Professional Documents
Culture Documents
DTR 1500 Eng - 12.2019
DTR 1500 Eng - 12.2019
MAINTENANCE
INSTRUCTIONS
ECOROTE 1500
1
ECOROTE 1500
TABLE OF CONTENTS
2
ECOROTE 1500
PRODUCTCHARACTERISTICS
The structure is based on Darrieus H rotor type, vertical wind axis turbine, using the
lift as in horizontal wind axis turbines.
It contains a rotor consisting of a shaft on which four pairs of laminar aerodynamic
profile arms are mounted, at equal angular intervals around the vertical axis of the turbine
and four blades are mounted at the ends of the arms. The effect of centrifugal force is
limited by crosspieces mounted near the ends at the top and bottom of the blades.
Aerodynamic and asymmetrical profile blades specially designed for work in a circle are
made entirely of aircraft aluminum, using extrusion method, while the surface is protected
by anodizing.
The high height-to-diameter ratio allows for higher speeds (circumferential speed is
2.5 times faster than wind speed - which significantly reduces generator costs). The
generator on permanent magnets, gearless coupled to the turbine with efficiency over 96%
does not have a coupling moment. Double protection was used against excessive RPM
increase and emergency stop. The most modern technical and technological solutions
based on research results conducted in the wind tunnel and our own experience have
allowed to create a wind turbine with high performance rarely achieved even in large
horizontal wind axis turbines.
3
ECOROTE 1500
TURBINES ADVANTAGES
4
ECOROTE 1500
10 High efficiency of wind energy use Cp ~ 0.42 resulting from the innovative
structure and shape of the blades.
11 The horizontal force per tower in relation to the generated power is less than
in other turbines.
12 More power from a given area if a large number of turbines are installed.
5
ECOROTE 1500
1 GENERAL REMARKS
Before starting installation work and starting up the device, all remarks and
recommendations must be followed.
HIPAR SP. Z O. O. is not responsible for their omissions.
The user is responsible for its own safety and the safety of others, it must know and
follow the following rules of use.
All specifications are subject to change without notice.
The wind turbine must be installed in accordance with the given country's standards.
Details and requirements for installation and connection should be consulted with
the power supplier or local spatial planning office.
The drawings contained in the instructions may differ from the actual state.
First read the instructions.
Any doubts should be resolved by contacting the Distributor.
6
ECOROTE 1500
2 ENERGY MANAGEMENT
FORMS
Ecorote 1500 power plants are intended for consumers who want to reduce
electricity costs, become independent of traditional power suppliers as well as protect the
environment.
On-Grid - a solution enabling the sale of surplus of generated and unused eclectic
energy to the power grid.
Off-Grid - island installation for people who do not have a connection to the power
grid. Our power plants are great as devices producing electricity stored in batteries
and consumed at the time of demand.
Water heating - the simplest form of managing the electricity obtained for heating
buildings and heating utility water.
7
ECOROTE 1500
8
ECOROTE 1500
3 LOCATION
REQUIREMENTS
The choice of a turbine operation place is a very important issue. Small changes in
wind speed can affect the decrease in energy production. The most important aspects when
choosing a wind turbine location include:
Safety requirements - the wind turbine must be placed in a safe place that does not
endanger life, health or the environment.
Roughness of the area - the rougher the surface of the earth is around the power
plant, the slower the wind will be. Large cities and forests significantly reduce wind
speed. On the other hand, water is a surface that is smooth enough that it almost
doesn't reduce the speed.
Tower height - the height of the tower should be between 5 and 15 meters. When
choosing a tower, make sure that the turbine is higher than obstacles (e.g. buildings)
in the turbine's operation area. In the case of Poland - 70% of the wind blows from
the west, therefore it should be taken into account that that direction is free of
obstacles.
9
ECOROTE 1500
HAZARDS
MECHANICAL
1 The turbine rotor during its operation can rotate at speeds up to 260 rpm. In
contact with rotating turbine components, physical damage and even loss of life
can occur. It is forbidden to:
5 The turbine blades must not rotate during installation, maintenance and
inspection works.
ELECTRICAL
1 The wind turbine produces voltage during operation that can cause electric
shock or death. It is forbidden to perform any operations on eclectic components
when the turbine is operating.
10
ECOROTE 1500
5 TECHNICAL DATA
TURBINE TECHNICAL PARAMETERS TABLE
Parameter 1.5 kW
Rotor diameter 2.2 m
Turbine height 1.5 m
Start speed 1.5 m/s
Rated speed 12 m/s
Total weight 155 kg
Wings and arms Aluminum structure tested for strength in extreme
conditions
Brake Electromagnetic brake
Work system Grid On/Off Grid/Hybrid
Controller Microprocessor controller
Inverter output voltage 1x230V AC or 3x230V AC 50Hz
Number of inverter phases 1 or 3
Generator output voltage AC
Noise level according to <46dB at 8m/s at a distance of 60m
PN-EN 61400-11
Working temperature From -40˚C to 70˚C
Corrosion protection Anodizing, galvanizing, varnish coat C5+M
Types of towers: Concrete and metal pillars, trusses and roof bases
Possibility of producing structures on individual
orders
Tower dimensions FROM 2 to 25 m
Compliance with CE, IEC 61400-2, 61400-11
11
ECOROTE 1500
0 0 0 0 0 0 0
0 1 0 20 43 0 5
0 2 0 39 87 0 10
12
ECOROTE 1500
KIT 1 CONTENTS:
Shaft x 1
Blade x 4
Generator cover x 4
Upper arm shield x 1
Lower arm x 4
Upper arm x 4
Screws set:
Quantity Name
8 Hexagon head screw M12x30
8 Hexagon head screw M12x35
16 Countersunk head screw M12x20
16 Countersunk head screw M12x25
8 Countersunk head screw M4x12
4 Countersunk head screw M4x6
24 Self drilling screw with countersunk head screw 3.9x16
Spare elements
13
ECOROTE 1500
Hammer 1kg
MOUNTING METHOD:
1. Unpack all components and put in a place ensuring their stable position.
2. First place the wings (Fig. 1) on a horizontal, stable surface and secure them against
uncontrolled movement.
3. Carefully slide the upper (longer) arm onto the wing profile (Fig. 2) as shown in Fig.
4. Use M12x30 and M12x35 screws to screw the arm with the wing. Use M12x35
screws from the side of the wing's leading edge (thicker section of the profile). Apply
a small amount of red thread adhesive to the screw threads and pre-tighten with a
flat spanner. Then tighten with a torque wrench with a tightening torque of 80Nm.
Apply white caps to the screws.
4. Carefully slide the lower (shorter) arm onto the wing profile (Fig. 2) as shown in Fig.
5. Then proceed in the same way as until Section 3.
5. The winglet should be fastened with six 3.9x16 countersunk self-drilling screws
through the holes finished with a cone. Screw in the screws with a screwdriver
equipped with a magnetic cross bit coupling.
8. Repeat Sections 2-5 for each wing. Tighten the upper arm disc using screws with
blue adhesive applied. The tightening torque of the upper arms disk is 75-80Nm.
9. Then screw the generator covers as shown in Fig.8. Tighten the screws by applying
blue adhesive to the threads beforehand. The tightening torque for the screws is
approx. 3Nm.
14
ECOROTE 1500
INSTALLATION REMARKS:
All the works should be executed in accordance with the
turbine installation instructions. The installation works must be
carefully planned.
Due to the size and weight of the assembled elements, all operations should
be approached with due caution and the rules of health and safety should be
observed.
15
ECOROTE 1500
FIGURE 1
Turbine blade
16
ECOROTE 1500
FIGURE 2
Arms
17
ECOROTE 1500
FIGURE 3
Turbine shaft
18
ECOROTE 1500
FIGURE 4
19
ECOROTE 1500
FIGURE 5
20
ECOROTE 1500
FIGURE 6
Winglet installation
3— Winglet
21
ECOROTE 1500
FIGURE 7
22
ECOROTE 1500
FIGURE 8
23
ECOROTE 1500
FIGURE 9
24
ECOROTE 1500
7 TURBINE INSTALLATION
ON THE SUPPORT
STRUCTURE INSTRUCTIONS
KIT 2 CONTENTS:
Vibration isolators x16
Screws set:
Quantity Name
8 Enlarged coarse round washer 13
8 Washer 13
8 Hexagon head screw with thread on the M12x70 shank part
8 Self-locking nut M12 with Teflon
16 White spinner 12
ADDITIONALLY:
A basket hoist or crane with a lifting capacity of approx. 300-500kg with a lifting
height by approx. 3-4 m higher than the height at which the fasting flange is placed.
Ladder
25
ECOROTE 1500
MOUNTING METHOD:
1 Unpack all components and put in a place ensuring their stable position.
2 Hang the turbine on the installation stand on the crane sling using M12 eye bolt
and lift it to a height of approx. 20 cm from the base of the installation stand.
3 Place the vibration isolators according to Fig. 9. Using M12x70 screws with round
coarse enlarged 13 washers
4 Place the turbine on the supporting structure so that the M12x70 screws fit into
the holes according to Fig. 10.
5 Screw the turbine shaft together with the supporting structure using M12 self-
locking nuts with washers, tighten them to 15 Nm.
6 Secure all hexagon screws and nuts with plastic safety caps.
7 Check the correct tightening of the turbine components.
26
ECOROTE 1500
FIGURE 9
1— Hexagon head screw with thread on the 2— Enlarged coarse round washer 13
M12 shank part
3— Vibration isolators
FIGURE 10
27
ECOROTE 1500
INSTALLATION REMARKS:
28
ECOROTE 1500
29
ECOROTE 1500
8 ECOROTE 1500
CONNECTION INSTRUCTION
KIT 3 CONTENTS:
Inverter
Braking resistor
Optional island inverter (OFF GRID version)
Screws set:
Quantity Name
4 M5x8 convex head screw with hexagon socket
4 Washer 5.3
TOOLKIT:
Flat-blade screwdriver
Cross screwdriver
Crimping tool for electric terminals
Cable insulation stripping tool
Electric wire cutter
ADDITIONALLY:
YKY 4x3 mm2<=100m stranded-core wire cable
YDY 4x3 mm2 <=100m stranded-core wire cable
4 mm2 electrical ring terminals
4 mm2 tubular electrical terminals
Four-way switch SFT 440 Hager
B+C surge arresters 1/3 Phase
Box for IP65 surge arresters
30
ECOROTE 1500
MOUNTING METHOD:
4 Before connecting the generator, complete the entire wiring installation and then
connect the terminals on the generator.
31
ECOROTE 1500
5mm diameter ring terminals should be used for cable ends from the generator side.
The ends should be fastened to the terminals indicated in Fig. 10 with M5x8 screws
included in the set. Use a washer under each screw.
FIGURE 2
32
ECOROTE 1500
CONNECTIONS REMARKS:
The turbine is delivered to the recipient with jumper installed on all three
generator terminals. The task of the jumper is to electrically block the turbine
before it can be rotated.
33
ECOROTE 1500
9
ECOROTE 1500 TURBINE
SUPPORTING STRUCTURES
PARAMETERS
The turbine supporting structure should be designed by a person authorized to
design this type of structure. The structure must meet the following strength conditions, as
per Fig. 2.
The place of the power plant installation must be chosen so that no person is in the turbine
work space.
The base on which the turbine will be mounted should have dimensions as per Fig. 1.
FIGURE 1
34
FIGURE 2
Forces
36
Ecorote 1500
10 OPERATING
RESTRICTIONS
1 After installation and connection of the turbine only by authorized persons, the
use of the turbine is maintenance-free, available to a wide range of recipients,
including people with disabilities. The usage is limited to guarantee inspections in
accordance with the guarantee conditions.
3 During the lifetime of the structure, the user, under pain of losing the guarantee,
is obliged to conduct periodic maintenance inspections- no requite.
8 Switch off
or block the turbine before starting maintenance and inspection works.
37
Ecorote 1500
9 System disassembly:
When disconnecting, first turn off the inverter. Then disconnect the cable
between the generator-inverter terminals, short-circuit all 3 generator
terminals together to brake the turbine.
Activities connected with operation may be performed only by authorized persons.
38
Ecorote 1500
39
Ecorote 1500
Revision 01/2019/DOK1500
Date of last update: 11/12/2019
40