MONTHLY MONITORING CHART- APRIL

Widening and Providing BM & BC surfacing to Tirur-Kadalundi Road km 0/000 - 14/000 in Tirur & Tanur LAC in
C No: 7458 Name of Work:
Malappuram Dist

Planned Completion Actual Completion


Sl No Item / Work Unit Planned Quantity Executed quantity Reasons for variants Remarks
Date Date

1 DRAIN 4/30/2019 4/30/2019 Mtr 1500 780 Labour shortage

2 Utility duct 4/30/2019 4/30/2019 Mtr 301 60 Labour shortage

3 CULVERT 4/30/2019 4/30/2019 Nos 1 1

4 Cross duct 4/30/2019 4/30/2019 Nos 4 4-one side completed

5 R R Masonry-For Road work 4/30/2019 M3 200 0 Boundry problem

Delay in Tree cutting ,


6 GSB 4/30/2019 4/30/2019 Mtr 1416 390
Post shifting

Delay Tree cutting ,


7 WMM 4/30/2019 Mtr 1416 0
Post shifting

Delay Tree cutting ,


8 DBM 4/30/2019 Mtr 1416 0
Post shifting

Site in charge: Director:


___________________
ULCCS/PM/F01/R1
MONTHLY MONITORING CHART- MAY 2019
Widening and Providing BM & BC surfacing to Tirur-Kadalundi Road km 0/000 - 14/000 in Tirur & Tanur LAC in Malappuram
C No: 7458 Name of Work:
Dist

Planned Completion Actual Completion


Sl No Item / Work Unit Planned Quantity Executed quantity Reasons for variants Remarks
Date Date
The qty planned for
May is 3445 m
1 DRAIN 5/31/2019 5/22/2019 Mtr 3445 669 Labour shortage including the previous
month delay qty of 720
m.
The qty planned for
May is 542 m
2 Utility duct 5/31/2019 5/22/2019 Mtr 542 236 Labour shortage including the previous
month delay qty of
241.11 m.

3 CULVERT 5/31/2019 5/22/2019 Nos 1 0.5

The qty planned for


May is 3 culverts and
4 half portion of
4 Cross duct 5/31/2019 5/22/2019 Nos 3 + 4 one side 5 one side culverts including the
previous month delay
qty of 4 half portion of
culverts.

The qty planned for


May is 735 m3
5 R R Masonry-For Road work 5/31/2019 M3 735 0 Boundry problem including the previous
month delay qty of 200
m3.
The qty planned for
Delay in Tree cutting , May is 2442 m
6 GSB 5/31/2019 5/22/2019 Mtr 2442 750 including the previous
Post shifting
month delay qty of
1026 m.
The qty planned for
Delay in Tree cutting , May is 2832 m
7 WMM 5/31/2019 5/22/2019 Mtr 2832 1140 including the previous
Post shifting
month delay qty of
1416m.
The qty planned for
Delay in Tree cutting , May is 2832 m
8 DBM 5/31/2019 Mtr 2832 0 including the previous
Post shifting
month delay qty of
1416m.

9 BC Mtr

Site in charge: Director:


___________________
ULCCS/PM/F01/R1
MONTHLY MONITORING CHART- JUN
C No: 7458 Name of Work: Widening and Providing BM & BC surfacing to Tirur-Kadalundi R
Planned Actual Completion
Sl No Item / Work Unit
Completion Date Date

1 DRAIN 6/30/2019 6/24/2019 Mtr

2 Utility duct 6/30/2019 6/24/2019 Mtr

3 CULVERT 6/30/2019 Nos

4 Cross duct 6/30/2019 6/24/2019 Nos

5 R R Masonry-For 6/30/2019
Road work M3

6 GSB 6/30/2019 6/24/2019 Mtr

7 WMM 6/30/2019 6/24/2019 Mtr

8 DBM 6/30/2019 6/24/2019 Mtr

9 BC Mtr

___________________
ULCCS/PM/F01/R1
ORING CHART- JUNE 2019
M & BC surfacing to Tirur-Kadalundi Road km 0/000 - 14/000 in Tirur & Tanur LAC in Malappuram Dist
Reasons for
Planned Quantity Executed quantity Remarks
variants
The qty planned for June is
5501 1210 Labour shortage 5501 m including the
previous month delay qty of
2776 m.

The qty planned for June is


607 630 Labour shortage 607 m including the previous
month delay qty of 306 m.

0.5 0

The qty planned for June is 5


5 one side 1 one side half portion of cross duct
which is the previous month
delay qty .

The qty planned for June is


735 0 Boundry problem 735 m3 which is the previous
month delay qty.

Delay in Tree The qty planned for June is


1692 400 cutting , Post 1692 m which is the previous
shifting month delay qty .

Delay in Tree The qty planned for June is


1692 290 cutting , Post 1692 m which is the previous
shifting month delay qty

Delay in Tree The qty planned for May is


2832 1270 cutting , Post 2832 m including the
shifting previous month delay qty of
1416m.

Site in charge: Director:


MONTHLY MONITORING CHART- J

C No: 7458 Name of Work: Widening and Providing BM & BC surfacing to Tirur-Kad
Planned Actual Completion
Sl No Item / Work Unit
Completion Date Date

1 DRAIN 7/31/2019 7/24/2019 Mtr

2 Utility duct 7/31/2019 7/24/2019 Mtr

3 CULVERT 7/31/2019 Nos

4 Cross duct 7/31/2019 7/24/2019 Nos

R R Masonry-For Road
5 7/31/2019 M3
work

6 GSB 7/31/2019 Mtr

7 WMM 7/31/2019 Mtr

8 DBM 7/31/2019 7/24/2019 Mtr

9 BC Mtr
ORING CHART- JULY 2019

BM & BC surfacing to Tirur-Kadalundi Road km 0/000 - 14/000 in Tirur & Tanur LAC in Malappuram Dist

Planned Quantity Executed quantity Reasons for variants Remarks

The qty planned for July is


7016 1580 7016 m including the previous
month delay qty of 4291 m.

The qty planned for July is


278 290 278m (which including the
previous month lead of 23m).

0.5 0

The qty planned for July is 4


4 one side 1 one side half portion of cross duct which
is the previous month delay qty .

The qty planned for July is 735


735 0 Boundry problem m3 which is the previous month
delay qty.

The qty planned for July is


Delay in Tree cutting , 3770 m which including the
3770 0
Post shifting previous month delay qty of
1292m .

The qty planned for July is


3880 0 Delay in Tree cutting , 3880 m which including the
Post shifting previous month delay qty of
1402 m.

Delay in Tree cutting , The qty planned for July is


1562 160 Post shifting 1562 m which is the previous
month delay qty.
MONTHLY MONITORING CHART- AU

C No: 7458 Name of Work: Widening and Providing BM & BC surfacing to Tirur-Kad
Planned Actual Completion
Sl No Item / Work Unit
Completion Date Date

1 DRAIN 8/31/2019 8/25/2019 Mtr

2 Utility duct 8/31/2019 8/25/2019 Mtr

3 CULVERT 8/31/2019 Nos

4 Cross duct 8/31/2019 Nos

R R Masonry-For Road
5 8/31/2019 M3
work

6 GSB 8/31/2019 Mtr

7 WMM 8/31/2019 Mtr

8 DBM 8/31/2019 Mtr

9 BC Mtr
RING CHART- AUGUST 2019

BM & BC surfacing to Tirur-Kadalundi Road km 0/000 - 14/000 in Tirur & Tanur LAC in Malappuram Dist

Planned Quantity Executed quantity Reasons for variants Remarks

The qty planned for August is


8161 1266 8161 m including the previous
month delay qty of 5436 m.

The qty planned for August is


289 372 289m (which including the
previous month lead of 12m).

0.5 0

The qty planned for August is 3


1.5 0 half portion of cross duct which
is the previous month delay qty .

The qty planned for August is


735 0 735 m3 which is the previous
month delay qty.

The qty planned for August is


6248 0 6248 m which including the
previous month delay qty of
3770 m .

The qty planned for August is


6358 0 6358 m which including the
previous month delay qty of
3880 m.

The qty planned for August is


1402 0 1402 m which is the previous
month delay qty.
MONTHLY MONITORING CHART-

C No: 7458 Name of Work: Widening and Providing BM & BC surfacing to Tirur-Kadalun
Planned Actual Completion
Sl No Item / Work Unit
Completion Date Date

1 DRAIN 9/30/2019 9/23/2019 Mtr

2 Utility duct 9/30/2019 9/23/2019 Mtr

3 CULVERT 9/30/2019 Nos

4 Cross duct 9/30/2019 Nos

R R Masonry-For
5 9/30/2019 M3
Road work

6 GSB 9/30/2019 9/23/2019 Mtr

7 WMM 9/30/2019 Mtr

8 DBM 9/30/2019 Mtr

9 BC Mtr
LY MONITORING CHART- SEP 2019

d Providing BM & BC surfacing to Tirur-Kadalundi Road km 0/000 - 14/000 in Tirur & Tanur LAC in Malappuram Dist

Planned Quantity Executed quantity Reasons for variants

9620 1100

218 147

0.5 0

1.5 0

735 45.28

8726 585

8836 0

1402 0
& Tanur LAC in Malappuram Dist

Remarks

The qty planned for September


is 9620 m including the previous
month delay qty of 6895 m.

The qty planned for September


is 218m (which including the
previous month lead of 83m).

The qty planned for September


is 3 half portion of cross duct
which is the previous month
delay qty .

The qty planned for September


is 735 m3 which is the previous
month delay qty.

The qty planned for September


is 8726 m which including the
previous month delay qty of 6248
m.

The qty planned for September


is 8836 m which including the
previous month delay qty of 6358
m.

The qty planned for September


is 1402 m which is the previous
month delay qty.
MONTHLY MONITORING CHART-

C No: 7458 Name of Work: Widening and Providing BM & BC surfacing to Tirur-Kadalun
Planned Actual Completion
Sl No Item / Work Unit
Completion Date Date

1 DRAIN 10/31/2019 Mtr

2 Utility duct 10/31/2019 Mtr

3 CULVERT 10/31/2019 Nos

4 Cross duct 10/31/2019 Nos

R R Masonry-For
5 10/31/2019 M3
Road work

6 GSB 10/31/2019 Mtr

7 WMM 10/31/2019 Mtr

8 DBM 10/31/2019 Mtr

9 BC 10/31/2019 Mtr
LY MONITORING CHART- OCT 2019

d Providing BM & BC surfacing to Tirur-Kadalundi Road km 0/000 - 14/000 in Tirur & Tanur LAC in Malappuram Dist

Planned Quantity Executed quantity Reasons for variants

11245

372

0.5

1.5

689.72

10619

11314

4706

4249
& Tanur LAC in Malappuram Dist

Remarks

The qty planned for October is


11245 m including the previous
month delay qty of 8520m.

The qty planned for October is


372m (which including the
previous month delay of 71m).

The qty planned for October is 3


half portion of cross duct which
is the previous month delay qty .

The qty planned for October is


689.72m3 which is the previous
month delay qty.

The qty planned for October is


10619 m which including the
previous month delay qty of
8141m .

The qty planned for October is


11314 m which including the
previous month delay qty of 8836
m.

The qty planned for October is


4706m which is the previous
month delay of 1402m.

The qty planned for October is


4249m.
MONTHLY MONITORING CHART- MAY

C No: 7458

Actual qty to be done


Sl No Item / Work Delay/lead in April May planned qty
in May

1 DRAIN -780.00 2725.00 Mtr 3505

2 Utility duct -241.11 301.11 Mtr 542

3 CULVERT 0.00 1.00 Nos 1

3both side + 4 one


4 Cross duct 4-one side 3.00 Nos side

5 R R Masonry-For Road work -200.00 535.00 M3 735

6 GSB -1026.00 1416.00 Mtr 2442

7 WMM -1416.00 1416.00 Mtr 2832

8 DBM -1416.00 1416.00 Mtr 2832

9 BC 2832.00 Mtr 2832