Professional Documents
Culture Documents
MOC Test 1
MOC Test 1
Your time: 01:09:27
Next QuizMain Menu
1. You are a construction project manager and have been recently hired in a
well known company as the manager of a highly crucial project. The project
is expected to be completed in 2 years. During the project initiation phase
you realize that some regulatory and environmental requirements have not
been considered in the contract.
o No, adding one more person adds more than one communication
channel for an eleven-member team.
Incorrect
Adding one additional person to an eleven-member team adds 11
additional communication channels, which can increase complexity.
Eleven members have 55 communication channels, and 12 members
have 66 channels:
o Accept the customer’s request and cut parts of the project scope to
meet the new deadline.
o Stick to your original schedule and tell the customer that once the
contract is signed the project duration won’t change under any
circumstances.
o Cut the duration of all project activities across the board to meet the
requirement.
Correct
Informing the customer of the impacts to project scope and other
constraints, then crashing the cost and schedule is the best approach.
Arbitrarily trimming estimates or scope without directly advising your
customer is dishonest, while simply refusing to make a change is
unprofessional.
4. According to the contract, your customer has assigned one of his staff to your
project office to attend the meetings and contribute to the decision making.
However, this person is too confrontational and his behavior to your project
team members is intimidating. What should be your action in this situation?
o Ask the customer to replace the person.
o You unilaterally decide to isolate the person and don’t let him in the
project meetings.
o Since the person is assigned by your client you don’t have any
authority over him, so don’t do anything.
o Confront the person about his behavior and its impact on the
project. Also, inform the customer about the issue.
Incorrect
The best approach to deal with the problems is to confront them. In this
situation you should respectfully confront the resource about this
behavior, and notify the customer about the situation. Failing to confront
the resource or intentionally excluding a required resource from a
project is unprofessional, and could negatively impact the project.
o Critical Diagramming
o Precedence Diagramming
o Activity-On-Arrows Diagramming
Incorrect
PDM, also called Activity-On-Node (AON), is the method used by most
project management and project planning software packages.
6. You have just been assigned to a new change-driven project. The team has
never worked together before, but they are experienced with agile techniques.
Which TWO of the following techniques would be most useful for promoting
your team’s performance?
o Creation of a detailed schedule with regular milestones.
o Allow the team to collaboratively develop a plan to execute the
project.
.
7. To formally authorize the project, which of the following documents is
necessary?
o Project Statement of Work (SOW)
o Project Charter
o Business Case
o Project Contract
Correct
The project charter is the document that officially authorizes a project
and gives the project manager the required authority to assign resources
to the project.
8. The photo transfer project will be starting in a few weeks, and it is up to you
to decide which project methodology the team will use. You have some
concerns about the project because the customer will not always be available,
and the team has mixed experience in agile methods.
Also, even though the sponsor is quite supportive in allowing you to choose
whichever approach is best, he has given you a warning. He suggests that you
be prepared since this particular customer is known to be demanding and
changes their mind frequently based on the latest market intelligence they’ve
heard. After reviewing the situation, which method would be most
appropriate?
o Scrum
o Predictive
o Hybrid
o Waterfall
Incorrect
Predictive and Waterfall are similar since waterfall is a type of predictive
approach. The fact that there will be frequent change implies that this
type of approach may not be suitable. Scrum is also risky since the
customer will not always be available to the team and the team has
mixed experience.
9. You are a project manager and you are about to perform the risk management
processes. Which one of the following documents evolves throughout the risk
management processes?
o Risk Mitigation Plan
o Contingency Plan
o Risk Profile
o Risk Register
Incorrect
The risk register is the document that evolves throughout the risk
management processes.
11. As the manager of a large project, you are performing the Control
Procurements process. Which one of the following activities would you likely
not be involved in?
o Audits
o Claims Administration
o Inspection
o Negotiation
Incorrect
Negotiation is used while performing the Conduct Procurements
process. The other answer choices are performed during the Control
Procurements process.
o Formal Presentation
o One-on-One discussion
o Bidder Conferences
Correct
Bidder Conferences (also called vendor conferences, contractor
conferences, or pre-bid conferences) are meetings between buyers and
all prospective sellers prior to the submittal of bids or proposals. They
are used to ensure that all sellers have a clear and common
understanding of the procurement and that no bidders receive
preferential treatment. Responses to questions are incorporated as
procurement document amendments. To be fair, buyers must ensure
that all sellers hear every question from individual sellers and every
answer from the buyer.
13. You have just been given the responsibility to staff and oversee a new
Scrum project. There are very limited resources, and you don’t have the
budget to hire new people. One individual has been pre-assigned to the
project, and she has asked to be the project’s scrum master. Although she has
participated in Scrum projects previously, she has never had this role. What
would be your best option in this situation?
o Tell the team member that you need someone who is experienced in
the role.
o Ask the functional manager if they have anyone available who can
serve as the scrum master.
o Allow the team member the role but ask that she enroll in scrum
master training right away.
14. As the project manager you are reviewing the earned value analysis
report performed by your team. The SPI is 0.87. What does this figure mean
to you?
o Your project is running according to the budget.
15. As the project manager you wish to use a document that shows the
work assigned to each project team member. What’s the title of the document
that you will use?
o Responsibility Assignment Matrix (RAM)
o Project Schedule
Incorrect
A Responsibility Assignment Matrix (RAM) illustrates association between
work packages/activities and team members. It makes it easy for team
members to view all the project activities for which a particular person is
assigned, and the level of their responsibility.
17. You are leading an Agile project for a new IT initiative in the company
that will get a lot of visibility. You have been disappointed that the quality of
the product delivered for the last several sprints has been poor. What is the
best option that the team should take?
o Ensure transparency of the work progress by displaying the
KanBan board in the team war room.
18. As a project manager you are involved in purchasing various items for
the project. However, you suddenly receive an official letter from your client
ordering the immediate termination of the project. What will be your best
course of action?
o Refer to Project Closure Guidelines in Organizational Process
Assets
19. Frank has been meeting with stakeholders to flesh out and understand
the requirements for his new project. Which activity would he likely not be
engaged in?
o Inspection
o Facilitation
o Prototypes
Correct
An inspection is a tool and technique for the Validate Scope process,
while the other options are all the tools used for the Collect
Requirements process.
20. In an industrial project the equipment installation can be started 15 days
after the equipment foundation is completed. What type of dependency is
this?
o Start-to-finish with a 15-day lead
21. According to Tuckman, which of the following is not one of the stages
of team development?
o Delegating
o Performing
o Forming
o Norming
Incorrect
According to Tuckman, the stages of team development are Forming,
Storming, Norming, Performing, and Adjourning.
22. Ashley, the agile team’s product owner, recently hired Bill as a
software developer for their team. Unfortunately, after Bill was hired, another
product owner was able to reserve 50% of Bill’s time for their project. What
is one of the key problems with not having Bill dedicated to Ashley’s team?
o Bill may not have the skills for the other team since he was not hired
with their project in mind.
o Bill may become dissatisfied with having too much work to do.
o Hold a networking event so that team members can get to know each
other better.
Incorrect
The key to this question is that a deliverable is due soon, and the team
conflict is putting that goal in jeopardy. The most efficient action for you
to take is to have the team agree on ground rules that they can then
hold themselves to. A team charter typically includes operating
guidelines, decision-making criteria, and communication expectations.
Enrolling a team in training may be of use long-term, along with a
networking event but will not help the immediate situation. It is never a
good idea to inform the sponsor there may be a delay due to a situation
that you, as the project manager, are ultimately accountable for.
25. The new cloud computing project had been going well when Tammy,
the project manager, received a call from an irate stakeholder that there were
several issues on the project, and they were not being addressed or being
given more visibility. Tammy knew that there was an issue log that had the
current status information on these problems. Tammy was, therefore, not
clear as to why the stakeholder was not aware of this. What would be the
most appropriate action for Tammy?
o Tammy should tell the stakeholder that they needed to review the
issue log if they were interested in knowing the latest status on a given
issue.
o Tammy does not need to take action since she had executed
everything correctly on her end.
Correct
Just because there is a process in place for documenting and updating
issues does not mean that it is an effective process. Tammy should
analyze whether there are problems with the process and make any
needed updates to it. Forwarding a copy of the log and telling the
stakeholder to review it may work in the short run but would not fix the
problem if there is truly an issue with the process. Taking no action
would annoy the stakeholder further and not solve the problem.
o Determine budget
o Estimate costs
o The critical path consumes the biggest portion of the project budget
compared to other paths
Incorrect
The critical path can have negative total float in the case that there is a
constraint set on the project finish date or positive float in the case
where the project is ahead of schedule. Typically, however, the critical
path has zero float.
29. While acquiring your project team you realize that according to the
project charter a specific consultant is required to be on your team. This
consultant has particular knowledge and your client has dictated that you hire
him as a team member. This situation describes which one of the tools and
techniques of the Acquire Resources process?
o Multicriteria Decision Analysis
o Negotiation
o Pre-Assignment
o Virtual Teams
Incorrect
Pre-assignment involves selecting project team members in advance. It
occurs when specific people were promised as part of the project
proposal, the project is dependent on expertise of particular persons, or
staff assignments are defined within the project charter.
o Progressive planning
31. Your project is 4 weeks behind schedule and you have been asked
to crash the project in order to make up the lost time. The tasks listed in
the table below are all on the critical path. Which of the tasks below
would you crash?
o Tasks C & E
o Tasks B & D
o Task A
Task A = 6,500
Tasks C & E = 2,000 + 3,500 = 5,500
Tasks B & D = 2,500 + 3,500 = 6,000
Tasks D & E & F = 3,500 + 3,500 + 4,000 = 11,000
32. You are managing a project and one of your close friends is also a
manager at the client organization. During the project execution, your friend
asks for changes to be made in the project scope, and with the reasoning that
the changes are critical to the success of the project, he asks you to handle
them on an informal basis. He argues that if you want to follow the normal
change procedures you will lose considerable time. What should you do in
this situation?
o Explain to the manager that the change should be handled
through the formal change management process and it should be
documented.
o Since what the manager has asked you is unethical you should refuse
the changes.
33. As a project manager you are using a fishbone diagram to find the
potential risks on your project. Which process are you in?
o Plan Risk Response
o Control Quality
o Identify Risk
Incorrect
A fishbone diagram (also called cause and effect analysis or Ishikawa
diagram) is used in the Identify Risks process to determine the potential
risks that might affect the project.
o Exploit
o Mitigate
o Accept
Correct
In this situation your are taking the Acceptance strategy. Acceptance is
adopted when there is no possibility to eliminate all threats from a
project. This means the project team has decided not to change the
project management plan to deal with a risk or is unable to identify a
response strategy. This strategy can be active or passive acceptance.
Passive Acceptance: No action except documenting the strategy and
leave project team to deal with the risks as they occur. Active
Acceptance: Establish a contingency reserve (time/money/resources).
39. For the purpose of recording project lessons learned, you are analyzing
the major delay in the project schedule. The root cause of the delay was a
demonstration done by a group of green initiative supporters. They were
unhappy because their representatives were not informed about all of the
arrangements that you are taking to protect the environment. What could you
and your team have done better to prevent this from happening?
o A more accurate risk response planning
o Quality measures
o Warranty
o Downtime
Incorrect
Quality measures are not an attribute of the cost of non-conformance.
The cost of non-conformance result in some kind of a loss or rejection of
the project’s output.
41. Categorizing identified stakeholders can assist the project team in
building valuable relationships with these stakeholders as the project
progresses. All of the following techniques are useful for this purpose except
for
o Stakeholder cube
o Salience model
o Power/Interest grid
Incorrect
Stakeholder cube, the Salience model, and the Power/Interest grid are
stakeholder mapping and categorization techniques and are used in the
Identify Stakeholders process. Stakeholder engagement assessment
matrix allows the team to analyze the variance between what the existing
and desired engagement levels of the stakeholders are and is used in
Plan Stakeholder Engagement.
42. Your company has a new product concept to replace its standalone
customer relationship management software with a cloud-based version that
has a number of new attractive features. The project is approximately two
months underway, and you are receiving complaints from some of the team
members that the information they need is not being readily shared by several
of the team. Some of this information involves knowledge from past projects
regarding how the old products were architected. What would be the most
helpful action for you to take that will improve this situation?
o Ask the more experienced team members to document their
knowledge on the past products and then pass out a copy to the project
team.
o Ask the team to work out the situation on their own and then check
back if they do not make progress.
o Speak to the team members who are not sharing information and
emphasize the importance of sharing.
o Risk Reassessment
Incorrect
This is the situation where the risk response happens after the trigger
which is the sudden shut down of an operational unit in the company.
Some responses are designed to use only if a specific event occurs. It is
appropriate for the project team to make a response plan that will be
executed only under certain predefined conditions (triggers like missing
intermediate milestones). The risk response occurs BEFORE the risk and
tries to alter the probability and/or impact while the contingency plan
only occurs AFTER the trigger (usually the risk event) and focuses only on
changing the impact.
o Advise the team member's supervisor that the team member was
inexperienced and should be mentored.
o Ask the client if the schedule can be extended since the project is no
longer on pace.
o Reassign the team member to tasks they are more familiar with.
Correct
Checking back with the team member to verify the effectiveness of the
training is the most appropriate next step. It is the job of the project
manager to not only recommend training opportunities for their team
but to ensure that the training was effective.
It may be a good idea to tell their supervisor that they will be taking the
training. However, it is not clear that mentoring is needed until the
project manager has had an opportunity to assess how well the training
went. Additionally, it is the responsibility of the project manager, rather
than the functional manager, to see to it that a mentor is assigned since
the skills in question are needed for his project. Reassigning tasks and
asking for a client extension would be premature and might be
unnecessary. Although the pace has slowed, there is no indication from
the question that the project is behind schedule.
The answer is safe. According to the APG, the most important cultural
norm needed is one that enables a safe work environment.
47. You are in charge of performing the financial analysis for a troubled
project in your company. The project is currently on hold and based on the
results of your work, top management will decide on continuing or dropping
the project. Which category of costs should you not consider in your
analysis?
o Indirect costs
o Fixed Costs
o Variable Costs
o Sunk Costs
Correct
Sunk costs are the costs that are expended in the past. Sunk costs should
not be considered when deciding on continuing a project.
o Gantt Charts
o Milestone reports
Correct
The only report that best suits to the needs of senior management is the
milestone report. The rest of the mentioned documents include a lot of
redundant or detailed information for this purpose.
49. Which of these is an output from the Acquire Resources process?
o Organizational chart
o Project team assignments
o RAM
50. Which one of the following is not an input to the Develop Project
Charter process?
o Agreements
o Business Case
o Stakeholders Register
Business Case
Agreements
Enterprise Environmental Factors
Organizational Process Assets
1. 1
2. 2
3. 3
4. 4
5. 5
6. 6
7. 7
8. 8
9. 9
10. 10
11. 11
12. 12
13. 13
14. 14
15. 15
16. 16
17. 17
18. 18
19. 19
20. 20
21. 21
22. 22
23. 23
24. 24
25. 25
26. 26
27. 27
28. 28
29. 29
30. 30
31. 31
32. 32
33. 33
34. 34
35. 35
36. 36
37. 37
38. 38
39. 39
40. 40
41. 41
42. 42
43. 43
44. 44
45. 45
46. 46
47. 47
48. 48
49. 49
50. 50
1. Correct
2. Incorrect