Wash Water
Wash Water
Wash Water
Date: 26-02-2017
Finding:
-On 25-02-2017 pump has been isolated to check alignment and piping parallelism
0,0 0,0
R A
+0,05 +0,05
Discharge pipe has been dismantled for inspection and piping misalignment was found
And bolts can’t install free after dismantling as shown below,
2
شـــــــرـكـة مصــــــر للصيانــــــــــــة
إحدى شركات قطاع البترول
Egyptian Maintenance
Co.
3.2mm
3.5mm 3.2mm
3.5mm
3
شـــــــرـكـة مصــــــر للصيانــــــــــــة
إحدى شركات قطاع البترول
Egyptian Maintenance
4
شـــــــرـكـة مصــــــر للصيانــــــــــــة
إحدى شركات قطاع البترول
Egyptian Maintenance
Alignment changed to unacceptable limits due to pipe strain effect
0,0 0,0
R A
-0,21 +0,05
5
شـــــــرـكـة مصــــــر للصيانــــــــــــة
إحدى شركات قطاع البترول
Egyptian Maintenance
Also pipe supports were looked fixed by welding and it should be free to slide between
guides,
All above pipe problems shown in illustration directly contribute in pump vibration
So, we are looking for your decision to start fix these problems ASAP
Best Regards