Adecon India: Test Report of Bimetallic Overload Relay

You might also like

Download as doc, pdf, or txt
Download as doc, pdf, or txt
You are on page 1of 1

TEST REPORT OF

BIMETALLIC OVERLOAD RELAY


ADECON INDIA
DATE : 03.03.2022
Report No.
IPPL/AI/DG/BMR/03/22/05

CLIENT : Indian Oil Petronas Pvt. Ltd., Haldia Terminal, West Bengal
LOCATION : DG MCC, IPPL, Haldia Terminal, West Bengal Sheet No 1 of 1
Testing Done by : Adecon India, Howrah-711104

1. Equipment Details : Bimetallic Overload Relay


Make : L&T
Type : MN2
Sl. No. : N.A

2. Location & Feeder Name : DG, Panel No. : 2F-3, PA – 37B


Indian Oil Petronas Pvt. Ltd., Haldia Terminal, West Bengal

3. General Inspection : OK

4. Secondary injection test : (Measuring Equipment Details) Multimeter, Timer


Digital Clamp Meter, Make : Fluke, Model No. 322, Serial No. : 10150374, Calibration due Date : 22.07.2022
Digital Time Interval Meter, Make : SCOPE T&M, Model : SCOT MUT4, Sl. No. : 906347, Calibration due
Date : 26.07.2022

CHECKING OF OPERATING TIME (INVERSE CHARACTERISTICS) :

Overload Injected Expected Operating Output Overload Remarks


Setting Current Operation Time Contacts Indication
Time Obtained
(Secs.) (Secs.)

6A 60 –150 Secs 62.10 Secs OK OK Test


3A Results OK
9A 20 – 48 Secs 22.40 Secs

5. Functional checks : (Whether Operational Checks OK / Not OK / Not Available)


1 Wiring checks NA
2 Correct initiation of signal relay contacts OK
3 Correct initiation of command relay contacts OK

6. Overall Remarks : Test Results Satisfactory.

Test Performed by
Witnessed by IPPL, Haldia Witnessed by IPPL, Haldia
ADECON INDIA
Name : Mirza Md. Mehabub Name : Mr. Debabrata Talukdar Name : Mr. Nirjhar Nath
Designation : Engineer Designation : Executive Designation : Dy. Manager
Signature & Signature & Signature &
Date Date Date