Safe Work Method Statement

Project Name: OLA Cell technologies private limited DATE:18.07.2023  


Company Name

Address:

Office Contact No:

Project Manager Name Contact No:

ACIVITY : SCAFFOLDING WORKS

Document Name: Version Correct as at:


SWMS for brickwork and plastering 01 11.01.2023
Safe Work Method Statement
The person who
Procedure (in steps) Possible Hazards Risk Control Measures will ensure this
Rating (Describe what action or procedure will be happens
(Break the job down into steps. Each step (Identify the hazards associated with (See taken to eliminate or minimize the risk of injury
should accomplish some major task and each step. Examine each to find below) or damage. Use the Hierarchy of Controls
be in logical sequence.) possibilities that could lead to an accident below as a guide
or potential harm arising.) 1. Eliminate the Hazard
2. Substitute the material or equipment
3. Isolate the hazard
4. Implement Engineering control
5. Implement Administrative control
6. PPE
1. Transportation of scaffolding  Fall of material, Hit by truck.  Place/Stack material within the trailer /
 trailer / tractor / Cut Injury. truck / tractor.
 fall injury  Fasten the material while transporting
by trailer.
 No person shall stay in the way of truck
/ trailer and on material.
 Ensure use of hand gloves while
loading or unloading of material.
 Ensure that vehicle is in good condition
and driver is having driving license and
other papers.
 No person should sit on loaded
materials while transportation.
 No person should walk side of the
running truck/trailer.

Document Name: Version Correct as at:


SWMS for brickwork and plastering 01 11.01.2023
Safe Work Method Statement
The person who
Procedure (in steps) Possible Hazards Risk Control Measures will ensure this
Rating (Describe what action or procedure will be happens
(Break the job down into steps. Each step (Identify the hazards associated with (See taken to eliminate or minimize the risk of injury
should accomplish some major task and each step. Examine each to find below) or damage. Use the Hierarchy of Controls
be in logical sequence.) possibilities that could lead to an accident below as a guide
or potential harm arising.) 1. Eliminate the Hazard
2. Substitute the material or equipment
3. Isolate the hazard
4. Implement Engineering control
5. Implement Administrative control
6. PPE
2. Shifting of material to desired  Fall of material.  Ensure use of hand gloves while
location  cut injury. shifting of scaffold material.
 crush injury.  Ensure that load is fastened during
 swinging of materials. shifting.
 hit by the material while shifting in  Allow material to rest over wooden
congested area. sleepers to facilitate removal of
sling.
 Ensure no swinging of material
during unloading.
 Use closed containers to shift the
staging and shuttering accessories.

Document Name: Version Correct as at:


SWMS for brickwork and plastering 01 11.01.2023
Safe Work Method Statement
The person who
Procedure (in steps) Possible Hazards Risk Control Measures will ensure this
Rating (Describe what action or procedure will be happens
(Break the job down into steps. Each step (Identify the hazards associated with (See taken to eliminate or minimize the risk of injury
should accomplish some major task and each step. Examine each to find below) or damage. Use the Hierarchy of Controls
be in logical sequence.) possibilities that could lead to an accident below as a guide
or potential harm arising.) 1. Eliminate the Hazard
2. Substitute the material or equipment
3. Isolate the hazard
4. Implement Engineering control
5. Implement Administrative control
6. PPE
 Fall of person / collapse of scaffolding /  Use all scaffolding pipes & accessories
cut injury /fall of material inspected only.
 Erect scaffolding
by competent riggers / scaffolds under
supervision of experienced & competent
supervisor only.
 During tightness of the clamp ensure that
using of correct size tool and required
tightness.
 Riggers must use safety belt while doing
the scaffolding work.
 Fall arrester and ladder must be used while
going up for work.
 The height of scaffold should not be more
than four times of its minimum base
dimension unless guy ropes ties or braces
are used.
3. Erection of scaffolding  Where scaffolds cannot be tied in to a
building, guy lines adequately secured
should be used to provide stability.
 No worker should be expected to expose
himself to an unprotected fall while getting
to the work location use of fall arrester to
be ensured.
 Scaffold should be vertical & checked

Document Name: Version Correct as at:


SWMS for brickwork and plastering 01 11.01.2023
Safe Work Method Statement
The person who
Procedure (in steps) Possible Hazards Risk Control Measures will ensure this
Rating (Describe what action or procedure will be happens
(Break the job down into steps. Each step (Identify the hazards associated with (See taken to eliminate or minimize the risk of injury
should accomplish some major task and each step. Examine each to find below) or damage. Use the Hierarchy of Controls
be in logical sequence.) possibilities that could lead to an accident below as a guide
or potential harm arising.) 1. Eliminate the Hazard
2. Substitute the material or equipment
3. Isolate the hazard
4. Implement Engineering control
5. Implement Administrative control
6. PPE
4. Use of Scaffold  Fall of person.  No loose material shall be left on the
 collapse of scaffolding. platform. Place the tools in tool box &
 cut injury /fall of material. other items in basket.
 Scaffolding shall be inspected every week /
after any adverse weather condition viz.
heavy rain, cyclone etc. and checklist shall
be revalidated.
 Don’t connect return cable of welding
machine with the scaffold.
 Don’t climb up on the rails of scaffold to
over reach job location.
 Take care of overhead electric lines always
keep you 3 mtrs away from the same.
Provide barricading so that it will not be hit
& run by any vehicle or equipment & also
will be free from man movement.
 Use of full body safety harness & fasten its
lanyard with the 4” dia.) Or fixed structure
or guard rail. Also use fall fixed line
(arrestor during vertical movement.

Document Name: Version Correct as at:


SWMS for brickwork and plastering 01 11.01.2023
Safe Work Method Statement
The person who
Procedure (in steps) Possible Hazards Risk Control Measures will ensure this
Rating (Describe what action or procedure will be happens
(Break the job down into steps. Each step (Identify the hazards associated with (See taken to eliminate or minimize the risk of injury
should accomplish some major task and each step. Examine each to find below) or damage. Use the Hierarchy of Controls
be in logical sequence.) possibilities that could lead to an accident below as a guide
or potential harm arising.) 1. Eliminate the Hazard
2. Substitute the material or equipment
3. Isolate the hazard
4. Implement Engineering control
5. Implement Administrative control
6. PPE
5. Dismantling of scaffolding  Fall of person.  Scaffolding to be dismantled by the
 collapse of scaffolding. scaffolders in presence of competent /
 cut injury /fall of material experienced supervisor.
 Display scaffolding status board at
prominent location all the time.
 Scaffolding removal shall be from top
to bottom plane wise.
 First remove bracing and then remove
all horizontal members in one plane.
 The area of dismantling should be
barricaded & no movement of
personnel underneath the same.
 Use of full body safety harness & fall
arrestor during vertical movement to be
ensured.
6. Housekeeping  Injury due to left over material  All the tools and tackles,
angles/channels must be removed from
the work place after completion of job.
 Clean the work place thoroughly.
 Ensure all material shall be stored in
designated area.

Document Name: Version Correct as at:


SWMS for brickwork and plastering 01 11.01.2023
Safe Work Method Statement

Personnel Summary

SUPERVISOR’S DETAILS
Supervisors Name & Qualifications: Name:
Experience:
Qualifications:

Prepared by: Signature: Date:


(Principle Contractor HSE Manager)

Reviewed by : Signature: Date:


(Principle Contractor Project Manager)

Reviewed by Signature Date:


(JLLSafety Manager)

Approved by
(JLL Project Manager) Signature Date: