Professional Documents
Culture Documents
BUSHP Civil Works BOQ
BUSHP Civil Works BOQ
COST ESTIMATE
Project: Bajhang Upper Seti Hydropower Project (216 MW) Study Level: Feasibility
Location: Bajhang
Title: Weir & Undersluice
S. No. Description of Particulars Unit Quantity Rate, Rs/unit Amount, NRS. Remarks
BUSHP
Cost Estimate
BUSHP
Cost Estimate
Dimension(m)
S. No. Description of Particulars Unit No. Length Breadth Height Quantity Rate, Rs/unit Remarks
L B H
01 Site Clearance m² 1 Area = 11742.03 11742.03
Total 11742.0
02 Excavation Works
I Loose Soil Excavation m³ 1 55.00 Area = 970.00 53350.00
II Rock Excavation m³ 1 5335.00
Total 58685.0
BUSHP
Cost Estimate
Dimension(m)
S. No. Description of Particulars Unit No. Length Breadth Height Quantity Rate, Rs/unit Remarks
L B H
d. Flood Wall (At banks)
i. Left Bank m³ 1 149.75 11.20 0.20 335.44
ii. Right Bank
Portion 1 (Side of u/s apron)
Rectangular Portion 1 m³ 1 31.97 15.00 0.20 95.91
Rectangular Portion 2 m³ 1 9.98 9.98 0.20 19.92
Wall upto the weir m³ 1 45.95 9.00 0.20 82.71
Portion 2 (upto el. 2770.5m to 2777m) m³ 1 23.08 5.00 0.20 23.08
Portion 3 (upto el. 2764m) m³ 1 45.82 5.00 0.20 45.82
Total= 1710.81
05 Gravel bed
a. For Weir
i. Pier 1 m³ 1 Area = 88.07 0.30 26.42
ii. Pier 2 m³ 1 Area = 148.23 0.30 44.47
iii. Pier 3 m³ 2 Area = 109.98 0.30 65.99
iv. Spillway
Free- flow spillway bottom m³ 1 14.00 51.43 0.30 216.01
Gated spillway m³ 2 5.00 51.43 0.30 154.29
v. Undersluice m³ 2 5.00 51.43 0.30 154.29
vi. Flood Wall at left side of undersluice m³ 1 63.79 2.00 0.30 38.27
b. For Upstream Apron
i. Along free-flow spillway m³ 1 14.00 32.10 0.30 134.82
iii. Along gated spillway m³ 1 18.51 32.10 0.30 178.25
iii. Intake part m³ 1 21.71 34.20 0.30 222.74
BUSHP
Cost Estimate
Dimension(m)
S. No. Description of Particulars Unit No. Length Breadth Height Quantity Rate, Rs/unit Remarks
L B H
Rectangular Portion 1 m³ 1 31.97 15.00 0.30 143.87
Rectangular Portion 2 m³ 1 9.98 9.98 0.30 29.88
Wall upto the weir m³ 1 0.00 9.00 0.30 0.00
Portion 2 (upto el. 2770.5m to 2777m) m³ 1 23.08 5.00 0.30 34.62
Portion 3 (upto el. 2764m) m³ 1 45.82 5.00 0.30 68.73
Total= 2429.52
a. For Weir
i Spillway
Free- flow spillway bottom m³ 1 17.00 Area = 308.29 5240.93
Pier 1 m³ 1 Area = 88.07 17.00 1497.11
Deduction for gallery m³ -1 3.00 Area = 4.82 -14.46
Deduction for drainage m³ -1 3.00 Area = 0.12 -0.36
Gated spillway m³ 1 18.00 Area = 294.00 5292.00
Beam for holding radial gate m³ 2 5.00 Area = 10.40 104.00
Pier 2 m³ 1 Area = 148.23 17.00 2519.83
Deduction for gallery m³ -1 4.80 Area = 4.82 -23.14
Deduction for drainage m³ -1 4.80 Area = 0.12 -0.58
Deduction for stoplog & radial gate groove m³ -4 0.30 0.80 16.00 -15.36
Slab between piers m³ 2 5.00 9.50 0.70 66.50
Deductions for stoplog m³ -2 5.00 1.00 0.70 -7.00
Trunnion Beam m³ 4 Area = 1.04 1.50 6.24
ii Undersluice
Pier 3 m³ 2 Area = 109.98 17.00 3739.32
Deduction for gallery m³ -2 3.00 Area = 4.82 -28.92
Deduction for drainage m³ -2 3.00 Area = 0.12 -0.72
Deduction for stoplog & radial gate groove m³ -4 0.30 0.80 16.00 -15.36
Undersluice bottom m³ 1 13.00 Area = 294.00 3822.00
Slab between piers m³ 2 5.00 9.50 0.70 66.50
Deductions for stoplog m³ -2 5.00 1.00 0.70 -7.00
Trunnion Beam m³ 4 Area = 1.04 1.50 6.24
BUSHP
Cost Estimate
Dimension(m)
S. No. Description of Particulars Unit No. Length Breadth Height Quantity Rate, Rs/unit Remarks
L B H
iii Divide wall (upstream) m³ 1 Area = 71.74 13.00 932.62
c. For Bridge
Deck slab m³ 1 48.00 8.00 0.70 268.80
Railing posts m³ 52 0.20 0.20 1.00 2.08
BUSHP
Cost Estimate
Dimension(m)
S. No. Description of Particulars Unit No. Length Breadth Height Quantity Rate, Rs/unit Remarks
L B H
Superstructure m³ 1 34.62 2.00 17.00 1177.08
Foundation m³ 1 34.62 2.00 5.00 346.20
ii. Portion 2 (upto el. 2770.5m)
Superstructure m³ 1 10.00 2.00 10.50 210.00
Foundation m³ 1 10.00 2.00 5.00 100.00
ii. Portion 3 (upto el. 2764m)
Superstructure m³ 1 40.23 1.25 11.00 553.16
Foundation m³ 1 40.23 8.00 1.75 563.22
BUSHP
Cost Estimate
Dimension(m)
S. No. Description of Particulars Unit No. Length Breadth Height Quantity Rate, Rs/unit Remarks
L B H
Rectangular portion 2 m³ 1 18.51 0.80 1.20 17.77
ii. Undersluice
Rectangular portion 1 m³ 1 21.71 35.00 0.80 607.88
Rectangular portion 2 m³ 1 21.71 0.80 1.20 20.84
Total 1164.77
08 High Strength Concrete (M60)
a. For Weir
Free- flow spillway top lining m³ 1 14.00 Area = 27.58 386.12
Gated spillway top lining m³ 2 5.00 Area = 52.10 521.00
Undersluice top lining m³ 2 5.00 Area = 52.10 521.00
b. For stilling basin
Top Lining m³ 1 48.00 33.23 0.50 797.52
Total 2225.64
BUSHP
Cost Estimate
Dimension(m)
S. No. Description of Particulars Unit No. Length Breadth Height Quantity Rate, Rs/unit Remarks
L B H
iii. Spillway
Free- flow spillway
BUSHP
Cost Estimate
Dimension(m)
S. No. Description of Particulars Unit No. Length Breadth Height Quantity Rate, Rs/unit Remarks
L B H
b. Right bank flood wall
Portion 1
Sloped portion
Foundation
Face along length m2 2 32.00 2.00 128.00
2
Faces at ends m 2 15.00 2.00 60.00
Superstructure
End faces m2 2 Area = 272.00 544.00
2
Straight side m 1 15.00 17.00 255.00
2
Sloped Side m 1 15.00 22.67 340.05
Wall upto weir
Foundation
Face along length m2 2 45.23 2.00 180.92
2
Faces at ends m 2 7.00 2.00 28.00
Superstructure
End faces m2 2 Area = 12.50 25.00
2
Straight side m 1 12.50 45.23 565.38
2
Sloped Side m 1 12.54 45.23 567.18
Portion 2
Foundation
Face along length m2 2 28.28 1.75 98.98
2
Faces at ends m 2 8.00 1.75 28.00
2
Straight face m 1 28.28 13.00 367.64
2
Sloped Face m 1 28.28 13.07 369.48
Portion 3
Foundation
Face along length m2 2 45.28 1.75 158.48
2
Faces at ends m 2 8.00 1.75 28.00
2
Straight face m 1 45.28 9.00 407.52
2
Sloped Face m 1 45.28 9.08 411.14
BUSHP
Cost Estimate
Dimension(m)
S. No. Description of Particulars Unit No. Length Breadth Height Quantity Rate, Rs/unit Remarks
L B H
c. Left bank flood wall
Foundation
Face along length m2 2 149.75 2.00 599.00
2
Faces at ends m 2 11.20 1.75 39.20
2
Straight face m 1 149.75 15.00 2246.25
2
Sloped Face m 1 149.75 15.06 2255.24
d. Upstream Apron
Spillway part
End faces
Rectangular portion m2 1 35.00 2.20 77.00
2
Trapezoidal portion m 1 Area= 6.16 6.16
2
Side faces m 2 32.47 5.00 324.70
Intake part
End face near intake gates m2 1 35.65 2.20 78.43
Side faces
Near launching apron m2 1 29.80 5.00 149.00
2
Near undersluice m 1 32.47 2.20 71.43
e. Stoplog control platform
Columns (bottom) m2 10 3.20 5.20 166.40
Slab
Bottom m2 1 42.02 3.60 151.27
2
Sides m 1 91.24 0.80 72.99
2
Deductions for Stoplog m -4 5.62 0.80 0.70 -12.59
2
Columns (top) m 10 0.30 0.30 2.80 2.52
f. Bridge
Deck
Bottom m2 1 48.00 8.00 384.00
BUSHP
Cost Estimate
Dimension(m)
S. No. Description of Particulars Unit No. Length Breadth Height Quantity Rate, Rs/unit Remarks
L B H
Sides m2 1 112.00 0.80 89.60
Railing Posts 52 1 0.80 1.00 0.80
Total 27219.02
130.60
d. Filter Layer, Gravel (20 mm down))
Stilling basin m³ 1.00 1306.00 1.00 0.20 130.60
130.60
e. Filter Layer, Coarse sand
Stilling basin m³ 1.00 1306.00 1.00 0.20 261.20
BUSHP
Cost Estimate
Dimension(m)
S. No. Description of Particulars Unit No. Length Breadth Height Quantity Rate, Rs/unit Remarks
L B H
261.20
f. Filter Fabric (Geotextile)
D/s riprap m2 1.00 1306.00 1.00 1,306.00
for flood wall
1,306.00
g. Geo-membrane
Weir up stream m2 1.00 0.00 - -
-
BUSHP
Cost Estimate
COST ESTIMATE
Project: Bajhang Upper Seti Hydropower Project (216 MW) Study Level Feasibility
Location:Bajhang
Title: Intake and Gravel trap
BUSHP
Cost Estimate
03 Rock Excavation
a. Rock excavation m3 1 5000.00
BUSHP
Cost Estimate
BUSHP
Cost Estimate
09 Form work
i. Piers m2 3 26.28 19.00 1497.96
ii. Side Walls
Left m2 1 94.70 19.00 1799.30
2
Right m 1 116.60 19.00 2215.40
iii. Intake Body
Side Faces
Upstream m2 4 6.00 12.01 288.24
BUSHP
Cost Estimate
BUSHP
Cost Estimate
11 Water bar
a. Intake rm 1 46.00 - - 46.00
46.00
12 Hydroseal
a. Intake rm 1 46.00 - - 46.00
13 Sealant 46.00
a. Intake rm 1 46.00 - - 46.00
46.00
BUSHP
Quantity Estimate
COST ESTIMATE
Project: Bajhang Upper Seti Hydropower Project Study Level Feasibility
Location: Bajhang
Title: Desander and Forebay
S. No. Description of Particulars Unit Quantity Rate, Rs/unit Amount, NRS. Remarks
BUSHP
Quantity Estimate
Dimension
S. No. Description of Particulars Unit No. Length,m Breadth,m Height,m Quantity Remarks
L B H
01 Site Clearance
Desander Basin m2 1 89.10 66.00 5880.60
Forebay area m2 1 Area= 821.17 821.17
Approach canal m2 1 15.00 7.40 111.00
6812.77
02 Excavation works
A BMS Excavation m3
207000.00
3
B Rock Excavation m
23000.00
03 Earthworks Filling and Backfilling
a General backfill (80% MDD) m3 1 6900.00
b Structural backfill(95% MDD) m3 1 6900.00
c Structural base (98% MDD) m3 1 2144.54
04 Blinding Concrete(M15)
a From transition to Forebay m3 1 91.40 67.60 0.20 1235.73
b Forebay m3 1 Area= 906.16 0.20 181.23
c Trashrack to tunnel start m3 1 8.60 7.40 0.20 12.73
Total 1429.69
BUSHP
Quantity Estimate
Dimension
S. No. Description of Particulars Unit No. Length,m Breadth,m Height,m Quantity Remarks
L B H
3
Beams between piers m 12 Area= 5.35 4.20 269.64
c. Slab between piers m3 12 4.20 5.90 0.30 89.21
Deduction for stoplog m3 -12 4.20 1.00 0.30 -15.12
c. Sloped portion
i. Triangular part
Sloped portion m3 16 Area= 40.47 1.50 971.28
Base m3 16 Area= 32.57 1.50 781.65
ii. Rectangular part m3 4 Area= 24.13 1.50 144.75
iii. Side walls m3 4 7.10 Area= 16.60 471.44
d. Divide Walls m3 3 75.00 Area= 44.06 9913.50
e. Left Side Wall m3 1 75.00 Area= 34.90 2617.50
f. Right Side Wall m3 1 75.00 Area= 34.90 2617.50
Foundation extension m3 2 77.00 1.00 0.70 107.80
g. Platform along length of desander m3 3 75.00 1.40 0.20 63.00
BUSHP
Quantity Estimate
Dimension
S. No. Description of Particulars Unit No. Length,m Breadth,m Height,m Quantity Remarks
L B H
3
Deduction for flushing gate m -4 2.50 0.80 81.00 -648.00
Blocks between piers m3 8 4.50 Area= 48.58 1748.88
Deduction for stoplog gate m3 -8 4.50 0.90 8.10 -262.44
ii. Piers (type 2: Smaller)
Superstructure m3 4 Area= 19.90 16.00 1273.60
Deduction for stoplog groove m3 -8 0.25 1.00 10.00 -20.00
ii. Piers (type 3: At ends)
Superstructure m3 2 Area= 13.90 16.00 444.80
Deduction for stoplog groove m3 -2 0.25 1.00 10.00 -5.00
l. Forebay
Plain platform m³ 1 Area= 557.31 0.70 390.12
Sloped Funnel m³ 1 Area= 97.37 0.70 68.16
Collection Portion upto trashrack m³ 1 Area= 67.02 0.70 46.91
Trashrack to gate m³ 1 5.00 8.57 0.70 30.00
BUSHP
Quantity Estimate
Dimension
S. No. Description of Particulars Unit No. Length,m Breadth,m Height,m Quantity Remarks
L B H
Forebay wall
Shallow Portion
Left bank m³ 1 49.60 0.90 9.20 410.69
Right bank m³ 1 14.20 0.90 9.20 117.58
Deeper Portion
Left bank m³ 1 18.98 Area= 16.00 303.68
Right bank m³ 1 20.43 Area= 16.00 326.88
Total 26026.30
07 Form Work
a Desander Body
i U/S of transition m2 11 4.20 8.90 411.18
ii. U/S Piers m2 11 13.17 27.00 3910.90
iii Side Walls (upto d/s pier) m2
Superstructure m2 5 82.1 32.00 13136.00
Foundation slab (Along the length of walls) m2 1 82.1 0.95 78.00
BUSHP
Quantity Estimate
Dimension
S. No. Description of Particulars Unit No. Length,m Breadth,m Height,m Quantity Remarks
L B H
2
Foundation(End faces) m 2 1 0.95 1.90
iv Sloped portion of transition m2 16 Area = 40.47 647.52
Rectangular portion of transition m2 4 11.10 1.5 66.60
v Desander sloped body m2 8 75.00 8.4 5040.00
Collection portion m2 8 75.00 1.75 1050.00
vi D/S Piers
Type 1 m2 4 Perimeter= 18.80 27.00 2030.40
Type 2 m2 3 Perimeter= 18.31 27.00 1483.11
Type3 m2 1 Perimeter= 12.37 27.00 333.99
b Stoplog control platform (upstream)
Bottom Columns m2 26 Perimeter 2.00 5.00 260.00
Top Columns m2 26 Perimeter 1.20 4.00 124.80
Slab m2 1 Perimeter 4.30 0.30 1.29
Beams (Longer) m2 2 59.50 Perimeter 1.70 202.30
Beams (Shorter) m2 13 1.5 Perimeter 1.70 33.15
BUSHP
Quantity Estimate
Dimension
S. No. Description of Particulars Unit No. Length,m Breadth,m Height,m Quantity Remarks
L B H
f Forebay
Sloped Funnel m2 1 Area 97.58 97.58
Sloped Funnel Arc m2 1 24.42 7.90 192.92
Bulk Head Outlet Structure
Sloped portion (left) m2 1 10.20 5.00 51.00
Bottom portion m2 1 7.81 5.00 39.05
Right portion m2 1 13.40 5.00 67.00
Concrete core m2 1 23.98 5.00 119.90
Forebay wall
Shallow Portion
Left bank(Along the length) m2 1 99.2 10.50 1041.60
Left bank (side faces) m2 2 Area= 10.08 20.16
Right bank(Along the length) m2 1 28.40 10.50
Right bank(Side face) 2 Area= 10.08 20.16
Deeper Portion m2
Left bank(Along the length) m2 1 37.96 17.40 660.50
Left bank (side faces) m2 2 Area= 18.00 36.00
Right bank(Along the length) m2 1 40.86 17.40 710.96
Right bank(Side face) m2 2 Area= 18.00 36.00
Foundation
Left bank Wall m2 1 68.63 Perimeter= 5.40 370.60
Right bank wall m2 1 34.68 Perimeter= 5.40 187.27
Total 34505.64
BUSHP
Quantity Estimate
Dimension
S. No. Description of Particulars Unit No. Length,m Breadth,m Height,m Quantity Remarks
L B H
BUSHP
Cost Estimate
COST ESTIMATE
Adits
SN Unit Quantity Rate Amount
1 Rock Excavation 23900 181.47 4,337,056.64
2 Adit pllug 1219.8 26,237.83 32,004,900.46
3 Excavation m3 36198.38 8,954.89 324,152,619.16
4 Fiber Shotcrete 50 mm m2 294.61 Nos. #VALUE!
100 mm m2 909.27 Nos. #VALUE!
150 mm m2 1522.32 Nos. #VALUE!
200 mm m2 296.02 #VALUE! #VALUE!
5 Rock Bolt 2.5 m m 53174.12 - -
6 Weep holes m 7122.16 - -
7 Steel ribs
ISMB 150 kg 77788.85 299.80 23,320,832.48
8 Tie bar kg 5352.82 219.67 1,175,833.87
9 Anchor bar kg 7965.51 219.67 1,749,752.79
10 Spiling m 3360.20 1,535.13 5,158,330.43
11 Concrete lining m3 -
12 Reinforcement ton -
13 Formwork m2 -
14 Backfill concrete m3 999.10 19988.41 19,970,468.04
15 Grouting kg 85477.40 60.53 5,174,305.37
16 Drilling for grouting m 9380.88 515.78 4,838,470.99
Sub-Total #VALUE!
BUSHP
Cost Estimate
Vertical Shaft
SN Unit Quantity Rate Amount
1 Excavation m3 7288.91 15,223.32 110,961,374.99
2 Fiber Shotcrete 50 mm m2 159.98 Nos. #VALUE!
100 mm m2 147.00 Nos. #VALUE!
150 mm m2 715.54 Nos. #VALUE!
200 mm m2
3 Rock Bolt 2m m
2.5 m m 25769.42 - -
4 Weep holes m 2320.20 - -
5 Wiremesh
Steel ribs ISMB 150 kg 17664.27 299.80 5,295,689.14
Tie bar kg 3425.11 219.67 752,380.42
6 Anchor bar kg 10193.78 219.67 2,239,227.44
7 Spiling m 5160.60 1,535.13 7,922,172.48
8 Invert concrete m3
9 Concrete lining m2
10 reinforcement ton
11 formwork m
12 backfill concrete m3 2830.64 19988.41 56,580,060.34
13 Grouting kg 41424.34 60.53 2,507,588.99
14 drilling for grouting m 3600.38 515.78 1,857,002.18
Sub-Total #VALUE!
Horizontal Shaft
SN Unit Quantity Rate Amount
1 Excavation m3 25749.42 8,954.89 230,583,321.95
2 Fiber Shotcrete 50 mm m2 335.92 Nos. #VALUE!
100 mm m2 432.52 Nos. #VALUE!
150 mm m2 1436.52 Nos. #VALUE!
200 mm m2
3 Rock Bolt 2m m
2.5 m m 42823.22 - -
4 Weep holes m 5697.72 - -
5 Wiremesh
6 Steel ribs ISMB 150 kg 15217.48 299.80 4,562,148.56
7 Tie bar kg 5144.86 219.67 1,130,151.03
8 Anchor bar kg 15312.08 219.67 3,363,544.73
9 Spiling m 7751.74 1,535.13 11,899,899.49
10 Invert concrete m3
11 Concrete lining m2
12 reinforc ton
13 formwork m2
14 backfill concrete m3 14856.80 19,988.41 296,963,842.04
15 Grouting kg 68838.33 60.53 4,167,072.61
16 drilling for grouting m 6764.13 515.78 3,488,803.12
Sub-Total #VALUE!
BUSHP
Cost Estimate
Surge Shaft
SN Unit Quantity Rate Amount
1 Excavation m3 5564.24 12,089.11 67,266,651.64
2 Fiber Shotcrete 50 mm m2 11.65 Nos. #VALUE!
100 mm m2 92.72 Nos. #VALUE!
150 mm m2 218.80 Nos. #VALUE!
200 mm m2
3 Rock Bolt 2m m
4m m 7948.63 - -
4 Weep holes m 314.00 - -
5 Wiremesh
6 Steel ribs ISMB 200 kg 3607.52 299.80 1,081,521.20
7 Tie bar kg 104.20 219.67 22,889.53
8 Anchor bar kg 310.12 219.67 68,123.61
9 Spiling m 157.00 1,535.13 241,014.82
10 Invert concrete m3
11 Concrete lining m2 2000.00 - -
12 reinforc ton 157.00 219,666.10 34,487,578.21
13 formwork m2 2095.17 2,500.00 5,237,912.50
14 backfill concrete m3
15 Grouting kg 12777.42 60.53 773,470.75
16 drilling for grouting m 392.50 515.78 202,443.73
Sub-Total #VALUE!
Ventilation Tunnel
SN Unit Quantity Rate Amount
1 Excavation m3 1046.60 8,954.89 9,372,146.69
2 Fiber Shotcrete 50 mm m2
100 mm m2 130.27 Nos. #VALUE!
150 mm m2
200 mm m2
3 Rock Bolt 2m m 1870.00 - -
4m m -
4 Weep holes m 330.00 - -
5 Wiremesh
6 Steel ribs ISMB 200 kg
7 Tie bar kg
8 Anchor bar kg
9 Spiling m
10 Invert concrete m3
11 Concrete lining m2
12 reinforc ton
13 formwork m2
14 backfill concrete m3
15 Grouting kg 3006.03 60.53 181,967.29
16 drilling for grouting m 412.50 515.78 212,759.34
Sub-Total #VALUE!
BUSHP
Cost Estimate
COST ESTIMATE
Project: Bajhang Upper Seti Hydropower Project (216 MW) Study Level: Feasibility
Location: Bajhang
Title: Tunnel quantity analysis
HRT
SC I II III IV V VI VII
SN I II III IV V VI VII SUM Unit
1 Excavation 25.87 25.87 25.87 25.87 25.87 25.87 25.87 m3/m 0.00 0.00 83193.70 80933.60 44971.06 18558.05 5065.45 232721.86 m3
2 Fiber Shotcrete 50 mm 0.69 0.69 0.69 0.69 0.69 m3/m 0.00 0.00 0.00 0.00 1199.46 494.98 135.10 1829.54 m2
100 mm 1.38 m3/m 0.00 0.00 4437.86 0.00 0.00 0.00 0.00 4437.86 m2
150 mm 2.05 2.05 m3/m 0.00 0.00 0.00 6413.37 3563.61 0.00 0.00 9976.98 m2
200 mm 2.72 2.72 0.00 0.00 0.00 0.00 0.00 1951.21 532.59 2483.80 m2
3 Rock Bolt 3m 3.00 19.41 26.00 m 0.00 0.00 83611.76 0.00 0.00 0.00 0.00 83611.76 m
4m 52.31 58.46 76.67 92.00 m 0.00 0.00 0.00 163643.20 101626.50 54997.45 18013.97 338281.12 m
4 Weep holes 4 4 4 4 4 4 4 rm/m 0.00 0.00 12863.35 12513.89 6953.39 2869.43 783.22 35983.28 rm
5 Steel ribs
ISMB 150 142.79 Kg/m 0.00 0.00 0.00 0.00 248212.97 0.00 0.00 248212.97 kg
ISMB 200 362.98 362.98 Kg/m 0.00 0.00 0.00 0.00 0.00 260385.67 71072.68 331458.36 kg
6 Tie bar 13.27 13.27 13.27 Kg/m 0.00 0.00 0.00 0.00 23074.96 9522.26 2599.12 35196.34 m
7 Anchor bar 19.75 19.75 19.75 Kg/m 0.00 0.00 0.00 0.00 34337.74 14170.03 3867.73 52375.51 m
8 Spiling 21.00 21.00 m/m 0.00 0.00 0.00 0.00 0.00 15064.52 4111.88 19176.40 m
9 Invert concrete 1.30 1.30 1.28 1.15 1.65 1.23 1.41 m3/m 0.00 0.00 4100.19 3589.92 2859.58 878.76 276.08 11704.54 m3
10 Concrete lining 4.04 m3/m 0.00 0.00 0.00 0.00 0.00 0.00 790.26 790.26 m3
11 Reinforcement 0.48 1.5% of RCC lining 0.00 0.00 0.00 0.00 0.00 0.00 93.05 93.05 ton
12 Formwork 12.98 m2/m 0.00 0.00 0.00 0.00 0.00 0.00 2541.54 2541.54 m2
13 Backfill concrete 1.29 1.29 1.29 1.29 5% of excavation 0.00 0.00 0.00 4046.68 2248.55 927.90 253.27 7476.41 m3
14 Grouting 4.82 31.20 41.80 84.08 93.98 123.24 147.89 kg/m 0.00 0.00 134405.91 263056.45 163364.60 88408.40 28957.45 678192.80 kg
15 Drilling for grouting 5.000 5.000 5.000 10.000 10.000 m/m 0.00 0.00 16079.19 15642.37 8691.74 7173.58 1958.04 49544.91 m
Adits Sum
Rock Excavation Rock Excavation 23900
Adit Plug Adit Plug 1219.8
SC I II III IV V VI VII
I II III IV V VI VII SUM Unit
SN Excavation 20.33 20.33 20.33 20.33 20.33 20.33 20.33 m3/m 0.00 1308.72 14907.60 11783.90 4945.16 3252.99 0.00 36198.38 m3
1 Fiber Shotcrete 50 mm 0.63 0.63 0.63 0.63 0.63 m3/m 0.00 40.56 0.00 0.00 153.24 100.81 0.00 294.61 m2
2 100 mm 1.24 m3/m 0.00 0.00 909.27 0.00 0.00 0.00 0.00 909.27 m2
150 mm 1.85 1.85 m3/m 0.00 0.00 0.00 1072.32 450.00 0.00 0.00 1522.32 m2
200 mm 1.85 2.45 0.00 0.00 0.00 0.00 0.00 296.02 0.00 296.02 m2
3 Rock Bolt 2.5 m 2.50 16.18 21.67 32.69 39.58 47.92 47.92 m 0.00 1041.34 15887.76 18949.48 9628.43 7667.12 0.00 53174.12 m
4 Weep holes 4 4 4 4 4 4 rm/m 0.00 257.50 2933.12 2318.52 972.98 640.04 0.00 7122.16 rm
5 Steel ribs 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
ISMB 150 192.90 192.90 191.65 Kg/m 0.00 0.00 0.00 0.00 46922.56 30866.29 0.00 77788.85 kg
6 Tie bar 13.27 13.27 13.27 Kg/m 0.00 0.00 0.00 0.00 3228.85 2123.98 0.00 5352.82 m
7 Anchor bar 19.75 19.75 19.75 Kg/m 0.00 0.00 0.00 0.00 4804.83 3160.68 0.00 7965.51 m
8 Spiling 21.00 21.00 Kg/m 0.00 0.00 0.00 0.00 0.00 3360.20 0.00 3360.20 m
9 Concrete lining 2.45 m3/m 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 m3
10 Reinforcement 0.04 1.5% of RCC lining 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 ton
11 Formwork 11.94 m2/m 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 ton
12 Backfill concrete 1.02 1.02 1.02 1.02 5% of excavation 0.00 0.00 0.00 589.19 247.26 162.65 0.00 999.10 m3
13 Grouting 4.02 26.00 34.83 52.55 63.63 77.03 77.03 kg/m 0.00 1673.96 25539.57 30461.28 15477.70 12324.90 0.00 85477.40 kg
14 Drilling for grouting 5.000 5.000 5.000 10.000 10.000 m3/m 0.00 0.00 3666.41 2898.16 1216.22 1600.10 0.00 9380.88 m
BUSHP
Cost Estimate
Vertical Shaft
SC I II III IV V VI VII
I II III IV V VI VII SUM
1 Excavation 12.57 12.57 12.57 12.57 12.57 12.57 12.57 m3/m 0.00 0.00 1507.92 2538.58 1482.85 1759.55 0.00 7288.91 m3
2 Fiber Shotcrete 50 mm 0.62 0.62 0.62 0.62 0.62 m3/m 0.00 0.00 0.00 0.00 73.16 86.82 0.00 159.98 m2
100 mm 1.23 m3/m 0.00 0.00 147.00 0.00 0.00 0.00 0.00 147.00 m2
150 mm 1.23 1.81 1.81 1.81 m3/m 0.00 0.00 0.00 247.47 214.06 254.01 0.00 715.54 m2
200 mm m3/m 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
3 Rock Bolt 2m kg/m 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 m
2.5 m 25 19.12 26.67 58.50 41.67 41.67 41.67 kg/m 0.00 0.00 3200.00 11818.17 4916.88 5834.38 0.00 25769.42 m
4 Weep holes 4 4 4 4 4 4 4 rm/m 0.00 0.00 480.00 808.08 472.02 560.10 0.00 2320.20 rm
5 Wiremesh 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Steel ribs ISMB 150 126.15 189.23 Kg/m 0.00 0.00 0.00 0.00 0.00 17664.27 0.00 17664.27 kg
Tie bar 13.27 13.27 13.27 Kg/m 0.00 0.00 0.00 0.00 1566.41 1858.70 0.00 3425.11 m
6 Anchor bar 39.51 39.51 39.51 Kg/m 0.00 0.00 0.00 0.00 4661.93 5531.85 0.00 10193.78 m
7 Spiling 20.00 20.00 20.00 Kg/m 0.00 0.00 0.00 0.00 2360.10 2800.50 0.00 5160.60 m
8 Invert concrete m3/m 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 m3
9 Concrete lining m3/m 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 m3
10 reinforcement 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11 formwork 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
12 backfill concrete 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2830.64
13 Grouting 40.19 30.73 42.87 94.04 66.98 66.98 66.98 kg/m 0.00 0.00 5144.00 18997.71 7903.88 9378.76 0.00 41424.34
14 drilling for grouting 5.000 5.000 5.000 10.000 10.000 m/m 0.00 0.00 600.00 1010.10 590.03 1400.25 0.00 3600.38
Horizontal Shaft
SC I II III IV V VI VII
SN I II III IV V VI VII SUM
1 Excavation 18.08 18.08 18.08 18.08 18.08 18.08 18.08 m3/m 0.00 3621.63 6852.51 8268.87 4679.18 2327.23 0.00 25749.42 m3
2 Fiber Shotcrete 50 mm 0.57 0.57 0.57 0.57 m3/m 0.00 115.00 0.00 0.00 147.54 73.38 0.00 335.92 m2
100 mm 1.14 m3/m 0.00 0.00 432.52 0.00 0.00 0.00 0.00 432.52 m2
150 mm 1.70 1.70 1.70 1.70 m3/m 0.00 0.00 0.00 777.62 440.04 218.86 0.00 1436.52 m2
200 mm 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
3 Rock Bolt 2m kg/m 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 m
2.5 m 7.50 16.18 21.67 32.69 39.58 47.92 47.92 kg/m 0.00 3240.87 8213.26 14954.28 10246.03 6168.79 0.00 42823.22 m
4 Weep holes 4.00 4.00 4.00 4.00 4.00 4.00 4.00 rm/m 0.00 801.38 1516.29 1829.70 1035.39 514.96 0.00 5697.72 rm
5 Wiremesh 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
6 Steel ribs 118.20 177.30 Kg/m 0.00 0.00 0.00 0.00 0.00 15217.48 0.00 15217.48 kg
7 Tie bar 13.27 13.27 13.27 Kg/m 0.00 0.00 0.00 0.00 3435.95 1708.90 0.00 5144.86 m
8 Anchor bar 39.51 39.51 39.51 Kg/m 0.00 0.00 0.00 0.00 10226.05 5086.02 0.00 15312.08 m
9 Spiling 20.00 20.00 20.00 Kg/m 0.00 0.00 0.00 0.00 5176.94 2574.80 0.00 7751.74 m
10 Invert concrete m3/m 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 m3
11 Concrete lining m3/m 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 m3
12 reinforc 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13 formwork 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
14 backfill concrete 0.00 0.00 0.00 0.00 0.00 0.00 0.00 14856.80
15 Grouting 12.06 26.00 34.83 52.55 63.63 77.03 77.03 kg/m 0.00 5209.69 13202.81 24039.00 16470.49 9916.33 0.00 68838.33
16 drilling for grouting 5.000 5.000 5.000 10.000 10.000 0.00 0.00 1895.37 2287.13 1294.24 1287.40 0.00 6764.13
BUSHP
Cost Estimate
Surge Shaft
SC I II III IV V VI VII
I II III IV V VI VII SUM
1 Excavation 70.88 70.88 70.88 70.88 70.88 70.88 70.88 m3/m 0.00 0.00 2225.69 2782.12 556.42 0.00 0.00 5564.24 m3
2 Fiber Shotcrete 50 mm 1.48 1.48 1.48 1.48 1.48 m3/m 0.00 0.00 0.00 0.00 11.65 0.00 0.00 11.65 m2
100 mm 2.95 m3/m 0.00 0.00 92.72 0.00 0.00 0.00 0.00 92.72 m2
150 mm 4.41 5.84 5.84 5.84 m3/m 0.00 0.00 0.00 172.94 45.87 0.00 0.00 218.80 m2
200 mm 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
3 Rock Bolt 2m kg/m 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 m
4m 4.00 52.00 80.00 106.67 159.23 187.50 187.50 kg/m 0.00 0.00 2512.00 4186.67 1249.96 0.00 0.00 7948.63 m
4 Weep holes 4.00 4.00 4.00 4.00 4.00 4.00 4.00 rm/m 0.00 0.00 125.60 157.00 31.40 0.00 0.00 314.00 rm
5 Wiremesh 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
6 Steel ribs 200 459.56 459.56 459.56 Kg/m 0.00 0.00 0.00 0.00 3607.52 0.00 0.00 3607.52 kg
7 Tie bar 13.27 13.27 13.27 Kg/m 0.00 0.00 0.00 0.00 104.20 0.00 0.00 104.20 kg
8 Anchor bar 39.51 39.51 39.51 Kg/m 0.00 0.00 0.00 0.00 310.12 0.00 0.00 310.12 kg
9 Spiling 20.00 20.00 20.00 m/m 0.00 0.00 0.00 0.00 157.00 0.00 0.00 157.00 m
10 Invert concrete m3/m 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 m3
11 Concrete lining m3/m 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 m3
12 reinforc 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13 formwork 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
14 backfill concrete 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15 Grouting 6.43 83.59 128.60 171.47 255.96 301.41 301.41 kg/m 0.00 0.00 4038.04 6730.07 2009.31 0.00 0.00 12777.42
16 drilling for grouting 5.000 5.000 5.000 10.000 10.000 0.00 0.00 157.00 196.25 39.25 0.00 0.00 392.50
Ventilation Tunnel
SC I II III IV V VI VII
I II III IV V VI VII SUM
1 Excavation 12.69 m3/m 0.00 0.00 0.00 1046.60 0.00 0.00 0.00 1046.60 m3
2 Fiber Shotcrete 50 mm m3/m 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 m2
100 mm 1.58 m3/m 0.00 0.00 0.00 130.27 0.00 0.00 0.00 130.27 m2
150 mm m3/m 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 m2
200 mm 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
3 Rock Bolt 2m 22.67 kg/m 0.00 0.00 0.00 1870.00 0.00 0.00 0.00 1870.00 m
4m kg/m 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 m
4 Weep holes 4.00 rm/m 0.00 0.00 0.00 330.00 0.00 0.00 0.00 330.00 rm
5 Wiremesh 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
6 Steel ribs 200 Kg/m 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 kg
7 Tie bar Kg/m 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 m
8 Anchor bar Kg/m 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 m
9 Spiling Kg/m 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 m
10 Invert concrete m3/m 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 m3
11 Concrete lining m3/m 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 m3
12 reinforc 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13 formwork 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
14 backfill concrete 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15 Grouting 36.44 kg/m 0.00 0.00 0.00 3006.03 0.00 0.00 0.00 3006.03
16 drilling for grouting 5.000 0.00 0.00 0.00 412.50 0.00 0.00 0.00 412.50
BUSHP
Cost Estimate
COST ESTIMATE
Project: Bajhang Upper Seti Hydropower Project (216 MW) Study Level: Feasibility
Location: Bajhang
Title: Tunnel
HRT1 Sum
Type 261.97 1000 852.61 1430.16 3092.13 705.17 979.02 674.76 8995.82 Type i ii iii iv v vi vii
i 0 Length 0.00 0.00 3215.84 3128.47 1738.35 717.36 195.804
ii 0
iii 45% 65% 55% 45% 40% 3215.837
iv 30% 35% 40% 45% 40% 20% 50% 3128.473
v 25% 45% 15% 45% 45% 10% 1738.348
vi 15% 35% 35% 717.358
vii 20% 195.804
8995.82
Horizont Horizontal
Horizontal Horizontal
al Shaft Shaft (Ch.
Shaft (Ch. Shaft (Ch.
Type (Ch.9+23 10+250 to Sum
9+500 to 9+704.51
3.84 to 11+054.11
9+704.51) to 10+250)
9+500) )
BUSHP
Cost estimate
COST ESTIMATE
Project: Bajhang Upper Seti Hydropower Project Study Level Feasibility
Location: Bajhang
Title: Powerhouse, Protection and Switchyard
BUSHP
Cost estimate
Dimension
Length, Breadth, Height, m
S. No. Description of Particulars Unit No. Quantity Remarks
m m
L B H
01 Site Clearance and Preparation m2 1 250.00 50.00 12500.00
12500.00
02 Excavation works
a. Boulder mix soil Excavation powerhouse m3 1 110.00 105.00 11550.00
Flood wall m3 1 250.00 72.00 18000.00
Tailrace m3 1 100.00 63.00 6300.00
28680.00
03 Rock Excavation works
a. Excavation for Powerhouse area m3 1 7170.00
7170.00
04 Backfilling
a. Powerhouse and area m3 1 110.00 94.00 10340.00
flood wall m3 1 250.00 41.00 10250.00
embankment m3 1 110.00 62.00 6820.00
27410.00
05 Concrete Works (M15)
Blinding concrete m3 1 79.00 24.00 0.150 284.40
284.40
06 Plain concrete on RCC work (M30)
Raft m3 1 79.00 24.00 2.00 3792.00
Side wall length m3 2 74.25 0.75 12.50 1392.19
Side wall breadth m3 2 19.25 0.75 12.50 360.94
Slab turbine floor m3 1 75.00 20.00 1.00 1500.00
Slab Intermdeiate floor m3 1 75.00 19.00 0.80 1140.00
Slab machine floor m3 1 75.00 19.00 0.60 855.00
Column m3 32 1.50 1.50 28.50 2052.00
Normal Beam m3 4 187.00 0.50 0.80 299.20
BUSHP
Cost estimate
Dimension
Length, Breadth, Height, m
S. No. Description of Particulars Unit No. Quantity Remarks
m m
L B H
3
Crane beam m 2 75.75 2.00 2.00 606.00
BUSHP
Cost estimate
Dimension
Length, Breadth, Height, m
S. No. Description of Particulars Unit No. Quantity Remarks
m m
L B H
09 Form work
Powerhouse
Raft m2 1 206.00 2.00 412.00
Side wall length m2 4 74.25 12.50 3712.50
Side wall breadth m2 4 19.25 12.50 962.50
Slab turbine floor m2 1 75.00 20.00 1500.00
Slab Intermdeiate floor m2 1 75.00 20.00 1500.00
Slab machine floor m2 1 75.00 20.00 1500.00
Column m2 32 6.00 28.50 5472.00
Normal Beam m2 4 187.00 1.10 822.80
Crane beam m2 2 75.75 3.00 454.50
Flood wall
Footing m2 2 250.00 2.00 1000.00
Wall vetical m2 1 250.00 12.00 3000.00
Wall slanting m2 1 250.00 12.10 3025.00
Tailrace
Wall m2 4 5.20 4.20 87.36
Slab m2 1 4.00 3.00 12.00
23460.66
BUSHP
Cost estimate
Dimension
Length, Breadth, Height, m
S. No. Description of Particulars Unit No. Quantity Remarks
m m
L B H
2576.00
14 Steel used in roof truss @35kg per sq.m ton 1 35.00 75.00 91.88
BUSHP