PROJECT TITLE: BHOLARI RESIDENTIAL AREA CONSTRUCTION (BRAC-05)

Daily Progress Report


Engineers & Contractors
Daily Manpower, Equipment and Progress Report DATE: 01-11-18

EQUIPMENTS /
MANPOWER (UIA) PROGRESS
PLANT OPERATIONAL (UIA)
Work in Progress
Designation Nos. Designation Nos. Description Nos. Description Nos. Sr Type of Works Qty Unit Executed
Progress in %
Office Staff Skilled Staff Hand Roller 3 TM TKF-138 1
JCO`s Quarters #1, 48/58 short
Project Manager 1 Skilled Labour Plate Compactor 2 Tractor Belarus T-2781 1 1 In Progress 83%
column poured
Quantity Surveyor 1 Semi Skilled Roller Compactor 3 Bowzer Tank 1
Accountant 1 Foreman 1 Steel Form Work (SFT) 7774 Tractor Trolly Two Wheels 1
JCO`s Quarters #2, 48/58 short column
AutoCAD Operator Molvi 1 Scaffolding Pipe (RFT) 11380 Tractor Trolly Four Wheels 3 2 In Progress 83%
poured
Admin Assistant 1 Total: 2 Scaffolding Joint 9270 Low Bed Trailer 1
Material Engineer 1 Un-Skilled Staff Wooden Runner 2832 Electrical Welding Plant 1
JCO`s Quarters #3 Short Columns
Lab Helper 1 Cooks 2 Vibrators Shaft 6 Ply Cutter Machine 1 3 In Progress 75%
Starter
Office Boy 1 Watchman & Guards 2 Tower Light 1 Water Pump 4
Purchase Officer 1 Trip Counter 1 Level Equipment 3 Power Generator 165kva 1
Store Keeper 1 Unskilled Labour 1 Total Station 2 Power Generator 60kva 1 4 Air Men Quarters # 1 Pouring of Raft. Executed 100%
Block Making Machine 4 Power Generator 11kva 1
Diesel Tank with Dispensor 1 Power Generator 10kva 1
Total: 9 Total: 6 Bar Bending Machine 32mm 1 Office Container 5
5 Air Men Quarters # 2 Pouring of Raft. Executed 100%
Site Staff Sub-Contractor Staff (1) (UIC) Bar Cutting Machine 1
Container For Cement 1
Bags
Site Engineer 1 Site Incharge 1 Roller Compactor 3 Concrete Pump (Schwing) 1
Construction Manager 1 Site Supervisor 1 Batching Plant with Cylo 1 Crane JS-4894 25Tons 1 6 Air Men Quarters # 3 Pouring of Raft. Executed 100%
Site Supervisor 1 Site Engineer 1 Power Generator 350 KVA 1 Trawlar JT-9003 1
Chief Surveyor 1 Shuttring Carpenter helper 2 Power Generator 42 KVA 1 Shehzor CS-2661 1
Air Men Quarters # 4 Steel Fixing &
Sr Surveyor 1 Shuttring Carpenter 3 Power Generator 5 KVA 1 Suzuki Hi-Roof 2 7
Formwork For Raft.
Executed 100%
Surveyor 4 Steel Fixer 15 Power Generator 6.5 KVA 1 Chiller Plant 2
Astt. Surveyors 1 Steel Fixer Helper 3 Power Generator 3.2 KVA 2 Complete Lab Equipments
Follower's Quarters # 1 Dressing &
Surveyor Helpers 5 Labour 6 Power Generator 3 KVA 2 Loader 950E+950B 2 8
Compaction.
In Progress 70%
Electricians 1 Mason 2 Power Generator 1 KVA 1
Foreman 1 Vibrator Engine 3
Follower's Quarters # 2 Dressing &
Total: 16 S/Folder 4 Trolley 15 9 Executed 100%
Compaction
Mechanical Staff Total: 39 Grinder 2
Batching Plant Fitter 1 Sub-Contractor Staff (2) (pak-Engg.) Drilling Tools 2
Follower's Quarters # 3
Batching Plant Operator 1 Site Incharge 1 Mixer Machine 4 10 Executed 100%
Lean Concrete.
Batching Plant Helper 1 Site Supervisor 1 Welding Generator 3
Batching Plant Electrician 1 C.M 1 Tandom Roller 3
SNCO MESS ; Concrete of Combined
Mechanic 1 Shuttring Carpenter 4 Bike 6 11 270 Cu.M. In Progress 75%
Footings
Mechanic Helper 2 Steel Fixer 15 W/Bouzer 2
Welder 1 Steel Fixer Helper 9 Nissan HC-083 1
SNCO MESS ; Steel Fixing for
TM Driver 2 Labour 10 Loader ZL509N 1 12 Executed 100%
Combined Footings
Tractor Driver 2 Mason 4 Excavator 2
Electricians 1 Foreman 2 Dumper 2 13 48-BOQ's Excavation for Raft Executed 100%

S/Folder 4 Tractor T-5768 1


48 - BOQ's Excavation for Footings
14 In Progress 50%
Total: 13 Total: 51 Potohar E-0868 1 (Depth Portions) in Raft Foundation

_______________________________ ______________________________
Planning Engineer Project Manager
PROJECT TITLE: UPGRADATION OF BHOLARI DRAINAGE SYSTEM

Engineers & Contractors

Daily Progress Report


Daily Manpower, Equipment and Progress Report DATE: 01-11-18
EQUIPMENTS /
MANPOWER (UIA)
PLANT OPERATIONAL (UIA)
Designation Nos. Designation Nos. Description Nos.
Office Staff Skilled Staff Baby Hand Roller 5
Project Manager 1 Skilled Labour 0 Plate Compactor 4
Quantity Surveyor 1 Mason 1 Steel Form Work (SFT) 6654
Planning Engineer 1 Foreman 2 Scaffolding Pipe (RFT) 17606
Accountant 1 Molvi 1 Scaffolding Joint (No) 6380
AutoCAD Operator 1 Wooden Runner 2316
Computer Operator 1 Total: 4 Vibrators Shaft 4
Admin Assistant 1 Un-Skilled Staff Tower Light 2
Material Engineer 1 Cooks 3 Level Equipment 7
Lab Assistant 1 Watchman & Guards 2 Total Station 4
Lab Helper 1 Trip Counter 1 Diesel Tank with Dispensor 1
Office Boy 1 Unskilled Labour 0 Bar Bending Machine 32mm 1
Purchase Officer 1 Carpenter 3 Bar Cutting Machine 1
Store Keeper 1 S-Folder+Helper 4 Batching Plant with Cylo 1+3
Total: 13 Total: 13 Power Generator 180 KVA 1

Site Staff Sub-Contractor Staff (Drain) Power Generator 3 KVA 4

Site Engineer 3 Foreman 5 Vibrator Engine 4


Construction Manager 0 Steel Fixer Wheel Barrow 5
Site Supervisor 3 Scaffolder 5 Grinder 2
Chief Surveyor 1 Shuttering Carpenter 5 Drilling Tools 2
Sr Surveyor 1 Mason 14 Mixer Machine 4
Surveyor 6 Unskilled Labour 30 Welding Generator 1
Astt. Surveyors 1 Skilled Labour 20 Bike 6
Surveyor Helpers 14 W/Bouzer 2
Electricians 1 Total: 79 Nissan HC-083 (single cabin) 1
Sub-Contractor Staff
Tandom Rollar 0
(Culverts)
Foreman 2 Tractor Belarus T-2781+5768 1
Steel Fixer 3 Bowzer Tank (Tractor Type) 1
Total: 30 Scaffolder 0 Tractor Trolly Two Wheels 2
Mechanical Staff Shuttering Carpenter 0 Tractor Trolly Four Wheels 1
Batching Plant Fitter 1 Mason 0 Electrical Welding Plant 1
Batching Plant Operator 1 Unskilled Labour 7 Ply Cutter Machine 1
Batching Plant Helper 1 Water Pump 1
Batching Plant Electrician 1 Loader ZL509N 1
Mechanic 1 Excavator 3
Mechanic Helper 2 Dumper 3
Welder 1 Potohar E-0868 1
TM Driver 2 Jack Hammer 1
Tractor Driver 2 Transit Mixer 4

Total: 12 Total: 12

_______________________________ ___________________________
Planning Engineer Project Manager
Usmani International Associates
Pakistan Air Force (Pvt.) Ltd.
Daily Man Power & Machinery Report
Date: 03-11-2018
Indirect Man Power Direct Man Power Machinery & vehicle
Project Manager 1 Office Boy 1 Baby Hand Roller 5
Quantity Surveyor 1 Cooks 2 Plate Compactor 4
Planning Engineer 1 Watchman & Guards 2 Steel Form Work (SFT) 6654
Construction Manager 1 Molvi 1 Scaffolding Pipe (RFT) 17606
Accountant 1 Cleaner 1 Scaffolding Joint (No) 6380
AutoCAD Operator 1 Electricians 1 Wooden Runner 2316
Computer Operator 1 Batching Plant Fitter 1 Vibrators Shaft 4
Admin Assistant 1 Batching Plant Operator 1 Tower Light 2
Material Engineer 1 Chiller Operator 1 Level Equipment 7
Lab Assistant 1 Batching Plant Helper 1 Total Station 4
Lab Helper 2 Batching Plant Electrician 1 Diesel Tank with Dispensor 1
Purchase Officer 1 Mechanic 2 Bar Bending Machine 32mm 1
Store Keeper 2 Mechanic Helper 2 Bar Cutting Machine 1
Store Helper 2 Welder 1 Batching Plant with Cylo 1+2
Site Engineer 4 TM Driver 5 Power Generator 180 KVA 1
Site Supervisor 3 TM Helper 4 Power Generator 3 KVA 4
Chief Surveyor 1 Tractor Driver 2 Vibrator Engine 4
Sr Surveyor 1 Foreman 8 Wheel Barrow 5
Surveyor 6 Shuttering Carpenter 8 Grinder 2
Astt. Surveyors 1 Shuttering Helper 4 Drilling Tools 2
Surveyor Helpers 14 Scaffolder 3 Mixer Machine 4
Mason 13 Welding Generator 1
Unskilled Labour 52 Bike 6
Steel Fixer 3 W/Bouzer 2
Nissan HC-083 (single cabin) 1
Tandom Machine 0
Tractor Belarus T-2781 1
Bowzer Tank (Tractor Type) 1
Tractor Trolly Two Wheels 2
Tractor Trolly Four Wheels 1
Electrical Welding Plant 1
Ply Cutter Machine 1
Water Pump 1
Loader ZL509N 1
Excavator 3
Dumper 3
Potohar E-0868 1
Jack Hammer 1
Transit Mixer 4
Total 47 Total 120 Total
Submitted By (Contractor) Submitted By (Consultant)
Name: Name:
Signature: Signature:
PAKISTAN AIR FORCE
UPGRADATION OF BHOLARI DRAINAGE SYSTEM (PACKAGE: UBDS)
PROGRESS REPORT DATE: UPTO 01-11-2018
TOTAL LENGTH WORK WORK
(Mtr) DONE LENGTH (Mtr) DONE % AGE RESIDENTIAL AREA TECHNICAL AREA

Sr. #ACTIVITY / DRAIN NO. D-1 D-1.1 D-2 D-2.1 D-2.2 D-3 D-3.1 D-3.2 D-1 D-1.2 D-2 D-4 D-4.1 D-5 D-5.1
Residential Technical Residential Technical Residential Technical
Area Area Area Area Area Area 2250 505 1970 1505 1505 6270 467 566 5500 391 3025 2294 1140 3260 1000
(Mtr) (Mtr) (Mtr) (Mtr) (Mtr) (Mtr) (Mtr) (Mtr) (Mtr) (Mtr) (Mtr) (Mtr) (Mtr) (Mtr) (Mtr)

1 SURVEY 15028 16610 Err:509 #REF! Err:509 #REF! 0 0 1926 Err:509 Err:509 #REF! 1700 #REF! #REF! #REF!

2 EXCAVATION 15028 16610 Err:509 #REF! Err:509 #REF! 1100 980 1926 Err:509 Err:509 1665 #REF! #REF!

LEVELING /
3 15028 16610 Err:509 #REF! Err:509 #REF! 980 1926 Err:509 Err:508 1500 #REF! #REF!
COMPACTION

4 CONCRETE IN RIBS 15028 16610 Err:509 #REF! Err:509 #REF! 0 0 Err:509 Err:509 #REF! #REF!

5 LEAN PLASTERING 15028 16610 Err:508 #REF! Err:508 #REF! Err:508 1700 Err:508 Err:508 950.5 #REF!

6 CONCRETE IN BED 15028 16610 Err:509 #REF! Err:509 #REF! 0 0 Err:509 Err:508 #REF! #REF!

AVERAGE WORK DONE % AGE Err:509 #REF!


PLANNED % AGE 67.08%

Issues/ Bottlenecks
1
Water Pipeline & Street Light Poles lies on Earthen Slope of dain
D-5 PCC part from (KM 2+288 to 3+250) that Issue submitted to RE
(Bholari) vide Letter no. UIA/UBDS/PM/2018/38 on Dated: November
2nd,2018
EXTERNAL DEVELOPMENT WORKS
Monthly Progress Report
From 01-04-2021 Upto 03-05-2021

Chainage Total Present Previous Cumulative Chainage Total Present Previous Cumulative Qty
Qty Qty Qty
Sr. No. Type Of Work Qty Executed Executed Executed
Sr. No. Type Of Work Qty Qty Executed Qty Executed Executed
From To (RFT) From To (RFT) (RFT) (RFT) (RFT)
(RFT) (RFT) (RFT)

ROAD NAME: SAGAR AVENUE ( LENGTH = 1128 RFT ) ROAD NAME: SAGAR ROAD ( LENGTH = 998 RFT )

1 C & G AND N.G.C. 0+000 TO 1+128 1128 1100 0 1100 1 C & G AND N.G.C. 0+000 TO 1+128 998 980 0 980

2 EMBANKMENT OF EARTHFILL 0+000 TO 1+128 1128 1100 0 1100 2 EMBANKMENT OF EARTHFILL 0+000 TO 1+128 998 980 0 980

3 GRANULAR SUB-BASE 0+000 TO 1+128 1128 1100 0 1100 3 GRANULAR SUB-BASE 0+000 TO 1+128 998 980 0 980

4 AGGREGATE BASE COARSE 0+000 TO 1+128 1128 1100 0 1100 4 AGGREGATE BASE COARSE 0+000 TO 1+128 998 980 0 980

5 PAVING WORKS 0 5 PAVING WORKS 0

6 EXCAVATION FOR UTILITIES 0 6 EXCAVATION FOR UTILITIES 0

7 SEWERAGE MANHOLE 0 7 SEWERAGE MANHOLE 0

8 SEWERAGE PIPE LINES 0 8 SEWERAGE PIPE LINES 0

9 WATER SUPPLY PIPE LINES 0 9 WATER SUPPLY PIPE LINES 0

10 ELECTRIC SUPPLY WORK 0 10 ELECTRIC SUPPLY WORK 0

PHYSICAL PROGRESS 39% PHYSICAL PROGRESS 35%

PHYSICAL PROGRESS OF TOTAL INFRA WORK 7%


Sr. No. Culvert # LENGTH UNIT Remarks
1 SAGAR AVENUE L/S 1128.00 RFT

2 SAGAR AVENUE R/S 1128.00 RFT

3 SAGAR ROAD 998.00 RFT

4 ROAD-01 260.00 RFT

5 ROAD-02 260.00 RFT

6 ROAD-03 1127.00 RFT

7 ROAD-04 856.00 RFT

8 ROAD-05 175.00 RFT

9 STREET-01 244.00 RFT

10 STREET-02 158.00 RFT

11 STREET-02 A 85.00 RFT

12 STREET-03 468.00 RFT

13 STREET-04 234.00 RFT

14 STREET-05 919.00 RFT

15 STREET-06 221.00 RFT

16 STREET-07 864.00 RFT

17 STREET-08 220.00 RFT

18 STREET-09 807.00 RFT

19 STREET-10 692.00 RFT

20 STREET-11 578.00 RFT

21 D-5-3 220.00 RFT

TOTAL LENGTH 11642.00 RFT

_______________________
Planning Engineer
EQUIPMENTS /
PLANT OPERATIONAL (UIA)
Sr# Description Nos. Sr# Description Nos.
1 Baby Hand Roller 6 32 Welding Generator 1
2 Plate Compactor 5 33 Bike 9
3 Steel Form Work (SFT) 8654 34 W/Bouzer 3
4 Scaffolding Pipe (RFT) 23606 35 Nissan HC-083 (single cabin) 1
5 Scaffolding Joint (No) 11380 36 Tandom Rollar 1
6 Wooden Runner 3316 37 Tractor Belarus T-2781+5768 2
7 Vibrators Shaft 6 38 Bowzer Tank (Tractor Type) 2
8 Tower Light 3 39 Tractor Trolly Two Wheels 3
9 Level Equipment 9 40 Tractor Trolly Four Wheels 1
10 Total Station 5 41 Electrical Welding Plant 1
11 Diesel Tank with Dispensor 1 42 Ply Cutter Machine 1
12 Bar Bending Machine 32mm 2 43 Water Pump 2
13 Bar Cutting Machine 2 44 Loader ZL509N 1
14 Batching Plant with Cylo (1+3) 4 45 Excavator 4
15 Power Generator 350 KVA (D.E) 1 46 Dumper 3
16 Power Generator 180 KVA (D.E) 1 47 Potohar E-0868 1
17 Power Generator 165kva (D.E) 1 48 Jack Hammer 1
18 Power Generator 60kva (D.E) 1 49 Transit Mixer 5
19 Power Generator 42 KVA (D.E) 1 50 Block Making Machine 4
20 Power Generator 11kva (D.E) 1 51 Office Container 5
21 Power Generator 10kva (D.E) 1 52 Container For Cement Bags 1
22 Power Generator 6.5 KVA (P.E) 1 53 Concrete Pump (Schwing) 1
23 Power Generator 5 KVA (D.E) 1 54 Crane JS-4894 25Tons 1
24 Power Generator 3.2 KVA (P.E) 2 55 Trawlar JT-9003 1
25 Power Generator 3 KVA (P.E) 4 56 Shehzor CS-2661 1
26 Power Generator 1 KVA (P.E) 1 57 Suzuki Hi-Roof 2
27 Vibrator Engine 4 58 Chiller Plant 2
28 Wheel Barrow 5 59 Loader 950E+950B 2
29 Grinder 2 60 Complete Lab Equipments -
30 Drilling Tools 2
31 Mixer Machine 4
Total 138

Store In-charge
PROJECT TITLE: UPGRADATION OF BHOLARI DRAINAGE SYSTEM

Engineers & Contractors

Daily Progress Report


Daily Manpower, Equipment and Progress Report DATE: ___________
EQUIPMENTS /
MANPOWER (UIA)
PLANT OPERATIONAL (UIA)
Designation Nos. Designation Nos. Description Nos.
Office Staff Skilled Staff Baby Hand Roller 5
Project Manager 1 Skilled Labour Plate Compactor 4
Quantity Surveyor 1 Mason Steel Form Work (SFT) 6654
Planning Engineer 1 Foreman Scaffolding Pipe (RFT) 17606
Accountant 1 Molvi Scaffolding Joint (No) 6380
AutoCAD Operator 1 Wooden Runner 2316
Computer Operator 1 Total: Vibrators Shaft 4
Admin Assistant 1 Un-Skilled Staff Tower Light 2
Material Engineer 1 Cooks Level Equipment 7
Lab Assistant 1 Watchman & Guards Total Station 4
Lab Helper 1 Trip Counter Diesel Tank with Dispensor 1
Office Boy 1 Unskilled Labour Bar Bending Machine 32mm 1
Purchase Officer 1 Carpenter Bar Cutting Machine 1
Store Keeper 1 S-Folder+Helper Batching Plant with Cylo 1+3
Total: 13 Total: Power Generator 180 KVA 1

Site Staff Sub-Contractor Staff (Drain) Power Generator 3 KVA 4

Site Engineer 3 Foreman Vibrator Engine 4


Construction Manager 0 Steel Fixer Wheel Barrow 5
Site Supervisor 3 Scaffolder Grinder 2
Chief Surveyor 1 Shuttering Carpenter Drilling Tools 2
Sr Surveyor 1 Mason Mixer Machine 4
Surveyor 6 Unskilled Labour Welding Generator 1
Astt. Surveyors 1 Skilled Labour Bike 6
Surveyor Helpers 14 W/Bouzer 2
Electricians 1 Total: Nissan HC-083 (single cabin) 1
Sub-Contractor Staff
Tandom Rollar 0
(Culverts)
Foreman Tractor Belarus T-2781+5768 1
Steel Fixer Bowzer Tank (Tractor Type) 1
Total: 30 Scaffolder Tractor Trolly Two Wheels 2
Mechanical Staff Shuttering Carpenter Tractor Trolly Four Wheels 1
Batching Plant Fitter 1 Mason Electrical Welding Plant 1
Batching Plant Operator 1 Unskilled Labour Ply Cutter Machine 1
Batching Plant Helper 1 Water Pump 1
Batching Plant Electrician 1 Loader ZL509N 1
Mechanic 1 Excavator 3
Mechanic Helper 2 Dumper 3
Welder 1 Potohar E-0868 1
TM Driver 2 Jack Hammer 1
Tractor Driver 2 Transit Mixer 4

Total: 12 Total:

_______________________________ ___________________________
Planning Engineer Project Manager