Tracking Progress - PD Order in LL Factory 2023
Tracking Progress - PD Order in LL Factory 2023
5165 90.07%
48 83.16%
15284 70.61%
157 44.91%
81800 14%
95500 0%
95500 0%
95500 0%
0 #DIV/0!
95500 0%
95500 0%
95500 0%
Tracking Progress Order Production of Laluad Factory
OS-049 92,700 pcs. Plan Actual onplan Delay
จำนวน หลา Month B1Jun-23 B1Jul-23 B1Aug-23 B1Sep-23 B1Oct-23
Main Process Quantity Unit Yards Date 5-10 12-17 19-24 26-1 3-8 10-15 17-22 24-29 30-5 7-12 14-19 21-26 28-2 4-9 11-16 18-23 25-30 2-7 9-14 16-21
Plan 6-Jun 22-Jul
Fabric from WH
39 Item 130445 Actual 5191 72942 2851
Plan 6-Jun 22-Jul
Accessorie from WH
283 Item Actual 183 32
Fabric put to Plan 14-Jul
produce 39 Item 130445 Actual 258 282.8
Accessorie put to Plan
produce 283 Item Actual
Plan
Cutting 92700 Pieces Actual
Plan
QT+Band Knife 92700 Pieces Actual
Plan
CTB 92700 Pieces Actual
Plan
Maker 92700 Pieces Actual
Plan
IE - Sample 0 Pieces Actual
Plan
Workload Support 92700 Pieces Actual
Plan
Sewing - Packing 92700 Pieces Actual
Plan
PPC Shipping 92700 Pieces Actual
Update 7/21/2023
B1Nov-23 Receive
23-28 30-4 6-11 13-18 20-25 Complete Balance %Receive Remark
215 68 75.97%
13-Nov
540.8 129904.2 0.41%
13-Nov
0 283 0.00%
0 92700 0%
0 92700 0%
0 92700 0%
0 92700 0%
0 0 #DIV/0!
0 92700 0%
0 92700 0%
0 92700 0%
Update 7/21/2023
Total Qty Matching R/M
Sewing Plan of OS-047 (Update after Matching Raw material in Laluad Factory) 95500 51000
51000
% Matching Balance
53% 44500
Update 7/21/2023 Total Qty
Sewing Plan of OS-049 (Update after Matching Raw material in Laluad Factory) 92700
1600
Matching R/M % Matching Balance
1600 2% 91100
Remark