Existing trip ends and trip distribution

Destinations
Zone A B C D Total (b) Total (t)
A 2 16 9 18 45 91
Origins

B 19 3 11 14 47 62
C 14 27 2 26 69 88
D 23 11 4 11 49 66
Total (b) 58 57 26 69
Total (t) 72 85 41 96

Destinations
Zone A B C D Total (b) Total (t)
A 2 16 9 18 45 91
Origins

B 19 3 11 14 47 62
C 14 27 2 26 69 88
D 23 11 4 11 49 66
Total (b) 58 57 26 69
Total (t) 72 85 41 96

From A Future Pi = 91
To Current Tij Current Aj Future Aj Fj Current Tij * Fj Ratio Future Tij
A 2 58 72 1.24 2.48 0.04 3
B 16 57 85 1.49 23.86 0.36 33
C 9 26 41 1.58 14.19 0.22 20
D 18 69 96 1.39 25.04 0.38 35
SUM 65.58 1.00 91

From B Future Pi = 62
To Current Tij Current Aj Future Aj Fj Current Tij * Fj Ratio Future Tij
A 19 58 72 1.24 23.59 0.36 23
B 3 57 85 1.49 4.47 0.07 4
C 11 26 41 1.58 17.35 0.27 17
D 14 69 96 1.39 19.48 0.30 19
SUM 64.88 1.00 62

From C Future Pi = 88
To Current Tij Current Aj Future Aj Fj Current Tij * Fj Ratio Future Tij
A 14 58 72 1.24 17.38 0.18 16
B 27 57 85 1.49 40.26 0.42 37
C 2 26 41 1.58 3.15 0.03 3
D 26 69 96 1.39 36.17 0.37 33
SUM 96.97 1.00 88

From D Future Pi = 66
To Current Tij Current Aj Future Aj Fj Current Tij * Fj Ratio Future Tij
A 23 58 72 1.24 28.55 0.43 28
B 11 57 85 1.49 16.40 0.25 16
C 4 26 41 1.58 6.31 0.09 6
D 11 69 96 1.39 15.30 0.23 15
SUM 66.57 1.00 66

NEW MATRIX
Zone A B C D Total (b) Total (t)
A 3 33 20 35 91 91
B 23 4 17 19 63 62
C 16 37 3 33 89 88
D 28 16 5 15 64 66
Total (b) 70 90 45 102
Total (t) 72 85 41 96
97% 106% 110% 106%