Professional Documents
Culture Documents
IB022018EN XGIS Instalación y Comisionamiento
IB022018EN XGIS Instalación y Comisionamiento
IB022018EN XGIS Instalación y Comisionamiento
2 EATON www.eaton.com
Instructions for the installation and Instruction Booklet IB022018EN
commissioning of Power Xpert TM Effective February 2019
XGIS gas insulated switchgear
Disclaimer of warranties and limitation of liability
This instruction booklet is published solely for information purposes In no event will Eaton be responsible to the purchaser or user in
and should not be considered all-inclusive. If further information is contract, in tort (including negligence), strict liability or otherwise
required, you should consult an authorized Eaton sales representative. for any special, indirect,incidental or consequential damage or loss
The sale of the product shown in this literature is subject to the whatsoever, including but not limited to damage or loss of use of
terms and conditions outlined in appropriate Eaton selling policies equipment, plant or power system, cost of capital, loss of power,
or other contractual agreement between the parties. This literature additional expenses in the use of existing power facilities, or claims
is not intended to and does not enlarge or add to any such contract. against the purchaser or user by its customers resulting from the
The sole source governing the rights and remedies of any purchaser use of the information, recommendations and description contained
of this equipment is the contract between the purchaser and Eaton. herein.
EATON www.eaton.com 3
Instruction Booklet IB022018EN Instructions for the installation and
Effective February 2019 commissioning of Power Xpert TM
XGIS gas insulated switchgear
Contents
Description Page
Section 1: Introduction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6
1.1 Preliminary comments and safety precautions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6
1.1.1 Safety precautions. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6
1.1.2 Switchgear identification . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6
1.2 General information. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7
1.3 Power Xpert XGIS elements. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8
1.3.1 Standard features. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9
1.3.2 Ground bus . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 13
1.3.3 Bracing. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 14
1.3.4 Arc resistant features. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 14
1.3.5 Optional features. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 14
1.3.6 XGIS vertical section configurations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 18
1.4 Type XGIS gas insulated switchgear ratings (tables 2, and 3) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 21
1.5 XGIS vertical section outlines and dimensions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 23
1.5.1 1250 ampere vertical section. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 23
1.5.2 2000 ampere vertical section. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 24
1.6 SSIS conductor system . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 25
1.6.1 SSIS bus in XGIS gas insulated switchgear . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 25
1.6.2 Power cable conductors in XGIS switchgear. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 26
Section 2: Safe practices. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 28
2.1 Recommendations. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 28
Section 3: Receiving, handling and storage . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 28
3.1 General. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 28
3.2 Receiving. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 28
3.3 Handling. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 28
3.4 Unpacking . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 28
3.5 Lifting vertical sections . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 29
3.5.1 Lifting angles attachment . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 29
3.5.2 Lifting. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 29
3.6 Storage. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 29
3.7 Tools and accessories. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30
3.8 XGIS gas insulated switchgear vertical section weights . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30
Section 4: Initial inspection. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30
Section 5: Installation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 31
5.1 Qualified personnel . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 31
5.2 General field installation requirements . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 31
5.3 Installation requirements. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 31
5.4 Typical floor plan and minimum recommended clearances around the switchgear . . . . . . . . . . . . . 31
5.5 Field installation precautions. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 34
5.5.1 Bolt tightening torques . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 34
5.5.2 Handling of ssis silicone rubber insulator parts. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 34
5.6 Assembly. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 34
5.6.1 Drawings. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 34
5.6.2 Assembly instructions. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 34
5.7 Low voltage control connections. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 38
5.7.1 Auxiliary circuits available to the user . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 38
5.8 Installing SSIS bus and connectors. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 38
5.8.1 SSIS bus installation in XGIS gas insulated switchgear . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 39
5.8.2 Field installation precautions. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 40
5.9 Installing the bus and bushing. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 40
4 EATON www.eaton.com
Instructions for the installation and Instruction Booklet IB022018EN
commissioning of Power Xpert TM Effective February 2019
XGIS gas insulated switchgear
5.10 Low-voltage control cables. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 42
5.11 Installing cable adapters. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 43
5.11.1 Cable T connectors. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 44
5.11.4 Cable cleats . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 45
5.12 Installing current transformers. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 45
5.12.1 Main bus compartment CTs . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 45
5.12.2 Cable compartment CTs. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 47
5.13 Voltage transformer installation and removal. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 54
5.13.1 Main bus voltage transformers. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 54
5.13.2 Cable side voltage transformers. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 54
5.13.3 Voltage transformer installation. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 55
5.13.4 Voltage transformer removal. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 55
Section 6: Commissioning. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 56
6.1 Pre-commissioning final inspection. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 56
6.2 Commissioning procedures. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 56
6.2.1 Preparations for commissioning . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 56
6.2.2 Startup. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 56
6.2.3 Commisioning. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 56
6.3 High voltage disconnect switch test record (will be modified for XGIS). . . . . . . . . . . . . . . . . . . . . . 57
6.4 High voltage breaker test record (will be modified for XGIS) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 58
6.5 SF6 Gas tests - satisfactory results for testing SF6 gas samples . . . . . . . . . . . . . . . . . . . . . . . . . . . 59
List of tables
Description Page
Table 1. Three-position disconnect switch status display table. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 12
Table 2. Vertical section dimensions. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 21
Table 3. Electrical data . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 21
Table 4. Relevant standards. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 22
Table 5. Operating conditions. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 22
Table 6. Approximate vertical section weights (see exclusions above) . . . . . . . . . . . . . . . . . . . . . . . . . . . 30
Table 7. XGIS bolt tightening specifications . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 34
Table 8. Silicone grease application guide . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 34
Table 9. Silicone grease application guide . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 40
EATON www.eaton.com 5
Instruction Booklet IB022018EN Instructions for the installation and
Effective February 2019 commissioning of Power Xpert TM
XGIS gas insulated switchgear
Read and understand these instructions before attempting Section 1: Introduction
installation, operation, or maintenance of this equipment. This
equipment must be installed and serviced only by qualified electrical 1.1 Preliminary comments and safety precautions
personnel. Retain this document for future use. This technical document is intended to cover most aspects associ-
ated with the installation and commissioning of Power XpertTM XGIS
gas insulated switchgear. It is provided as a guide for authorized
and qualified personnel only. Please refer to the specific WARNING
messages in paragraph 1.1.2 before proceeding past Section 1. If
further information is required regarding a particular installation,
IMPROPERLY INSTALLING OR MAINTAINING THESE PRODUCTS CAN application or maintenance activity, an Eaton representative should
RESULT IN DEATH, SERIOUS PERSONAL INJURY, OR PROPERTY DAMAGE. be contacted.
READ AND UNDERSTAND THESE INSTRUCTIONS BEFORE ATTEMPTING 1.1.1 Safety precautions
ANY UNPACKING, ASSEMBLY, OPERATION OR MAINTENANCE OF THE
CIRCUIT BREAKERS. All safety codes, safety standards and/or regulations must be strictly
observed in the installation, operation and maintenance of this
INSTALLATION OR MAINTENANCE SHOULD BE ATTEMPTED ONLY device.
BY QUALIFIED PERSONNEL. THIS INSTRUCTION BOOK SHOULD NOT
BE CONSIDERED ALL INCLUSIVE REGARDING INSTALLATION OR
MAINTENANCE PROCEDURES. IF FURTHER INFORMATION IS REQUIRED,
YOU SHOULD CONTACT EATON.
6 EATON www.eaton.com
Instructions for the installation and Instruction Booklet IB022018EN
commissioning of Power Xpert TM Effective February 2019
XGIS gas insulated switchgear
1.2 General information An option of the XGIS design is available that is certified to IP4X
requirements.
The purpose for this document is to provide instructions for unpack-
ing, storage, installation, and commissioning of Power Xpert XGIS The XGIS design is not rated for outdoor service.
gas insulated switchgear (referred to as Type XGIS gas insulated
switchgear from this point forward). These switchgear vertical
sections employ state-of-the-art gas insulation, shielded solid
insulation, vacuum interrupters, and modular plug-in technologies.
Combined with laser welding technology and a helium gas leakage
testing process, this system provides high reliability and a small
installation footprint. They provide reliable control and protection for
electrical equipment and circuits, up to 38 kV.
EATON www.eaton.com 7
Instruction Booklet IB022018EN Instructions for the installation and
Effective February 2019 commissioning of Power Xpert TM
XGIS gas insulated switchgear
1.3 Power Xpert XGIS elements
Low-voltage
compartment
Three-position
disconnect switch
indicating lights
Low-voltage
panel
Meters
and Three-position
relays disconnect switch
view port
Tank pressue
gauge
VT disconnect switch
Three-position disconnect
switch operator
Three-position
disconnect switch
controls
Breaker control
switch and
indicating lights
Circuit breaker
operator
Charge spring
indicating light and
control switch
Cable terminations
8 EATON www.eaton.com
Instructions for the installation and Instruction Booklet IB022018EN
commissioning of Power Xpert TM Effective February 2019
XGIS gas insulated switchgear
1.3.1 Standard features The vacuum interrupter circuit breaker operating mechanism is
also mounted on the gas tank front panel, below the three-position
XGIS switchgear includes a three-position disconnect switch for disconnect switch’s operating mechanism. The circuit breaker mecha-
circuit isolation, and a vacuum interrupter circuit breaker. nism includes stored energy springs for breaker closing and opening.
The three-position disconnect switch and circuit breaker can each be The springs are charged either by an electric drive (normal mode)
operated electrically or manually. The circuit breaker can be charged, or using a manual charging handle mounted in the circuit breaker
closed or opened locally or remotely. The circuit breaker trip opera- operating mechanism front cover.
tion is initiated by external protective relays or other control devices. The circuit breaker operating mechanism includes mechanical indica-
The three-position disconnect switch is interlocked with the circuit tors for spring charged/discharged status and circuit breaker open/
breaker. closed status. These indicators are visible through cutouts in the
SF6 gas as an insulating medium circuit breaker mechanism front cover.
Sulfur Hexafluoride is an odorless, colorless, inert, non-toxic, non- The circuit breaker can be operated mechanically by buttons located
corrosive and non-flammable gas. It is thermally stable and must be on its front cover or electrically by pushbuttons mounted on the
heated to more than 500º Celsius (932º F) before it will decompose. vertical section door, or remotely.
The symmetry of the atoms in its molecular structure makes it The three-position disconnect switch and circuit breaker are both
extremely stable, with a very high dielectric strength. Its dielectric mechanically and electrically interlocked to prevent improper opera-
capability is approximated three times that of air at atmospheric tion during normal (electrical) and manual (mechanical) operation.
pressure. This means that equipment insulated with SF6 can be
much more compact than air-insulated equipment. Low-voltage control wiring is routed from the internal vertical section
terminal boards to an Eaton blue colored top hat, above the low-
Power Xpert XGIS vertical section characteristics voltage compartment. Control wiring from vertical section to vertical
An XGIS vertical section is divided into two functional areas: low- section in a lineup is routed through these top hats.
and medium-voltage. SF6 tank gauge
1.3.1.1 Low-voltage area The SF6 tank has a pressure gauge mounted on the tank upper
left front face, with a color-coded scale indicating safe, caution and
The XGIS vertical section front door is used to access the low-volt- danger pressure values. In addition, the gauge includes pressure
age section. This section houses low-voltage control and operating sensors with two contact outputs, for safe and low pressure levels.
mechanisms for the three-position disconnect switch and vacuum
interrupter circuit breaker.
The vertical section door has control devices mounted on it for:
• Circuit breaker open/closed switch and status indicating lights.
• Three-position disconnect switch status indicator lights and push-
buttons for three-position disconnect switch ground, open, and
close operations.
• Three-position disconnect switch (grounding function) status
indicators and pushbuttons for three-position disconnect switch
grounding open and close.
• Customer specific control devices.
• Customer specific protective device(s).
EATON www.eaton.com 9
Instruction Booklet IB022018EN Instructions for the installation and
Effective February 2019 commissioning of Power Xpert TM
XGIS gas insulated switchgear
SF6 Three-position disconnect switch position viewing port The tanks are laser-welded to be gas tight and have bushings on
their top surface and bottom front surfaces. These bushings accom-
To the right of the tank charging fitting, a viewing port is available to
modate connections for main bus and cables. The tank faces have
observe the three-position disconnect switch position. This port is
gasketed ports for three-position disconnect switch and circuit
available for mounting a camera if desired.
breaker mechanical drive mounting. If repairs are needed, a rear
access panel can be removed to access the devices inside the tank.
If repairs inside the tank are required, an Eaton service representa-
tive should be contacted.
The gas tank includes a fitting and gauge for gas pressure monitor-
ing, and another fitting for filling or evacuating the tank. Both fittings
are viewable in the low-voltage area, below the low-voltage control
DIN rails and wire channels.
A viewing port is mounted on the gas tank front face, beside the
tank pressure gauge and charging fitting, for viewing the three-
position disconnect switch position. This port can be fitted for a
Figure 5. Tank viewing port mounted camera.
The tank has an overpressure relief fitting mounted on the lower
Circuit breaker cycle counter part of the tank rear vertical face. The overpressure relief fitting will
The 1250A XGIS circuit breaker is rated for 10,000 load or no-load rupture at 2 bar absolute.
operations. The 2000A XGIS circuit breaker is rated for 2,000 load For the 2000 ampere vertical section design, a heatsink assembly
or no load operations. Each closing spring charging operation is is mounted on the rear of the tank, with fins extending out into the
recorded on the cycle counter mounted on the left side of the circuit back portion of the vertical section. This heatsink provides additional
breaker frame, and viewable through a window in the front cover. cooling for the busbar connections within the tank.
10 EATON www.eaton.com
Instructions for the installation and Instruction Booklet IB022018EN
commissioning of Power Xpert TM Effective February 2019
XGIS gas insulated switchgear
When a vacuum circuit breaker is furnished in the vertical section,
the three-position disconnect switch is mounted and connected to
the top of the circuit breaker assembly in the tank, and conductors
run from the breaker’s output terminals to the tank output bushings.
EATON www.eaton.com 11
Instruction Booklet IB022018EN Instructions for the installation and
Effective February 2019 commissioning of Power Xpert TM
XGIS gas insulated switchgear
Circuit breaker
12 EATON www.eaton.com
Instructions for the installation and Instruction Booklet IB022018EN
commissioning of Power Xpert TM Effective February 2019
XGIS gas insulated switchgear
The circuit breaker assembly consists of three vacuum interrupters,
one per phase, housed in a molded frame. Input power connections
from the three-position disconnect switch couple to top center input
terminals mounted on each vacuum interrupter frame. The breaker
outputs are bused to cable compartment bushings.
The circuit breaker vacuum interrupter poles are actuated by a
stored-energy spring system, mounted in the breaker operating
mechanism. Under normal conditions, an electric motor drive
charges the springs with close and opening energy. For manual
operation, the mechanism is charged using a lever with gear reduc-
tion. The charging lever is located on front of the circuit breaker
operating mechanism.
The circuit breaker can be electrically or manually charged, and elec-
trically or manually opened or closed.
Push buttons (I, O) provided on the circuit breaker front panel are
used to trigger mechanical opening and closing of the breaker.
Electrical charging, opening and closing can be initiated either locally
or remotely via electrical controls as required for a given application.
The molded vacuum interrupter frame is attached to its operating
mechanism. The operating mechanism is located outside the sealed
tank. The molded vacuum interrupter frame assembly is located
inside the sealed tank. The interrupter operating shafts are attached
to the operating mechanism using sealed metal bellows that permit
shaft travel without compromising the tank gas seal.
Figure 14. Vacuum interrupter bottle cutaway view.
EATON www.eaton.com 13
Instruction Booklet IB022018EN Instructions for the installation and
Effective February 2019 commissioning of Power Xpert TM
XGIS gas insulated switchgear
1.3.3 Bracing
Incoming SSIS buses are inherently braced by their mechanical
design. Output cables are clamped in place using cable cleats and
vertical section braces.
Operations
counter
Figure 15. Typical front views of XGIS vacuum circuit breaker mechanism with cover plate on and off.
Voltage transformers
Bus side voltage transformers (non-fused or fused) are mounted in
the XGIS vertical section in the voltage transformer compartment,
behind the busbar compartment, and are equipped with a front panel
accessible disconnect switch. The VT disconnect switch operator
either connects the VTs or grounds the VTs (there is no disconnect
position).
Cable side voltage transformers (non-fused or fused) can be
mounted in the XGIS vertical section in the voltage transformer
compartment, behind the busbar compartment, only when bus VTs
are not included in the same vertical section. These vertical sections
are equipped with a front panel accessible VT disconnect switch. The
VT disconnect switch operator either connects the VTs or grounds
them. If bus VTs are included in the same vertical section, then the
Figure 16. Cable cleats attached to cable compartment brackets. cable side VTs are mounted in the MV cable compartment on the
vertical section rear base if the VTs are non-fused, or outside the
1.3.4 Arc resistant features vertical section in the cable vault if the VTs are fused.
The XGIS design is arc resistant and offers designs with attachment NNote: If the system utilizes a ducted arc exhaust (required to achieve an arc
resistant rating), then a top mount VT cannot be installed in the same vertical
points for arc ducts at the sides or rear of the vertical section. If an
section to which the arc duct connects.
XGIS vertical section is configured for arc resistance, exhaust flaps
to integrate the vertical section into an arc resistant lineup prevent
the use of top-mounted voltage transformers in the vertical section
in which the arc duct attaches to the lineup.
Arc resistant lineups can be designed for arc gas exhaust from the
lineup left end, right end, or the rear of any vertical section.
14 EATON www.eaton.com
Instructions for the installation and Instruction Booklet IB022018EN
commissioning of Power Xpert TM Effective February 2019
XGIS gas insulated switchgear
Figure 19. Fused remote voltage transformer (mounted in cable Figure 21. Example input voltage transformers.
vault).
EATON www.eaton.com 15
Instruction Booklet IB022018EN Instructions for the installation and
Effective February 2019 commissioning of Power Xpert TM
XGIS gas insulated switchgear
Current transformers
Main bus CTs
Main bus CTs can be furnished on the horizontal bus in the space
above the gas tank, with the SSIS conductors passing through the
CTs before terminating at the tank input bushings. Main bus CT
dimensions will depend upon the CT ratio and design.
Main bus CTs are installed as part of the system installation process.
After the vertical sections have been put in place and attached to
their adjacent sections, SSIS bus sections and their connectors
connect to each vertical section main bus compartment bushings.
Bus bushings
Bus CTs
Cable connections
In the 1250 ampere rated XGIS vertical section, cable compart-
ment CTs can be furnished in single, double or triple transformers
per phase. The CTs mount on an output bus horizontal bushing.
Separable connectors connect cable to the bushing.
16 EATON www.eaton.com
Instructions for the installation and Instruction Booklet IB022018EN
commissioning of Power Xpert TM Effective February 2019
XGIS gas insulated switchgear
Figure 29. 1250 ampere cable compartment with three CTs per
phase.
Figure 30. 2000 ampere cable compartment with one CT for two
bushings per phase.
EATON www.eaton.com 17
Instruction Booklet IB022018EN Instructions for the installation and
Effective February 2019 commissioning of Power Xpert TM
XGIS gas insulated switchgear
Surge arresters
Surge arresters can be mounted in the cable compartment. Each
cable compartment bushing can accommodate up to three cable
connectors. When surge arresters are included, they replace one
of the power cable connectors, allowing a maximum of two power
cable connections per phase.
Figure 31. 2000 ampere cable compartment with two CTs for
two bushings per phase.
Bus connections
XGIS sections can be configured for output bus connections, so
that adjacent vertical section output bushings are directly connected
using SSIS bus. In that case, the output bushings are connected to
adapters connecting SSIS bus sections. Figure 33. Surge arrester.
Key interlocks
The XGIS design can be furnished with key interlocks.
18 EATON www.eaton.com
Instructions for the installation and Instruction Booklet IB022018EN
commissioning of Power Xpert TM Effective February 2019
XGIS gas insulated switchgear
1.3.6.1 Feeder/incoming 1.3.6.2 Bus tie
The feeder/incoming vertical section includes both the three-position The bus tie vertical section includes both the three-position discon-
disconnect switch and the vacuum interrupter circuit breaker. It nect switch and the vacuum circuit breaker. It is intended to
includes SSIS main bus and cable connections. This section can connect two separate buses. It can be furnished with a set of VTs
be furnished with fused VTs with a disconnect switch, cable CTs, with the VT disconnect switch and bus CTs.
remote-mounted fused VTs or surge arresters.
Figure 34. Feeder/incoming ANSI one-line. Figure 35. Bus tie ANSI one-line.
EATON www.eaton.com 19
Instruction Booklet IB022018EN Instructions for the installation and
Effective February 2019 commissioning of Power Xpert TM
XGIS gas insulated switchgear
1.3.6.3 Bus sectionalizer 1.3.6.4 Disconnector
The bus sectionalizer vertical section is intended to connect or The disconnector vertical section includes only the three-position
isolate buses without circuit breaker protection. It includes the three- disconnect switch. It is intended to connect or isolate direct connec-
position disconnect switch, but no circuit breaker. It can be furnished tions to the XGIS main bus. This section can be furnished with
with a set of VTs with the VT disconnect switch and bus CTs. fused VTs with a disconnect switch, cable CTs, remote-mounted
fused VTs or surge arresters.
Figure 36. Bus sectionalizer ANSI one-line. Figure 37. Disconnector ANSI one-line.
20 EATON www.eaton.com
Instructions for the installation and Instruction Booklet IB022018EN
commissioning of Power Xpert TM Effective February 2019
XGIS gas insulated switchgear
1.4 Type XGIS gas insulated switchgear ratings (tables 2, and 3)
EATON www.eaton.com 21
Instruction Booklet IB022018EN Instructions for the installation and
Effective February 2019 commissioning of Power Xpert TM
XGIS gas insulated switchgear
Table 4. Relevant standards
Relevant standards
IEC 62271-100 High-voltage switchgear and controlgear - Part 100: Alternating current circuit breakers
IEC 62271-102 High-voltage switchgear and controlgear - Part 102: Hi-voltage alternating current three-position disconnect switches and earthing switches
IEC 62271-200 High-voltage switchgear and controlgears - Part 200: AC metal-enclosed switchgear and control gear for rated voltages above 1 kV and up to and
including 52 kV
IEC 60529 Degrees of protection provided by enclosures (IP code)
IEC 62271-1 High-voltage switchgear and controlgear - Part one: Common specifications
22 EATON www.eaton.com
Instructions for the installation and Instruction Booklet IB022018EN
commissioning of Power Xpert TM Effective February 2019
XGIS gas insulated switchgear
1.5 XGIS vertical section outlines and dimensions
1.5.1 1250 ampere vertical section
EATON www.eaton.com 23
Instruction Booklet IB022018EN Instructions for the installation and
Effective February 2019 commissioning of Power Xpert TM
XGIS gas insulated switchgear
1.5.2 2000 ampere vertical section
24 EATON www.eaton.com
Instructions for the installation and Instruction Booklet IB022018EN
commissioning of Power Xpert TM Effective February 2019
XGIS gas insulated switchgear
1.6 SSIS conductor system
Solid Shielded Insulation System components provide modular
shielded busbar conductors protected by solid insulation. The system
includes shielded bus sections and coupling adapters that provide
mechanically robust installation that is impervious to environmental
conditions, and free from local electric field around the conductors.
The SSIS conductors and connecting adapters consist of three
concentric layers:
• The live conductor
• The insulating layer over the conductor, and
• The conductive shield outer layer
Figure 40 shows some example SSIS components and their
arrangement as bus sections and terminations. Bus sections start at
bus connection bushings (fitted in the tank) coupled to end or cross
adapters, extend using SSIS busbar, and terminate at bus connection
bushings connected to end or cross type adapters. Figure 43 shows
typical end and cross adapters utilized for main SSIS bus assembly.
For details, refer to the project specific drawings. Figure 41. Top view of XGIS tank showing tank bushings for
busbar connections.
The bushings are mounted on top of the gas tank and are connected
to the switching components in the tank via busbar inside the tank.
EATON www.eaton.com 25
Instruction Booklet IB022018EN Instructions for the installation and
Effective February 2019 commissioning of Power Xpert TM
XGIS gas insulated switchgear
SSIS cross adapters are used to extend the bus between the adja-
cent vertical sections.
End adapter
Bus CT
Cross adapter
The SSIS busbar end adapters, cross adapters, caps, and busbar Figure 45. Cable separable connectors in 1250 ampere cable
include a shield layer that is used to ground the exterior of the compartments.
busbar system. The ground wires must be fastened to the ground
studs on the tank. This will ensure the outer surface of the entire The installed cables are clamped in place using cable cleats mounted
busbar system is at ground potential. on the cable compartment cable brackets.
The maximum number of cable connectors that can be accommo-
dated depends on the XGIS rating. Multiple connectors per phase
are configured using tee or elbow type separable connectors as
shown in Figure 47. A surge arrester fitted behind an elbow type
connector can be used instead of a power cable when specified.
The 2000 ampere XGIS uses dual cable bushings per phase for cable
connections (see Figure 46).
The separable connector design will change depending upon the
output cable dimensions. In every case, a maximum of three output
connections per phase can be made: up to one tee connector
and two coupling connectors, or one tee connector, one coupling
connector and a surge arrester (see Figure 47).
The 2000 ampere XGIS uses dual cable bushings per phase for cable
connections.
26 EATON www.eaton.com
Instructions for the installation and Instruction Booklet IB022018EN
commissioning of Power Xpert TM Effective February 2019
XGIS gas insulated switchgear
EATON www.eaton.com 27
Instruction Booklet IB022018EN Instructions for the installation and
Effective February 2019 commissioning of Power Xpert TM
XGIS gas insulated switchgear
Section 2: Safe practices Section 3: Receiving, handling and storage
2.1 Recommendations 3.1 General
Type XGIS vacuum circuit breaker elements are equipped with high Type XGIS switchgear is subjected to complete factory production
speed operating mechanisms. They are designed with several built-in tests and inspection before being packed. XGIS vertical sections are
interlocks and safety features to provide safe and proper operating shipped in packages designed to provide maximum protection to
sequences. the equipment during shipment and storage and at the same time
to provide convenient handling. Tools, such as the T-handle tool for
manual three-position disconnect switch operation, and an Allen
wrench for attaching voltage transformers, are shipped separately.
All SF6 tanks are shipped with the gas filled at rated pressure, with
desiccant pouches inside the tank for interior moisture control. All
TO PROTECT PERSONNEL ASSOCIATED WITH INSTALLATION, OPERATION, vertical section-mounted power cable connectors are shipped with
AND MAINTENANCE OF THESE SWITCHGEAR ELEMENTS, THE FOLLOWING dust-proof caps installed.
PRACTICES MUST BE FOLLOWED:
3.2 Receiving
• Only qualified persons, as defined in the local electrical code, who If an XGIS vertical section is not to be used immediately but is to be
are familiar with the installation and maintenance of medium- placed in storage. Maximum protection can be obtained by keeping
voltage circuits and equipment, should be permitted to work on it packed as shipped.
switchgear. Upon receipt of the equipment, inspect the vertical sections for any
• Read these instructions carefully before attempting installation or signs of damage or rough handling. The vertical sections should have
commissioning of this equipment. been shipped in their upright position, as indicated on the shipping
materials.
• Do not work on a closed breaker or a breaker with closing springs
charged. The closing spring should be discharged and the main Open the vertical sections carefully to avoid any damage to the
contacts opened before working on the breaker. Failure to do so contents. Use a nail puller rather than a crow bar when required.
could result in injuries. When opening the containers, be careful to save any loose items or
hardware that may be otherwise discarded with the packing mate-
• Do not use a circuit breaker by itself as the sole means of isolat-
rial. Check the contents of each package against the packing list.
ing a high voltage circuit. Open the three-position disconnect
switch and follow good lockout and tagging rules, as well as all Examine the XGIS element for any signs of shipping damage such as
applicable codes, regulations and work rules. broken, missing or loose hardware, damaged or deformed insulation
and other components. File claims immediately with the carrier if
• XGIS switchgear employs sulfur hexafluoride (SF6) in the enclo-
damage or loss is detected and notify the nearest Eaton office.
sure tank, at slightly higher than nominal atmospheric pressure.
Special precautions must be followed if service is required on the 3.3 Handling
SF6 tank.
The XGIS vertical section may be top heavy and subject to tipping
• SF6 is heavier than air and will displace air in a confined space.
danger.
This can present a suffocation hazard.
Walking on or placing heavy objects on the vertical section top is
• Never allow only one person access to the XGIS tank to perform
prohibited.
maintenance or service work.
Depending on the shipped vertical section weight, use one of the
• Always replace the tank desiccant after performing tank
following to transport the vertical sections:
maintenance.
• Fork lift
• Once XGIS tank service is completed, personnel must clean their
hands, faces and exposed skin immediately. Tools and PPE must • Crane
also be cleaned. If using a fork lift, care must be taken to move the vertical section
• SF6 MUST NOT be discharged into the atmosphere. It should be on its pallet, with the vertical section fully supported by the fork lift
collected and may be reused only after treatment and testing by forks. Partial support of the vertical section may result in vertical
qualified experts. section tilting with risk of falling over.
Avoid the use of abrupt movements of the vertical sections, to avoid
equipment damage.
If using a crane, use a spreader bar rated for XGIS vertical section
for lifting with the side mount lifting angles.
3.4 Unpacking
Contact Eaton for more information.
28 EATON www.eaton.com
Instructions for the installation and Instruction Booklet IB022018EN
commissioning of Power Xpert TM Effective February 2019
XGIS gas insulated switchgear
3.5 Lifting vertical sections
3.5.1 Lifting angles attachment
A top lifting bracket (Figure 48 below) is available, and shall be
attached to any XGIS vertical section (Figure 49 below) to enable the
section to be lifted from the top.
The front of the bracket attaches to the rear of the LV
compartment using (5) M10-1.25 x 25 lg SHCS, M10 wide washer
(Figure 50). The rear of the bracket attaches to the rear panel of the
upper assembly using (5) M10-1.25 x 25 lg SHCS, M10 wide washer
(Figure 51).
3.5.2 Lifting
When an XGIS vertical section is ready for installation, an overhead
lifter or portable floor lifter can be used to move the vertical section
in conjunction with the Eaton top lifting bracket.
When a vertical section is to be lifted, position the lifter over the
vertical section and insert hooks into the vertical section top lifting
brackets holes. Once the lifting hooks are securely seated in the
lifting bracket holes, the vertical section can be carefully lifted and
moved. Lifting chains should each be of equal length, at least 1
meter long each.
Figure 49. Top lifting bracket. 3.6 Storage
If the XGIS vertical section is to be placed in storage, maximum
protection can be obtained by keeping it packed as shipped. Before
placing it in storage, checks should be made to make sure that the
vertical sections are free from shipping damage and is in satisfactory
operating condition.
The storage area where XGIS vertical sections are stored must be
clean, dry and well-ventilated, with an interior temperature of no less
than 23o F. (-5o C.) Check the area periodically for condensation.
Store the vertical section packages upright, and do not stack them.
Indoor storage should be in a building with sufficient heat and air
circulation to prevent condensation. If the building is not heated, the
same general rule for heat as for outdoor storage, as noted below,
should be applied.
EATON www.eaton.com 29
Instruction Booklet IB022018EN Instructions for the installation and
Effective February 2019 commissioning of Power Xpert TM
XGIS gas insulated switchgear
Outdoor storage of the switchgear element is NOT recommended. Section 4: Initial inspection
If unavoidable, the outdoor location must be well drained and
sheltered from sun, rain, snow, corrosive fumes, dirt, falling objects
and excessive moisture. Containers should be arranged to permit
free circulation of air on all sides and temporary heaters should be
used to minimize condensation. Moisture can cause rusting of metal
parts and deterioration of medium-voltage insulation. A heat level
of approximately 400 watts for each 100 cubic feet of volume is BEFORE PLACING THE XGIS SWITCHGEAR IN SERVICE, CAREFULLY
recommended with the heaters distributed uniformly throughout the FOLLOW THE INSTALLATION PROCEDURE GIVEN BELOW. NOT FOLLOWING
structure near the floor. THE PROCEDURE CAN FAIL TO UNCOVER SHIPPING DAMAGE THAT MAY
3.7 Tools and accessories RESULT IN INCORRECT UNIT OPERATION LEADING TO DEATH, BODILY
INJURY, AND EQUIPMENT DAMAGE.
The following tools are provided with the Type XGIS switchgear.
• Manual operating handle for three-position disconnect switch Before attempting to put an XGIS switchgear into service, it should
be carefully examined and operated manually and electrically. In
• SSIS accessories - cleaning materials, solvents, lubricant, etc.
addition, carefully examine the equipment for loose or obviously
• Top-mount voltage transformer installation/removal tool damaged parts. The following information is a guide for performing
recommended checks and tests.
The following tools and accessories are recommended for installa-
tion and commissioning (not provided with the XGIS switchgear). NNote: To ensure a satisfactory installation sequence and quality, the Power
Xpert XGIS switchgear vertical sections’ installation should be performed
• SF6 leak detector under the supervision of trained and qualified field engineers.
• Portable voltage transformer lifting system The vertical section circuit breaker is shipped with its contacts open
and closing springs in discharged state. The mechanical indicators on
3.8 XGIS gas insulated switchgear vertical section weights the front panel will indicate this.
The weights in Table 6 below are for vertical sections including Charge the closing springs by pumping the manual charging handle
three-position disconnect switches and circuit breakers (as appropri- up and down approximately 25 times until a crisp metallic “click”
ate), incoming bus bar, bus fused VTs and cable CTs but excluding is heard. This indicates that the closing springs are charged and is
control and protection relays, and other custom features. shown by the closing spring “charged” (yellow) indicator. Operate
the push-to-close button.
Table 6. Approximate vertical section weights (see exclusions
above) The breaker will close as shown by the breaker contacts “closed”
(red) indicator. Operate the push-to-open button. The breaker will
Vertical section Incoming/feeder Bus section Bus sectionalizer
ampere rating Lb. (kg.) Lb. (kg.) Lb. (kg.) open as shown by the breaker contacts “open” (green) indica-
1250 3262 (1483) 3223 (1465) 3003 (1365) tor. After completing this initial check, leave the closing springs
“discharged” and breaker contacts “open”.
2000 3669 (1668) 3633 (1651) 3411 (1550)
30 EATON www.eaton.com
Instructions for the installation and Instruction Booklet IB022018EN
commissioning of Power Xpert TM Effective February 2019
XGIS gas insulated switchgear
Section 5: Installation It is recommended but not necessary to finish the foundation to the
same requirements in front of the XGIS switchgear assembly in a
5.1 Qualified personnel traffic area defined by the end user. The minimum recommended
foundation and anchoring system requirements are sufficient to with-
stand the combined ensile and overturning reactive forces imposed
on the foundation at the XGIS switchgear assembly mounting points
during a seismic event.
Any deviation from these recommendations is the sole responsibility
IMPROPERLY INSTALLING OR MAINTAINING THESE PRODUCTS CAN of the end user. Consult with a licensed structural or civil engineer if
RESULT IN DEATH, SERIOUS PERSONAL INJURY, OR PROPERTY DAMAGE. some other foundation methods are to be considered.
Power and signal cable separation in the cable vault must be suffi-
READ AND UNDERSTAND THESE INSTRUCTIONS BEFORE ATTEMPTING cient to prevent induced eddy currents in power and signal cables.
ANY UNPACKING, ASSEMBLY, OPERATION OR MAINTENANCE OF THE
CIRCUIT BREAKERS. Refer to the customer drawings for installation guidance.
When XGIS switchgear is specified to have arc-resistant rating,
INSTALLATION OR MAINTENANCE SHOULD BE ATTEMPTED ONLY BY switchgear room must be equipped with an arc duct bulkhead, to
QUALIFIED PERSONNEL. THIS INSTRUCTION BOOK SHOULD NOT BE provide expanding gases with an escape path in the event of an
CONSIDERED ALL INCLUSIVE REGARDING INSTALLATION OR arcing fault.
MAINTENANCE PROCEDURES. IF FURTHER INFORMATION IS REQUIRED,
XGIS vertical sections are designed to meet IP4X standards. IP4X
YOU SHOULD CONTACT EATON.
requires that the enclosure cannot be penetrated by a solid object
1.0 mm (0.04 inches) in diameter.
5.2 General field installation requirements
All low-voltage power cables and signal wiring passing through the
XGIS vertical section installation should be completed after construc- switchgear must be gasketed and caulked to meet IP4X require-
tion of the site electrical rooms are completely finished and power is ments.
available for lighting and field installation.
The destination electrical room should be kept dry and well venti-
5.4 Typical floor plan and minimum recommended clearances
lated. Cable vaults for power and control wiring must be completed, around the switchgear
with structural support beams installed as in Figure 52 and XGIS switchgear is designed for input power cables entering from
Figure 53. the top, output power cables entering from the bottom. Cables are
Indoor operating conditions for the XGIS vertical sections must supported by cable clamps provided in the cable compartment to
conform to an ambient temperature <40o C, altitude < 1000 m prevent cable movement during an external fault. Depending upon
(consult Eaton representative for higher altitudes), with no dust, the design, there may be external voltage transformers located in
smoke or corrosive or inflammable gas or vapor, or salt (clean indus- the cable vault but connected to separable cable connectors in the
trial air). XGIS cable compartment.
Figure 52 shows an elevation view of typical vertical section cable
5.3 Installation requirements vault requirements. Refer to the project design drawings for details.
The XGIS switchgear is designed for installation in the electrical Figure 53 shows an elevation view of typical vertical section front
room over cable vaults. It is very important that the installed lineup and rear access clearance requirements.
be level and mounted on the same plane. Eaton recommends that
Refer to the project design drawings for the details of the project
the electrical room design include steel rails embedded in the vault
clearance requirements.
concrete, for mounting the XGIS switchgear.
The XGIS vertical sections must be placed so that they have
The finished foundation surface shall be flat and level within 1.6 mm
sufficient clearance for access to both front and rear of the vertical
(0.06 in) in 914 mm (36 in) in any direction, left to right, front to back,
section. Front access is required for the operation of panel-mounted
and diagonally. Alternatively, a local flatness value of 50 or higher and
local devices, or for manual operation as needed.
an accompanying value of 37 to 40 as defined in industry standard
ASTM-E1155-96 and industry standard ACI 117-90 may be used to
establish the flatness and levelness of the finished foundation.
EATON www.eaton.com 31
Instruction Booklet IB022018EN Instructions for the installation and
Effective February 2019 commissioning of Power Xpert TM
XGIS gas insulated switchgear
32 EATON www.eaton.com
Instructions for the installation and Instruction Booklet IB022018EN
commissioning of Power Xpert TM Effective February 2019
XGIS gas insulated switchgear
EATON www.eaton.com 33
Instruction Booklet IB022018EN Instructions for the installation and
Effective February 2019 commissioning of Power Xpert TM
XGIS gas insulated switchgear
5.5 Field installation precautions Table 8. Silicone grease application guide
Part Silicone grease amount
5.5.1 Bolt tightening torques
SSIS bus and adapters About 20g
Use standard bolts with a mechanical strength of 5.
SSIS bus plug About 10g
Cable tee connector About 20g
Table 7. XGIS bolt tightening specifications
Voltage transformer, voltage sensor, lightning About 10g
Recommended tightening torque in Nm(ft-lb)
arrester, test tube and cable plug
Bolts Lubricant - None
M6 10.5 (7.7)
M8 26 (19.2) Clean and dry the contact surface of the socket and the silicone
rubber part (the cable socket and bus insulator may also need clean-
M10 50 (36.9)
ing). Apply another thin layer of silicone grease.
Assemble the cleaned conductors and couplings immediately.
5.5.2 Handling of ssis silicone rubber insulator parts
5.6 Assembly
SSIS (Solid Shielded Insulation System) components are insulated
with silicone. All conductors, terminations and covering devices XGIS vertical sections are shipped individually, for assembly into
must be inspected for damage or defects prior to operation. lineups at the project site. Attaching the vertical sections together
according to the following instructions provides mechanical strength
All SSIS silicone insulator surfaces must have no and is required for the XGIS seismic rating.
• Bubbles See section 5.6.2 for detailed assembly instructions.
• Scratches
5.6.1 Drawings
• Visible damage
XGIS switchgear are furnished with project drawings specific to the
• Foreign material contaminants
project and client. Refer to the project drawings for details of the
• Evidence of wear equipment and its installation.
If any surface contamination is noticed on any SSIS component, 5.6.2 Assembly instructions
it must be cleaned. Remove any dirt, oil or grease on any silicone
insulator using a soft clean, lint-free wipe; Refer to Figure 54 for information on attachment hardware place-
ment. Following the figure is a checklist of attachment instructions
Clean silicone rubber insulators using a special wet cleaning wipe, including hardware requirements.
furnished as part of the SSIS hardware kits. Apply medium force to
clean the black area of the silicone rubber insulator connect to the
bus. Never wipe from the black area to the red insulation surface;
Use a dry, soft, clean lint-free wipe to remove excessive cleaning
solution. The solution may cause a slight expansion of the silicone
rubber, so any cleaned silicone parts must be air-dried for at least 15
minutes.
Apply silicone grease evenly to the insulator and silicone rubber part,
according to the following table.
34 EATON www.eaton.com
Instructions for the installation and Instruction Booklet IB022018EN
commissioning of Power Xpert TM Effective February 2019
XGIS gas insulated switchgear
EATON www.eaton.com 35
Instruction Booklet IB022018EN Instructions for the installation and
Effective February 2019 commissioning of Power Xpert TM
XGIS gas insulated switchgear
The following installation and attachment instructions are set up in a Main bus compartment front bracket (see Figure 54, item 2)
checklist format to facilitate the process. Checkboxes are provided to
aid in record keeping. Attach using 5 sets of M10-1.5 x 30 lg SHCS, M10 wide flat
washer, M10 split lock washer, and M10 nut.
5.6.2.1 Locate the first vertical section on its cable vault
foundation
Main bus compartment rear bracket (see Figure 54, item 3)
NNote: Vertical sections intended as end vertical sections will be shipped with Attach using 5 sets of M10-1.5 x 30 lg SHCS, M10 wide flat
end caps mounted on their intended outside walls. Refer to the project draw- washer, M10 split lock washer, and M10 nut.
ings for lineup details.
Position the vertical section on the cable vault foundation according
to the project lineup arrangement drawings. Refer to Figure 52 for VT/upper relief compartment (see Figure 54, item 4)
details on vault rail flatness and level. Attach using 5 sets of M10-1.5 x 30 lg SHCS, M10 wide flat
washer, M10 split lock washer, and M10 nut.
5.6.2.2 Bolt the vertical section to its rails
See Figure 53 and the project drawings for the details of attaching
XGIS vertical sections to the system foundation rails. Use the hard- Lower relief compartment (see Figure 54 item 5)
ware and torque specified. If the vertical section is a coupler section: Attach using 6 sets
of M10-1.5 x 30 lg SHCS, M10 wide flat washer, M10 split lock
5.6.2.3 Connect the vertical section to system ground washer, and M10 nut.
Note: in keeping with the facility’s ground system design, connect If the vertical section is a feeder section: Attach using 9 sets
the first installed vertical section’s vertical section main grounding of M10-1.5 x 30 lg SHCS, M10 wide flat washer, M10 split lock
terminal to the facility ground system. washer, and M10 nut along vertical plus one at mid-height, mid-
Although additional lineup vertical sections will be grounded to each depth.
other using interconnecting ground bus sections, it is recommended
to connect the grounding terminals of the first and the last vertical
sections’ vertical sections, as well as every two or three vertical Main bus compartment vertical joins
sections in a lineup, to system ground. Attach using 5 sets of M10-1.5 x 30 lg SHCS, M10 wide flat
washer, M10 split lock washer, M10 nut.
5.6.2.4 Position the next vertical section
Position the next vertical section on the cable vault rails and next to
the preceding section, according to the project lineup arrangement
drawings.
36 EATON www.eaton.com
Instructions for the installation and Instruction Booklet IB022018EN
commissioning of Power Xpert TM Effective February 2019
XGIS gas insulated switchgear
Vertical section rear edge bolts (see Figure 54, item 8)
Attach using 17 sets of M10-1.5 x 30 lg SHCS, M10 wide flat
washer, M10 split lock washer, and M10 nut.
EATON www.eaton.com 37
Instruction Booklet IB022018EN Instructions for the installation and
Effective February 2019 commissioning of Power Xpert TM
XGIS gas insulated switchgear
Attach at the cutout top and bottom using 4 sets of M8-1.25 x
25lg SHCS, M8 wide flat washer, and M8 split lock washer.
Figure 60. Coupler cable compartment attachments. 5.5.2.6 Obtain the next vertical section in the lineup, and
repeat from section 5.5.2.4
38 EATON www.eaton.com
Instructions for the installation and Instruction Booklet IB022018EN
commissioning of Power Xpert TM Effective February 2019
XGIS gas insulated switchgear
Figure 65. Top view of XGIS tank showing tank bushings for
busbar connections.
The bushings are mounted on top of the gas tank and are connected
via bus to the switching components in the tank.
Figure 66. Interior view of XGIS showing bus connection
bushings.
EATON www.eaton.com 39
Instruction Booklet IB022018EN Instructions for the installation and
Effective February 2019 commissioning of Power Xpert TM
XGIS gas insulated switchgear
SSIS cross adapters are used to extend the bus between the adja- Table 9. Silicone grease application guide
cent vertical sections. Part Silicone grease amount
SSIS bus and adapters About 20g
End adapter SSIS bus plug About 10g
Bus CT
• Clean and dry the contact surface of the socket and the silicone
Cross adapter rubber part. Apply another thin layer of silicone grease.
• Assemble the cleaned conductors and couplings immediately.
40 EATON www.eaton.com
Instructions for the installation and Instruction Booklet IB022018EN
commissioning of Power Xpert TM Effective February 2019
XGIS gas insulated switchgear
Apply enough NB52 grease to lubricate the clamshell conductors. Lubricate the outside of the bus connection bushing (type C or
Insert the clamshell conductor into the end or cross adapter. If F cone bushing) on the top of the tank with silicone. Lower the
assembling an end adapter, insert the round copper disk into the busbar assembly onto the bus connection bushing (type C or F cone
clamshell and push in fully. bushing), such that threaded rod protrudes through the hole in the
Apply supplied silicone grease (translucent white) evenly on the ash- copper clamshell. Add the provided flat washer and lock washer
colored cylindrical face of the insulated busbar. over the rod to the top of the clamshell. Hand thread the provided
nut onto the threaded rod. Torque the nut to 45 Nm (33.2 ft-lb) with
Insert one end of the SSIS busbar into the end or cross adapter. a calibrated torque wrench.
Blowing compressed air between the joint with a nozzle can ease
the assembly process.
Threaded rod
Nut and
washer
Clamshell
Tank bushing
cone
Repeat this process for each joint. Then screw the attached ground
wires to each joint, in a daisy chain fashion, with provided fasteners.
Tighten them to finger tightness. The assembled joint should look
like the image below for intermediate joints.
Lubricate the outside of the bus plug with silicone gel and insert the
plug into the top of the bushing adaptor. It helps to place a small
wire between the two surfaces to allow air to escape as you push
down on the plug. Push the plug down and turn it with a socket
Figure 72. SSIS busbar and bushing.
to tighten. Remove the wire if one was used to create an air gap.
Torque to 45 Nm with a calibrated torque wrench. Add the black
Lubricate the threads on the threaded rod. Insert the threaded rod insulating cap to the top of the plug. Repeat this process for each
into the bus connection bushing (type C or F cone bushing) on the joint.
top of the tank, with the socket side up, and tighten by hand. Then
torque the rod to 45 Nm with a calibrated torque wrench. NNote: When the joints are loose, they are flexible. New sections of busbar
assemblies can be added one at a time to existing sections of busbar.
EATON www.eaton.com 41
Instruction Booklet IB022018EN Instructions for the installation and
Effective February 2019 commissioning of Power Xpert TM
XGIS gas insulated switchgear
42 EATON www.eaton.com
Instructions for the installation and Instruction Booklet IB022018EN
commissioning of Power Xpert TM Effective February 2019
XGIS gas insulated switchgear
Fixed opening
e) If it is necessary to install additional wiring between any
sections in the front of a switchgear vertical section, it is neces-
sary to remove the factory installed caulk, install additional
wiring, then reapply caulk as described in paragraph f) or para-
graph g) below.
f) Fill all wiring openings through which wiring passes from
the center mounted control compartment to the upper front
compartment or to the lower front compartment (see
Figure 79). Bundle wires together on each side of the opening
with a wire tie prior to applying caulk (silicone sealant certified
to MIL -A-46106, Type I).
g) Fill all wiring openings through which wiring passes from the
center mounted low voltage compartment to medium voltage
compartments with caulk as shown in Figure 79. Bundle wires
together on each side of the opening with a wire tie prior to
applying caulk (silicone sealant certified to MIL -A-46106,
Type I).
Adjustable opening
h) If it is necessary to install additional wiring between any Figure 80. External control wiring plate.
sections in the front of a switchgear vertical section, or to install
wiring from external equipment, it is necessary to disassemble m) For bottom entry of external low voltage conductors, there
the wir-ing pass-through system, install additional wiring, then are two removable cover plates on the floor of the front of a
reassemble the wiring pass-through system as described in vertical section . For any foundation method it is the respon-
paragraph i) or paragraph k) below. sibility of the customer to provide a suitable means to seal to
prevent escape of arc products or accommodate the escape
i) Wrap gasket material 1C19549H01 at least 1½ times around the of arc products through the cutouts made in the cover plates.
wire bundle where it passes through the opening of the pass- Sub-paragraphs a and b following are suggestions for two
through system. commonly encountered foundations .
j) Slide the movable plate of the pass-through system until the 1. For switchgear installed on a concrete slab foundation,
gasket is compressed and fills the opening completely. Tighten conduits are typically installed prior to the switchgear being
hardware to fasten the plate in place. set in place . For this situation, it is recommended the
k) Place a 3/16” wide wire tie about 1/2” (12.7 mm) from the edge cover plates be cut to clear each conduit, reinstalled and
of the gasket material on each side of the opening. sealed with caulk around the perimeter of the conduit, and
around the wires or multiple conductor cables entering
Customer installed external control wiring entering the top or bottom each conduit.
of a switchgear vertical section
2. For switchgear installed on a steel floor, conduits may
l) For top entry of external low voltage conductors, there are two be installed prior to installation of the switchgear or after
removable cover plates (see Figure 80) on the top front of each switchgear is installed. In this case, it is recommended the
vertical section . same procedure be followed as described in paragraph l)
Water-tight conduit hubs or water-tight gland fittings must be for conduits, jacketed multiple conductor cables, or bundled
mounted in the cover plates to pass multi-conductor jacketed unjacketed conductors.
cables or multiple unjacketed wires ran in conduits into the
switchgear . 5.11 Installing cable adapters
If bundled unjacketed conductors are to be brought into the Cables are connected to the tank bushings using medium-voltage
front section of the switchgear, they must be brought through a separable connectors, connected to the cables.
water-tight conduit hub in a workmanship manner (protection of
insulation), then the conductors must be bundled together and The cables must be restrained to prevent movement in the event of
conduit hub filled with caulk as described for the internal wiring short circuit conditions. Cable cleats and cable compartment cable
in paragraphs f) and g) above . bracing are used to fix the cables in place.
DTS1242 and DTB1242 cable adapters are used on XGIS switchgear.
DTS1242 are used for one cable per phase. If more than one cable
per phase is required, a combination of DTS1242 and DTB1242 cable
adapters are used.
Surge arresters can also be applied to cable bushings. When surge
arresters are required, the cable bushing will accommodate a
maximum of two output cable adapters and the surge arrester.
EATON www.eaton.com 43
Instruction Booklet IB022018EN Instructions for the installation and
Effective February 2019 commissioning of Power Xpert TM
XGIS gas insulated switchgear
Safety information
The instructions in this manual are not intended as a substitute for POWER DISTRIBUTION AND TRANSMISSION EQUIPMENT MUST BE
proper training or adequate experience in the safe operation of the PROPERLY SELECTED FOR THE INTENDED APPLICATION. IT MUST BE
equipment described. Only competent technicians who are familiar INSTALLED AND SERVICED BY COMPETENT PERSONNEL WHO HAVE BEEN
with this equipment should install, operate, and service it. TRAINED AND UNDERSTAND PROPER SAFETY PROCEDURES. THESE
INSTRUCTIONS ARE WRITTEN FOR SUCH PERSONNEL AND ARE NOT A
A competent technician has these qualifications: SUBSTITUTE FOR ADEQUATE TRAINING AND EXPERIENCE IN SAFETY
• Is thoroughly familiar with these instructions. PROCEDURES. FAILURE TO PROPERLY SELECT, INSTALL OR MAINTAIN
• Is trained in industry-accepted high and low-voltage safe operating POWER DISTRIBUTION AND TRANSMISSION EQUIPMENT CAN RESULT IN
practices and procedures. DEATH, SEVERE PERSONAL INJURY, AND EQUIPMENT DAMAGE.
• Is trained and authorized to energize, de-energize, clear, and
ground power distribution equipment.
• Is trained in the care and use of protective equipment such as arc
flash clothing, safety glasses, face shield, hard hat, rubber gloves,
clampstick, hotstick, etc.
ALL ASSOCIATED APPARATUS MUST BE DE-ENERGIZED DURING ANY
Safety instructions HANDS-ON INSTALLATION OR MAINTENANCE. FAILURE TO COMPLY WILL
Following are general caution and warning statements that apply to RESULT IN DEATH, SEVERE PERSONAL INJURY AND EQUIPMENT DAMAGE.
this equipment. Additional statements, related to specific tasks and
procedures, are located throughout the manual.
44 EATON www.eaton.com
Instructions for the installation and Instruction Booklet IB022018EN
commissioning of Power Xpert TM Effective February 2019
XGIS gas insulated switchgear
5.11.4 Cable cleats
All cables terminated at the XGIS cable bushing must be secured
with cable cleats. Detailed installation instructions for cable cleats
can be found in Eaton Cooper installation manual CTCC-10.
Main bus CTs are attached to the main bus compartment top
surface using brackets and mounting hardware. Figure 86 and
Figure 87 show the details of the main bus CT mounting system.
EATON www.eaton.com 45
Instruction Booklet IB022018EN Instructions for the installation and
Effective February 2019 commissioning of Power Xpert TM
XGIS gas insulated switchgear
46 EATON www.eaton.com
Instructions for the installation and Instruction Booklet IB022018EN
commissioning of Power Xpert TM Effective February 2019
XGIS gas insulated switchgear
5.12.2 Cable compartment CTs
Cable side CTs are also held in place using mounting brackets. There
are two possible ways to connect the cable compartment output
bushings: using cable connections or using bus connections.
Figure 89. 1250 ampere XGIS single CTs (one bushing per
phase).
EATON www.eaton.com 47
Instruction Booklet IB022018EN Instructions for the installation and
Effective February 2019 commissioning of Power Xpert TM
XGIS gas insulated switchgear
Figure 93. Cable compartment single CT per phase bracket for 1250 amperes.
48 EATON www.eaton.com
Instructions for the installation and Instruction Booklet IB022018EN
commissioning of Power Xpert TM Effective February 2019
XGIS gas insulated switchgear
Figure 94. Cable compartment dual CT per phase bracket for 1250 amperes.
EATON www.eaton.com 49
Instruction Booklet IB022018EN Instructions for the installation and
Effective February 2019 commissioning of Power Xpert TM
XGIS gas insulated switchgear
Figure 95. Cable compartment triple CT per phase bracket for 1250 amperes.
50 EATON www.eaton.com
Instructions for the installation and Instruction Booklet IB022018EN
commissioning of Power Xpert TM Effective February 2019
XGIS gas insulated switchgear
Figure 96. Cable compartment single CT per phase bracket for 2000 amperes (dual bushing).
EATON www.eaton.com 51
Instruction Booklet IB022018EN Instructions for the installation and
Effective February 2019 commissioning of Power Xpert TM
XGIS gas insulated switchgear
Figure 97. Cable compartment dual CT per phase bracket for 2000 amperes (dual bushing).
52 EATON www.eaton.com
Instructions for the installation and Instruction Booklet IB022018EN
commissioning of Power Xpert TM Effective February 2019
XGIS gas insulated switchgear
Figure 98 shows the separable connectors applied to the cable
compartment cable bushing. Up to three cables per phase, or two
cables and one surge arrestor can be applied in the cable compart-
ment.
Figure 98. Cable compartment single CT per phase bracket for 2000 amperes (dual bushing).
EATON www.eaton.com 53
Instruction Booklet IB022018EN Instructions for the installation and
Effective February 2019 commissioning of Power Xpert TM
XGIS gas insulated switchgear
5.13 Voltage transformer installation and removal 5.13.2 Cable side voltage transformers
Voltage transformers can be furnished on XGIS switchgear. If they Cable side fused VTs can also be mounted behind the bus bush-
are supplied, they are field mounted after the switchgear has been ings (if bus side VTs are not furnished) and switched by the manual
installed. disconnect switch.
XGIS voltage transformers are heavy ( ~ 165 lb.) and require a If main bus VTs are furnished, unfused cable side VTs can be
special tool to install or remove them. mounted behind the cable compartment.
If main bus VTs are furnished, cable side fused VTs can also be
5.13.1 Main bus voltage transformers
mounted outside the XGIS vertical section, in the cable vault.
Fused or unfused main bus voltage transformers (if furnished) are
mounted behind the bus bushings and are switched in or out of the
power circuit by a manual disconnect switch mounted on the low-
voltage compartment back wall.
54 EATON www.eaton.com
Instructions for the installation and Instruction Booklet IB022018EN
commissioning of Power Xpert TM Effective February 2019
XGIS gas insulated switchgear
5.13.3 Voltage transformer installation
Top voltage transformer compartment mounted VTs (fused and
unfused)
• The voltage transformer should be provided with a lifting bracket
installed. The lifting bracket also serves as an installation bracket.
Do not remove this bracket.
• Remove the top cover from the VT compartment. Remove the VT
port cover plate from the top of the XGIS tank.
• Apply silicone grease to the VT port inner cone on the top of the
XGIS tank.
• Lift the VT using the lifting bracket and eye bolt and lifting device
rated for over 1000 lbs.
• Lower the VT into place.
• Using the VT installation tool, bolt the VT into place.
• Bolt the VT lifting bracket to the mounting bracket on the back
side of the VT compartment.
EATON www.eaton.com 55
Instruction Booklet IB022018EN Instructions for the installation and
Effective February 2019 commissioning of Power Xpert TM
XGIS gas insulated switchgear
Section 6: Commissioning • Perform function tests for connected protective devices according
to relevant standards.
Commissioning the XGIS system will include wire checks, power-
off sequencing checks using external control power, electrical and
• Check the overall condition of the system.
manual operation checks for the three-position disconnect switch • Locate the SF6 gas handling instructions in a prominent place in
and circuit breaker, and local and external control checks as per the the control room.
project diagrams. • Locate emergency procedures for SF6 gas leaks in a prominent
See Section 6.3 for representative test record documents address- place in the control room.
ing the three-position disconnect switch, the circuit breaker, and SF6 • Train the site operations personnel in the operation of the XGIS
gas samples taken from the XGIS tank. equipment.
• Insulation resistance (10KV) • Confirm that upstream and downstream electrical equipment has
• Field power frequency withstand test (60) been prepared for the commissioning of the XGIS switchgear.
• Contact resistance (100 amps) • Check the switchgear power and control connections, power
• SF6 gas leak check (sniffer or pressure check) supplies, external control, grounding and environment:
• Power bus
• SF6 sample (moisture and purity)
• Control wiring
• Ground continuity check to ensure switch is properly grounded
(100 amp ductor) • Auxiliary power and its polarity (as appropriate)
• Test voltage transformers (megger and ratio) • Remote control system connections and operation
• Test current transformers (ratio and polarity) • External grounding of the switchgear grounding terminals
• Equipment in switchgear
6.1 Pre-commissioning final inspection
• If the switchgear is furnished with vertical section space heaters,
Final Inspection prior to commissioning energize them for 24 hours before operation. Close the vertical
• Check that air pressure in the sealed case is within the specified section front access doors after energizing the space heaters.
range.
6.2.2 Startup
• Clean the cabinet surface and the control chamber; check coating
of the cabinet for damage; if there is any, use the right paint to • Comply with all relevant safety regulations.
touch up. • Confirm that the vertical section circuit breaker is in its open
• Replace parts removed during installation, such as the actuator position.
and the cover plate of the cable channel. • Confirm that the vertical section three-position disconnect switch
• Take out all tools and other devices that do not belong to the is in its closed position.
switchgear. • Clear the switchgear area of miscellaneous debris, work tools and
• Verify that the switchgear is in normal state. extraneous equipment.
• Verify that surrounding environment is in normal state. • Check phase sequence for all relevant power connections.
• Start the switchgear as per normal procedures; observe signals
6.2 Commissioning procedures
displayed on the three-position disconnect switch position indica-
6.2.1 Preparations for commissioning tor, the circuit breaker status indicator (and protective devices if
furnished).
Prepare for commissioning by performing the following tasks before
connecting high-voltage power: • Use the connected high voltage power supply to check the
measurements and other features.
• Connect auxiliary and control power and check the polarities as
appropriate. • Pay attention to unusual situations. Comply with all relevant safety
regulations.
• Check the effectiveness of three-position disconnect switch and
circuit breaker (if furnished) mechanical and electrical interlocks 6.2.3 Commisioning
according to the information in Section 3-2.3 of the Operation and
Maintenance Manual, IB022017EN. Contact your Eaton Engineering Systems and Services professional
to perform testing outlined in sections 6.3 through 6.5
56 EATON www.eaton.com
Instructions for the installation and Instruction Booklet IB022018EN
commissioning of Power Xpert TM Effective February 2019
XGIS gas insulated switchgear
6.3 High voltage disconnect switch test record (will be modified for XGIS)
EATON www.eaton.com 57
Instruction Booklet IB022018EN Instructions for the installation and
Effective February 2019 commissioning of Power Xpert TM
XGIS gas insulated switchgear
6.4 High voltage breaker test record (will be modified for XGIS)
58 EATON www.eaton.com
Instructions for the installation and Instruction Booklet IB022018EN
commissioning of Power Xpert TM Effective February 2019
XGIS gas insulated switchgear
6.5 SF6 Gas tests - satisfactory results for testing SF6 gas samples
EATON www.eaton.com 59
Instruction Booklet IB022018EN Instructions for the installation and
Effective February 2019 commissioning of Power Xpert TM
XGIS gas insulated switchgear
Notes:
60 EATON www.eaton.com
Instructions for the installation and Instruction Booklet IB022018EN
commissioning of Power Xpert TM Effective February 2019
XGIS gas insulated switchgear
Notes:
EATON www.eaton.com 61
Instruction Booklet IB022018EN Instructions for the installation and
Effective February 2019 commissioning of Power Xpert TM
XGIS gas insulated switchgear
Eaton
1000 Eaton Boulevard
Cleveland, OH 44122
United States
Eaton.com
© 2019 Eaton
All Rights Reserved Eaton is a registered trademark.
Printed in USA
Publication No. IB022018EN / TBG 001430 All other trademarks are property
February 2019 of their respective owners.