Download as pdf or txt
Download as pdf or txt
You are on page 1of 6

See discussions, stats, and author profiles for this publication at: https://www.researchgate.

net/publication/26903239

A Simple and Quick Chilled Water Loop Balancing for Variable Flow System

Article · January 2000


Source: OAI

CITATIONS READS
2 1,277

5 authors, including:

Yunchao Zhu David Claridge


The University of Sheffield Texas A&M University
84 PUBLICATIONS   339 CITATIONS    359 PUBLICATIONS   2,878 CITATIONS   

SEE PROFILE SEE PROFILE

Mao Liu
Chinese Academy of Sciences
179 PUBLICATIONS   1,104 CITATIONS   

SEE PROFILE

All content following this page was uploaded by Mao Liu on 22 January 2016.

The user has requested enhancement of the downloaded file.


ESL-HH-00-05-20

A Simple and Quick Chilled Water Loop Balancing


for Variable Flow System

Yeqiao Zhu, Ph.D. Mingsheng Liu, Ph.D. Tommy Batten Dan Turner, Ph. D.
Project Manager Associate Professor Researcher Professor
Texas A&M University University of Nabraska Texas A&M University

David Claridge, Ph.D. Ben Keeble Chuck Cameron Roy Hirchak


Professor Project Manager Lead UCS operator Chief
Texas A&M University Johnson Controls, Inc. at BAMC BAMC Facility Management

ABSTRACT pumps, some of the variable flow chilled water


For many modem buildings, the chilled water loops or risers are still balanced in the traditional
loops and risers are equipped with variable speed way. Manual balancing valves are still heavily
pumping systems. How to quickly balance the used to balance the water flow to different floors
loop or riser to satisfy the cooling requirement and to the cooling coils.
and reduce energy consumption is a very
interesting topic today. In this paper, a method During the building commissioning process,
for simple and quick balancing of the chilled the authors have developed a simple and quick
water risers for a large medical facility has been approach to balance the variable flow chilled
developed and implemented. Through water loop water risers. This paper presents the approach,
commissioning, the cold air temperature is and the results are shown for the buildmg
maintained very well and the energy commissioned.
consumption for the pumping system is reduced
by about 40%. APPROACH AND APPLICATION
Approach
Key words: chilled water, loop, riser, The traditional method of balancing the
balancing, commissioning, cold deck, pump, chilled water loop sets the variable speed pump
energy consumption, EMCS. to full speed and the cooling coils valves to their
full open position. The manual valves are then
INTRODUCTION adjusted to make sure that there is design flow
Variable flow pumping systems are becoming through each coil and that a certain differential
more prevalent in the chilled water loops or pressure is maintained for each floor, e.g. 10 to
risers for new buildings. Also, more and more 20 psi. For most cases, through traditional
constant volume chilled water systems are being balancing, the manual balance valves are
converted to the variable flow systems as major adjusted to a partially open position and will
energy retrofit items for existing buildings [Zhu, remain in that position until somebody adjusts it
Liu, et al., 1997; Zhu, Turner and Claridge, later. Sometimes, the valves remain at 50% open
1999;l. This gives the building owner, facility or less for each floor. The chilled water
engineers or HVAC operators more requirement or the cooling loads are subject to
opportunities to run the chilled water system change, depending on the weather conditions and
more efficiently. Generally, the pump speeds are the internal load ratio. Most of the time, the
controlled by the EMCS or a stand-alone cooling load is under partial load conditions. Due
controller to maintain the differential pressure to the partial opening of the balance or manual
setpoints or the differential pressure plus the valves, the pump power reduction for variable
return water temperature setpoints. The speed pumps will be much less than expected.
implementation of the improved setpoints to The traditional approach to system balancing
control the chilled water loops can greatly thus negates some of the benefits of installing
benefit the energy savings of the HVAC systems variable speed drives.
[Zhu, Liuand Claridge, eg a!, 1997; Zhu, Liu, et
al., 1999; Liu, Zhu, et ai., 1997; &i+ilge, Liu -1..
Through the commissioning process, the
and Zhu, et al., 19961. Even though the chilled 'bthors developed a new approach to quickly
water systems are equipped with variable speed balance the chilled water risers if the risers are

Proceedings of the Twelfth Symposium on Improving Building Systems in Hot and Humid Climates, San Antonio, TX, May 15-17, 2000
ESL-HH-00-05-20

equipped with VFDs. The new approach of two variable speed pumps. Only one pump is on
balancing the variable flow chilled water risers line for each riser with the other in standby,
is: according to the leadlag control sequence. The
1. Fully open the entire manual balancing differential pressure (AP) is maintained by
valves for each coil on each floor. modulating the VFD of the chilled water pumps.
2. Optimize the differential pressure (AP) A typical riser diagram is shown in Figure 1. The
setpoints based on the riser layout and the AF' differential pressure sensor (AF'sensor) is located
sensor location. about 10 to 20 feet away fiom the far-end
3. After the implementation of the new cooling coil of the AHU on the top floor for each
setpoints, check the cold deck temperature for riser. The risers were balanced after the systems
each coil, the AF' for the furthest coils, critical were built.
coils, or any special coils. Make sure that there is
good cold deck temperature control and enough Measurement and Inspection Results
AP for each coil. The authors performed a detailed inspection
4. Identify each faulty sensor and valve and and took measurements for all the riser systems.
any control problems for the coil control valve. Measurements include loop AP, building AF', far-
Repair any that are malfunctioning. end coil AP or riser control AF' (sensor location),
5. Fine-tune the setpoints based on the actual each manual balance valve status, VFDs speed
load conditions and the control results. and cold deck temperature.

Application The following major issues were found:


Building Information 1. The manual balance valves were balanced to
The building is a multi-functional, state-of- the position of 30% to 60% open for each coil or
the-art medical center with a gross area of each floor.
1,470,000square feet. It was built in 1995 with a 2. Only one coil after the AP sensor for each
modem EMCS control for the HVAC systems. riser.
The building was mostly occupied in late 1996. 3. VFD speed ranged fiom 41 Hz to 60Hz.
The whole complex primarily consists of 4. The AF' setpoint ranged from 13 psi to 26 psi
outpatient clinic rooms, pharmacy, nuclear for different risers.
medicine, ICUs, CCUs, surgical areas, inpatient 5. The measured AF's were close to the setpoint
beds, diagnostic areas, research labs, animal values.
holding areas, offices, cafeteria, computer rooms, 6. Most of cold deck temperatures were
classrooms and an auditorium. The building is controlled very well; however, 13 AHUs had
maintained by an outside contractor, and they do cooling coils that were with 100% open of
a very good job in handling the day-to-day control valve or had cold deck temperatures
operational problems of such a large medical higher than the setpoints.
facility.
Analysis and Implementation of Balancing
H VAC System Information From the inspection and measured results, it
There is a central chiller plant, which provides was discovered that the manual balance valves
the chilled water to the complex. The loop were open about 50% on average, and the AF'
pumps pump the chilled water to the building setpoint is primarily for the last coil on the top
entrance. A total of 14 chilled water risers with floor for each riser. The authors determined to
28 building chilled water pumps pump the use a new approach to quickly balance the risers.
chilled water to the entire building which has 90 Based on the sensor location and condition of the
major air handling units (AHUs) and some small coil and valve, it was determined a constant
fan-coils units. All of the building chilled water value can be used for the AP setpoint and the
pumps are equipped with variable speed drives range should be from 6 psi to 13 psi for different
(VFDs). Most of the AHUs are double duct risers.
units. The HVAC systems are controlled by a
modem EMCS. From September 24 to October 1, 1998,the
authors followed the developed procedures and
Chilled Water Risers completed the balancing of the 14 risers for the
The entire complex includes five major entlre buildmg. During the balancing process, we
buildings and a research building. T h e r ~arc a not only opened the manual valves of the major
total of 14 risers for the cnmplex. Each riser has

Proceedings of the Twelfth Symposium on Improving Building Systems in Hot and Humid Climates, San Antonio, TX, May 15-17, 2000
ESL-HH-00-05-20

AHUs, but also the small FCUs. The new AF' and after the balancing.
setpoints were implemented through the EMCS.
The cold deck temperatures were checked before

Riser A 1

Figure 1. Typical chilled.water riser for the building

Troubleshooting and Fine-tuning were full open, but were maintaining excessively
From the EMCS readings and field-measured low cold air temperatures. This problem was
results, the following problems were identified: solved after calibrating the sensors and balancing
1. Cold air temperature sensor problem: the systems.
For AHUS 1 - 5 ,- n - t . m & - w ontl
2M4, the sensor readings were higher than w f increased cooling load:
actual temperature. Consequently, the valves

1.
Proceedings of the Twelfth Symposium on Improving Building Systems in Hot and Humid Climates, San Antonio, TX, May 15-17, 2000
L.
ESL-HH-00-05-20

For AHU 8A2, the coil could not maintain the


cooling load, we investigate the problem and 3. Control range settings problem:
found there was excessive outside air intake For 4M3,3B2,7B2, LR4, LA4 and 1A5, the
(much more than the design value). control ranges for the PID loop were insufficient.
Consequently, the AP setpoint was set to 13 psi They were also corrected following the
on this A2 riser as a temporary measure. After balancing.
the air flow correction, the AP setpoint could be
adjusted. Measured Results from New Balancing
For AHU 3B2, the coil cooling load was The results from the new balancing are shown
increased significantly because of excessive in Table 1.
outside air intake (over 50% above the design After the balancing, the chilled water flows all
value). remained at the same level as before, the cold air
Consequently, the chilled water valve was temperatures were maintained at the setpoints,
wide open and could not meet the load. After the and the pumping power consumption was
air flow correction, the AP setpoint could be set reduced by approximately 40% or 80 kW.
at 8 psi or lower.

Table 1. Summary of chilled water system condition before and after reset and estimated savings

CONCLUSION distance down stream fiom the pump, the reset


A quick and simple balance approach to schedule of AP is recommended. The reset LW
balance the variable chilled water riser or the can be based on the load condition or outside air
chilled water loop was developed by the authors temperature.
and was also applied to a commissioning project.
The approach considers the real system layout ACKNOWLEDGMENTS
and the operating condition of the riser or loop. The authors wish to express their gratitude to
When compared to the traditional balancing the Johnson Controls at BAMC and BAMC
methods, this new approach can reduce the Facility Management for the building
pumping power consumption much more and commissioning project. A special thanks for the
make the VFD conversion payback much support fiom Ms Lydia Decker of Johnson
shorten. If the AF' sensor is located on 213 piping Controls at BAMC, Mr. Scott Smith and Mr.

Proceedings of the Twelfth Symposium on Improving Building Systems in Hot and Humid Climates, San Antonio, TX, May 15-17, 2000
ESL-HH-00-05-20

Ruben Garcia of BAMC Facility Management.


The cooperation from Mr. Armando Flores and Y. Zhu, M. Liu, T. Batten, J. Zhou, et al., 1999,
Mr. Ron Bettinazzi is hlghly appreciated. Continuous Commissioning Report for Brooke
Army Medical Center.

REFERENCE M. Liu, Y. Zhu, D. E. Claridge, 1997, Use of


Y. Zhu, M. Liu, D. E. Claridge, D. Feary, T. EMCS Recorded Data to Identify Potential
Smith, 1997, A Continuous Commissioning Case Savings Due to Improved HVAC Operation &
Study of A State-of-the-Art Building, Proceedings Maintenance (O&M), ASHRAE Transaction-
of 5th National Conference on Building Research, Vol. 103, part 2, pp. 122-129.
Commissioning, Huntington Beach, California,
Session 13. Y. Zhu, M. Liu, T. Batten, J. Zhou, et al., 2000,
Integrated Commissioningfor A Large Medical
Y. Zhu, W. D. Turner, D. E. Claridge, 1999, Facility, Proceedings of 12th Symposium on
Report ofEnergv Eficiency Study and Improving Building Systems in Hot and Humid
Metering/Utilities Projile for Electricity Climates, San Antoino, Texas
Deregulation at Texas A&M International
University, Laredo, Texas, ESL-TW99-12/03. D. E. Claridge, M. Liu, Y. Zhu, et al., 1996,
Implementation of Continuous Commissioning in
Y. Zhu, W. D. Turner, D. E. Claridge, 1999, the Texas LoanSTAR Program: "Can You
Report of Energy Eficiency Study and Achieve 150% of Estimated RetroFt Savings"
Meteringnrtiities Profilefor Electricity Revisited, Proceedings of ACEEE, Vol4, pp
Deregulation at Texas A& M University-Corpus 4.59 - 4.67.
Christi, Corpus Christi. Texas. ESL-TR199-
12/04.

Proceedings of the Twelfth Symposium on Improving Building Systems in Hot and Humid Climates, San Antonio, TX, May 15-17, 2000

View publication stats

You might also like