Code Description Unit Quantity Rate Rs. Amount RS.: Sub Head: 14-Repairs To Building

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 2

Add 1 % Water charges on "W" 15.

09
TOTAL 1523.67 X
Add GST on "X" (multiplying factor 0.1405) 214.08
TOTAL 1737.74 Y
Add 15% CPOH on "Y" 260.66
TOTAL 1998.41 Z
Add Cess @ 1% on "Z" 19.98
Cost of 5000 litres 2018.39
Cost of 1 litre 0.40
Say 0.40

14.76 Cleaning and desilting of gully trap chamber, including removal of rubbish mixed with earth etc.
and disposal of same, all as per the direction of Engineer-in-charge.

Code Description Unit Quantity Rate Rs. Amount Rs.


Details of cost for 10 Nos.
LABOUR
0129 Sewerman day 1.00 645.00 645.00
9999 T & P Bamboo, bucket, whell barrow etc. L.S. 11.20 2.12 23.74
TOTAL 668.74 W
Add 1 % Water charges on "W" 6.69
TOTAL 675.43 X
Add GST on "X" (multiplying factor 0.1405) 94.90
TOTAL 770.33 Y
Add 15% CPOH on "Y" 115.55
TOTAL 885.88 Z
Add Cess @ 1% on "Z" 8.86
Cost of 10 nos 894.74
Cost of each 89.47
Say 89.45

14.77 Cleaning of chocked sewer line by diesel running vehicle mounting hydraulic operated high
pressure suction cum jetting sewer cleaning machine fitted with pump having 4000 litres suction
capacity and 6000 litres water jetting tank capacity including skilled operator, supervising
engineer etc. for cleaning and partial desilting of manholes and dechocking of sewer lines.
Dechocking and flushing of sewer line from one manhole to another by high pressure jetting
system of 2200 PSI for sewer line from 150mm dia upto 300mm

Code Description Unit Quantity Rate Rs. Amount Rs.


Details of Cost for 208 metres
MATERIAL
9999 Soap, brush, cloths & sundries L.S. 345.00 2.12 731.40
8500 Water for jetting / blowback 1000 litre 0.002 1500.00 3.00
Machineries
0087 Hire Charges of Suction Jeting machine 2200 PSI
machine i/c POL and operator day 1.00 40000.00 40000.00
LABOUR
0139 Skilled Beldar (for floor rubbing etc.) day 4.00 714.00 2856.00
0160 Technician day 1.00 853.00 853.00
TOTAL 44443.40 W
Add 1 % Water charges on "W" 444.43
TOTAL 44887.83 X
Add GST on "X" (multiplying factor 0.1405) 6306.74
TOTAL 51194.57 Y
Add 15% CPOH on "Y" 7679.19
TOTAL 58873.76 Z
Add Cess @ 1% on "Z" 588.74
Cost of 208 metres 59462.50
Cost of 1.00 metre 285.88
Say 285.90

SUB HEAD : 14- REPAIRS TO BUILDING 861


14.78 Cleaning of under ground sump, Over Head R.C.C. Tank ( independent staging) including
disposal of slit and rubbish, all as per direction of Engineer-in-Charge. The cleaning shall consist
following operations:-

(i)Tank shall be emptied of water by pumping & bottom shall be cleaned of silt and other
deposits.
(ii) Entire surface area of the sump shall then scrubbed thoroughly with wire brush etc. and
pressure washed with water.

(iii) Chlorination of RCC internal surface by liquid chlorine.


(iv) The treated surface shall be dried using air jetting and all loose particles shall be removal
from the surface.
(v) Finally the surface shall be treated with ultraviolet radiation etc. as per direction of Engineer-
in-Charge.
Code Description Unit Quantity Rate Rs. Amount Rs.
Let a underground tank of capacity 272000
litre or 272 KL and area of tank is 570sqm
(a) Dewater and slit cleaning
Considering through pumping 20% of water to be
lifted, water discharge =(272 x 20/100=54.40KL)
Cost of pumping water with pump of capacity 4000
litres per hours , = (54.4/4 =13.6 hours = @ 8 hours/
day = 1.7 day)
0011 Hire charges of Pump set of capacity 4000 litres/hour
day 1.70 700.00 1190.00
0114 Beldar day 10.88 645.00 7017.60
(b) Scrabing the internal surface of tank
0114 Beldar day 5.13 645.00 3308.85
0115 Coolie day 2.28 645.00 1470.60
0101 Bhisti day 2.28 714.00 1627.92
9999 Sundries L.S. 142.50 2.12 302.10
(c) Bleaching
1301 Bleaching powder quintal 0.57 1800.00 1026.00
0006 Hire charges of Spraying machine including electric
charges day 14.25 250.00 3562.50
0138 Sprayer (for bitumen, tar etc.) day 14.25 714.00 10174.50
(d) Air jetting
0058 Air compressor hour 2.00 200.00 400.00
0114 Beldar day 0.25 645.00 161.25
(e) Ultra Violet Radiation
0085 Using cost of Ultra Violet Radiation tube hour 0.50 190.00 95.00
0114 Beldar day 0.0625 645.00 40.31
TOTAL 30376.63 W
Add 1 % Water charges on "W" 303.77
TOTAL 30680.40 X
Add GST on "X" (multiplying factor 0.1405) 4310.60
TOTAL 34990.99 Y
Add 15% CPOH on "Y" 5248.65
TOTAL 40239.64 Z
Add Cess @ 1% on "Z" 402.40
Cost of 570 sqm 40642.04
Cost of 1 sqm 71.30
Say 71.30

14.79 Disconnecting damaged overhead/terrace PVC water storage tank of any size from water supply
line and removing from the terrace including shifting at ground level as per direction of Engineer-
in-charge.

SUB HEAD : 14- REPAIRS TO BUILDING 862