/25/2006 8 bbl tub with
horizontal paddle
C. Alvarez Quartz School. Module 13: Work Over Operations / Section 7: Introduction to Hydraulic Fracturing
7. Introduction to Hydraulic Fracturing
Monitoring and Control VAN
FracCAT ControlRoom TCV pump Room

Data Display
Computer control Digital & graphic Remote
operator
POD Monitoring

Catfrac
remote panel

Client Witness
Client Digital & graphic and engineer
Monitoring

Well Services
SPF 942
Pump operator
remote panel

45 PA
Frac
04/25/2006
Engineer
Frac
Quartz School. Module 13: Work OverMaster
Operations / Section 7: Introduction to Hydraulic Fracturing
C. Alvarez
7. Introduction to Hydraulic Fracturing
Fracturing Equipment Layout – Massive Fracs Pumps

2" Re-circulation
Hose Tank

8" Suction
Frac Tanks Hose
High Choke 2" Bleed
off Pipe
PCM pressure 3" Pipe 2 x 1 Plug
POD II manifold valves
3-way
Chiksan
3x3
3" Pipe plug
valve 2-way Chiksan

Wellhead and
Schlumberger Mast
Valve
Bridge:
2-way & Flapper
3-way Check
Chiksan valve Pressure
4" 3 x 3 Isolation Transducers
Discharge Plug Valve In- line
Hose densitometer

8" Suction
Hose
4 “ Suction 4"Discharge
Hoses
Hose 4 pin
sensor
cable

Sand Hopper
FracCAT

125 ft 37 pin
pump cable

7 pin POD
data cable

Sensor Cable
46 PA
04/25/2006
Sand Chief 7 pin PCM
data cable
C. Alvarez

You might also like